Industry Day Slides - FTC Hangar (8 Oct 2026).pptx
PPTX presentation 5 MB Posted
- Solicitation number
- W912QR-PDB-FTC-Aircraft-Maintenance-Hangar
About this file
This file contains industry day presentation slides for the U.S. Army Corps of Engineers (USACE), Louisville District, announcing an upcoming Progressive Design-Build (PDB) competition for Fort Campbell, Kentucky. The presentation, delivered on October 8, 2026, by Project Manager Erich Hoehler and Agreements Officer April Judd, outlines the procurement strategy, evaluation process, and applicable regulations for two major construction projects.
The Aircraft Maintenance Hangar project has an estimated value of $220 million and is currently 35% designed. USACE will issue a Request for Qualifications (RFQ) in the first quarter of FY27, with Phase 1 award targeted for the second quarter of FY27. The acquisition strategy employs Progressive Design-Build with Other Transaction Authority (OTA) under 10 U.S.C. 2808a, exempt from Federal Acquisition Regulation (FAR) requirements. The UEPH Barracks project comprises two 260-person unaccompanied enlisted personnel housing barracks valued at $205 million with 100% design complete. A Market Intelligence Notice was issued September 28, 2026, with responses due October 13, 2026. The barracks acquisition will utilize Construction Manager at Risk (CM@Risk) via OTA, with RFQ issuance targeted for the second quarter of FY27, Phase 1 award in the third quarter of FY27, and Guaranteed Maximum Price (GMP) modification in the fourth quarter of FY27. Both acquisitions employ a three-step selection process: qualifications-based RFQ evaluation, pitch presentations by up to three selected firms, and negotiations with the most highly qualified offeror. Applicable laws include Buy American Act, Davis-Bacon, Miller Act, FOIA, fiscal laws, Procurement Integrity Act, and laws of general applicability. Interested firms must register in System for Award Management (SAM) and submit qualifications through the Procurement Integrated Enterprise Environment (PIEE).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Sign-In Sheets.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Industry day Fort Campbell, KY
Presenters:
Erich Hoehler – Project Manager April Judd – Agreements Officer
Date: 8 October 2026
”The views, opinions and findings contained in this report are those of the author(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
ADMINISTRATIVE ANNOUNCEMENTS
Please ensure that you have signed in:
Company Name, POC Name, Email, Phone Interest in being the Prime or Subcontractor Subs: State the type of work you are interested in (Electrical, Mechanical, Roofing, etc.)
This briefing and the attendee roster will be posted to SAM Please be advised that none of the information discussed today is contractually-binding
Overview of the Current Projects Aircraft Maintenance Hangar UEPH Barracks
Procurement Processes Other Transactional Authority (OTA) Construction Manager at Risk (CM@R) Progressive Design Build (PDB)
Q&A Session
AGENDA
Dollar Value: $220M Current Authority: 35% Design Acquisition Strategy: Design Build Progressive Design-Build (PDB) & Other Transaction Authority (OTA) being evaluated Estimated Schedules:
| PDB/OTA Path |
| Issue Request for Qualifications (RFQ) = 1st QTR FY27 |
| Award Agreement Phase 1 = 2nd QTR FY27 |
| Award Guaranteed Maximum Price (GMP) Modification = TBD |
Typical DB - TBD
AIRCRAFT MAINTENANCE HANGAR
Two (2) 260-person Unaccompanied Enlisted Personnel Housing Barracks Estimated Acquisition Magnitude: $205M Design Status: 100% Design Complete Market Intelligence Notice Issued: 28 Sept 2026; responses due 13 Oct 2026 We need industry feedback!
Acquisition Strategy being evaluated: Construction Manager at Risk (CM@Risk) via Other Transaction Authority (OTA) Estimated Schedule:
Issue Request for Qualifications (RFQ) = 2nd QTR FY27 Award Agreement Phase 1 = 3rd QTR FY27 Award Guaranteed Maximum Price (GMP) Modification = 4th QTR FY27
UEPH BARRACKS
Legal authority to enter transactions other than standard contracts, grants, or cooperative agreements.
OTAs are NOT subject to the Federal Acquisition Regulation (FAR).
Historically used for Research and Development (R&D) procurements, however, expanded to use for construction (10 U.S.C. 2808a).
Agreements are awarded by Agreements Officers (AO) and supported by Administrative Agreements Officers (AAO) Benefits:
Provides flexibility to adopt commercial industry standards and best practices.
Attracts non-traditional partners and encourages collaboration.
WHAT IS OTHER TRANSACTION AUTHORITY (OTA)?
Buy American Act Davis-Bacon Miller Act
FOIA
Prohibition against using cost-plus for military construction Fiscal Law (e.g. Purpose Statute at 31 USC 1301, Anti-deficiency Act, 31 USC 1341-1342, 1350-1351, The Recording Statute, 31 USC 1501(a)(9)) Tucker Act (28 USC 1491) Procurement Integrity Act (41 USC 2101-2107) Other ethics laws and regulations Laws of general applicability that would apply to any entity doing business in the United States (e.g. environmental laws, import/export control, criminal laws, civil rights, etc.)
Trade Secrets and Defend Trade Secrets Acts (18 USC Ch. 90 and 18 USC 1836)
APPLICABLE LAWS
Maximum Agility and Collaboration Unites Design-Builder from project inception
Streamlined Selection Process Simplified, Qualifications-based selection focused on team competence, past performance, and chemistry General contractor and AE team evaluated
Negotiated Terms Exempt from rigidity of FAR/DFARS, allowing for tailored terms and conditions
Early Cost Fidelity & Integrated Design Continuous open-book pricing, upfront risk mitigation, and unified constructability reviews
PROGRESSIVE DESIGN-BUILD (PDB) w/OTA OVERVIEW
CM@Risk w/OTA Overview CM@Risk with OTA allows for more flexibility/collaboration than traditional FAR-based acquisitions.
Streamlined and simplified selection processed – Qualifications based
Negotiated terms and conditions
Increased cost fidelity, early identification of risks, and Construction Manager input/involvement during design phase
Government maintains separate AE contract throughout life of project
Step 1: Request for Qualifications (RFQ) Rapid, credentials-focused evaluation to identify a short list of highest qualified Design-Builders.
Step 2: Pitch Presentations Target of three (3) firms will provide live pitch presentations to Government team.
Oral presentation demonstrating an understanding of project requirements, PDB, and why they are most highly qualified team.
Step 3: Negotiations Enter into negotiations with single, most highly qualified offeror based on qualifications and pitch presentations.
Fair and reasonable price for Phase I Agreement (Design & Pre-construction) services must be determined prior to award.
THE PROCESS
Interested firms will submit qualification package to demonstrate their qualifications and understanding of the project.
The district is considering the following evaluation factors:
Corporate Experience and Relevance Technical Merit Narrative
Additional mandatory requirement: Proof of Bonding and Financial Capacity
Advertisement Period: Estimated 2-3 weeks to prepare qualifications Step 1: Request for Qualifications (RFQ)
A target of three (3) of the most highly qualified firms will be invited to individual, confidential Pitch Meetings.
The district is considering the following evaluation factors:
Collaborative Chemistry and Team Dynamics Technical Approach and Project Understanding Proactive Risk Management
Firms will have 60 minutes to deliver an oral presentation about why they are the best qualified firm to deliver the project.
After 60 minutes, a panel of government reviewers will ask questions about the presentation and the team. *The Pitch Meetings are intended to be conversational, rather than a strict Q&A session.
Step 2: Pitch Presentations
USACE will provide a draft agreement to the selected firm.
Parties will meet to negotiate and finalize the terms of the agreement
Negotiations may include the agreement articles, pricing, and other considerations.
Fair and reasonable price must be determined to award the Phase I Agreement.
If USACE and selected offeror cannot reach consensus on the agreement, USACE reserves the right to discontinue negotiations and take any action determined to be in the Government’s best interest, including entering negotiations with another firm, revising the acquisition approach, or canceling the RFQ.
Step 3: Negotiations
Offerors must be registered in the System for Award Management (SAM) database. You must sign up and sign-in to your account to use many features of SAM.gov (saving searches, viewing solicitations, etc.)
Locate and access the Solicitation notice Go to Attachments/Links section to download documents
You must register your business entity (as an individual or organization)
All qualifications/proposals must be submitted through the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module on time*. Therefore, offerors must register in advance for a user ID and Password to access this system.
Instructions for submission will be included in the Solicitation Package
*Proposals must be submitted on time (The Louisville District is in the Eastern Time Zone)
OBTAINING & SUBMITTING DOCUMENTS
Evaluation Process and Award Selection Step 1: Request for Statement of Qualifications Rapid, credentials-focused evaluation to identify a short list of highest qualified Construction Managers
Step 2: Pitch Presentations Up to three (3) firms will provide live pitch presentations to Government team.
Oral presentation demonstrating understanding of project requirements, CM@Risk and why they are most highly qualified firm.
Step 3: Negotiation with Most Highly Qualified Offeror Enter into negotiations with single, most highly qualified Offeror based on qualifications and pitch presentations. Fair and reasonable price for Phase I – Pre-construction services must be determined prior to award.
What Questions do you have for us?