This is a Draft Request for Qualifications (RFQ) for a Construction Manager at Risk (CMAR) contract to design and construct an Army Reserve Center (ARC) in Richmond, Virginia.

The U.S. Army Corps of Engineers (USACE) Louisville District will execute this acquisition using Other Transaction Authority (OTA) under 10 U.S.C. § 2808a. The project involves delivery of a fully functional 56,678 square-foot facility designed for up to 300 personnel, plus 1,217 square feet of unheated organizational storage. The facility will serve three units: a Ground Ambulance Company, Finance Company, and Training Command Headquarters, and must comply with all Unified Facilities Criteria (UFC), including Antiterrorism/Force Protection (AT/FP) standards and Army Sustainable Design and Development Policy. The acquisition is structured in two phases: Phase 1 (Preconstruction Advisory Services) and Phase 2 (Construction Execution). During Phase 1, the selected contractor will perform constructability reviews, finalize design to 100% completion, conduct open-book subcontractor outreach, and develop a Guaranteed Maximum Price (GMP) to be incorporated via bilateral modification. The Government retains an "Off-Ramp" provision allowing termination if GMP cannot be agreed upon or funding becomes unavailable, with the contractor retaining all preconstruction service payments and the Government retaining design deliverable rights.

The selection process employs a two-step Qualifications-Based Selection (QBS) approach: Step 1 consists of a public RFQ solicitation on SAM.Gov for approximately four weeks, limited to 10 pages (excluding supporting documentation), with down-selection of approximately three firms to Step 2; Step 2 involves individual pitch presentations lasting up to three hours, with 60 minutes for firm presentation and remaining time for government panel questions. Award will proceed to exclusive negotiations with the single most highly qualified firm. Evaluation criteria in order of importance are: (1) Past Performance on projects completed within the last 10 years, demonstrated through up to three submitted projects with CPARS evaluations, Past Performance Questionnaires, or letters of recommendation; (2) Technical Merit Narrative addressing Phase 1 preconstruction services, lean construction, subcontractor management, site coordination risks, and execution within a secure active military installation; and (3) Bonding and Financial Capacity (Pass/Fail requirement) verifying single-project bonding capacity of at least $100,000,000 and aggregate capacity of at least $250,000,000 from a Treasury-approved surety company. No pricing is evaluated during qualification selection; pricing for Phase 1 services is negotiated exclusively with the selected firm using an Independent Government Estimate (IGE) benchmark. Early Work Packages may be authorized for long-lead items (switchgear, transformers, structural steel) or site work once GMP is negotiated. Upon Phase 2 award, the contractor assumes at-risk responsibility for construction means, methods, schedule, and coordination, and must furnish performance and payment bonds covering the full construction value.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT REQUEST FOR QUALIFICATIONS: Provided for Informational Purposes Only.

Subject to Change.

Project: Construction of an Army Reserve Center (ARC) located at Richmond, VA

Authority: This acquisition will be executed using the Other Transaction Authority (OTA) at 10 U.S.C. § 2808a.

The U.S. Army Corps of Engineers (USACE) Louisville District plans to solicit and execute this requirement via Construction Manager at Risk (CMAR) with OTA. This Plan of Action establishes a comprehensive strategy for the design and construction of the Army Reserve Center located in Richmond, Virginia. The primary objective is to award an initial OTA for Preconstruction Advisory Services to the most highly qualified construction contractor when the design is at approximately 95% completion. The contractor will act as an expert consultant to help the Government and the Designer of Record (DOR) finalize the design to 100%, perform constructability reviews, conduct open-book subcontractor outreach, and establish a validated Guaranteed Maximum Price (GMP) to be incorporated into the agreement through a bilateral modification for Phase 2 construction execution.

1. PROJECT OVERVIEW

This acquisition will deliver a fully functional, 56,678 SF, 300-member Army Reserve Center (ARC) at Defense Supply Center – Richmond, VA. The facility will include Unheated Organizational Storage and key features that support future growth and modernization. The facility is specifically designed to serve three (3) units and localized consolidation effort that will enhance readiness and operational capability across multiple support units, including a Ground Ambulance Company, Finance Company, and the Training Command Headquarters.

The operational readiness of these units is essential for both training Army Reserve Soldiers and supporting units from which the Active component will draw upon for critical warfighting capabilities inherent to deployable combat forces.

1.1. Core Facilities include:

• Army Reserve Center (ARC): A 56,678 square-foot (SF) facility designed for the training and functional operations of up to 300 personnel.

• Unheated Organizational Storage: A 1,217 SF unheated storage facility.

1.2. Supporting Infrastructure & Specialized Systems include:

• Parking & Site Work: Includes site clearing and storm drainage. Work also consists of curbs, walks, lighting, signage, and parking,

• UFC Compliance: The entire facility complex will be designed and constructed to meet all applicable Unified Facilities Criteria (UFC), including AT/FP (Antiterrorism/Force

Protection) standards and sustainable design principles as outlined in the Army Sustainable Design and Development Policy.

2. Agreement Phase 1 Overview: Pre-Construction Services

The selected CMAR will act as an expert consultant to the Government, collaborating directly with USACE and the third-party A/E firm (DOR) during active design progression.

• Scope: The CMAR will perform constructability reviews and reports, evaluate design documents for operability, plan site logistics and sequencing, conduct local subcontractor outreach, and develop a comprehensive, live project schedule in Primavera P6.

• Purpose: The purpose of Phase 1 is to mitigate project risk; certify design and cost; and ensure that the parties are on a common path forward before establishing the final construction price.

• Open-Book Costing: The CMAR will develop a transparent, open-book cost model. All subcontractor bids, vendor quotes, labor/equipment rates, and detailed pricing data will be shared openly with USACE. This pricing will be continuously reconciled against the Government's Independent Government Estimate (IGE) using the MII cost database as the design progresses to 100%.

• Early Work Packages (EWPs): If critical long-lead systems (switchgear, transformers, or structural steel) must be ordered before the final design is 100% complete, the Agreements Officer may authorize separately funded EWPs or Limited Notices to Proceed, as soon as the GMP is negotiated. Site work may also be included as an EWP if determined to be in the Government’s best interest. These packages will establish the technical basis, pricing, cancellation exposure, and storage/insurance requirements to secure early fabrication slots without committing the Government to the full construction phase. EWPs will not be executed until after the GMP has been established and funding authorized.

• The Off-Ramp: The Government is not obligated to move into Phase 2 of the agreement.

If the parties are unable to reach an agreement on a fair and reasonable GMP, or if funding is unavailable, the Government retains the right to exercise its "Off-Ramp" provision. In an off-ramp scenario, the Government pays the contractor for all authorized preconstruction services performed to date and retains full rights to utilize the design deliverables to complete the project via alternative acquisition methods. Neither party is liable for anticipated profit on unawarded construction work.

3. Agreement Phase 2 Overview: Construction Services

• Scope: Agreement Phase 2 consists of the completion of all physical construction activities required to deliver the fully functional ARC in Richmond, Virginia.

• Pricing & Negotiation: The price for Agreement Phase 2 is established through the following process that occurs within Agreement Phase 1:

1. Upon sufficient design and pre-construction services in Phase 1, the contractor will submit a formal GMP proposal based on the validated open-book cost model.

The GMP is the absolute ceiling for the construction phase.

2. The Agreements Officer will lead formal negotiations to establish a fair and reasonable GMP.

• Award: If the parties successfully negotiate a fair and reasonable price, the Agreements

Officer will execute a bilateral modification to the OT Agreement, incorporating the GMP, funding the physical construction, and authorizing the contractor to go "At-Risk" for construction execution where the contractor assumes single-point responsibility for construction means, methods, schedule, and trade coordination. They will furnish the required performance and payment bonds covering the full value of the construction phase upon execution of Phase 2.

4. Selection Process

To maximize commercial agility and technical innovation, the Government will utilize a two-step, Qualifications-Based Selection (QBS) process under the authority of 10 U.S.C. § 2808a.

Price is not evaluated during the initial selection steps; instead, a fair and reasonable price for Agreement Phase 1 is negotiated exclusively with the most highly qualified firm.

4.1. Request for Statement of Qualifications

This initial phase serves as a rapid, credentials-focused down-select to identify a short list of the most credible and experienced builders.

The Request for Qualifications (RFQ) will be solicited publicly for approximately four (4) weeks on SAM.Gov via the PIEE Solicitation Module, allowing all responsible sources to submit responses. In addition, the Deputy for Small Business will provide this opportunity to non-traditional federal contractors, with a link to the SAM.Gov announcement. Draft articles may be included with the RFQ, in addition to the existing design.

To reduce industry submission burdens, submissions are limited to a format of 10 pages or less (excluding the surety letter, Contractor Performance Assessment Ratings - CPARS, PPQs, Letters of Recommendation). Submissions are evaluated against the criteria in Section 6.1. The Government intends to short list and invite a target of three (3) of the highest-qualified firms to Step 2 – Pitch Presentations.

4.2. Initial Evaluation and Down Select (Pitch Meeting Invites)

The government evaluation team will evaluate the qualification packages and advise the Agreements Officer on which firms should be invited to a Pitch Meeting. Neither consensus nor a majority vote is required, because the Agreements Officer will be the sole authority to make the determination. Any documentation created by the reviewers will be preserved.

The Agreements Officer will determine which firms demonstrate the highest potential in their qualifications package, document their rationale, and invite a target of three (3) of the highest qualified firms to participate in Pitch Presentations/Meetings.

4.3. Pitch Presentations

This step is the cornerstone of the evaluation, moving beyond a paper-based assessment to a direct evaluation of the team's expertise, problem-solving abilities, and collaborative chemistry. A target of three (3) of the highest qualified firms will be invited to individual, confidential, pitch presentation meetings. (The actual number of invites may be higher or lower based on the AO’s assessment of the relative quality of the submitted qualifications.)

Pitch presentation meetings will be held shortly after qualifications packages are due. The pitch presentation meetings will serve as the final competitive evaluation step.

Each pitch presentation is expected to last a maximum of three (3) hours. Firms will have 60 minutes to deliver an oral presentation about why they believe they are the best qualified firm to deliver the project. After 60 minutes, a panel of government reviewers will use the remaining time to ask questions about the qualifications package, presentation, and the firm’s capabilities. The firm may be asked to respond to hypothetical scenarios and potential innovative solutions to address the compressed timeframes of the customer. The Pitch Meetings are intended to be conversational, rather than a strict question and answer session.

Pitch presentations will include the Government Evaluation Team.

Nothing discussed during the pitch presentations will be legally binding on either party unless incorporated into the final agreement. Government reviewers will not disclose the identity of other firms, nor the contents of other firms’ qualifications packages/pitch presentations. However, if pitch presentation discussions result in changes to project requirements, all firms will be notified of the changes and given an opportunity to respond.

Based upon the evaluation of the pitch presentations, the Government will select one firm to enter negotiations with for the Articles and Agreement Phase 1 pricing.

4.4. Negotiation with the Most Highly Qualified Offeror & Award

The single, most highly qualified firm will be selected to enter exclusive negotiations. The AO will request a detailed price proposal for Phase I (pre-construction services) and negotiate the final design fee and Agreement Articles using an IGE as a benchmark. Either party may suggest changes to the draft articles. Upon agreement, the AO executes Phase I OTA. If the parties cannot reach an agreement, USACE reserves the right to discontinue negotiations and take any action determined to be in the Government’s best interest, including entering negotiations with another firm, revising the acquisition approach, or canceling the Request for Qualifications.

5. Requirements for Qualification Packages

The Government will evaluate the written RFQ submissions to identify a shortlist with a target of the three (3) most highly qualified offerors to advance to the pitch presentation phase. The following factors, listed in relative order of importance, will be evaluated:

5.1. Factor 1: Past Performance

The Offeror shall demonstrate relevant corporate experience on projects completed within the last ten (10) years from the issuance date of this solicitation.

To ensure a streamlined and comprehensive evaluation, submittals are restricted to the following parameters:

• Maximum Projects: A maximum of three (3) projects may be submitted for the

Construction Manager that best demonstrates the firm’s qualifications as they relate to the current acquisition. If more than three projects are submitted, only the first three in order of appearance will be evaluated.

• Required Format: Project details must be submitted on a single page per project, in accordance with the formatting rules above. At a minimum, firms should include the following details for each project:

• Project Name and Location

• Contract Number

• Unique Entity Identifier (UEI)/CAGE Code

• Role (i.e. Prime, Sub, JV Partner)

• Name of Customer/Agency/End User

• Delivery Method (e.g. D/B, D/B/B, CMAR, Progressive Design Build, Early

Contractor Involvement, etc.)

• MO/YR Construction Started and Completed

• % Cost and Time Growth from Initial Award

• Total Cost of Contract (if prime)/Total Cost of Performed Work (if sub)

• Scope Details

• Quality of Performance: For each submitted project, the Offeror must submit recent performance evaluations to demonstrate the quality of past work. Acceptable documentation includes:

• Completed Contractor Performance Assessment Reporting System (CPARS) evaluations.

• Past Performance Questionnaires (PPQs) utilizing Attachment 3 – Past Performance Questionnaire.

• Letters of Recommendation or direct, verifiable evidence of performance quality from the end-user.

• As noted in the table above, this information is not included in the 10-page limit.

5.1.1. Government Evaluation:

The Government will evaluate the depth, breadth, and relevance of the Offeror's corporate experience in relation to the solicited requirements. Projects that demonstrate successful completion of training centers, office buildings, headquarters, and/or school facilities may be evaluated more favorably.

Demonstrated experience utilizing collaborative project delivery methods will also be viewed more favorably. This includes experience with: Construction Management at Risk (CMAR), Progressive Design-Build (PDB), Integrated Design and Construction (IDaC), and Early Contractor Involvement (ECI). A consistent record of high-performance (e.g., "Exceptional" or "Very Good" ratings on CPARS/PPQs) will receive higher consideration during the evaluation team’s assessment.

5.2. Factor 2: Technical Merit Narrative

A written technical approach demonstrating how the firm will execute the specialized requirements of the Richmond Army Reserve Center. The narrative should provide a highly credible, realistic understanding of:

• Approach to executing Phase I preconstruction services, including value engineering and constructability reviews/reports, schedule integration and open-book cost estimating.

• Lean Construction and scheduling to prevent trade stacking on-site.

• Management of subcontractors during construction phase. Identify key subcontractors or specialty consultants and provide firm’s approach to expanding the local trade partner pool and mitigating regional labor shortages.

• Site, utility, permitting, and installation coordination risks and mitigation strategies.

• Executing seamless coordination within a secure, active installation, including access control, badging and gate logistics, heavy haul route deconfliction, Anti- Terrorism/Force Protection (AT/FP) posture compliance, and zero-disruption protocols for ongoing tenant missions and military convoy movements.

5.2.1. Government Evaluation:

The Government will evaluate the depth, credibility, and feasibility of the Offeror's technical approach in executing the highly specialized requirements of the Richmond Army Reserve Center. The evaluation will assess how well the proposed narrative demonstrates a realistic understanding of active military installation constraints and regional civil challenges.

6. Other Requirements

6.1. Bonding and Financial Capacity:

Verifiable evidence of the required bonding capacity to execute the project. The offeror's surety letters must confirm a single-project bonding capacity of at least $100,000,000 ($100M) and an aggregate capacity of at least $250,000,000 ($250M) from a bonding company on the approved Treasury list available at https://fiscal.treasury.gov/about-us/doing-business-with-fiscal-service/surety-bonds/list-certified-companies.

6.1.1. Government Evaluation:

This is evaluated on a Pass/Fail compliance basis. Offerors failing to submit verified evidence meeting this standard will be excluded from further evaluation.

https://fiscal.treasury.gov/about-us/doing-business-with-fiscal-service/surety-bonds/list-certified-companies https://fiscal.treasury.gov/about-us/doing-business-with-fiscal-service/surety-bonds/list-certified-companies

Authority: This acquisition will be executed using the Other Transaction Authority (OTA) at 10 U.S.C. § 2808a.
The U.S. Army Corps of Engineers (USACE) Louisville District plans to solicit and execute this requirement via Construction Manager at Risk (CMAR) with OTA. This Plan of Action establishes a comprehensive strategy for the design and construction of th...
2. Agreement Phase 1 Overview: Pre-Construction Services
Scope: Agreement Phase 2 consists of the completion of all physical construction activities required to deliver the fully functional ARC in Richmond, Virginia.
4. Selection Process
5.2. Factor 2: Technical Merit Narrative
5.2.1. Government Evaluation: