DTA Stormwater Retention Basin Market Survey 9.9.26.pdf
PDF 113 KB Posted
- Attached to
- Construction of the new Regional Storm Water Retention Basin at Detroit Arsenal, Warren, MI
- Solicitation number
- W912QR-27-DTA-SWRB
About this file
This is a presolicitation market survey for construction of a Regional Storm Water Retention Basin at Detroit Arsenal in Warren, Michigan. The U.S. Army Corps of Engineers is conducting market research to determine the number of interested contractors and to inform potential set-aside decisions for this project. A future Invitation for Bid (IFB) will be issued for Design-Bid-Build construction with an anticipated total project cost between $7.5 million and $8.5 million.
The project requires construction of a 43,000 cubic yard regional storm water retention basin with primary and secondary overflow systems, a new 635 linear foot 60-inch storm sewer pipe, site development, demolition, clearing and grubbing, soil erosion and sediment control measures, potential PFAS-contaminated soil mitigation (hauling approximately 21,500 cubic yards of excavated material to a State-certified landfill), utility relocation coordinating with DTE Energy and DTA DPW, and landscaping. The applicable NAICS code is 237110 (Water and Sewer Line and Related Structures Construction) and the Product Service Code is Y1NE (Construction of Water Supply Facilities). Contractors must submit responses by October 13, 2026 at 4:00 PM Eastern Time to Ms. Shanaye Davis at Shanaye.S.Davis@usace.army.mil. Responses must include company size status verification, Unique Identifier Number and CAGE Code(s), and descriptions of no more than three completed prime contractor projects within the past five years with minimum 20,000 cubic yards of excavation or similar scope. The submittal package shall not exceed 8 pages and include only narrative information. This is not a Request for Proposal and does not constitute a government commitment.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
As of 9/9/2026
Construction of the new Regional Storm Water Retention Basin at Detroit Arsenal, Warren, MI
A market survey is being conducted to determine if there are a reasonable number of interested business concerns to determine any future set-asides for this project. If your firm is a Small Business, certified HUBZone, 8A, Woman-Owned Small Business, Service-Disabled Veteran Owned Small Business, or Other than Small and you are interested in this project please respond appropriately. The intent of this future solicitation will be to select one Prime Contractor for the Design-Bid-Build (DBB) construction of a New Regional Storm Water Retention Basin at Detroit Arsenal, Warren, MI. An Invitation for Bid (IFB) will be the procurement mechanism for this construction action with an anticipated total project cost of $7.5M to $8.5M.
Project Location: Detroit Arsenal, Warren, MI 48092
Construct a 43,000 cubic yard regional storm water retention basin. Project includes a storm water basin with a storage capacity of approximately 43,000 CYD and primary and secondary overflow systems to capture runoff from the Arsenal’s watershed and control/restrict discharge. Project includes a new 635 L.F. 60" storm sewer pipe constructed from Arsenal Avenue to the proposed pond location to direct storm water to the basin. Supporting facilities include site development, demolition of existing pavement and utilities, clearing and grubbing, soil erosion and sediment control (utilizing silt fencing, inlet protection, and soil erosion control measures), potential PFAS-contaminated soil mitigation (hauling approximately 21,500 CYD of excavated material to a State of Michigan Certified Landfill), utility relocation (coordinating with DTE Energy and DTA DPW for relocation of electrical, gas, water, and communication lines), landscaping and turf establishment to blend in with the surrounding areas.
NAICS Code: 237110 - Water and Sewer Line and Related Structures Construction.
Product Service Code: Y1NE – Construction of Water Supply Facilities
All interested firms are asked to provide responses to this market survey. Each firm is asked to identify its size status (Other than Small, Small Business, certified HUBZONE, 8A, Woman- Owned Small Businesses or Service-Disabled Veteran Owned Business) as part of its response. Contractors should respond to this survey by email on 13 October 2026 by 4:00 PM Eastern Time.
Responses should include:
Identification and verification of the company’s size status to include small business status, if applicable.
Contractor’s Unique Identifier Number and CAGE Code(s).
Descriptions of Experience – Interested construction firms must provide no more than three (3) example projects with a fully complete construction of the project being substantially complete (approximately 90 percent complete) within the past five (5) years. Submitted projects should be examples of projects where the interested firm served as the Prime Contractor for the project.
Each project must include the name, title, project role, e-mail address, and telephone number of
As of 9/9/2026 at least one reference. References may be used to verify project size, scope, dollar value, percentages, and quality of performance. Example projects must be of similar size and scope.
a. Projects considered similar in scope to this project include construction of municipal or military stormwater retention/detention basins, heavy civil earthwork, installation of large-diameter concrete storm piping (48-inch or larger), utility relocation, and handling of contaminated soils.
b. Projects considered similar in size to this project include construction of a minimum of 20,000 cubic yards of excavation or earthwork operations.
c. Based on the information above, for each project submitted, include:
1. Current percentage of construction complete and the date when it was or will be completed.
2. Scope of the project.
3. Size of the project.
4. The dollar values of the construction contracts and whether it was design-bid build or design-build.
5. The aspects and dollar value of the construction that were self-performed as the Prime Contractor.
6. For each project, identify those design elements for which subcontractors were utilized.
NOTE: Total submittal package shall be no longer than 8 pages. Please only include a narrative of the requested information; additional information will not be reviewed.
Email responses to Ms. Shanaye Davis at Shanaye.S.Davis@usace.army.mil. If you have questions, please contact Shanaye Davis at Shanaye.S.Davis@usace.army.mil . This is NOT a Request for Proposal and does not constitute any commitment by the Government. Responses to this sources sought notice will be used by the Government to make appropriate acquisition planning decisions. All interested sources must respond to future solicitation announcements separately from responses to this market survey.
Link: https://forms.osi.apps.mil/r/XX6Nifc6pb mailto:Shanaye.S.Davis@usace.army.mil mailto:Shanaye.S.Davis@usace.army.mil https://forms.osi.apps.mil/r/XX6Nifc6pb
File details come from the government source that posted it. Updated .