JT Meyers - Contractor Questions.pdf

PDF 72 KB Posted

Attached to
Crossover Pipe & Ladder Repair at JT Myers Locks and Dam
Solicitation number
W912QR23Q0005
Issued by

View the file

Other files

File Type Posted
Amendment0003.pdf PDF
Amendment0002.pdf PDF
W912QR23Q0005.pdf PDF
Amendment0001.pdf PDF
Horizntal Hydraulic Pipe.JPG JPG image
Utility Piping.pdf PDF
Crossover Hatch Inside.jpg JPG image
W912QR23Q0005.pdf PDF
Air Fuel Non Potable Water Sewer Pipes.JPG JPG image
Downstream Crossover.pdf PDF
Crossover Ladder.jpg JPG image
Ladder Middle.jpg JPG image
DS Ladder.pdf PDF
Hydraulic Pipe 90 Degree.jpg JPG image
Crossover Hatch Outside.jpg JPG image
Utility Pipe.jpg JPG image
Vertical Hydraulic Pipe.JPG JPG image
Piping.pdf PDF
Hydraulic System.pdf PDF
Air Fuel Non Potable Water Sewer Pipes 2.JPG JPG image
1200 and 600 Chamber Overview.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JT Meyers L&D – Crossover Pipe & Ladder Repair - Contractor Asked Questions

• Question #1 – Please clarify the anticipated limits of repair for line item #3 – Pressurized Air Line?

• Question #2 - Please clarify the anticipated limits of repair for line item #4 – Non-Potable Water Line?

• Question #3 - Please clarify the anticipated limits of repair for line item #5 – Fuel Line?

• Question #4 - Please clarify the anticipated limits of repair for line item #6 – Sewage Line?

• Question #5 – Please confirm that the auxiliary lock may be closed for two (2) 12-hour periods within a seven (7) day period and closed for five (5) 4-hour periods the remaining days of the seven (7) day period?

Answer

Anticipated limits for all piping are the same as the limits for hydraulic pipe, 5ft horizontal, 25ft vertical.

Confirmed two (2) 12-hour periods within a seven (7) day period and closed for five (5) 4-hour periods the remaining days of the seven (7) day period.

• Question #7 Please confirm the replaced pressurized air line material will be same material type as the existing pipe?

• Question #8 Please confirm the replaced non-potable water line material will be same material type as the existing pipe?

• Question #9 Please confirm the replaced fuel line material will be same material type as the existing pipe?

• Question #10 Please confirm the replaced sewage line material will be same material type as the existing pipe?

Answer

The piping materials shall be replaced in kind.