Industry Day Slides - Final.pdf
PDF 4 MB Posted
- Solicitation number
- W912QR-INDUSTRYDAY-FHLBARRACKS
About this file
This document is an Industry Day Forum briefing presentation for the Fort Hunter Liggett Collective Training Enlisted (CTE) and Advanced Skills Training (AST) Barracks Project, held November 17, 2026, by the U.S. Army Corps of Engineers Louisville District.
The project scope includes construction of four CTE Barracks (approximately 46,000 square feet each) with open-bay configurations for 300 beds per building, and one AST Barracks (approximately 45,000 square feet) with 156 individual sleeping quarters. The project also requires complete demolition of five existing legacy multi-story barracks. The acquisition will utilize Progressive Design-Build (PDB) with Other Transaction Authority (OTA), which is not subject to Federal Acquisition Regulation (FAR) and permits flexibility in commercial practices and tailored terms. The procurement approach includes three evaluation steps: Request for Qualifications (RFQ) with 3-4 weeks for preparation, pitch presentations by approximately three selected firms, and negotiation with the most highly qualified offeror. Competition is full and open with small business subcontracting and mentor/protégé opportunities available. The formal RFQ was expected to issue mid-December 2026 through www.SAM.Gov, with qualifications submitted via the Procurement Integrated Enterprise Environment (PIEE) solicitation module. Phase I will cover design and pre-construction services, with Phase II as a bilateral modification for construction. Applicable laws include Davis-Bacon, Miller Act, Buy American Act, and prohibitions on cost-plus military construction contracts. The presentation also identified other potential Fort Hunter Liggett projects including water and wastewater system improvements, and briefed attendees on the Sacramento Resident Office organizational structure and broader Sacramento Procurement District OTA strategy encompassing multiple projects across California military installations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sign-In Sheet - Industry Day.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDUSTRY DAY FORUM
FORT HUNTER LIGGETT CTE & AST BARRACKS PROJECT
Presenters:
Justin Roosa – Project Manager Jesse Scharlow – Agreements Officer Crystal Harbin – Small Business Greg Sokolis – Resident Engineer
Date: 17 November 2026
”The views, opinions and findings contained in this report are those of the author(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
ADMINISTRATIVE ANNOUNCEMENTS
• Please ensure that you have signed in
• Company Name, POC Name, Email, Phone
• Are you interested in being the Prime or Subcontractor
• If you’re interested in being a subcontractor, state the type of work you are interested in (Electrical, Mechanical, Roofing, etc.)
• Please turn off all mobile devices
• No recording
• This briefing and the attendee roster will be posted to SAM
• Please be advised that none of the information discussed today is contractually-binding
• Introduction of Team Members
• Overview of the Fort Hunter Liggett Barracks Project
• USACE Procurement Process Overview
• Other Potential Project Opportunities
• Sacramento Resident Office Overview
• Q&A Session
• Site Visit
AGENDA
Justin Roosa Project Manager
U.S. Army Corps of Engineers Louisville District
FORT HUNTER LIGGETT BARRACKS OVERVIEW
Ramarao Vuddagiri Project Engineer
U.S. Army Corps of Engineers Louisville District
Project: New Training Barracks Location: Ft Hunter-Liggett
The primary scope of work includes four (4) Collective Training Enlisted (CTE) Barracks and one (1) Advanced Skills Training (AST) Barracks to restore modern housing capabilities to the installation. The four (4) CTE Barracks will each be approximately 46,000 square feet, utilizing open-bay configurations equipped with integrated officer sleeping rooms, team rooms, laundry facilities, restrooms, showers, storage, and janitorial closets.
The single approximate 45,000-square-foot AST Barracks will provide individual sleeping quarters with private bathrooms, study/day rooms, laundry rooms, storage, and janitorial closets.
Also, part of this project is to completely demolish and dispose of the five existing legacy multi-story barracks that have exceeded their useful life.
6FT HUNTER-LIGGETT – NEW TRAINING BARRACKS
Propose location of new CTE Barracks
COA –
• Demo four CT Barracks. All barracks are three-story with load bearing masonry construction.
• Construct four CTE Barracks.
Existing four Barracks to be demolished
7FT HUNTER-LIGGETT – NEW TRAINING BARRACKS
Proposed location of new AST Barracks
COA –
• Demo existing Training
Barracks.
• Construct new AST Barracks.
Existing Barracks to be demolished
AERIAL VIEW OF THE PROJECT SITE
Five Existing Training Barracks to be demolished
Proposed four CTE Barracks Location
Proposed AST Barracks Location
The purpose of the Collective Training Enlisted Barracks (CTEB) is to provide a 300-bed open bay barracks for
COLLECTIVE TRAINING ENLISTED BARRACKS
***Note: Information in this presentation is for informational purposes only and is not/will not be contractually binding.
• Major Exercises
• Annual Training
• Battle Assembly
• Mobilization Training
Typical CTEB Floor Plan
COLLECTIVE TRAINING ENLISTED BARRACKS
***Note: Information in this presentation is for informational purposes only and is not/will not be contractually binding.
Example of 24-person open bay
Example of Senior Enlisted Room
• Educational/Conference Room
• Laundry Facilities
• Latrines
• Showers
Example of Laundry Facility
Example of Education/Conference Room
Example of Laundry Facilities
Example of Corridor Area
Example of Entrance
Example of a Two-person Senior Enlisted Room
The purpose of the Advanced Skills Training Barracks is to provide 156-beds for soldiers attending advance training schools.
ADVANCED SKILLS TRAINING BARRACKS
***Note: Information in this presentation is for informational purposes only and is not/will not be contractually binding.
* Recent changes to bedroom module, as noted on next slide, but this floor plan provides a general example
• Laundry Facilities
• Multipurpose/Study Room
• Typically 2-to-4-person bedroom suites.
ADVANCED SKILLS TRAINING BARRACKS
***Note: Information in this presentation is for informational purposes only and is not/will not be contractually binding.
• Kitchenette
• Desk/Nightstand
• Closet
• Shared Bathroom &
Sinks
Two Person (E5/E6) Four Person (E1-E4)
WHAT QUESTIONS DO YOU HAVE ON THE
PROJECT OVERVIEW?
USACE PROCUREMENT PROCESS OVERVIEW
Jesse E. Scharlow Agreements Officer
• Legal authority to enter into transactions other than standard contracts, grants, or cooperative agreements. Provides flexibility to adopt commercial industry standards and best practices.
• OTAs are NOT subject to Federal Acquisition Regulation (FAR). This can attract non-traditional partners and encourages flexible, collaborative, and commercial arrangements.
• Historically used for R&D/prototypes. New authority has expanded use for construction (10 U.S.C.
§2808a).
• OTAs are awarded by Agreements Officers (AOs).
• Will have Administrative Agreements Officers (AAO) for Construction Administration support
WHAT IS OTHER TRANSACTION AUTHORITY?
PROGESSIVE DESIGN BUILD w/OTA Overview
• Progressive Design Build (PDB) with OTA allows for more flexibility/collaboration than traditional FAR-based acquisitions.
• Streamlined and Simplified Selection Process – Qualifications Based Simplified, Qualifications-based selection focused on team competence, past performance, chemistry.
• Negotiated terms and conditions Exempt from rigidity of FAR/DFARS, allowing for tailored terms and conditions
• Early Cost Fidelity & Integrated Design Continuous open-book pricing, early identification of risks, and unified constructability reviews.
Applicable Laws
• Buy American Act (if otherwise would apply)
• Davis-Bacon (for construction)
• Miller Act (for construction)
• Prohibition against using cost-plus for military construction
• Fiscal Law (e.g. Purpose Statute at 31 USC 1301, Anti-deficiency Act, 31 USC 1341-1342, 1350-
1351, The Recording Statute, 31 USC 1501(a)(9))
• Tucker Act, 28 USC 1491
• Procurement Integrity Act 41 USC 2101-2107
• Other ethics laws and regulations
• Laws of general applicability that would apply to any entity doing business in the United
States (e.g. environmental laws, inport/export control, criminal laws, civil rights, etc.)
• Trade Secrets and Defend Trade Secrets Acts (18 USC Ch. 90 and 18 USC 1836)
• FOIA
PDB w/OTA FHL, CA BARRACKS
• Competition will be full and open
• Small business subcontracting and/or mentor/protégé opportunities
• Request for Qualifications (RFQ) will be solicited publicly through www.SAM.Gov
• Qualifications packages will be submitted via the PIEE solicitation module
• Agreement will be awarded in two phases:
• Phase I Agreement – Design and Pre-Construction Services
• Phase II – Bilateral modification to agreement for Construction Phase http://www.sam.gov/
Evaluation Process and Award Selection
• Step 1: Request for Statement of Qualifications
• Rapid, credentials-focused evaluation to identify a short list of highest qualified offerors.
• Step 2: Pitch Presentations
• Target of three (3) firms will provide live pitch presentations to Government team.
• Oral presentation demonstrating an understanding of project requirements, acquisition approach, and why they are most highly qualified team.
• Step 3: Negotiation with Most Highly Qualified Offeror
• Enter into negotiations with single, most highly qualified offeror based on qualifications and pitch presentations.
• Fair and reasonable price for Phase I Agreement services must be determined prior to award.
Step 1: Request for Qualifications (RFQ)
• Interested firms will submit qualification package to demonstrate their qualifications and understanding of the project.
• The district is considering the following evaluation factors:
• Corporate Experience and Relevance
• Technical Narrative
• Proof of Bonding Capability
• Advertisement Period: Estimated 3-4 weeks to prepare qualifications.
• The Agreements Officer will determine which firms demonstrate the highest potential in their qualifications statement.
• Approximately 3 of the most qualified firms will be invited to individual, confidential Pitch Meetings.
• Firms will have 60 minutes to deliver an oral presentation about why they are the best qualified firm to deliver the project.
• After 60 minutes, a panel of government reviewers will ask questions about the qualification statement, presentation, and the firm’s capabilities.
• The Pitch Meetings are intended to be conversational, rather than a strict Q&A session.
Step 2: Pitch Presentations
• The USACE acquisition team, led by the Agreements Officer, will meet to discuss the advantages and disadvantages of each firm.
• The team may consider:
• The firm’s proposal
• Pitch meeting discussions
• Other information within the government’s possession
• Any other publicly available information about the firms
• Agreements Officer will select one qualified firm to proceed to negotiations.
• All other firms will be notified that they were not selected. However, non-selected firms may be asked to return for negotiations if the negotiations with the selected firm are unsuccessful.
Selection of Single/Highest Qualified Firm
• USACE will provide a draft agreement to the selected firm.
• Parties will meet to negotiate and finalize the terms of the agreement.
• Negotiations may include the agreement articles, pricing, and other considerations.
• Fair and reasonable price must be determined in order to award the Phase I Agreement.
• If USACE and selected offeror cannot reach consensus on the agreement, USACE reserves the right to discontinue negotiations and take any action determined to be in the Government’s best interest, including entering negotiations with another firm, revising the acquisition approach, or canceling the RFQ.
Step 3: Negotiations
• If negotiations are successful, the Agreements Officer will award Phase I of the Agreement for Design and Pre-Construction Services to the awardee.
• Phase II – Full Construction will be incorporated as bilateral modification as design nears completion.
Award
• Offerors must be registered in the System for Award Management (SAM) database. You must sign up and sign-in to your account to use many features of SAM.gov (saving searches, viewing solicitations, etc.)
» Locate and access the Solicitation notice » Go to Attachments/Links section to download documents
• You must register your business entity (as an individual or organization)
• All qualifications/proposals must be submitted through the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module on time*. Therefore, offerors must register in advance for a user ID and Password to access this system.
• Instructions for submission will be included in the Solicitation Package
• *Proposals must be submitted on time (The Louisville District is in the Eastern Time Zone)
OBTAINING & SUBMITTING DOCUMENTS
Feedback
• Please provide all feedback on PDB process for Fort Hunter Liggett
Barracks requirement by 26 November 2026.
• All feedback, questions and/or concerns can be provided to Jesse Scharlow at Jesse.E.Scharlow@usace.army.mil.
• Formal RFQ should be issued in mid December.
mailto:Jesse.E.Scharlow@usace.army.mil
Crystal Harbin Regional Small Business Director
Great Lakes and Ohio River Division
SBO-LRL@usace.army.mil mailto:SBO-LRL@usace.army.mil mailto:SBO-LRL@usace.army.mil mailto:SBO-LRL@usace.army.mil
• Subcontracting
• Successful utilization of subcontractors is critical to success of the project
• Pitch presentations will include a collaboration focus
• Attend Industry Days, Pre-Proposal Conferences, and Site Visits
• Obtain copies of attendee listings for subcontracting opportunities
• Register as an interested Vendor on SAM
• Attend Workshops, Conferences, Trade Fairs
• Annual Louisville District Open House will be held 03 February 2027
• Contracting opportunities are posted in the System for Award Management (SAM) website at www.sam.gov. Use “W912QR” to search for Louisville District projects.
• Review Forecast & Current IDIQs, https://www.lrd.usace.army.mil/Business-With- Us/
OPPORTUNITIES
http://www.fbo.gov/ https://www.lrd.usace.army.mil/Business-With-Us/ https://www.lrd.usace.army.mil/Business-With-Us/ https://www.lrd.usace.army.mil/Business-With-Us/ https://www.lrd.usace.army.mil/Business-With-Us/ https://www.lrd.usace.army.mil/Business-With-Us/
OTHER POTENTIAL PROJECT OPPORTUNITIES
Justin Roosa Program Manager
FT HUNTER LIGGETT WATER & WASTEWATER
COLLECTION SYSTEM IMPROVEMENTS
• Water Main Transmission Line and Storage
• Install approximately 5 miles of water main transmission line to connect the existing well field to the main distribution system within the cantonment area.
• New water storage infrastructure as required to satisfy requirements for fire safety, emergency needs, and operational storage (estimated to be a minimum of 2 million gallons).
• Modernizing SCADA components and upgrades to existing water supply wells to enhance water-supply reliability and redundancy
• Water Distribution and Wastewater Collection within the Cantonment Area
• Repairs to many pipelines, valves, and hydrants within the cantonment water distribution and wastewater collection system that have currently exceeded their useful life expectancy and have failed or failing.
• Repairs to the wastewater treatment lagoon liner and potentially other repairs to the wastewater treatment plant.
FT HUNTER LIGGETT WATER & WASTEWATER
COLLECTION SYSTEM IMPROVEMENTS
Existing 3 wells
Potential New Water Tank Farm and Booster System
Potential New Water Transmission Line
Potential Repairs & Improvements to the Water Distribution & Wastewater Collection System Within Cantonment Area
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
Greg Sokolis, Resident Engineer November 17, 2026
37File Name
SACRAMENTO RESIDENT OFFICE OVERVIEW
SACRAMENTO RESIDENT OFFICE
Main Office – Gold River
Hub Office – Presidio of Monterey
Project Offices – Beale AFB, DDJC San Joaquin (Tracy), Fort Hunter Liggett Field Offices – Sierra AD, Travis AFB, CP Parks, CP
Roberts, Redding, Fresno, BT Collins
Direct Support to Military Installations Army – Sierra AD, Presidio of Monterey / Ord Military
Community, Camp Parks, Camp Roberts, Fort Hunter Liggett
Air Force – Beale AFB, Travis AFB Navy – Naval Research Laboratories and SATCOM DOD Agencies – Moffett Field, DDJC Tracy (DLA)
Other Agency Support US Forest Service, US Dept. of Agriculture, Naval Research Laboratories, US Dept. of Homeland Security (FBI & Coast Guard)
Gold River
Redding
Sierra AD
Presidio of Monterey
Beale AFB
Travis AFB
Camp Parks
DDJC Tracy
Fort Hunter Liggett
Camp Roberts
BT Collins
Moffett Field
SACRAMENTO RESIDENT OFFICE
Greg Sokolis
Resident Engineer Gold River
Kaiki Ragragola Deputy Resident Engineer
Presidio of Monterey
Beale AFB Travis AFBDDJC Tracy Fort Hunter Liggett
Rosie Sotelo Office Admin
Ronnie Valencia Office Engineer Laszlo Nagy
Project Engr.
Michael Brown
QA / COR
Woody Bradley
QA
Kedric Argueta
QA
Dallas Lee Jr. Proj. Engr.
Cynthia Baksys Sr. Project Engr.
Josh Slaughter
QA
Robert Roy Project Engineer
Fred Martin
QA
Presidio of Monterey
Dylan Jenkins Project Engr.
Shawn McCauley
QA
BT Collins
Steve Sanden
QA
Mike Brown Sr. QA
SPK PROPOSED OTA STRATEGY
Project Location PA ($M) Phase 1 Award Progressive Design-Build (PDB) Radiation Research Facility LMTF (URO) +$100M 1Q27 Building 1515 Renovation Hill AFB (URO) +$30M 3Q27 *F-35A Maintenance Facility & Composite Repair PH1 Hill AFB (URO) +$100M 3Q27 Multi Domain Ops Complex Beale AFB (SRO) +$100 M 3Q27 *B1308/B1309 & B1304/B1305 Repair by Replacement Dorms Travis AFB (SRO) +$100M 4Q27 *B25307 & B25309 Dorm Renovation Beale AFB (SRO) $30-50M 4Q27 Wheatland Entry Control Facility Beale AFB (SRO) <$10M TBD Chemistry Lab Dugway PG (URO) +$100M TBD Design Build to Budget UTTR Fire Station Addition Hill AFB (URO) <$10M 27 Barracks Camp Roberts UPE (SRO) $50-70M TBD Fire Station (CAP 076283) Dugway PG (URO) $30-50M TBD Fire Station (CAP 076282) Dugway PG (URO) $30-50M TBD Construction Management at Risk (CMAR) F-16 Emergency Power Unit Overhaul Facility LMTF (Hill AFB) $70-100M 3Q27 Delivery Method TBD Access Control Point Sierra AD (SRO) $30-50M FY28 Loading Unloading Ramp Repair MOTCO (MRO) <$10
Data Date 02NOV26
*Consolidated OT
WHAT QUESTIONS DO YOU HAVE FOR US?
| INDUSTRY DAY FORUM�FORT HUNTER LIGGETT CTE & AST Barracks PROJECT |
| ADMINISTRATIVE ANNOUNCEMENTS |
| AGENDA |
| Fort HUNTER LIGGETT BARRACKS OVERVIEW |
| Slide Number 5 |
| Ft Hunter-Liggett – New Training Barracks |
| Ft Hunter-Liggett – New Training Barracks |
| Aerial View of the Project Site |
| Collective Training Enlisted Barracks� |
| Collective Training Enlisted Barracks� |
| Collective Training Enlisted Barracks |
| Collective Training Enlisted Barracks |
| Collective Training Enlisted Barracks |
| Collective Training Enlisted Barracks |
| Collective Training Enlisted Barracks |
| Advanced skills training barracks� |
| Advanced skills training barracks� |
| What Questions do you have on the project overview? |
| USACE PROCUREMENT PROCESS OVERVIEW |
| What is other transaction authority? |
| PROGESSIVE DESIGN BUILD w/OTA Overview |
| �Applicable Laws� |
| PDB w/OTA FHL, CA BARRACKS |
| Evaluation Process and Award Selection |
| Step 1: Request for Qualifications (RFQ) |
| Step 2: Pitch Presentations� |
| Selection of Single/Highest Qualified Firm |
| Step 3: Negotiations |
| Award |
| OBTAINING & SUBMITTING DOCUMENTS� |
| �Feedback� |
| Slide Number 32 |
| opportunities |
| Other Potential PROJECT OPPORTUNITIES |
| Ft Hunter Liggett water & wastewater collection system improvements |
| Ft Hunter Liggett water & wastewater collection system improvements |
| SACRAMENTO RESIDENT office overview |
| Slide Number 38 |
| Slide Number 39 |
| SPK Proposed OTA Strategy |
| What Questions do you have for us? |
File details come from the government source that posted it. Updated .