W912QR24R0049_PH2_CERT_FINAL_VOL1-0002.pdf
PDF 4 MB Posted
- Attached to
- Seagoville, Texas - Army Reserve Center
- Solicitation number
- W912QR24R0049
About this file
This document is a solicitation for a Design-Build contract to repair and renovate an Army Reserve Center (ARC) in Seagoville, Texas. The project consists of repairing, replacing or installing interior walls, doors, flooring, windows, plumbing, mechanical, electrical, and fire/life safety systems. The solicitation uses a two-phase procurement approach, with Phase II proposals due by September 3, 2024. The contract will be Firm-Fixed-Price, awarded on a Best Value Trade-Off basis. The solicitation includes a Price Breakout Schedule detailing base bid and option line items, which cover building repairs, abatement, sitework, design fees, and additional CFCI OMAR-funded items. Small business participation goals are required, and large businesses must submit an acceptable subcontracting plan. The government will evaluate technical factors such as design approach, management plan, and schedule, in addition to price.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Army Reserve Center P-1001, Seagoville, TX
P2: 515203
Design-Build
Specifications Vol. 1 of 3 (Div. 00 - 01)
20 June 2024
W912QR24R0049
Phase 1
02 August 2024
W912QR24R0049-0002
Phase II Certified Final ARIMS: 200A Disposition: Maintain for 15yrs after construction.
W912QR24R0049_PH2_CERT_FINAL_VOL1-0002
This Page Intentionally Left Blank
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
1 45
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR24R0049
X 9B. DATED (SEE ITEM 11)
20-Jun-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3.EFFECTIVE
DATE
02-Aug-2024
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
Design and Construction for the Maintenance & Repair, Army Reserves (MRAR) of an Army Reserve Center (ARC), Seagoville Building 1001, located in Seagoville, Texas is hereby amended as follows:
A. The PRICE BREAKOUT SCHEDULE is hereby incorporated in its entirety.
B. All SPECIFICATIONS SECTIONS have been updated in their entirety.
C. Offerors must acknowledge all Amendments.
D. FAR Provision 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995) has been updated.
E. The proposal due date is hereby extended to 03 September 2024 at 2:00 P.M. (Eastern Daylight Time) for Phase II proposals.
F. All other terms and conditions remain unchanged.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 19-Jul-2024 02:00 PM to 03-Sep-2024 02:00 PM.
The following have been added by full text:
PRICE BREAKOUT SCHEDULE
PRICE BREAKOUT SCHEDULE
PROJECT: ARMY RESERVE CENTER – REPAIR TRAINING BUILDING P-1001
LOCATION: Seagoville TX
PROPOSER’S NAME:
BASE PROPOSAL
ITEM
NO.
DESCRIPTION UNIT BID
AMOUNT
BID
AMOUNT
0001 Primary Facilities – Building P-1001 Repair JOB $ 0002 Bldg. P-1001 Asbestos Abatement JOB $ 0003 Bldg. P-1001 Lead Abatement JOB $ 0004 Primary Facilities - Project Repair Sitework JOB $ 0005 Bldg. P-1001 UG Storm Water Tie-In JOB $ 0006 Utility Connection Costs JOB $ 0007 Fire Water Pump and Tank (New Work) JOB $ 0008 Project Design Fees JOB $ 0009 Project Design Fees (New Work) JOB $
SUB-TOTAL BASE PROPOSAL – REPAIR WORK $_______
SUB-TOTAL BASE PROPOSAL – NEW WORK $_______
OPTION PROPOSAL
0010 Repair Option – Mill and Overlay Exist West Lot JOB $ 0011 Bldg. P-1001 Asbestos Abatement - 500 SF JOB $ 0012 Bldg. P-1001 Asbestos Abatement - 1000 SF JOB $ 0013 Bldg. P-1001 Lead Abatement - 500 SF JOB $
SUB-TOTAL OPTION PROPOSAL – REPAIR WORK $
0014 West Lot Expansion and BMP (New Work) JOB $ 0015 West Lot Exp. and BMP Design Fees (New Work) JOB $ 0016 MKT Pad (New Work) JOB $ 0017 MKT Pad Design Fees (New Work) JOB $ 0018 CFCI OMAR Funded Items JOB $ 0019 CFCI Bona Fide Need OMAR Funded Items JOB $
SUB-TOTAL OPTION PROPOSAL - NEW $
TOTAL BASE BID PLUS OPTION PROPOSAL – REPAIR WORK $_______
TOTAL BASE BID PLUS OPTION PROPOSAL – NEW WORK $_______
TOTAL BASE PLUS OPTION PROPOSAL – REPAIR AND NEW WORK $_______
W912QR24R0049
NOTES FOR PROPOSAL SCHEDULE
1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest proposal schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to proposal items, all proposers should state their revised prices for each item. The company name should be indicated on the face of the proposal schedule to preclude being misplaced.
2. Proposers must insert a price on all numbered items of the Proposal Schedule. The price may be zero dollars or a deduct amount. Failure to do so will disqualify the proposal.
3. Attach a separate sheet describing each Option and Betterment, with the Option Items keyed to the Proposal Item Number and providing sufficient information for the Government to evaluate the quality and quantity of the Option or Betterment being offered.
4. If a modification to a proposal is submitted which provides for a lump-sum adjustment to the total estimated cost, the application of the lump-sum adjustment to each unit price and/or lump-sum price in the proposal schedule must be stated or, if it is not stated, the proposer agrees that the lump-sum adjustment shall be applied on a pro rata basis to every proposal item in the proposal schedule.
5. CONDITIONS GOVERNING EVALUATION OF PROPOSALS AND AWARD OF
CONTRACT.
One contract only will be awarded on this project and evaluation will be made on the Total Base Proposal plus Option Proposal, in accordance with the paragraph entitled "Evaluation of Options" in the Instructions to Offerors.
The Government may require the delivery of the numbered line items, identified in the schedule as option items, in the quantity and at the price stated in the schedule.
6. Description of Proposal Items - The general outline of the principal features of each item as listed below does not in any way limit the responsibility of the proposer for making a thorough investigation of the drawings and the specifications to determine the scope of work including each item of the proposal form. Further descriptions of the Options may be found in the Statement of Work.
Description of Base Proposal Items
Item No. 0001 “Primary Facilities – Building P-1001 Repair” includes Base Proposal construction work required within a line five feet outside of the building. This is a “Repair” line item.
Item No. 0002 “Bldg. P-1001 Asbestos Abatement” includes Base Proposal Asbestos Abatement work required within the building as indicated in the Hazardous Materials Report of this solicitation. This is a “Repair” line item.
Item No. 0003 “Bldg. P-1001 Lead Abatement” includes Base Proposal Lead Abatement work required within the building as indicated in the Hazardous Materials Report of this solicitation.
This is a “Repair” line item.
Item No. 0004 “Primary Facilities - Project Repair Sitework” includes Base Proposal demolition and construction work required beyond a line five feet outside the buildings.
Includes all work required to repair existing pavement, and to furnish and install additional pavement, sidewalks, as indicated on civil site drawings and the specification requirements of this solicitation. This is a “Repair” line item. The work in Item Nos.
0005, 0007, 0010, 0014, 0016 below are excluded from this line item.
Item No. 0005 “Bldg P-1001 UG Storm Water Tie-In” includes all work to furnish and install the underground storm drainage work indicated on civil site drawing CS100- CS103 and the specification requirements of this solicitation. This is a “Repair” line item.
Item No. 0006 “Utility Connection Costs” includes Base Proposal costs required for all connections for new and existing utility improvements. This is a “Repair” line item.
Item No. 0007 “Fire Water Pump and Tank” includes Base Proposal costs required (if necessary) for installation of Fire Water Storage Tank and Fire Pump and Pump House. This is a “New Work” line item.
Item No. 0008 “Project Design Fees” includes the fees for the Offerors’ design professionals to complete design and construction documents for Base Proposal Items 0001, 0002, 0003, 0004, 0005, 0006 and Option Proposal Items 0010, 0011, 0012, and 0013. This is a “Repair” line item.
Item No. 0009 “Project Design Fees” includes the fees for the Offerors’ design professionals to complete design and construction documents for Base Proposal Item 0007. This is a “New Work” line item.
Description of Option Proposal Items
Item No. 0010 “Repair Option – Mill and Overlay Exist West Lot” includes work required to resurface the existing POV lot on the west side of the facility, replacement of (6) six existing site lighting fixtures and poles plus the addition of new site lighting fixtures and poles as required. This is a “Repair” line item.
** This Option item can be exercised within 120 calendar days from Notice to Proceed.
Item No. 0011 “Bldg. P-1001 Asbestos Abatement - 500 SF” includes additional Asbestos Abatement. This is to account for any additional material or additional material quantity not identified in the Hazardous Materials Report. This is a “Repair” line item.
** This Option item can be exercised within 365 calendar days from Notice to Proceed.
Item No. 0012 “Bldg. P-1001 Asbestos Abatement - 1000 SF” includes additional Asbestos Abatement. This is to account for any additional material or additional material quantity not identified in the Hazardous Materials Report. This is a “Repair” line item.
Item No. 0013 “Bldg. P-1001 Lead Abatement - 500 SF” includes additional Lead Abatement.
This is to account for any additional material or additional material quantity not identified in the Hazardous Materials Report. This is a “Repair” line item.
Item No. 0014 “West Lot Expansion and BMP” includes all work to furnish and install the parking lot expansion and retention pond on the west side of the facility as indicated on civil site drawing CS103 and the specification requirements of this solicitation and additional new site lighting fixtures and poles as required. This is a “New Work” line item.
Item No. 0015 “West Lot Expansion and BMP Design Fees” includes the fees for the Offerors’ design professionals to complete design and construction documents for Optional Proposal Items 0014. This is a “New Work” line item.
Item No. 0016 “MKT Pad” includes all work to furnish and install the MKT Pad as indicated on civil site drawing CS102 and the specification requirements of this solicitation. This is a “New Work” line item.
Item No. 0017 “MKT Pad Design Fees” includes the fees for the Offerors’ design professionals to complete design and construction documents for Optional Proposal Items 0016. This is a “New Work” line item.
Item No. 0018 “CFCI OMAR Funded Items” includes work required to furnish and install “CFCI OMAR funded” items. CFCI OMAR funded items are to be contractor provided and installed, unless otherwise noted in this RFP. Refer to publication entitled “Army Reserve OMAR Project Funding Requirements, October 2013” available on the Louisville Design Guide Website. These items include:
Metal lockers Caging for Storage
Item No. 0019 “CFCI Bona Fide Need OMAR Funded Items” includes work required to furnish and install “CFCI Bona Fide Need OMAR Items. CFCI Bona Fide Need OMAR Items are to be contractor provided and installed, unless otherwise noted in this RFP. Refer to publication entitled “Army Reserve OMAR Project Funding Requirements, October 2013” available on the Louisville Design Guide Website. These items include:
Refrigerator and Microwave in Break Room(s) Metal shelving Fire extinguishers and window blinds
** This Option item can be exercised within 540 calendar days from Notice to Proceed.
*** End of Section ***
The following have been modified:
BLOCK 10 CONTINUATION PAGE
The offer due date and time specified in Block 13.A. is in the Eastern Time (ET) zone.
Technical inquiries and questions relating to the proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://projnet.org/projnet. Please see Section 00 21 00, ProjNet Instructions / Offeror’s Questions and Comments for further instructions.
The Government is requiring electronic submission of proposals. Please follow the provided instructions precisely.
Please see Section 00 21 00, Proposal Submission Instructions.
The term bid and proposal are used interchangeably in industry and may be used interchangeably throughout this Solicitation.
Box 13 is marked as 0 sealed offer copies due to this solicitation requiring full electronic proposals.
Please see FAR 52.236-27 ALT 1 for Site Visit information with the release of the Phase II amendment.
Please note, page numbering in this document may not be accurate.
All days are to be considered calendar days, unless otherwise noted.
SECTION 00 21 00 - INSTRUCTIONS
PROJNET INSTRUCTIONS
OFFEROR'S QUESTIONS AND COMMENTS
Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet.
Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.
To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system.
The Solicitation Number is: W912QR24R0049
The Bidder Inquiry Key is: Q8Q7IX-84PHJC
Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Select Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
From this page you may view all bidder inquiries or add an inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
NOTES:
1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.
2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form (SF) 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to: (a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation; or
(c) Notice that a response is not necessary.
3. The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled 10 days prior to the proposal due date. No Government responses will be entered into the ProjNet system 5 days prior to the proposal due date.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 14 August 2024 10:00-12:30 Central Time. This site visit will include a tour of Building 1001.
(c) Participants will initially meet in Room 105 of Building 1002. 701 W Simonds Rd, Seagoville, TX 75159.
(d) Please RSVP to Sonia Jacksonsuggs, sonia.l.suggs@usace.army.mil, by Thursday, 08 August 2024. Provide the full name, phone number, and email address of each person attending the site visit.
SECTION 00 22 16 - SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS
EVALUATION CRITERIA - PHASE II
SECTION 00 22 18
PROCEDURES FOR SUBMITTAL AND EVALUATION OF OFFERS FOR
PHASE TWO
1. Overview.
1.1 The intent of this solicitation is to select one (1) contractor for Design and Construction for the
Maintenance & Repair, Army Reserves (MRAR) of an Army Reserve Center (ARC), Seagoville Building 1001, located in Seagoville, Texas. This will be a Design/Build repair project comprises total of approximately 30,000 square feet. Required improvements consist of repair, replacement, or installation of interior walls, doors, flooring, windows, window frames and ceilings, replacement/addition of plumbing fixtures, piping, and equipment; installation and/or replacement of mechanical equipment;
replacement/installation of fire suppression sprinkler system, replacement/installation of the fire alarm system/mass notification system; installation of lighting and upgrade interior electrical service;
replacement/installation of information systems; repair of exterior wall finish, repair of downspout/gutters, replace roofing, modify/replace exterior doors and door openings, and replace exterior signage; removal of lead, lead based paint and asbestos as necessary. This project is a full facility repair and will be designed and constructed to current Department of Army sustainable design standards.
1.2 This is a two-phase procurement, and the basis of award is the Best Value Trade-Off Process. Following completion of the evaluation of Phase I, up to a maximum of five (5) most highly qualified offerors will be selected to participate in Phase II. A site visit will be held for these selected offerors following the Phase II notification. The selected offerors for Phase II will be invited to submit the information described in this Section 00 22 18, Procedures for Submittal and Evaluation of Offers for Phase II, for review and evaluation by the Government. Following completion of the Phase II evaluation, the Contracting Officer will award a Firm-Fixed-Price (FFP) contract to the responsible offeror whom the Source Selection Authority determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, all factors considered. The Government reserves the right to accept other than the lowest priced offer or to reject all offers. For Phase II submittals, requirements stated in this RFP are minimums.
NOTE: The rating information from Phase I will not be considered in Phase II or in the final selection.
2. Submittal of Offers.
2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals so that a minimum of time and monies will have been expended in preparing information required herein. However, in order to be effectively and equitably evaluated, the proposals must include information sufficiently detailed to clearly describe the offeror's capability for successfully completing the solicited project. For Phase II, requirements stated in this Request for Proposal (RFP) are minimums.
Innovative, creative, or cost-saving proposals that meet or exceed the requirements are encouraged and will be rated accordingly. Proposals should follow in the order of sequence set forth in the RFP. Information provided out of sequence may not be evaluated and may result in the offeror’s disqualification from award.
2.2 Offerors shall submit their proposals electronically in accordance with the Proposal Submission
Instructions in Section 00 21 00 of the solicitation. Please follow the instructions precisely as proposals must complete the upload no later than the time and date specified in Block 13 of Standard Form 1442.
NOTE: The Louisville District is in the Eastern Time Zone.
2.3 The Government is using a two-phase procurement approach for this Design/Build project. For Phase II, offerors are required to submit a proposal consisting of the information identified in paragraphs 2.4 and 2.5 below. All proposal materials shall be electronically in accordance with the Proposal Submission Instructions in Section 0 21 00 of the solicitation. The sections should parallel the submission requirements identified herein.
2.4 Volume I for Phase II shall include the following information:
Volume I – Factor I: Design Narrative Volume I – Factor II: Management Plan Volume I – Factor III: Schedule Narrative Volume I – Factor IV: Small Business Participation Plan
*NOTE: Failure to place the required submission information under the appropriate tab (factor or sub factor) may result in a lower rating if the evaluators cannot readily find the appropriate information. Any specified page limits will be strictly adhered to and enforced. Information submitted that exceeds the specified limit(s) will not be evaluated.
2.5 Volume II for Phase II shall be submitted electronically in accordance with the Proposal Submission
Instructions in Section 00 21 00 of the solicitation and shall include the following information:
Volume II – Tab A: Standard Form 1442 and Price Breakout Schedule Volume II – Tab B: Subcontracting Plan
*NOTE: Failure to place the required submission information under the appropriate tab may result in a lower rating if the evaluators cannot readily find the appropriate information. Any specified page limits will be strictly adhered to and enforced. Information submitted that exceeds the specified limit(s) will not be evaluated.
3. Proposal Evaluation Process.
3.1 A Source Selection Evaluation Board (SSEB) comprised of representatives of the Corps of Engineers, User/Customer, and other required personnel will evaluate the proposals. Offerors are advised that the technical evaluation and rating of proposals will be conducted in strict confidence. Technical (Volume I) proposals will be reviewed and rated without knowledge of the price offered. The number and identities of offerors are not revealed to anyone not involved in the evaluation and award process or to other offerors.
Proposals will be evaluated based on the factors described herein, and the basis of award is a Best Value Trade-Off, as stated above.
3.2 The evaluation process for Phase II essentially consists of four (4) parts: proposal compliance review and responsibility review, technical evaluation, price evaluation, and price/technical trade-off analysis.
3.2.1 Proposal Compliance / Responsibility Review: This is an initial review to ensure that both a technical and price proposal and (for Large Business offerors) a Subcontracting Plan were received.
3.2.2 Technical Evaluation: The SSEB will evaluate and rate the Phase II Volume I proposals against the RFP requirements. Factors I through III (Design Narrative, Management Plan, and Schedule Narrative) will be rated using Table 4 found in Section 4.7. Factor IV – Small Business Participation Plan will be rated using Table 5 in Section 4.7.
3.2.3 Price Evaluation: The SSEB and Contracting Officer/SSA will evaluate price proposals independent of the technical evaluation. The SSEB will not have access to price information until completion of the technical evaluation.
3.2.4 Price/Technical Trade-off Analysis: After all the above evaluations are complete, the Contracting Officer/SSA will compare the relative advantages and disadvantages of technical proposals and compare prices. The Source Selection Authority (SSA) will then consider all factors to select the proposal offering the best value to the Government.
4. Proposal Information and Related Evaluation Factors.
4.1 Phase II proposals will be evaluated in accordance with the factors below, listed in relative order of importance. All evaluation factors, other than price, when combined are considered approximately equal to price. The Government intends to evaluate proposals and award a contract without discussions with offerors. Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. The Government also reserves the right to conduct Clarifications or Communications with offerors as described in FAR 15.306(a) and (b). If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
4.2 Volume I – Factor I: Design Narrative Equally important to Factors II and III. More important than Factors IV.
4.3 Volume I – Factor II: Management Plan Equally important to Factors I and III. More important than Factors IV.
4.4 Volume I – Factor III: Schedule Narrative Equally important to Factors I and II. More important than Factors IV.
4.5 Volume I – Factor IV: Small Business Less important than Factors I, Participation Plan II, and III.
4.6 Volume II – Price and Pro Forma Information
Tab A Standard Form 1442 and Price Breakout Schedule Not Rated
Tab B Subcontracting Plan Not Rated (Large Business Offerors Only)
4.7 Ratings
Evaluators will apply the rating for the definition that most closely matches the evaluation.
TABLE 4
Combined Technical/Risk Ratings Rating Description
Outstanding Proposal demonstrates an exceptional approach and understanding of the requirements and contains multiple strengths and/or at least one significant strength, and risk of unsuccessful performance is low.
Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength or significant strength, and risk of unsuccessful performance is low to moderate.
Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable Proposal does not meet requirements of the solicitation and, thus Proposal contains one or more deficiencies and is unawardable, and/or risk of performance is unacceptably high.
TABLE 5
Small Business Ratings
Rating Description Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the small business objectives.
Unacceptable Proposal does not meet small business objectives.
4.8 Definitions
1. Deficiency. A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
2. Strength. An aspect of an offeror’s proposal with merit or will exceed specified performance or capability requirements to the advantage of the Government during contract performance.
3. Significant Strength. An aspect of an Offeror’s proposal with appreciable merit or will exceed specified performance or capability requirements to the considerable advantage of the Government during contract performance.
4. Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See
FAR 15.001.
5. Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
6. Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).
7. Risk. As it pertains to source selection, the potential for unsuccessful contract performance. The consideration of risk assesses the degree to which an offeror’s proposed approach to achieving the technical factor or subfactor may involve risk of disruption of schedule, degradation of performance, the need for increased Government oversight, and the likelihood of unsuccessful contract performance.
8. Clarification. Limited exchanges between the Government and offerors that may occur when award without discussions is contemplated. See FAR 15.306(a)(1).
5. Volume I – Factor I: Design Narrative
5.1 Submission Requirements:
5.1.1 Provide a clear and concise narrative describing your proposed design process for this project, especially with regard to sequencing of work within the building renovation. Proposed narratives shall also address the design process and logic/rationale for the following project features:
Architectural Structural HVAC System Abatement of Hazardous Materials Energy Conservation Technique Sustainable Design Strategies (LEED)
The narrative shall also note any improvements exceeding the RFP requirements, including an explanation of proposed building systems, as outlined in Section 01 02 00.00 48, Statement of Work.
NOTE: There is a limit of ten (10) 8.5” x 11” pages, using a minimum font size of 11 and a minimum margin of one-half inch on all sides, for the Design Narrative factor. Any information that exceeds the page limit will not be evaluated.
5.2 Evaluation Criteria:
5.2.1 The Design Narrative will be evaluated based on the offeror’s understanding of the requirements of the
USACE design / build process. The design narrative shall provide a clear rationale of the DOR's internal design processes, the design submittal process and submittal requirements, Dr. Checks and comment resolution, and design completion. Proposals should demonstrate a comprehensive understanding for the design of this project’s requirements. The design narrative will be evaluated for completeness by including the building features of the RFP as outlined in Section 01 02 00.00 48 Statement of Work.
6. Volume I – Factor II: Management Plan
6.1 Submission Requirements:
Provide a management plan narrative for the project that describes how your labor, resources, designers, subcontractors, and material suppliers will be managed, supervised, coordinated, and used to ensure successful completion of the project. Additionally, the Management Plan shall include the following information:
Identification of the three (3) most significant risks and demonstrate your mitigation strategy to address those risks.
NOTE: There is a page limit of five (5), 8.5” x 11” pages, using a minimum font size of 11 and a minimum margin of one-half inch on all sides for this factor. Any information that exceeds the page limit will not be evaluated. Certificates and qualifications do NOT count towards the total page limit.
6.2 Evaluation Criteria:
6.2.1 Management Plan narratives will be evaluated based on the level of understanding of the work and the involvement the contractor will have in the management, oversight, control, and coordination of the work performed during construction of the project. The Management Plan will be evaluated for how well it demonstrates how the offeror plans to manage this project in particular, what critical tasks in this solicitation they believe needs more attention to help mitigate risk, experience managing other USACE projects, and experience using the Resident Management System (RMS). Narratives that demonstrate a clear understanding of the Army Reserve design requirements and USACE construction execution processes, and provide a thorough approach for successfully managing the solicited project may be rated more favorably by the SSEB.
7. Volume I – Factor III: Schedule Narrative
7.1 Submission Requirements:
Based on the project budget and scope, provide a schedule narrative describing the construction sequence / process for successful completion of each phase of the project (Design, Construction, Commissioning and Close-Out) within the duration shown in FAR 52.211-10. The Schedule Narrative shall address at a minimum the major construction milestones and tasks indicated below:
Design Phase / Packages Construction Phasing Pre-Construction Submittals and Review Long Lead Items Commissioning with critical submittals As-Builts Closeout
NOTE: There is a page limit of five (5) 8.5” x 11” pages, using a minimum font size of 11 and a minimum margin of one-half inch on all sides for narrative portion of this factor. Any information that exceeds the page limit will not be evaluated.
7. 2 Evaluation Criteria:
The narrative will be evaluated based on the understanding of events identified in paragraph 7.1 above and the offeror’s capability to complete the schedule within the contract duration. Narratives that demonstrate a clear understanding of the schedule impacts of the major milestones and tasks and provide a thorough approach for successfully completing the contract within the contract duration may be rated more favorably by the SSEB. Schedules offering duration less than that shown in 52.211-10 may receive a higher rating if the proposed schedule is shown to be realistic and achievable while still addressing the major milestones and tasks required without reducing Government Review time.
NOTE: The SSEB will evaluate the offeror’s schedule narrative using calendar days, not dates. The Government reserves the right to accept or decline a proposed shorter duration as part of the contract award. Should the Government accept the proposed shorter duration, the contract completion stated in 52.211-10 will be replaced with the offeror’s proposed completion duration.
8. Volume I – Factor IV: Small Business Participation Plan
8.1 Submission Requirements
ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN.
The Small Business Participation Plan shall be based on the offeror’s best effort and is required to address each of the following areas individually:
The extent to which the Small Business Programs listed in FAR 19 (Small Business, Small
Disadvantaged Business, Woman-Owned Small Business, HUBZone, Service-Disabled Veteran- Owned Small Business, etc.) are specifically identified in the Small Business Participation Plan;
The extent of participation of such firms in terms of the value of the total acquisition in %’s for the Base proposal and for each individual Option; the extent of commitment to use such firms (for example, enforceable commitments, i.e., teaming agreements signed, are to be considered more heavily than non-enforceable ones);
The complexity and variety of the work small firms are to perform on this acquisition;
The practicality of the Small Business Participation Plan, i.e., aggressive goals.
The Small Business Participation Plan shall be organized as follows:
(1) Prime Contractor type of business (check all that apply):
( ) Large ( ) Small (also check type of small business) ( ) Small Non-Disadvantaged Business ( ) Small Disadvantaged Business ( ) Woman-Owned Small Business ( ) HUBZone Small Business ( ) Veteran-Owned Small Business ( ) Service-Disabled, Veteran-Owned Small Business
(2) Percentage of your participation as a prime contractor: __________________ %
NOTE: Small Business primes’ self-performance counts as Small Business Participation, and Small Business primes may achieve Small Business Participation goals through their own performance/participation as a prime and/or through subcontracting to other Small Businesses.
(3) Percentage of total contract value of subcontracts planned for:
% of Total
Contract Value Large % Total Small % Small Non-Disadvantaged % Small Disadvantaged % Small Woman Owned % Small HUB Zone % Small Veteran-Owned % Small Service-Disabled-Veteran Owned %
Each percentage above shall be accompanied by detailed supporting documentation regarding individual commitments.
NOTE: The sum of the percentages of Small Non-Disadvantaged and Small Disadvantaged should equal the entries for the Total Small; however, the sum of all of the percentages need not equal 100% since the prime is not included and individual subcontractors may be counted towards more than one category.
(4) List principal supplies/services (be specific) to be subcontracted to:
Name of
Company Type of
Service/Supply Large Small Non-Disadvantaged Small Disadvantaged Small Woman Owned Small HUB Zone Small Veteran Owned Small Service-Disabled Veteran-Owned
(5) Prior Performance Information: Provide any information substantiating the offeror’s track record of utilizing small business on past contracts.
(6) For Large and Small Businesses provide descriptive information for all small business categories.
Any information concerning long-term relationships with Small Business subcontractors, such as mentor-protégé relationships, should be provided.
(7) Extent of Commitment: Provide documentation regarding enforceable commitments to utilize any small business category as defined in FAR Part 19 as subcontractors.
(8) Small Business Subcontracting Plan: Each Large Business Offeror shall provide a Small Business Subcontracting Plan that contains all of the elements required by FAR Clause 52.219-9 Alt. II. This Plan shall be submitted separately from the Small Business Participation information required above which applies to both Large and Small Businesses. The Subcontracting Plan is not a requirement for evaluation in source selection but rather a requirement for award to a Large Business. The approved Small Business Subcontracting Plan will be incorporated into any resultant contract(s).
8.2 Evaluation Criteria:
The Small Business Participation Plan will be evaluated based on the offeror’s best efforts, the level of small business commitment that is being demonstrated for the proposed acquisition, and the prior level of commitment to utilizing small businesses in performance of prior contracts. The Small Business Participation Plan must meet the minimum Total Small Business Participation goal of fifteen (15%) percent of the total contract value (through collective small business participation from any type of small business or sub-category small business).
The Small Business Participation Plan will be rated using the adjectival ratings listed in Table 5 – Small Business Ratings provided in Section 4.7.
Pursuant to DFARS PGI 215.304(c)(i)(A), the following elements will be considered in evaluating an offeror’s Participation Plan:
The extent to which such firms, as defined in FAR Part 19, are specifically identified in plans;
The extent of commitment to use such firms (enforceable commitments will be weighted more heavily than non-enforceable ones);
The complexity and variety of the work such firms are to perform;
The realism of the plans;
Past performance of offerors in complying with the requirements of the Subcontracting Plan Goals for such firms and monetary targets for participation;
The extent of participation of such firms in terms of the proposed subcontracted value; and The extent to which the offeror provides detailed explanations/documentation supporting the proposed participation percentages, or lack thereof. The Department of Defense (DOD) has established small business goals to help ensure small business receives a fair proportion of DOD awards.
9. Volume II – Price and Proforma Information
9.1 Tab A – Standard Form 1442 and Proposal Price Breakout Schedule.
9.1.1 Submission Requirements:
The offeror shall complete and submit Standard Form 1442 and Section 00 10 00, Proposal Price Breakout Schedule.
9.1.2 Evaluation Criteria:
The price will be evaluated on base proposal plus all options. The price will be evaluated for fairness and reasonableness through the use of a price analysis. Price will also be checked for unbalancing of line items.
Offerors are cautioned to distribute costs appropriately. For HUBZone offerors the HUBZone price evaluation preference of 10% in accordance with FAR 52.219-4 will be applied for evaluation purposes only.
9.2 Tab B – Subcontracting Plan
9.2.1 Submission Requirements:
Large Business offerors shall submit a Subcontracting Plan in accordance with FAR Clauses 52.219-8 and 52.219-9 Alt. II. To be acceptable, plans must adequately address the required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively questions 1 through 13 of Appendix DD, Part 3, AFARS 5119.705-4. The offeror may use the attached sample Sub- Contracting Plan as a starting point. Percentage goals apply to the total amount being subcontracted.
9.2.2 Evaluation Criteria:
Submitted information will be evaluated for acceptability in accordance with AFARS 5119.705. To be acceptable, subcontracting plans must:
(a) Adequately address the required statutory elements.
(b) Provide sufficient information to enable the Contracting Officer to answer affirmatively questions 1 through 13 of Appendix DD, Part 3, AFARS 5119.705-4, a copy of which is attached.
(c) To be acceptable, subcontracting plans must meet all of the requirements outlined in Appendix DD, Part 3, AFARS 5119.705. If discussions with offerors are necessary, those areas where the plan is deficient will be reviewed with each offeror with the goal of correcting deficiencies.
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. THE
GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
RATING DEFINITION NOTE
(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the Contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that Contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions. The Contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal rating is appropriate when a significant event occurred from which the Contractor had trouble overcoming and that impacted the Government/Owner.
(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the Contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred from which the contractor had trouble overcoming and that impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an Unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING THAT BEST REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
a) Quality of technical data/report preparation efforts E VG S M U N
b) Ability to meet quality standards specified for technical performance E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
E VG S M U N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
E VG S M U N
b) Rate the contractor’s use of…