SEE ADDENDUM

(No Collect Calls)

W912QR23Q0015

b. TELEPHONE NUMBER

502.315.6213

8. OFFER DUE DATE/LOCAL TIME

12:00 PM 13 Jan 2023

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

20-Dec-2022

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912QR9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

MARCIE BILLOTTO

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

FAX:

TEL: 502.315.7494 SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$16,500,000

NAICS:

238190

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF42

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W912QR23Q0015

Section SF 30 - BLOCK 14 CONTINUATION PAGE

SPECIAL INSTRUCTIONS

Contractor shall provide Axtel Shoreline Stabilization at Rough River Lake in accordance with the attached Performance Work Statement.

The contractor’s work and responsibility will include furnishing all labor, materials, supplies, tools and, equipment necessary to assure that all work is conducted in accordance with the contract requirements and all applicable Federal, State and Local laws and regulations. All work will be performed in strict compliance with the attached specifications and all other terms and conditions incorporated herein. Work shall begin within 14 days after receiving award and must be completed no later than 90 calendar days after receiving the award.

Location:

United States Corps of Engineers Rough River Lake 14957 Falls of Rough Rd Falls of Rough, KY 40119

This procurement is 100% set-aside for Small Business, NAICS 238190, Size Standard $16,500,000.00.

Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.

Note: The contract award will be based on lowest price to the Government. Contractors are encouraged to attend a site visit to review the complexities of the work site, verify existing conditions, and exact measurements.

A site visit is strongly recommended, please reach out to Adam Taylor, Park Ranger at (270) 257-2061 to schedule a site visit.

Quotes are due 13 January 2023, 12:00PM Eastern Time. Fax submittals will not be accepted. Electronic submittals may be emailed to Marcie Billotto at marcie.billotto@usace.army.mil.

All contractors must be registered in the System for Award Management (www.SAM.gov) prior to submission of proposal. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier (formerly DUNS number) for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov.

Refer to www.SAM.gov for information formerly found in CCR, EPLS, ORCA and FedReg.

Please begin the registration process immediately in order to avoid delay of the contract award should your firm be selected.

ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.

Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) within 30 days of activation or the vendor risks no longer being active in SAM.

Vendors can check whether an account is active by performing a query by their CAGE or Unique Entity Identifier (formerly known as DUNS). The new registration process may now take several weeks, so vendors are highly encouraged to begin registering as soon as possible to avoid any possible delays in future contract awards.

Remember, there is no cost to use SAM.

To find out additional information about the changes of the SAM registration process, contractors should visit the Frequently Asked Questions (FAQ) link located at the top of the SAM homepage (www.sam.gov).

Price Breakout Schedule

Item No. Description Unit Qty Total

1 Shoreline Stabilization and revetment Area #1 Job 1 $

2 Shoreline Stabilization and revetment Area #2 Job 1 $

Total Amount $__________

Performance Work Statement Axtel Shoreline Stabilization

U.S. Army Corps of Engineers Rough River Lake

14957 Falls of Rough Rd Falls of Rough, KY 40119 Phone: 270-257-2061

Technical Point of Contact: Adam Taylor

TP-1.1 GENERAL:

1. Description. The contractor shall furnish all materials, labor, supplies, tools, parts, equipment, transportation, labor, supervision, communication, and quality control to conduct shoreline stabilization utilizing a variety of methods and materials. All work shall be in accordance with the specifications listed in section “TP-3.1 General Specifications”. All work will be conducted on the designated shoreline in the Axtel Campground located at 663 South Hwy 79, McDaniels, KY.

2. Terms. Work shall be provided in accordance with all Terms, Conditions, General, Specific and Technical Provision, Maps, etc. contained herein or incorporated by Reference. This includes all mandatory provisions of the Federal Acquisition Regulation (FAR), current at time of award.

3. Contractor Responsibility. Contractor’s work and responsibility shall include but are not limited to supply of equipment/materials, all planning, programming, administration, management, supervision, and inspection required to assure all equipment/materials are acquired and services are conducted in accordance with the contract and all applicable laws, regulations, or directives. The Contractor shall ensure all work meets or exceeds specifications.

The prime Contractor shall be responsible for ensuring all subcontractors comply with the provisions of this contract.

4. Performance Required. Special consideration of the Contractor is directed to the fact that the required accuracy, thoroughness, safety, and progress of this work are essential to the intended purpose. The contractor must be cognizant of the difficulties involved and of the contingencies which may arise, and must make certain that their personnel, equipment, transportation facilities and supply of materials are adequate at all times to ensure complete compliance with all provisions of these specifications. The work shall be done under supervision by competent employees. All contract services shall be in accordance with the submitted documents, and any additions, revisions or deletions must be approved by the Contracting Officer.

5. Completion of Work. Completion of work shall include acceptable performance of all aspects of this contract.

6. Compliance and Certifications: The contractor is responsible for obtaining any permits, conducting any tests or inspections, and paying any associated fees necessary to complete work as specified herein. The work shall be accomplished in accordance with all local, state, and federal laws and regulations including but not limited to American Society for Testing and Material (ASTM), American Society of Mechanical Engineering (ASME), American Nation Standards Institute (ANSI), Occupational Safety and Health Administration (OSHA) and all applicable codes.

The Contractor’s work and responsibility shall include all planning, measurements and estimates of quantities, administration, supervision, communications, and inspections necessary to assure that all services are conducted in accordance with the contract requirements and all applicable Federal, state, and local laws and regulations.

7. Pre-Work Conference. The contractor will be required to attend a pre-work conference at least one week prior to beginning work, during which time the Contractor shall supply the Technical Point of Contact (TPOC) with an Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA), in accordance with EM385-1-1 (latest edition) covering the contractor’s plan of work procedures, safety procedures, security, schedule, and equipment.

This manual will be available on the Internet at:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

The Contractor shall supply material submittals for this project, which must be approved by the TPOC prior to start of work.

8. Damages. The contractor shall be responsible for all damages to government or private property resulting from negligent operations during the course of this contract. The contractor shall have appropriate insurance to cover liability and damages. The contractor shall be responsible for compensating the government for any damage to government property and/or restoring and replacing in kind any such existing property damaged or destroyed by the Contractor through faulty handling as the Technical Point of Contact (TPOC) directs, at no expense to the Government.

9. Hours and Days of Work. Construction work may be conducted between 0630 and 1600, Monday through Friday. No work shall be performed outside of these times, on Saturday or Sunday, or on federal Holidays, unless approved by the TPOC.

New Year's Day (January 1st) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Juneteenth (June 19th) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)

10. Payment Procedure/Additional Work. At no time should the contractor do additional work without prior authorization of the Contracting Officer, and no work shall be performed that will cause the Contractor to exceed the contract price. Work performed without a binding contract document authorizing such work shall result in the Contractor not being paid for that work performed. During the course of the contract, any additional work determined to be needed may be requested by the TPOC to the Contracting Officer for a Contract Modification.

11. Contract Start and Completion Dates. Work under this contract shall begin within 14 days after receiving the award and must be completed no later than 90 calendar days after receiving the award. All work must be completed when lake levels are below 485 ft. Additional time may be granted for inclement weather.

12. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. In order for the Contracting Officer to award a time extension due to an excusable delay, the following conditions must be satisfied.

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

c. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER

DELAY WORK DAYS BASED ON (5) DAY WORK

WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

[5] [4] [5] [6] [6] [6] [5] [4] [4] [4] [4] [6]

Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated listed above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification.

14. Liquidated Damages. Not Used.

15. Wage Rates: Department of Labor wage rates apply to this work and are included. The contractor is required to provide payroll documents for all work performed under this contract.

16. Material, Equipment, Supplies Protection. The Contractor shall, at all times prior to delivery, take care to protect and preserve all materials, supplies, and equipment of every description (including material and property which may be Government owned) and all work performed. All reasonable requests of the Contracting Officer or his/her authorized representative to enclose or specially protect such property shall be complied with. If so determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payment due to them. This work will take place in a public use area. The contractor is responsible for the security of any equipment left on the job site. The contractor shall provide for the safety of the public through housekeeping, signage, and adequate designation of treatment zones.

17. Communication. The Contractor will notify the Contracting Officer or TPOC, upon commencement of work activities, and difficulties, interruption, or suspension of work, and when the required work has been completed. The Contractor shall update the Contracting Officer, or TPOC, no less than once weekly on status of work being done. Work will commence when a notice to proceed has been issued from the Contracting Officer and TPOC notified.

18. SITE VISIT. The Scope of Work only contains approximate measurements for reference. Each offeror should visit the job site and assume responsibility for quantities, materials, critical dimensions, and work conditions used to calculate a quote. Interested bidders should contact the TPOC to schedule a site visit. The TPOC contact information is as follows:

Adam Taylor USACE Louisville District Rough River Lake 14957 Falls of Rough Road Falls of Rough, KY 40119 Phone: 270-257-2061

19. Utilities. The contractor may utilize Government furnished utilities (electricity) to undertake work under this contract.

TP-1.2 CONTRACTOR SUBMITTAL. Unless otherwise specified, the Contractor shall submit the following information to the TPOC prior to the pre-work conference for this contract:

1. Safety Plans. The Contractor shall submit, for acceptance by the TPOC, an Accident Prevention Plan, Activity Hazard Analysis (AHA), Fall Protection Plan, and Scaffolding Plan in accordance with the requirements of the Corps of Engineer’s Safety and Health Requirements Manual, EM 385-1-1, hereinafter referred to as the Safety Manual, current at the time of award.

Certification of Employees Qualified to Administer First Aid and CPR. The Contractor shall submit proof the appropriate number of employees, as required in the Safety Manual, are certified to administer First Aid and CPR. 3. Certificate of Insurance. The Contractor shall, at their own expense, provide and maintain during the entire performance of this contract the following Insurance Type: General Liability (Bodily Injury and Property Damage Combined) Minimum Amounts of Liability, $1,000,000.00 Each Occurrence, $1,000,000.00 Aggregate. The contractor is required to provide a Certificate of Insurance to the TPOC at the time of the Pre-Work Conference.

TP-1.3 SAFETY.

1. General Safety. The Contractor shall comply with the safety standards contained in Corps of Engineers Manual, EM 385-1-1, “Safety and Health Requirements Manual”, current at the time of award, as well as all current provisions of the Occupational Safety and Health Act (OSHA). Per Par. 01.A.17 of EM 385-1-1, the Site Safety and Health Officer (SSHO) is only required to have the minimum listed requirements. The contractor can find it at this link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

Copies of documents proving that the Site Safety and Health Officer has met all minimum requirements per Par.01.A.17 of EM 385-1-1 shall be provided to the TPOC before work begins under this contract.

2. Safety Manual Requirements. The Contractor and employees shall comply with all pertinent sections of the Corps of Engineer’s Safety and Health Requirements Manual, EM 385-1-1, current at the time of award, and any subsequent revisions. The Contractor’s safety plan must be submitted in writing prior to onsite work and can be turned in at the same time as the pre-work conference.

3. Personal Protective Apparel and Equipment. Protective apparel and equipment, as identified in the Activity Hazard Analysis (AHA), shall be provided by the contractor to eliminate or minimize hazards to personnel. As a minimum, each employee shall wear a sleeved shirt, long trousers and safety-toe shoes or boots during all contract work. Hard hats, face shields, safety glasses with side-shields, or goggles, and hearing protection shall be worn by employees when required by safety manual. Fire extinguisher(s) and first aid kit(s) meeting the Safety Manual standards shall also be provided and easily accessible to all employees.

4. Contractor Employees Certified in First Aid & CPR. The Contractor shall schedule employees, so the appropriate numbers of certified personnel are on duty to administer First Aid and CPR as required by the Safety Manual. Copies of their certification shall be provided before work begins under this contract.

5. Equipment Compliance. The USACE EM 385-1-1 is more stringent than OSHA, especially for load handling equipment. IT specifically includes, but is not limited to the items in Chapter 16 (Load Handling Equipment) and 18 of the manual or the items listed below:

a. Certification of compliance (16.A.02)

b. Standard lift planning (16.A.03)

c. Critical lift planning (16.H)

d. Personnel Qualifications (16.B) (i.e. NCCCO and physicals)

e. Equipment Inspections and forms (16.D)

f. Safety Devices and Operational Aids (16.E)

g. Operational Manuals, Load Charts, Logs (16.G.01)

TP-1.4 ACCIDENT REPORTING. The Contractor shall maintain accurate accident records and report accidents as prescribed by the TPOC. Accidents shall be reported within 24 hours of occurrence, including accidents occurring on holidays and weekends and all serious accidents (those resulting in death or injury requiring medical attention or lost time) shall be reported immediately.

TP-1.5 DAMAGE REPORTS. In all instances where Government property, equipment, natural features, landscape, or trees are damaged by contract employees, an immediate notification shall be made to the TPOC. A full report of the incident and extent of such damage shall be submitted to the TPOC within two working days of occurrence, excluding weekends and holidays.

TP-1.6 CONTRACT EMPLOYEES. All contract employees shall conduct themselves in a proper and courteous manner at all times. Contract employees shall comply with all provisions of Title 36, Chapter III, Part 327, CFR and obey all posted signs and regulations in the performance of the work under this contract. Being under the influence of, or consuming alcoholic beverages or controlled substances by the Contractor or employees while on duty is prohibited.

TP-1.7 QUALITY ASSURANCE. The Government will monitor the Contractor’s work and examine completed work to determine whether work is performed and completed in compliance with purchase order specifications.

The TPOC is responsible for the Government’s Quality Assurance Program under the purchase order. The TPOC and/or his designated Quality Assurance Inspector (QAI) will observe the work being performed and inspect completed work. The contractor and the TPOC/QAI shall coordinate work schedules and inspections to best evaluate contractor performance. The Government will use 100% inspections to evaluate the work provided under this contract. If the completed work does not conform to the requirements under the contract, the Government may require the contractor to remedy the work until it satisfactorily meets the requirements of the contract specification. When the deficiencies cannot be corrected by re-performance, the Government may reduce or deduct the purchase order price to reflect the reduced value of the work performed or pursue claims as detailed in the FAR clauses contained in the contract.

TP-1.8 Security.

1. General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative.

The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

2. Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

3. Suspicious Activity Reporting Training (e.g., iWATCH, CorpsWatch, or See something, Say Something).

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the TPOC, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the TPOC NLT 5 calendar days after the completion of the training.

4. Pre-Screen Candidates/E-Verify Program. Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

TP- 2.1 SPECIAL REQUIREMENTS:

1. Payment. Payment will be made by Electronic Funds Transfer (EFT), upon acceptance of the completed work and providing final invoice and labor records. This process can take approximately 30 calendar days to process after the invoice is submitted to the U.S. Army Corps of Engineers at Rough River Lake for payment following completion of work.

Unique Entity Identifier and SAM Registration. The successful offeror will be required to provide a Unique Entity Identifier, (http://dnb.com), and will be required to be registered with System for Award Management (SAM), (https://www.sam.gov/) to do business with the government. (NOTE: Pay careful attention when typing in the SAM website address on your browser). In order to register with SAM, you must have a Unique Entity Identifier. If you are unsure of your Unique Entity Identifier, or have questions regarding this, you can call 1-800-333-0505 for assistance. Offerors must complete their registration in SAM in order to be eligible submit a quote under this contract.

2. Unresponsive Quote. Failure to provide all information requested within this solicitation and to complete SAM registration may be grounds for considering the quote unresponsive.

FOR OFFICIAL USE ONLY

SUPPLEMENTAL SECURITY REQUIREMENTS

All Contractors and subcontractor employee(s) working on this contract who require access to any Louisville District Lake Projects and Lock and Dam Projects shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12:

Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12). The Louisville District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Louisville District Security Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Louisville District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.

FOR ALL LOUISVILLE DISTRICT CONTRACTS:

Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Louisville District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted access to Louisville District facilities.

The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working,

(2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) US Citizens Security Access Form or Pre-Bid/Site Visit Form; each employee working on site must have a background investigation form submitted directly to the Louisville District Security Office.

The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.

Contractors shall have background checks completed for their employees annually in the case of Contracts with an initial period of performance (POP) greater than 1 year and those Contracts with Options or Modifications Which Extend the POP beyond 1 year. For instance, if the employee was cleared in May of 2022, they shall be cleared again in May of 2023. It is the Contractor’s responsibility to ensure that each employee’s security is up to date.

Failure to comply may lead to possible removal from the project/jobsite.

The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they must process the employee through the Louisville District USACE Security Office for background purposes.

FOR CONTRACTORS REQUIRING DOD COMMON ACCESS CARDS (CAC)

The documents listed below are required:

SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). Fingerprints are captured electronically at the closest Army Recruiting Station to the contractor’s home of record or at the USACE, Louisville District Security Office.

Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.

FOR OFFICIAL USE ONLY

Following submission of paperwork, the Louisville District Security Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Louisville District Security Office will make recommendations to the PCO or their Designated Representative. The Louisville District Security Office cannot give approval due to unfavorable report(s). The Louisville District Security Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.

FOREIGN NATIONALS

The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:

In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.

In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Louisville District Security Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.

Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.

The Contractor shall contact the Louisville District Security Office by phone, letter, or email at the following numbers/addresses:

CELRL-SC

600 Martin Luther King Jr. Pl Louisville, KY 40202

Charles R. Tanner, phone (502) 315-6929; email Charles.R.Tanner@usace.army.mil James R. Milner, phone (502) 315-6916; email James.R.Milner@usace.army.mil Jason Almodovar, phone (502) 315-6754; email Jason.Almodovar@usace.army.mil

Performance Work Statement (PWS):

1. General. The work will involve stabilizing the reservoir bank by re-sloping an area of shoreline, installing a toe barrier, adding, and compacting topsoil, drilling seed, spreading straw, overlaying and placing new sections of rip rap, and creating pedestrian accesses to the water. This work shall be accomplished though different line items and will be split between two separate sections of the same bank named Area #1 and Area #2 in Axtel Campground.

A. Area #1 (Exhibit A):

1. Re-sloping approximately 250’ of shoreline with low impact equipment to no more than a 2:1 slope:

a. Re-slope and grade an area approximately 250 ft x 50 ft to remove current cutbank and large loose rocks to create a smooth grade. Only tracked equipment will be used to reduce soil disturbance in the area.

b. Riprap toe anchor 2 ft in depth x 4 ft in width will be installed along the shoreline. This toe anchor will be approximately 200 ft. in length to catch any sedimentary material and retain it on the bank. This toe anchor will run along the summer pool line with the bottom edge of the toe being elevation 495 ft. The rip rap toe shall tie into the existing rock features upon the termination at the beginning and the end. See Exhibit C for an example of a rock toe drawing.

c. The contractor will add 24 inches of topsoil and compact the area to bring the slope back to an adequate grade that blends into existing topography. Once the topsoil is in place and compacted, all disturbed areas will be slightly agitated to a maximum depth of ½ inch, cleaned of all clumps and debris, and ready to seed.

d. Drill a 50/50 mixture of Kentucky 31 fescue combined with a shade tolerant grass seed mix into newly prepared seed bed and all other disturbed areas. Cover all disturbed areas with straw mat to reduce erosion. Straw mat must be biodegradable.

e. Refresh existing riprap areas shown on Exhibit A by adding new riprap to create a smooth uniform surface. The riprap in these areas should not exceed 18 inches in depth.

B. Area #2 (Exhibit B):

2. Refresh and extend current sections of Rip rap below sites 112, 113, and 114 in Axtel Campground to stabilize the shoreline.

a. Re-slope and grade an area approximately 200ft x 10ft to remove current cutbank and large loose rocks to create a smooth grade. Only tracked equipment will be used to reduce soil disturbance in the area.

b. Add riprap to the same section of shoreline mentioned in (a) above, approx. 200ft long and 25ft wide.

c. Create 4ft wide pedestrian access through the riprap to the water from campsite 113 and 114. This area should be constructed from 2-4 inches of compacted dense grade gravel. Install treated 4x4 water bar every 20 ft to reduce erosion. 4x4 will be anchored to the ground with 18-inch cross tied rebar pins on both ends. Water bars will be flush with the final surface of the compacted dense grade and will extend across the entire width of the pathway. The slope of the newly created access will match slope of the existing topography and the pathway will be built in a manner which is suitable for easy walking and will not easily erode.

TP-3.1 GENERAL SPECIFICATIONS:

d. Spread or drill native grass seed mix into all disturbed areas. Cover all disturbed areas with straw or straw mat to reduce erosion. Straw mat must be biodegradable.

Considerations:

1. The Technical POC must be contacted prior to beginning work to allow access into the area.

A minimum of 24 hours’ notice must be given to the technical POC to gain access to the area.

2. All staging areas must be left in the same condition prior to use and delivery of any products.

Any apparent degradation from use because of this project will be restored back to the previously disturbed condition.

3. Disturbed Areas Outside of Shoreline Stabilization Work Area: All disturbed areas shall be seeded with a 50/50 mixture of Kentucky 31 fescue combined with a shade tolerant grass.

Upon completion of the seeding the entire disturbed area shall be covered with straw.

4. All work shall be done at or below elevation 485 MSL.

5. All rock utilized shall be sound, dense, durable, and free of toxic pollutants in accordance with the KY DOT.

6. All work must be completed prior to December 31 2023.

2. Dimensions. The contractor should field verify dimensions, etc. prior to submitting a quote. The dimensions listed in the specification herein are approximate and should not be considered completely accurate.

3. Submittals. The Contractor submittals shall be furnished in accordance with the specifications. All listed items shall be submitted for Government approval by the TPOC. Associated work items shall not be performed until receiving approval from the TPOC. The TPOC shall provide a response to the submittals within 15 calendar days of receipt.

a. Accident Prevention Plan (APP)

b. Activity Hazard Analysis (AHA)

c. Project Schedule

4. Waste Disposal. The contractor will remove all demolition debris and left-over construction debris to a site licensed to receive/recycle construction debris. The contractor is responsible for any waste disposal and any permits and fees associated with disposal.

5. Permits. The contractor is responsible for obtaining any construction permits, conducting any tests or inspections, and paying any associated fees necessary for this contract. All work shall be coordinated through the TPOC, Adam Taylor, 270-257-2061.

REPRESENTATIONS & CERTIFICATIONS

COMPANY NAME AND ADDRESS: __________________________________________

PHONE NUMBER _____________________ FAX NUMBER _____________________

EMAIL ADDRESS ________________________________________________________

BUSINESS SIZE (select one)

Large Business _____ Small Business_____ HUBZone Business_____ 8A _____

Woman-Owned ____ Service-Disabled Veteran-Owned ____

Contractor is registered with SAM: _____ YES _____ NO

(See FAR 52.204-7)

TAX ID # ______________________

INDICATE Unique Entity Identifier (previously DUNS NUMBER) ___________________ (This is 9 digit numeric code)

CAGE NO. _________ (Note: See Unique Entity Identifier (FAR 52.204-7)

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.212-4 Contract Terms and Conditions--Commercial Products and

Commercial Services

NOV 2021

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

SEP 2013

52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

AUG 2018

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

NOV 2021

52.245-1 Government Property SEP 2021 52.245-9 Use And Charges APR 2012 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

SEP 2022

252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019 252.204-7015 Notice of Authorized Disclosure of Information for Litigation

Support

MAY 2016

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

JAN 2021

252.211-7007 Reporting of Government-Furnished Property MAR 2022 252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7055 Representation Regarding Business Operations with the

Maduro Regime

MAY 2022

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime

MAY 2022

252.225-7972 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems (DEVIATION 2020-O0015)

MAY 2020

252.225-7973 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems - Representation (DEVIATION 2020- O0015)

MAY 2020

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports

DEC 2018

252.232-7010 Levies on Contract Payments DEC 2006 252.232-7017 Accelerating Payments to Small Business Subcontractors--

Prohibition on Fees and Consideration

APR 2020

252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel

JUN 2013

252.244-7000 Subcontracts for Commercial Items JAN 2021 252.245-7001 Tagging, Labeling, and Marking of Government-Furnished

Property

APR 2012

252.245-7002 Reporting Loss of Government Property JAN 2021 252.245-7003 Contractor Property Management System Administration APR 2012 252.245-7004 Reporting, Reutilization, and Disposal DEC 2017 252.247-7023 Transportation of Supplies by Sea FEB 2019

CLAUSES INCORPORATED BY FULL TEXT

52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)

(a) Definitions. As used in this clause--

Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.

Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).

Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

Safeguarding means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and…