Questions_Carpet_Install_RFI_answers.pdf
PDF 152 KB Posted
- Attached to
- Carpet Replacement with installation Federal contract opportunity
- Solicitation number
- W912TF-18-T-5012
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Clauses_and_Provisions_Carpet.pdf | ||
| 254-FLOOR_PLAN.pdf | ||
| 255_-_FLOOR_PLAN.pdf | ||
| 247-STAIR_TREADS.pdf | ||
| 145_-_FLOOR_PLAN.pdf | ||
| 247-FLOOR_PLAN.pdf | ||
| 262-FLOOR_PLAN.pdf | ||
| Clauses_and_Provisions.pdf | ||
| Carpet_Excel_Rooms.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers
1. Please confirm if taxes should be carried in proposals?
a. No Taxes will be carried in the proposals.
2. Please confirm if any state, local, and/or Federal permits will be required on this project?
a. We will need the schedule to coordinate with the base occupants and electrical disconnection.
3. Please confirm if there are any known hazardous materials?
a. None, I will include past inspections into the bid docs.
4. The PWS/Para 2.6 states the period of performance as 2-1-17 to 6-30-17. Please confirm the period of performance for this project?
a. 2 July 2018 to 31 Oct 2018. A minimum of a 30 day notice for all facilities and schedule will need to be submitted. Assuming a 3 day down time to remove furniture, remove flooring and install new flooring. CE Operations will coordinate all facility schedules and moves.
5. Please confirm if we are to use the base flooring excel spreadsheet as the bid schedule or will one be issued?
a. Please utilize the excel sheet if the specified carpet is used. If an alternate carpet is purposed I will need samples and 3 weeks to confirm that they meet standards and have colors approved by the base occupants.
6. Please confirm wages to be used on this project?
a. Wage Determination will not be needed. FAR Clause 52.222-41 has been removed from the solicitation and the Service Contract Act is no longer applicable.
7. Please confirm proposal submission method (i.e. mail, electronic)?
a. Electronic via e-mail to the Point of Contact(s) provided within the solicitation.
File details come from the government source that posted it.