This document is an Asbestos Survey report for the Nolin River Lake Project Office, which is scheduled for demolition. The survey was conducted by Bluegrass Technologies Corporation at the request of the U.S. Army Corps of Engineers. It identified the presence of asbestos-containing vinyl flooring materials in the receptionist area, manager's office, and ranger's office, totaling approximately 735 square feet. The purpose of the survey was to support the demolition project by identifying and quantifying any asbestos-containing materials that require abatement prior to demolition.
The related federal contract opportunity is for the demolition of the existing project office and adjacent storage building at the Nolin River Lake facility located at 2150 Nolin Dam Rd, Bee Spring, KY 42207. The contractor shall be responsible for all planning, programming, administration, management, supervision, communications, and inspection necessary to complete the demolition work in accordance with the contract requirements and all applicable federal, state, and local laws and regulations. The work is to be completed within 120 calendar days of the notice to proceed. Quotes are due on 15 Aug 2024 at 11:00 AM Eastern Time and should be submitted to Donavon.j.waterbury@usace.army.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912QR24Q0098 amendment 1.pdf | ||
| W912QR24Q0098.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLUEGRASS TECHNOLOGIES CORPORATION
Asbestos Abatement.Testing.Consulting
February 2, 2024
Subject:
ASBESTOS SURVEY
2150 Nolin Dam Rd
Bee Spring, KY 42207
Prepared for:
US Army Corps of Engineers
2150 Nolin Dam Rd
Bee Spring, Kentucky 44207
Project:
Nolin Inspection 2024
Prepared by :
Jeff Robinson
Bluegrass Technologies Corp
4533 Poplar Level Rd
Louisville, KY 40213
BLUEGRASS TECHNOLOGIES CORP
Scope of Work - Asbesto Survey
Bluegrass Technologies Corp. conducted asbestos sampling at 2150 Nolin Dam Rd, KY 42207.
It is our understanding that the asbestos needs to be identified for demolition. The purpose of this survey was to identify and sample suspect asbestos containing materials and provide information regarding the identity, location, condition and quantities of ACM in buildding material components.
A survey was conducted on 1-29-2024 by a State of Kentucky-accredited asbestos inspector.
Thirtynine samples were taken in a suspect areas.
Introduction
Bluegrass Technologies Corp. . conducted asbestos sampling at 2150 Nolin Dam Rd, KY. The survey was conducted on 1-29-2024 by a State of Kentucky-accredited asbestos inspector.
Three samples were delivered to an accredited laboratory for analysis by polarized light microscopy. Methodology EPA Method 600/R-93-116
Project Objective
The asbestos survey was requested due to the demolition of the property.
Field Activities
The survey was conducted by Mr. Jeff Robinson, a State of Kentucky - accredited asbestos inspector. License is on file.
Visual Assessment
The survey began with visual observation of the interior structure to identify homogeneous areas of suspect ACM. A homogeneous area consists of building materials that appear similar throughout in terms of color, texture, and date of application.
Building materials identified as concrete, glass, wood, metal or rubber were not considered suspect.
BLUEGRASS TECHNOLOGIES CORP
Findings and Recommendations:
There was asbestos found in the receptionist area, managers office and rangers office.
Building Description: The office building was built in the 1960’s. It is a one story frame building on a concrete slab with a metal roof with vinyl siding approx. 4000
SF.
Summary Review:
Samples 7,12 and 25 were positive for asbestos. The reception area, managers office and rangers office have positive vinyl flooring.
Conclusion:
There is approx. 735 SF of asbestos positive vinyl flooring.
Page 1 Cover Sheet
Page 2 Executive Summary
Page 3 Findings, Summary, Conclusion
Page 4 Bulk Samples 1-29-2024
Page 5 Bulk Samples 1-29-2024
Page 6 Bulk Samples 1-29-2024
Page 7 Bulk Results 1-31-2024
Page 8 Bulk Results 1-31-2024
Page 9 Asbestos Management Planner
Blank Page