This file is the Specifications Volume 3 of 4 for a Design-Bid-Build construction project to build an Aeromedical Evacuation Squadron (AES) training facility at Joint Base Charleston, South Carolina under Solicitation W912QR26BA019. The specifications cover Divisions 21-25 and partial Divisions 26-33, detailing construction standards and product requirements. Key requirements include: wet pipe sprinkler fire suppression systems designed to NFPA 13 standards with a minimum density of 0.3 gpm per square foot over 2,500 square feet, hydraulically calculated based on a water supply test showing 69 psi static and 44 psi residual pressure at 835 gpm; general plumbing systems per ICC IPC including fixtures, backflow prevention assemblies, and water distribution with minimum 25 percent recycled content for steel pipe; HVAC systems with common piping, thermal insulation, and commissioning; integrated automation with cybersecurity controls for lighting, fire alarm, and utility monitoring; electrical distribution, lightning protection, and interior/exterior lighting; telecommunications cabling; fire alarm and mass notification systems; earthwork and site utilities including water distribution, sanitary sewerage, and stormwater management.

The contractor must submit shop drawings, product data, and hydraulic calculations for the sprinkler system prepared by a NICET Level III-certified sprinkler designer and reviewed by a licensed Professional Engineer with fire protection engineering credentials. All materials and equipment must be listed or approved by a Nationally Recognized Testing Laboratory (NRTL) such as UL or FM Global. Pre-Government testing and final Government testing are required before system acceptance. The specifications reference numerous standards including ASME, ASTM, NFPA, AWWA, and NSF/ANSI for materials, equipment, installation, and testing. The contract is a firm-fixed-price, unrestricted procurement with a duration of 1,150 calendar days from the Administrative Notice to Proceed, issued by the U.S. Army Corps of Engineers Louisville District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation For Aeromedical Evacuation Squadron (AES) Joint Base Charleston, SC

P2: 517646

Design-Bid-Build

Specifications - Vol 3 of 4 (Div 21-25)

Certified Final Design 14 July 2026

W912QR26BA019

RRS-A: 200A Disposition: Maintain for 15 yrs after construction.

W912QR26BA019_Specs_Vol3-0000

Aeromedical Evacuation Squadron (AES), JB Charleston, SC P2 517646

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 80 00.00 06 04/21, CHG 1: 06/23 SPECIAL PROVISIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 32 01.00 06 10/23 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29.00 06 11/17 SUSTAINABILITY REPORTING

01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 04.10 06 CONTRACTOR QUALITY CONTROL

01 45 35 05/24 SPECIAL INSPECTIONS

01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19.00 06 04/20 TEMPORARY ENVIRONMENTAL CONTROLS AND

PERMITS

01 74 19 JBC (Oct 2024) CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 23 05/23 OPERATION AND MAINTENANCE DATA

01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING

01 91 19 05/2023 BUILDING ENCLOSURE COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 08/22 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 02/19, CHG 8: 05/24 CAST-IN-PLACE CONCRETE

03 70 00 02/10, CHG 2: 08/20 MASS CONCRETE

DIVISION 04 - MASONRY

04 20 00 05/25 UNIT MASONRY

DIVISION 05 - METALS

05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY

ANCHORS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 30 00 05/15, CHG 2: 08/18 STEEL DECKS

05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING

05 50 13 08/24, CHG 1: 08/25 MISCELLANEOUS METAL FABRICATIONS

05 51 00 08/23 METAL STAIRS

05 52 00 08/23 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16, CHG 3: 05/25 ROUGH CARPENTRY

06 41 16.00 10 08/25 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

PROJECT TABLE OF CONTENTS Page 1

CERTIFIED FINAL

SPECIFICATIONS VOLUME 1 OF 4

SPECIFICATIONS VOLUME 2 OF 4

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 08/23 BOARD AND BLOCK INSULATION

07 27 10 08/23 BUILDING AIR BARRIER SYSTEM

07 27 19.01 08/23, CHG 1: 08/24 SELF-ADHERING AIR BARRIERS

07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 60 00 08/23 FLASHING AND SHEET METAL

07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/23 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES

08 14 00 08/16, CHG 1: 08/18 WOOD DOORS

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS

08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND

STOREFRONTS

08 51 13 05/19 ALUMINUM WINDOWS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL LOUVERS

DIVISION 09 - FINISHES

09 22 00 08/24 SUPPORTS GYPSUM BOARD

09 29 00 08/24 GYPSUM BOARD

09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 08/20 ACOUSTICAL CEILINGS

09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING

09 65 00 11/24 RESILIENT FLOORING

09 68 00 11/17, CHG 2: 08/20 CARPETING

09 90 00 02/21 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.20 08/20 INTERIOR SIGNAGE

10 21 13 08/20 TOILET COMPARTMENTS

10 22 39 08/20 FOLDING PANEL PARTITIONS

10 26 00 08/20 WALL AND DOOR PROTECTION

10 28 13 08/20 TOILET ACCESSORIES

10 44 16 11/19 FIRE EXTINGUISHERS

10 51 13 08/24 LOCKERS

DIVISION 12 - FURNISHINGS

12 24 13 08/20 ROLLER WINDOW SHADES

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 73 05/25 SEISMIC CONTROL FOR NONSTRUCTURAL

COMPONENTS

DIVISION 14 - CONVEYING EQUIPMENT

14 24 23 05/16 HYDRAULIC PASSENGER ELEVATORS

PROJECT TABLE OF CONTENTS Page 2

CERTIFIED FINAL

DIVISION 21 - FIRE SUPPRESSION

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

DIVISION 22 - PLUMBING

22 00 00 05/24 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, VIBRATION, AND

SEISMIC CONTROL

22 14 29.00 02/23 SUMP PUMPS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 05/22, CHG 1: 02/24 COMMON PIPING FOR HVAC

23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC

23 05 93.00 06 08/16 TESTING, ADJUSTING, AND BALANCING

(TAB) OF HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00 05/23 COMMISSIONING OF MECHANICAL AND

PLUMBING SYSTEMS

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 21 23 08/17 HYDRONIC PUMPS

23 23 00 08/21 REFRIGERANT PIPING

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 64 26 08/09, CHG 7: 02/24 CHILLED, CHILLED-HOT, AND CONDENSER

WATER PIPING SYSTEMS

23 74 33 05/24 DEDICATED OUTDOOR AIR SYSTEMS (DOAS)

23 81 00 05/24 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 83 00.00 20 04/06 ELECTRIC SPACE HEATING EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 08/24 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS - LIGHTING CONTROLS

25 05 11.02 08/24 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS - FIRE ALARM & MASS

NOTIFICATION SYSTEM

25 05 11.03 08/24 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS - UTILITY MONITORING

AND CONTROL SYSTEM

25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM

(UMCS) FRONT END AND INTEGRATION

DIVISION 26 - ELECTRICAL

26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL

EQUIPMENT

26 05 73 08/23 POWER SYSTEM STUDIES

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,

MEDIUM-VOLTAGE TRANSFORMERS

26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM

PROJECT TABLE OF CONTENTS Page 3

CERTIFIED FINAL

SPECIFICATIONS VOLUME 3 OF 4

SPECIFICATIONS VOLUME 4 OF 4

26 29 23 02/26 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 41 00 08/23 LIGHTNING PROTECTION SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 00 08/21 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 08/20 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00.00 06 05/24 EARTHWORK

31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK

31 62 13.20 11/20, CHG 2: 02/24 PRECAST/PRESTRESSED CONCRETE PILES

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 23 05/22 AGGREGATE BASE COURSE

32 12 13 05/24 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 13 13.06 06 06/18 PORTLAND CEMENT CONCRETE PAVEMENT FOR

ROADS AND SITE FACILITIES

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 08/16 PAVEMENT MARKINGS

32 92 19 08/17, CHG 1: 08/21 SEEDING

32 92 23 04/06 SODDING

DIVISION 33 - UTILITIES

33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING

33 30 00 05/18 SANITARY SEWERAGE

33 32 16 11/19, CHG 1: 11/23 PACKAGED UTILITY STORMWATER PUMPING

STATIONS

33 40 00 11/21 STORMWATER UTILITIES

33 61 13.13 02/16 PREFABRICATED UNDERGROUND HYDRONIC

ENERGY DISTRIBUTION

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

SECTION TABLE OF CONTENTS

DIVISION 21 - FIRE SUPPRESSION

SECTION 21 13 13

WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION

08/20

PART 1 GENERAL

1.1 REFERENCES

1.2 SYSTEM DESCRIPTION

1.2.1 Hydraulic Design

1.2.1.1 Basis for Calculations

1.2.1.2 Hydraulic Calculations

1.2.1.3 Design Criteria

1.2.2 Sprinkler Coverage

1.2.3 Qualified Fire Protection Engineer (QFPE)

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Preconstruction Submittals

1.4.1.1 Shop Drawing

1.4.1.2 Product Data

1.4.1.3 Hydraulic Calculations

1.4.1.4 Operating and Maintenance (O&M) Instructions

1.4.2 Qualifications

1.4.2.1 Sprinkler System Designer

1.4.2.2 Sprinkler System Installer

1.4.3 Regulatory Requirements

1.5 DELIVERY, STORAGE, AND HANDLING

1.6 EXTRA MATERIALS

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

2.1.1 Standard Products

2.1.2 Nameplates

2.1.3 Identification and Marking

2.1.4 Pressure Ratings

2.2 UNDERGROUND PIPING COMPONENTS

2.2.1 Pipe

2.2.2 Fittings and Gaskets

2.2.3 Gate Valve and Indicator Posts

2.2.4 Valve Boxes

2.2.5 Buried Utility Warning and Identification Tape

2.3 ABOVEGROUND PIPING COMPONENTS

2.3.1 Steel Piping Components

2.3.1.1 Steel Pipe

2.3.1.2 Fittings

2.3.1.3 Grooved Mechanical Joints and Fittings

2.3.1.4 Flanges

2.3.2 Copper Tube Components

2.3.2.1 Copper Tube

2.3.2.2 Copper Fittings and Joints

SECTION 21 13 13 Page 1

2.3.3 Flexible Sprinkler Hose

2.3.4 Pipe Hangers and Supports

2.3.5 Valves

2.3.5.1 Control Valve

2.3.5.2 Check Valves

2.3.5.3 Hose Valve

2.3.6 Riser Check Valves

2.4 ALARM INITIATING AND SUPERVISORY DEVICES

2.4.1 Sprinkler Alarm Switch

2.4.2 Valve Supervisory (Tamper) Switch

2.5 BACKFLOW PREVENTION ASSEMBLY

2.5.1 Backflow Preventer Test Connection

2.6 FIRE DEPARTMENT CONNECTION

2.7 SPRINKLERS

2.7.1 Pendent Sprinkler

2.7.2 Upright Sprinkler

2.7.3 Sidewall Sprinkler

2.8 ACCESSORIES

2.8.1 Sprinkler Cabinet

2.8.2 Pendent Sprinkler Escutcheon

2.8.3 Pipe Escutcheon

2.8.4 Sprinkler Guard

2.8.5 Relief Valve

2.8.6 Air Vent

2.8.7 Identification Sign

PART 3 EXECUTION

3.1 VERIFYING ACTUAL FIELD CONDITIONS

3.2 INSTALLATION

3.2.1 Waste Removal

3.3 UNDERGROUND PIPING INSTALLATION

3.4 ABOVEGROUND PIPING INSTALLATION

3.4.1 Protection of Piping Against Earthquake Damage

3.4.2 Piping in Exposed Areas

3.4.3 Piping in Finished Areas

3.4.4 Pendent Sprinklers

3.4.5 Upright Sprinklers

3.4.6 Pipe Joints

3.4.7 Reducers

3.4.8 Pipe Penetrations

3.4.9 Escutcheons

3.4.10 Inspector's Test Connection

3.4.11 Backflow Preventer

3.4.11.1 Test Connection

3.4.12 Drains

3.4.13 Installation of Fire Department Connection

3.4.14 Identification Signs

3.5 ELECTRICAL

3.6 PAINTING

3.7 FIELD QUALITY CONTROL

3.7.1 Test Procedures

3.7.2 Pre-Government Testing

3.7.2.1 Verification of Compliant Installation

3.7.2.2 Request for Government Final Test

3.7.3 Correction of Deficiencies

3.7.4 Government Final Tests

3.8 MINIMUM SYSTEM TESTS

3.8.1 Underground Piping

SECTION 21 13 13 Page 2

3.8.1.1 Flushing

3.8.1.2 Hydrostatic Test

3.8.2 Aboveground Piping

3.8.2.1 Hydrostatic Test

3.8.2.2 Backflow Prevention Assembly Forward Flow Test

3.8.3 Main Drain Flow Test

3.9 SYSTEM ACCEPTANCE

3.10 ONSITE TRAINING

-- End of Section Table of Contents --

SECTION 21 13 13 Page 3

SECTION 21 13 13

WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION

DELEGATED DESIGN

08/20

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B16.1 (2020) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250

ASME B16.3 (2021) Malleable Iron Threaded Fittings, Classes 150 and 300

ASME B16.4 (2021) Gray Iron Threaded Fittings;

Classes 125 and 250

ASME B16.18 (2021) Cast Copper Alloy Solder Joint Pressure Fittings

ASME B16.21 (2021) Nonmetallic Flat Gaskets for Pipe Flanges

ASME B16.22 (2021) Wrought Copper and Copper Alloy Solder Joint Pressure Fittings

ASME B16.26 (2024) Cast Copper Alloy Fittings for Flared Copper Tubes

AMERICAN SOCIETY OF SANITARY ENGINEERING (ASSE)

ASSE 1013 (2021) Performance Requirements for Reduced Pressure Principle Backflow Prevention Assemblies

ASSE 1015 (2021) Performance Requirements for Double Check Backflow Prevention Assemblies

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C104/A21.4 (2022) Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water

AWWA C110/A21.10 (2021) Ductile-Iron and Gray-Iron Fittings

AWWA C111/A21.11 (2023) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings

AWWA C203 (2020) Coal-Tar Protective Coatings and

SECTION 21 13 13 Page 4

Linings for Steel Water Pipe

AWWA M14 (2024) Manual: Recommended Practice for Backflow Prevention and Cross-Connection Control

ASTM INTERNATIONAL (ASTM)

ASTM A47/A47M (1999; R 2022; E 2022) Standard Specification for Ferritic Malleable Iron Castings

ASTM A53/A53M (2024) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A135/A135M (2021) Standard Specification for Electric-Resistance-Welded Steel Pipe

ASTM A153/A153M (2023) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware

ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts

ASTM A536 (2024) Standard Specification for Ductile Iron Castings

ASTM B62 (2017) Standard Specification for Composition Bronze or Ounce Metal Castings

ASTM B75/B75M (2020) Standard Specification for Seamless Copper Tube

ASTM B88 (2022) Standard Specification for Seamless Copper Water Tube

FM GLOBAL (FM)

FM APP GUIDE (updated on-line) Approval Guide https://www.approvalguide.com/

INTELLIGENCE COMMUNITY STANDARD (ICS)

ICS 705-1 (2010) Physical and Technical Security Standard for Sensitive Compartmented Information Facilities

MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS

INDUSTRY (MSS)

MSS SP-71 (2018) Gray Iron Swing Check Valves, Flanged and Threaded Ends

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 13 (2025; TIA 24-3) Standard for the Installation of Sprinkler Systems

SECTION 21 13 13 Page 5

NFPA 13R (2025) Standard for the Installation of Sprinkler Systems in Low-Rise Residential Occupancies

NFPA 24 (2025) Standard for the Installation of Private Fire Service Mains and Their Appurtenances

NFPA 101 (2024) Life Safety Code

NFPA 291 (2025) Recommended Practice for Fire Flow Testing and Marking of Hydrants

NFPA 1963 (2019) Standard for Fire Hose Connections

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES

(NICET)

NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler System Layout

UL SOLUTIONS (UL)

UL 199 (2022; Reprint Feb 2025) UL Standard for Safety Automatic Sprinklers for Fire-Protection Service

UL 262 (2004; Reprint Jul 2023) Gate Valves for Fire-Protection Service

UL 312 (2022) UL Standard for Safety Check Valves for Fire-Protection Service

UL 405 (2013; Reprint Dec 2024) UL Standard for Safety Fire Department Connection Devices

UL 668 (2025) UL Standard for Safety Hose Valves for Fire-Protection Service

UL 789 (2004; Reprint May 2024) UL Standard for Safety Indicator Posts for Fire-Protection Service

UL Fire Prot Dir UL Product IQ (updated online) at https://productiq.ulprospector.com/en

1.2 SYSTEM DESCRIPTION

Provide wet pipe sprinkler system(s) in all areas of the building .

Except as modified herein, the system must meet the requirements of NFPA 13 .

Pipe sizes which are not indicated on the Contract drawings must be determined by hydraulic calculations.

SECTION 21 13 13 Page 6

1.2.1 Hydraulic Design

1.2.1.1 Basis for Calculations

A waterflow test was performed on 03 October 2024 at Joint Base Charleston in Charleston, South Carolina and resulted in a static pressure of 69 psi with a residual pressure of 44 psi while flowing 835 gpm at each of two separate flowing hydrants. Perform a fire hydrant flow test prior to shop drawing submittal in accordance with NFPA 291 . Results must include hydrant elevations relative to the building and hydrant number/identifiers for the tested hydrants, including which were flowed, which had a gauge.

This information must be presented in a tabular form if multiple hydrants were flowed. The results must be included with the hydraulic calculations. Hydraulic calculations must be based on flow test noted in this paragraph, unless approved by Contracting Officer. Hydraulic calculations must be based upon the Hazen-Williams formula with a "C" value noted in NFPA 13 for piping, and 140 for existing underground piping.

The minimum residual pressure in a service lateral (lead-in) at the design flow rate must be 20 psi at the inlet to the backflow preventer.

1.2.1.2 Hydraulic Calculations

a. Water supply curves and system requirements must be plotted on semi-logarithmic graph (N^1.85) paper so as to present a summary of the complete hydraulic calculation.

b. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, minimum discharge pressures and minimum flows. Elevations of hydraulic reference points (nodes) must be indicated.

c. Documentation must identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe.

d. Where the sprinkler system is supplied by interconnected risers, the sprinkler system must be hydraulically calculated using the hydraulically most demanding single riser. The calculations must not assume the simultaneous use of more than one riser.

e. All calculations must include the backflow preventer manufacturer's stated friction loss at the design flow or 8 psi for double check backflow preventer, whichever is greater.

f. All calculations must be performed back to the actual location of the flow test, taking into account the direction of flow in the service main at the test location.

g. For gridded systems, calculations must show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. A flow diagram indicating the quantity and direction of flows must be included.

1.2.1.3 Design Criteria

Hydraulically design the system to discharge a minimum density of 0.3 gpm/square foot over the hydraulically most demanding 2500 square feet of

SECTION 21 13 13 Page 7 floor area as indicated on the drawings. Hydraulic calculations must be in accordance with the Area/Density Method of NFPA 13 . Add an allowance for exterior hose streams of 500 gpm to the sprinkler system demand at the fire hydrant shown on the drawings closest to the point where the water service enters the building .

1.2.2 Sprinkler Coverage

Sprinklers must be uniformly spaced on branch lines. Provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms (regardless of the fire resistance rating of the enclosure), boiler rooms, switchgear rooms, transformer rooms, attached electrical vaults and other electrical and mechanical spaces. Coverage per sprinkler must be in accordance with NFPA 13 . Provide sprinklers below all obstructions in accordance with NFPA 13 . Exceptions are as follows:

a. Sprinklers may be omitted from small rooms which are exempted for specific occupancies in accordance with NFPA 101 .

b. Facilities that are designed in accordance with NFPA 13R.

1.2.3 Qualified Fire Protection Engineer (QFPE)

An individual who is a licensed professional engineer (P.E.) who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveying (NCEES) and has relevant fire protection engineering experience. Services of the QFPE must include:

a. Reviewing SD-02, SD-03, and SD-05 submittal packages for completeness and compliance with the provisions of this specification. Working (shop) drawings and calculations must be prepared by, or prepared under the immediate supervision of, the QFPE. The QFPE must affix their professional engineering stamp with signature to the shop drawings, calculations, and material data sheets, indicating approval prior to submitting the shop drawings to the DFPE.

b. Provide a letter documenting that the SD-02, SD-03, and SD-05 submittal package has been reviewed and noting all outstanding comments.

c. Performing in-progress construction surveillance prior to installation of ceilings (rough-in inspection).

d. Witnessing pre-Government and final Government functional performance testing and performing a final installation review.

e. Signing applicable certificates under SD-07.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Partial submittals and submittals not fully complying with NFPA 13 and this specification section must be returned disapproved without review. SD-02, SD-03 and SD-05 must be submitted simultaneously.

SECTION 21 13 13 Page 8

Shop drawings (SD-02), product data (SD-03) and calculations (SD-05) must be prepared by the designer and combined and submitted as one complete package. The QFPE must review the SD-02/SD-03/SD-05 submittal package for completeness and compliance with the Contract provisions prior to submission to the Government. The QFPE must provide a Letter of Confirmation that they have reviewed the submittal package for compliance with the contract provisions. This letter must include their professional engineer stamp and signature. Partial submittals and submittals not reviewed by the QFPE must be returned disapproved without review.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Qualified Fire Protection Engineer (QFPE) ; G, AE

Sprinkler System Designer ; G, AE

Sprinkler System Installer ; G, AE

SD-02 Shop Drawings

Shop Drawing ; G, AE

SD-03 Product Data

Pipe ; G, AE

Fittings ; G, AE

Valves , including gate, check, butterfly, and globe; G, AE

Relief Valves ; G, AE

Sprinklers ; G, AE

Pipe Hangers and Supports ; G, AE

Sprinkler Alarm Switch ; G, AE

Valve Supervisory (Tamper) Switch ; G, AE

Fire Department Connection ; G, AE

Backflow Prevention Assembly ; G, AE

Air Vent ; G, AE

Hose Valve ; G, AE

Seismic Bracing ; G, AE

Nameplates ; G, AE

SD-05 Design Data

Seismic Bracing ; G, AE

SECTION 21 13 13 Page 9

Load calculations for sizing of seismic bracing

Hydraulic Calculations ; G, AE

SD-06 Test Reports

Test Procedures ; G, AE

SD-07 Certificates

Verification of Compliant Installation ; G, AE

Request for Government Final Test ; G, AE

SD-10 Operation and Maintenance Data

Operating and Maintenance (O&M) Instructions ; G, RO

Spare Parts Data; G, RO

SD-11 Closeout Submittals

As-built drawings

1.4 QUALITY ASSURANCE

1.4.1 Preconstruction Submittals

Within 36 days of contract award but no less than 28 days prior to commencing work on site, the prime Contractor must submit the following for review and approval. SD-02, SD-03 and SD-05 submittals received prior to the review and approval of the qualifications will be returned Disapproved Without Review.

1.4.1.1 Shop Drawing

Six copies of the shop drawings, no later than 28 days prior to the start of system installation. Working drawings conforming to the requirements prescribed in NFPA 13 and must be no smaller than the Contract Drawings.

Each set of drawings must include the following:

a. A descriptive index with drawings listed in sequence by number. A legend sheet identifying device symbols, nomenclature, and conventions used in the package.

b. Floor plans drawn to a scale not less than 1/8-inch equals 1-foot clearly showing locations of devices, equipment, risers, and other details required to clearly describe the proposed arrangement.

c. Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from walls to branch lines; from sprinkler feed mains, cross mains and branch lines to finished floor and roof or ceiling. A detail must show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.

d. Longitudinal and transverse building sections showing typical branch line and cross main pipe routing, elevation of each typical sprinkler above finished floor and elevation of "cloud" or false ceilings in

SECTION 21 13 13 Page 10 relation to the building ceilings.

e. Plan and elevation views which establish that the equipment will fit the allotted spaces with clearance for installation and maintenance.

f. Riser layout drawings drawn to a scale of not less than 1/2-inch equals 1-foot to show details of each system component, clearances between each other and from other equipment and construction in the room.

g. Details of each type of riser assembly, pipe hanger, sway bracing for earthquake protection, and restraint of underground water main at point-of-entry into the building, and electrical devices and interconnecting wiring. The dimension from the edge of vertical piping to the nearest adjacent wall(s) must be indicated on the drawings when vertical piping is located in stairs or other portions of the means of egress.

h. Details of each type of pipe hanger, seismic bracing/restraint and related components.

1.4.1.2 Product Data

Six copies of annotated catalog data to show the specific model, type, and size of each item. Catalog cuts must also indicate the NRTL listing. The data must be highlighted to show model, size, options, and other pertinent information, that are intended for consideration. Data must be adequate to demonstrate compliance with all contract requirements. Product data for all equipment must be combined into a single submittal.

1.4.1.3 Hydraulic Calculations

Calculations must be as outlined in NFPA 13 except that calculations must be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings.

Calculations must include isometric diagram indicating hydraulic nodes and pipe segments.

1.4.1.4 Operating and Maintenance (O&M) Instructions

Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA as supplemented and modified by this specification section.

Provide six manuals and one pdf version on electronic media. The manuals must include the manufacturer's name, model number, parts list, list of parts and tools that should be kept in stock by the owner for routine maintenance, troubleshooting guide, and recommended service organization (including address and telephone number) for each item of equipment. Each service organization submitted must be capable of providing 2-hour on-site response to a service call on an emergency basis.

Submit spare parts data for each different item of material and equipment specified. The data must include a complete list of parts and supplies, and a list of parts recommended by the manufacturer to be replaced after 1-year and 3 years of service. Include a list of special tools and test equipment required for maintenance and testing of the products supplied.

SECTION 21 13 13 Page 11

1.4.2 Qualifications

1.4.2.1 Sprinkler System Designer

The sprinkler system designer must be certified as a Level III Technician by National Institute for Certification in Engineering Technologies (NICET) in the Water-Based Systems Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 .

1.4.2.2 Sprinkler System Installer

The sprinkler system installer must be regularly engaged in the installation of the type and complexity of system specified in the contract documents, and must have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.4.3 Regulatory Requirements

Equipment and material must be listed or approved. Listed or approved, as used in this Section, means listed, labeled or approved by a Nationally Recognized Testing Laboratory (NRTL) such as UL Fire Prot Dir or FM APP GUIDE. The omission of these terms under the description of an item or equipment described must not be construed as waiving this requirement. All listings or approvals by testing laboratories must be from an existing ANSI or UL published standard. The recommended practices stated in the manufacturer's literature or documentation are mandatory requirements.

1.5 DELIVERY, STORAGE, AND HANDLING

Protect all equipment delivered and placed in storage from the weather, excessive humidity and temperature variations, dirt and dust, or other contaminants. All pipes must be either capped or plugged until installed.

1.6 EXTRA MATERIALS

Spare sprinklers and wrench(es) must be provided as spare parts in accordance with NFPA 13 .

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

2.1.1 Standard Products

Provide materials, equipment, and devices listed for fire protection service when so required by NFPA 13 or this specification. Select material from one manufacturer, where possible, and not a combination of manufacturers, for a classification of material. Material and equipment must be standard products of a manufacturer regularly engaged in the manufacture of the products for at least 2 years prior to bid.

2.1.2 Nameplates

Major components of equipment must have the manufacturer's name, address, type or style, model or serial number, catalog number, date of installation, installing Contractor's name and address, and the contract number provided on a new name plate permanently affixed to the item or

SECTION 21 13 13 Page 12 equipment. Nameplates must be etched metal or plastic, permanently attached by screws to control units, panels or adjacent walls.

2.1.3 Identification and Marking

Pipe and fitting markings must include name or identifying symbol of manufacturer and nominal size. Pipe must be marked with ASTM designation. Valves and equipment markings must have name or identifying symbol of manufacturer, specific model number, nominal size, name of device, arrow indicating direction of flow, and position of installation (horizontal or vertical), except if valve can be installed in either position. Markings must be included on the body casting or on an etched or stamped metal nameplate permanently on the valve or cover plate.

2.1.4 Pressure Ratings

Valves, fittings, couplings, alarm switches, and similar devices must be rated for the maximum working pressures that can be experienced in the system, but in no case less than 175 psi.

2.2 UNDERGROUND PIPING COMPONENTS

2.2.1 Pipe

Pipe must comply with NFPA 24 . Minimum pipe size is 6 inches. Piping more than 5 feet outside the building walls must comply with Section 33 11 00 WATER UTILITY DISTRIBUTION PIPING. A continuous section of welded stainless steel fire water service piping from a point outside the building perimeter to a flanged fitting at least 1-foot above the finished floor within the building is acceptable.

2.2.2 Fittings and Gaskets

Fittings must be ductile-iron conforming to AWWA C110/A21.10 with cement mortar lining conforming to AWWA C104/A21.4 . Gaskets must be suitable in design and size for the pipe with which such gaskets are to be used.

Gaskets for ductile-iron pipe joints must conform to AWWA C111/A21.11 .

2.2.3 Gate Valve and Indicator Posts

Installation must comply with NFPA 24 . Gate valves for use with indicator post must conform to UL 262 . Indicator posts must conform to UL 789 .

Provide each indicator post with one coat of primer and two coats of red enamel paint.

2.2.4 Valve Boxes

Except where indicator posts are provided, for each buried valve, provide a cast-iron, ductile-iron, or plastic valve box of a suitable size.

Plastic boxes must be constructed of acrylonitrile-butadiene-styrene (ABS) or inorganic fiber-reinforced black polyolefin. Provide cast-iron, ductile-iron, or plastic cover for valve box with the word "WATER" cast on the cover. The minimum box shaft diameter must be 5.25 inches. Coat cast-iron and ductile-iron boxes with bituminous paint applied to a minimum dry-film thickness of 10 mils.

2.2.5 Buried Utility Warning and Identification Tape

Provide detectable aluminum foil plastic backed tape or detectable

SECTION 21 13 13 Page 13 magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape must be detectable by an electronic detection instrument. Provide tape, 3 inches minimum width, color coded for the utility involved with warning and identification imprinted in bold block letters continuously and repeatedly over the entire tape length.

Warning and identification must read "CAUTION BURIED WATER PIPING BELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material.

2.3 ABOVEGROUND PIPING COMPONENTS

2.3.1 Steel Piping Components

2.3.1.1 Steel Pipe

Except as modified herein, steel pipe must be black as permitted by NFPA 13 and conform to the applicable provisions of ASTM A53/A53M, ASTM A135/A135M or ASTM A153/A153M .

Steel pipe must be minimum Schedule 40 for sizes 2 inches and less; and minimum Schedule 10 for sizes larger than 2 inches. Steel piping with wall thickness less than Schedule 40 must not be threaded or cut-grooved.

2.3.1.2 Fittings

Fittings must be welded, threaded, or grooved-end type. Threaded fittings must be cast-iron conforming to ASME B16.4 , malleable-iron conforming to ASME B16.3 or ductile-iron conforming to ASTM A536. Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe, steel press fittings and field welded fittings are not permitted. Fittings, mechanical couplings, and rubber gaskets must be supplied by the same manufacturer. Threaded fittings must use Teflon tape or manufacturer's approved joint compound. Saddle tees using rubber gasketed fittings are permitted only when connecting to existing piping for additions or modifications. Saddle tees must use a connection method that completely wraps around the pipe. Reducing couplings are not permitted except as allowed by NFPA 13 .

2.3.1.3 Grooved Mechanical Joints and Fittings

Joints and fittings must be designed for not less than 175 psi service and the product of the same manufacturer. Field welded fittings must not be used. Fitting and coupling housing must be malleable-iron conforming to ASTM A47/A47M, Grade 32510; ductile-iron conforming to ASTM A536, Grade 65-45-12. Rubber gasketed grooved-end pipe and fittings with mechanical couplings are permitted in pipe sizes 2 inches and larger. Gasket must be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts must be heat-treated steel conforming to ASTM A183 and must be cadmium-plated or zinc-electroplated.

2.3.1.4 Flanges

Flanges must conform to NFPA 13 and ASME B16.1 . Gaskets must be non-asbestos compressed material in accordance with ASME B16.21 , 1/16-inch thick, and full face or self-centering flat ring type.

SECTION 21 13 13 Page 14

2.3.2 Copper Tube Components

2.3.2.1 Copper Tube

Copper tube must conform to ASTM B88, Types L and M.

2.3.2.2 Copper Fittings and Joints

Cast copper alloy solder-joint pressure fittings must conform to ASME B16.18 and wrought copper and bronze solder-joint pressure fittings must conform to ASME B16.22 and ASTM B75/B75M. Cast copper alloy fittings for flared copper tube must conform to ASME B16.26 and ASTM B62. Brass or bronze adapters for brazed tubing may be used for connecting tubing to flanges and to threaded ends of valves and equipment.

2.3.3 Flexible Sprinkler Hose

The use of flexible hose is not permitted.

2.3.4 Pipe Hangers and Supports

Provide galvanized pipe hangers, supports and seismic bracing in accordance with NFPA 13 . Design and install seismic protection in accordance with the requirements of NFPA 13 section titled "Protection of Piping Against Damage Where Subject to Earthquakes for Seismic Design Category D, Site Class E.

2.3.5 Valves

Provide valves of types approved for fire service. Valves must open by counterclockwise rotation.

2.3.5.1 Control Valve

Manually operated sprinkler control/gate valve must be outside stem and yoke (OS&Y) type or butterfly type as indicated on the drawings and must be listed.

2.3.5.2 Check Valves

Check valves must comply with UL 312 . Check valves 4 inches and larger must be of the swing type, have a clear waterway and meet the requirements of MSS SP-71 , for Type 3 or 4. Inspection plate must be provided on valves larger than 6 inches.

2.3.5.3 Hose Valve

Valve must comply with UL 668 .

2.3.6 Riser Check Valves

Provide riser check valve, pressure gauges and main drain.

2.4 ALARM INITIATING AND SUPERVISORY DEVICES

2.4.1 Sprinkler Alarm Switch

Vane or pressure-type flow switch(es). Connection of switch must be by the fire alarm installer. Vane type alarm actuating devices must have

SECTION 21 13 13 Page 15 mechanical diaphragm controlled retard device adjustable from 10 to 60 seconds and must instantly recycle.

2.4.2 Valve Supervisory (Tamper) Switch

Switch must be integral to the control valve or suitable for mounting to the type of control valve to be supervised open. The switch must be tamper resistant and contain SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.

2.5 BACKFLOW PREVENTION ASSEMBLY

Double-check valve assembly backflow preventer complying with ASSE 1013 , ASSE 1015 and AWWA M14. Each check valve must have a drain. Backflow prevention assemblies must have current "Certificate of Approval from the Foundation for Cross-Connection Control and Hydraulic Research, FCCCHR List" and be listed for fire protection use. Listing of the specific make, model, design, and size in the FCCCHR List is acceptable as the required documentation.

2.5.1 Backflow Preventer Test Connection

Test connection must consist of a series of listed hose valve s with 2 1/2-inch National Standard male hose threads with cap and chain.

2.6 FIRE DEPARTMENT CONNECTION

Fire department connection must be projecting type with cast-brass body, matching escutcheon lettered "Auto Spkr" with a polished-brass finish.

The connection must have individual self-closing clappers, caps with drip drains and chains. Female inlets must have 2 1/2-inch diameter American National Fire Hose Connection Screw Threads (NH) per NFPA 1963 . Comply with UL 405 .

2.7 SPRINKLERS

Sprinklers must comply with UL 199 and NFPA 13 . Sprinklers with internal O-rings are not acceptable. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters must have temperature classification in accordance with NFPA 13 . Extended coverage sprinklers are permitted for loading docks, residential occupancies and high-piled storage applications only.

2.7.1 Pendent Sprinkler

Pendent sprinkler must be recessed quick-response type with nominal K-factor of 5.6, 8.0, or 11.2. Pendent sprinklers must have a polished chrome finish. Assembly must include an integral escutcheon.

2.7.2 Upright Sprinkler

Upright sprinkler must be brass quick-response type and have a nominal K-factor of 5.6, 8.0, or 11.2.

2.7.3 Sidewall Sprinkler

Sidewall sprinkler must be the quick-response recessed type. Sidewall sprinkler must have a nominal K-factor of 5.6, 8.0, or 11.2. Sidewall

SECTION 21 13 13 Page 16 sprinkler must have a polished-chrome finish.

2.8 ACCESSORIES

2.8.1 Sprinkler Cabinet

Provide spare sprinklers in accordance with NFPA 13 and must be placed in a suitable metal or plastic cabinet of sufficient size to accommodate all the spare sprinklers and wrenches in designated locations. Spare sprinklers must be representative of, and in proportion to, the number of each type and temperature rating of the sprinklers installed as required by NFPA 13 . At least one wrench of each type required must be provided.

2.8.2 Pendent Sprinkler Escutcheon

Escutcheon must be one-piece metallic type with a depth of less than 3/4-inch and suitable for installation on pendent sprinklers. The escutcheon must have a factory finish that matches the pendent sprinkler.

2.8.3 Pipe Escutcheon

Provide split hinge metal plates for piping entering walls, floors, and ceilings in exposed spaces. Provide polished stainless steel plates or chromium-plated finish on copper alloy plates in finished spaces. Provide paint finish on metal plates in unfinished spaces.

2.8.4 Sprinkler Guard

Listed guard must be a steel wire cage designed to encase the sprinkler and protect it from mechanical damage. Guards must be provided on sprinklers located within 7 feet of the floor.

2.8.5 Relief Valve

Relief valves must be listed and installed at the riser in accordance with

NFPA 13 .

2.8.6 Air Vent

Air vents must be of the automatic type and piped to drain to the building exterior.

2.8.7 Identification Sign

Valve identification sign must be minimum 6 inches wide by 2 inches high with enamel baked finish on minimum 18 gage steel or 0.024-inch aluminum with red letters on a white background or white letters on red background. Wording of sign must include, but not be limited to "main drain", "auxiliary drain", "inspector's test", "alarm test", "alarm line", and similar wording as required to identify operational components. Where there is more than one sprinkler system, signage must include specific details as to the respective system.

PART 3 EXECUTION

3.1 VERIFYING ACTUAL FIELD CONDITIONS

Before commencing work, examine all adjoining work on which the contractor's work that is dependent for perfect workmanship according to

SECTION 21 13 13 Page 17 the intent of this specification section, and report to the Contracting Officer's Representative a condition that prevents performance of first class work. No "waiver of responsibility" for incomplete, inadequate or defective adjoining work will be considered unless notice has been filed before submittal of a proposal.

3.2 INSTALLATION

The installation must be in accordance with the applicable provisions of NFPA 13 , NFPA 24 and publications referenced therein. Locate sprinklers in a consistent pattern with ceiling grid, lights, and air supply diffusers. Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively affect or disrupt the sprinkler discharge pattern and coverage.

a. Piping offsets, fittings, and other accessories required must be furnished to provide a complete installation and to eliminate interference with other construction.

b. Wherever the contractor's work interconnects with work of other trades the Contractor must coordinate with other Contractors to insure all Contractors have the information necessary so that they may properly install all necessary connections and equipment. Identify all work items needing access (dampers and similar equipment) that are concealed above hung ceilings by permanent color coded pins/tabs in the ceiling directly below the item.

c. Provide required supports and hangers for piping, conduit, and equipment so that loading will not exceed allowable loadings of structure. Submittal of a bid must be a deemed representation that the contractor submitting such bid has ascertained allowable loadings and has included in his estimates the costs associated in furnishing required supports.

3.2.1 Waste Removal

At the conclusion of each day's work, clean up and stockpile on site all waste, debris, and trash which may have accumulated during the day as a result of work by the contractor and of his presence on the job.

Sidewalks and streets adjoining the property must be kept broom clean and free of waste, debris, trash and obstructions caused by work of the contractor, which will affect the condition and safety of streets, walks, utilities, and property.

3.3 UNDERGROUND PIPING INSTALLATION

The fire protection water main must be laid, and joints anchored, in accordance with NFPA 24 . Minimum depth of cover must be 3 feet or the frost line, whichever is deeper. The supply line must terminate inside the building with a flanged piece, the bottom of which must be set not less than 1-foot above the finished floor. A blind flange must be installed temporarily on top of the flanged piece to prevent the entrance of foreign matter into the supply line. A concrete thrust block must be provided at the elbow where the pipe turns up toward the floor. In addition, joints must be anchored in accordance with NFPA 24 . Buried steel components must be provided with a corrosion protective coating in accordance with AWWA C203. Piping more than 5 feet outside the building walls must meet the requirements of Section 33 11 00 WATER UTILITY

DISTRIBUTION PIPING.

SECTION 21 13 13 Page 18

3.4 ABOVEGROUND PIPING INSTALLATION

The methods of fabrication and installation of the aboveground piping must fully comply with the requirements and recommended practices of NFPA 13 and this specification section.

3.4.1 Protection of Piping Against Earthquake Damage

Seismic restraint is required.

3.4.2 Piping in Exposed Areas

Install exposed piping without diminishing exit access widths, corridors or equipment access. Exposed horizontal piping, including drain piping, must be installed to provide maximum headroom.

3.4.3 Piping in Finished Areas

In areas with suspended or dropped ceilings and in areas with concealed spaces above the ceiling, piping must be concealed above ceilings. Piping must be inspected, hydrostatically tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas must be concealed.

3.4.4 Pendent Sprinklers

a. Drop nipples to pendent sprinklers must consist of minimum 1-inch pipe with a reducing coupling into which the sprinkler must be threaded.

b. Where sprinklers are installed below suspended or dropped ceilings, drop nipples must be cut such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. The outlet of the reducing coupling must not extend below the underside of the ceiling.

c. Recessed pendent sprinklers must be installed such that the distance from the sprinkler deflector to the underside of the ceiling must not exceed the manufacturer's listed range and must be of uniform depth throughout the finished area.

d. Pendent sprinklers in suspended ceilings must be located in the center of the tile (plus or minus 2 inches).

e. Where the maximum static or flowing pressure, whichever is greater at the sprinkler, applied other than through the fire department connection, exceeds 100 psi and a branch line above the ceiling supplies sprinklers in a pendent position below the ceiling, the cumulative horizontal length of an unsupported armover to a sprinkler or sprinkler drop must not exceed 12 inches for steel pipe and 6 inches for copper tube.

3.4.5 Upright Sprinklers

Riser nipples or "sprigs" to upright sprinklers must contain no fittings between the branch line tee and the reducing coupling at the sprinkler.

SECTION 21 13 13 Page 19

3.4.6 Pipe Joints

Pipe joints must conform to NFPA 13 , except as modified herein. Not more than four threads must show after joint is made up. Welded joints will be permitted, only if welding operations are performed as required by NFPA 13 at the Contractor's fabrication shop, not at the project construction site. Flanged joints must be provided where indicated or required by NFPA 13 . Grooved pipe and fittings must be prepared in accordance with the manufacturer's latest published specification according to pipe material, wall thickness and size. Grooved couplings, fittings and grooving tools must be products of the same manufacturer. For copper tubing, pipe and groove dimensions must comply with the tolerances specified by the coupling manufacturer. The diameter of grooves made in the field must be measured using a "go/no-go" gauge, vernier or dial caliper, narrow-land micrometer, or other method specifically approved by the coupling manufacturer for the intended application. Groove width and dimension of groove from end of pipe must be measured and recorded for each change in grooving tool setup to verify compliance with coupling manufacturer's tolerances.

3.4.7 Reducers

Reductions in pipe sizes must be made with one-piece tapered reducing fittings. When standard fittings of the required size are not manufactured, single bushings of the face or hex type will be permitted.

Where used, face bushings must be installed with the outer face flush with the face of the fitting opening being reduced. Bushings cannot be used in elbow fittings, in more than one outlet of a tee, in more than two outlets of a cross, or where the reduction in size is less than 1/2-inch.

3.4.8 Pipe Penetrations

a. Cutting structural members for passage of pipes or for pipe-hanger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors must be core-drilled and provided with pipe sleeves. Each sleeve must be Schedule 40 galvanized steel, ductile-iron or cast-iron pipe and extend through its respective wall or floor and be cut flush with each wall surface. Sleeves must provide required clearance between the pipe and the sleeve per NFPA 13 .

The space between the sleeve and the pipe must be firmly packed with mineral wool insulation.

b. Where pipes and sleeves penetrate fire walls, fire partitions, or floors, pipes/sleeves must be firestopped in accordance with Section

07 84 00 FIRESTOPPING.

c. In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe must be sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.

d. All penetrations through the boundary of rooms/areas identified as secure space area must meet ICS 705-1 .

3.4.9 Escutcheons

Escutcheons must be provided for pipe penetration in finished areas of ceilings, floors and walls. Escutcheons must be securely fastened to the pipe at surfaces through which piping passes.

SECTION 21 13 13 Page 20

3.4.10 Inspector's Test Connection

Unless otherwise indicated, the test connection must consist of 1-inch pipe connected at the riser as a combination test and drain valve; a test valve located approximately 7 feet above the floor; a smooth bore brass outlet equivalent to the smallest orifice sprinkler used in the system;

and a painted metal identification sign affixed to the valve with the words "Inspector's Test". All test connection piping must be inside of the building and penetrate the exterior wall at the location of the discharge orifice only. The discharge orifice must be located outside the building wall no more than 2 feet above finished grade, directed so as not to cause damage to adjacent construction or landscaping during full flow discharge, or to the sanitary sewer.

This is the start of the file's text. The full file is on GovTribe.