QA-20100823.pdf
PDF 31 KB Posted
- Attached to
- Aircraft Corrosion Prevention
- Solicitation number
- W912SV-10-R-0028
About this file
Answers to questions posed through 22 August 2010.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WD 05-2261 Rev 11.pdf | ||
| EAL.doc | DOC document | |
| Pre-Solicitation.docx | DOCX document | |
| DD254s.pdf | ||
| SOW -- Barnes - 2 April 2010.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
W912SV-10-R-0028
Q01 Reference RFP: FAR 52.222-41 “Service Contract Act of 1965,” and FAR 52.222-42, “Statement of Equivalent Rates for Federal Hires,” with the appropriate rates, have not been incorporated. We are assuming this was an oversight and will use the applicable Wage Determination and employee classification, but having it included does help to ensure that offerors are competing under the same set of assumptions.
A01 Wage Determination is WD 05-2261 Rev 11. This document is attached.
Q02 Reference SOW, Section 4.4, “Security Requirements:” Will an offeror’s ability to comply with this requirement be taken into account during evaluation (i.e. whether they possess a “Facility Clearance”)? If so, how shall an offeror demonstrate?
A02 Security clearance status for all employees proposed by the contractor after contract award will be verified via various agency checks.
Q03 For mailed-in proposals, how many copies of each section are desired?
A03 The original is the only documents required. There are no copies required.
Q04 Is it a correct assumption that emailed submissions are preferred?
A04 Yes. E-mailed submissions are preferred.