These are Industry Day Slides for a U.S. Army Corps of Engineers (USACE) Louisville District project to construct a new Army Reserve Center in Birmingham, Alabama. The project involves building a 600-member facility with primary components including a 53,000 sq ft Army Reserve Center, a 19,300 sq ft Vehicle Maintenance Shop, and supporting infrastructure such as utilities, military equipment parking, storm drainage, fencing, and landscaping. The project aims to achieve LEED Silver certification and will utilize a Design-Bid-Build procurement method with a Best Value Trade-off source selection process.

Key procurement details include a solicitation number W912QR25R0020, anticipated release in early April 2025, with a contract award expected in June/July 2025 and construction completion targeted for Fall 2027. The project is an unrestricted, full and open procurement with an estimated construction value between $25-$100 million, using NAICS code 236220. Contractors must be registered in SAM and PIEE, submit a Small Business Participation Plan, and will have approximately 30 calendar days to prepare and submit proposals after the solicitation release. The contract duration is estimated at 800 calendar days from the Administrative Notice to Proceed.

View the file

Other files

File Type Posted
Industry Day Attendees.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Industry Day Forum Birmingham, Alabama Army Reserve Center and associated secondary facilities

DATE: 20 MARCH 2025

TIME: 1400 EST

LOCATION:

Online

Teams link:

https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_06c485f5493248a5bd5d5b657484a006%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%2204451f1e-4f73-4df1-b70b-03e93788f50d%22%7d

”The views, opinions and findings contained in this report are those of the author(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Please ensure that you have signed in Company Name, POC Name, Email, Phone Are you interested in being the Prime or Subcontractor If you’re interested in being a subcontractor, state the type of work you are interested (Electrical, Mechanical, Roofing, etc.)

Please turn off all mobile devices

No recording

This briefing and the attendee roster will be posted to SAM

Please be advised that none of the information discussed today is contractually-binding

ADMINISTRATIVE ANNOUNCEMENTS

Introduction of Team Members Army Reserve Overview USACE Procurement Process Overview Subcontracting Requirements Other USACE Future Contracts Q & A Session Networking / Discussions Site Visit

AGENDA

US Army Reserve OVERVIEW

Sonia L Suggs Project Manager U.S. Army Corps of Engineers Louisville District

Sonia Jackson-SuggsProject Manager (Louisville District Office)
Bruce EaleyProject Engineer (Louisville District Office)
Laura Phillips-PayneContract Specialist (Louisville District Office)
Crystal HarbinDeputy for Small Business (Louisville DistrictOffice)
Christopher MartinResident Engineer, ACO (Mobile District Office)
Roger RiddickRegional Resident Engineer, ACO (LouisvilleDistrict Office)

Designer of Record RSP Architects Louisville & MOBILE District Team Members

Army reserve program 88th Readiness Division Ft McCoy, WI

California Nevada Arizona New Mexico Texas Oklahoma Arkansas Kansas Nebraska Iowa Missouri Minnesota Ohio Illinois Utah Colorado South Dakota North Dakota Montana Wyoming Idaho Oregon Mississippi Alabama Georgia

MD

DC

Maine

VT

NH

RI

DE

81st Readiness Division Ft Jackson, SC

63rd Readiness Division Mountain View, CA

99th Readiness Division Ft Dix, NJ OCAR - Fort Belvoir, VA USARC - Fort Bragg, NC

OCAR - Fort Belvoir, VA USARC - Fort Bragg, NC Puerto Rico

Army reserves milcon communication plan

Birmingham, Alabama Army Reserve Center and associated secondary facilities

Sonia L. Suggs Project Manager US Army Corps of Engineers

Bruce E. Ealey Project Architect US Army Corps of Engineers

Birmingham, AL army reserve center The purpose of the Army Reserve is to provide trained units and qualified individual soldiers for active duty in the time of need.

Training Center Vehicle Maintenance Shop Organizational Storage Unheated Storage Building Military Equipment Parking Private Occupancy Vehicle Parking

Project Information:

Construct a 600-member Army Reserve Center in Birmingham, AL. Primary facilities include land acquisition and construction of an Army Reserve Center (53,000 sf), Vehicle Maintenance Shop (19,300 sf), Organizational Storage Building, and an Unheated Storage Building (3,400 sf).

Supporting facilities include site development, utilities and connections, Military Equipment Park (MEP), non-organizational parking, vehicle wash rack/platforms, bi-level equipment loading ramp, circulation pavements, storm drainage, paving, walks, curbs and gutters, fencing, gates, lighting, information systems, landscaping, and signage. Accessibility for the disabled will be provided.

Birmingham, al army reserve center

The Training Building is designed as a two-story building.

First Floor. Retention and Family Support Offices; Assembly Hall; Kitchen; Physical Readiness; Classrooms Second Floor. Administrative spaces.

Exterior Wall System.

The Training Building and AMSA/VMS buildings will have Insulated Concrete Form (ICF) cavity wall construction with a masonry veneer.

The Organizational Storage Building will have insulated metal wall panels over horizontal z-girts attached to a Pre-Engineered Metal Building structure.

Birmingham aerial

Birmingham, AL army Reserve Center

Birmingham, Al army reserve center

Sustainability Goal – LEED Silver (USGBC)

Project Delivery Method - Design/Bid/Build

Procurement Method- Best Value Trade Off/ Source Selection Board

Estimated Construction Duration - 800 days

Stakeholders – USARC & 81st Readiness Division Scheduled Milestones (subject to change):

Advertise Period – April – May 25 SSEB (Phase I) – June 2025 Contract Award – June/July 2025 Notice to Proceed – July/August 2025 Construction Completion – Fall 2027

Procurement Process

Laura Phillips-Payne – CONTRACTING specialist Louisville district Office Phone: 502-315-6214 laura.Phillips-payne@usace.army.mil

SAM – www.sam.gov Solicitation Numbers will begin with “W912QR” Solicitation Name: Army Reserve Center in Birmingham, AL _ DBB Solicitation will be:

W912QR25R0020

Interested vendors list Register/Follow to receive notifications and updates / amendments RFP technical information will be posted on www.sam.gov

HOW TO OBTAIN THE SOLICITATION

A list of general contractors bidding the project is not maintained. The Government does not know who is bidding the project until a proposal is received.

SAM.gov does contain an Interested Vendors List to which you may add your firm’s name.

Obtaining the Issue Documents Laura Phillips-Payne – Contract specialist, Louisville district Requirements to download Technical Data Package:

Need to be registered in System for Award Management (SAM) database. You must sign up and sign-in to your account to use many features of SAM.gov (saving searches, viewing solicitations, etc.)

You must register your business entity (you as an individual or your organization) to be able to propose on contracts or apply for federal assistance (grants, loans, etc.) from the federal government.

Any amendments issued to the RFP will also be posted on www.sam.gov Pre-Solicitation Notice – posted on www.sam.gov at least 15 days prior to the initial issuance of the Solicitation package.

Advertisement – minimum 30 days to prepare proposals.

You must be registered and signed in to download any documents. Pre-Solicitation Notice was posted to SAM.gov on 06 March 2025.

The solicitation is anticipated to be released early April and offerors will have a minimum of 30 calendar days to submit a proposal.

The Procurement process Laura Phillips-Payne – Contract specialist, Louisville district

Both projects will be a Design-Bid-Build (D-B-B) Request for Proposals (RFP).

Project awards will be made on a “Best Value Trade-off” basis as described in the evaluation criteria.

Proposals must be submitted on time.

* The Louisville District is in the Eastern time zone.

The Source Selection Evaluation Board (SSEB) will evaluate contractors’ proposals based on specific factors which are defined in the RFP Package.

This will be a Full and Open procurement utilizing a Single-Phase Design/Bid/Build solicitation and evaluation. The NAICS code for this project is 236220 and the size standard is $45M.

The basis of award is the Best Value Trade-off process. The Government may opt not to award to the lowest price – All evaluation factors, other than price, when combined are considered approximately equal to price.

This solicitation will likely include options. Evaluation of price will be made on the total of the base and all options price.

The contract period of performance is estimated to be 800 calendar days from Administrative Notice to Proceed.

Source Selection Criteria for a “Best Value Trade-Off” usually consists of the following:

Past Performance Evaluation Recent projects, similar in size, and scope

Management Plan

Narrative Schedule

Small Business Participation Plan

Pro-Forma Evaluation (Price, JV agreements, Bonding, etc.)

Submit your best proposal the 1st time. If we receive an initial proposal that is awardable, discussions may not be opened.

Proposal Requirements Laura Phillips-Payne – Contract specialist, Louisville district

Section 00 22 12 will contain the proposal submission requirements and evaluation criteria. Follow the format described in Section 00 22 12 to keep the proposal in order, success is in the details. Please pay close attention to the requirements of the RFP.

For the Past Performance Factor, we will evaluate both the relevancy of experience and performance quality of prior experience. We will at a minimum review Contractor Performance Assessment Reporting System (CPARS) information available but reserve the right to check any and all sources of past performance information. This level of review will be conducted for the Prime Construction Contractor. This review will result in an overall assessment of confidence in performance.

Pro-Forma information will be reviewed for submission and completion. Failure to provide what is required may result in the proposal being considered non-responsive.

Standard Form (SF) 1442 must be signed, and all amendments must be acknowledged. If this is not done, the proposal may be considered non-responsive.

Proposal prices are to be good for ninety (90) days from the proposal submittal due date.

A bid bond/offer guarantee will NOT be required.

Do not assume that you will be permitted to make revisions to a proposal. Following the completion of the evaluation, if there is a technically qualified contractor at an affordable price, the Government has no reason to open discussions and ask for proposal revisions. The initial proposal should include your best effort.

Instructions for submitting a Request for Information (RFI) will be included in the solicitation.

RFIs for this project will be received and answered through the Projnet system: www.projnet.org Any RFIs submitted directly to the project team will not receive a response and will be directed to the Projnet system.

Each project will have a Projnet Bidder’s Key, which is used to post your RFIs to the proper project.

The project Bidder’s Key will be included in the Projnet Instructions section of the RFP.

Requests for Information and their responses will be available for public review through Projnet.

Proposal Requirements Laura Phillips-Payne – Contract specialist, Louisville district

All technical inquiries and questions relating to this solicitation must be submitted via Bidder Inquiry in Projnet at www.projnet.org/projnet. Information for accessing ProjNet will be included in the solicitation.

We will utilize the Electronic Receipt of Proposal process – Instruction will be in Section 00 21 00 of the solicitation package Proposals uploaded to PIEE Don’t wait until the last minute to upload your proposal. Late is Late! No exceptions!

PROPOSAL SUBMISSION

Crystal Harbin Deputy for Small Business

SBO-LRL@usace.army.mil

Courtney Luckett Small Business Professional

Small Business Participation plan & Subcontracting PLAN The Small Business Participation Plan is a rated evaluation factor in all unrestricted procurements Both large and small business offerors must submit a participation plan.

The participation plan is based on total contract value.

The Small Business Participation Plan must meet the minimum Total Small Business Participation goal. The percentage will be included the solicitation.

Small Business prime self-performance counts as Small Business Participation.

Large Business offerors must submit a Small Business Subcontracting Plan Mandated by FAR 19.702 This is not a rated element as a part of the Source Selection process but the offeror shall submit an acceptable plan prior to award The subcontracting plan is based on total subcontracted dollars Failure to comply in good faith is in material breach of the contract

Obtain information Attend Site Visits, Pre-Proposal Conferences, & Industry Days Obtain copies of attendee roster for subcontracting opportunities

Register as an Interested Vendor on SAM

Attend Workshops and Conferences

Louisville District Networking: Tentative 29 July 2025

Construction & IDIQ Forecast is maintained on the Business with Us page of the Great Lakes and Ohio River Division website, https://www.lrd.usace.army.mil/Opportunity-Forecast/ opportunities We anticipate executing approximately $1.3B in FY25 through both small and large businesses.

Contracting opportunities are posted in the System for Award Management (SAM) website at www.sam.gov. Use “W912QR” to search for Louisville District projects.

Actively Respond to Sources Sought Notices (Market Surveys) posted to SAM

Actively Respond to Competitive Requirements posted to SAM

WHEN: Will be included in Solicitation

WHERE: Will be included in Solicitation

POC: Will be included in Solicitation

BIDDER site visit

Thank you for your time and interest!

image3.png image4.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.jpeg image16.emf image17.tmp image18.tmp image19.tmp image20.tmp image21.tmp image22.jpeg oleObject1.bin image23.emf image24.png image1.png image2.png image5.png image6.png

File details come from the government source that posted it. Updated .