W912QR23Q0003 - Renovation of Yates Log House at Taylorsville Lake
Solicitation number
W912QR23Q0003
Issued by

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovation of existing Yates' historical log house and Ashes Creek Schoolhouse located at Taylorsville Lake in Spencer County, Kentucky.

Estimated construction cost is betw een $100,000.00 and $250,000.00.

Aw ard w ill be based on the low est total price (base plus options).

This project is set-aside 100% for Small Business.

NAICS Code: 236220. Size Standard: $39.5 Million.

Please note that business size in SAM is determinated by the NAICS code. If the vendor size is not listed correctly for a particular NAICS code in SAM, the business w ill be considered other than a small business.

Central Contractor Registration and ORCA are now available through the System for Aw ard Management (SAM), available at w w w .sam.gov.

PLEASE NOTE: SAM is completely free of charge for both registrants and users.

Block 12A Below : In lieu of Performance and Payment bonds, per FAR 52.228-13 Alternate Payment Protections (2000), Payment Bonds or Irrevocable Letter of Credit is required. A Performance Bond is not required.

ADYSON MEDLEY 502.315.7494

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

01-N0V-2022

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______30 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time 21 NOV 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR

PAGE OF PAGES

1 OF

CODE W912QR

(Title, identifying no., date):

12B. CALENDAR DAYS

10:00 AM (hour)

Sealed envelopes containing offers

CIVIL/OPS/ENVIRONMENTAL BR

ATTN: ADYSON MEDLEY

600 DR M L KING JR PL RM 821

LOUISVILLE KY 40202-2236

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: 502.315.7494 TEL: 502.315.6211 FAX:

W912QR23Q0003 41

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912QR23Q0003

Section 00 10 00 - Solicitation

SPECIAL INSTRUCTIONS

This Request for Quote (RFQ) is for the contractor to furnish all personnel, equipment, supplies and materials necessary. Prices should include mobilization & de-mobilization, fuel, labor, material, and equipment for the renovation of existing Yates Log House and Ashes Creek Schoolhouse located at Taylorsville Lake in Spencer County, Kentucky in accordance with the attached Scope of Work (SOW).

Location:

United States Corps of Engineers Taylorsville Lake 2825 Overlook Road Taylorsville, KY 40071

This procurement is 100% set-aside for Small Business, NAICS 236220 (Size Determination $39.5M).

Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.

One award will be made from this Solicitation.

Note: The contract award will be based on Lowest Total Price (base plus options) to the Government.

Quotes are due on 21 November 2022 at 10:00 AM Eastern Time.

Electronic submittals will be accepted. You may submit your quote to adyson.medley@usace.army.mil. Fax submittals will not be accepted.

For contractual questions, please contact Adyson Medley at (502) 315-6211 or by e-mail at adyson.medley@usace.army.mil.

**ALERT: All contractors must be registered in the System for Award Management (www.SAM.gov) prior to contractors’ submission. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. Effective June 29, 2018 vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) within 30 days of activation or the vendor risks no longer being active in SAM. Vendors can check whether an account is active by performing a query by their CAGE or Unique Entity Identifier (known as DUNS).

The new registration process may now take several weeks, so vendors are highly encouraged to begin registering as soon as possible to avoid any possible delays in future contract awards. Remember, there is no cost to use SAM. To find out additional information about the changes of the SAM registration process, contractors should visit the Frequently Asked Questions (FAQ) link located at the top of the SAM homepage (www.sam.gov).

PLEASE NOTE: SAM is completely free of charge for both registrants and users.

Note: Page numbering in this document may not be accurate.

PRICE BREAKOUT SCHEDULE

ITEM DESCRIPTION UNIT

PRICE

UNIT OF

ISSUE

QTY. TOTAL

BASE Selective log replacement/repair, installation of lap siding, and construction of north side porch

$ JOB 1 $

OPTION 1 Roof Replacement Yates Log House

$ JOB 1 $

OPTION 2 Roof Replacement Ashes Creek Schoolhouse

$ JOB 1 $

OPTION 3 Roof Decking, Inspection, Replacement, and Preparation Yates Log House & Ashes Creek Schoolhouse

$ PER BOARD 1 $

TOTAL OF BASE AND ALL OPTIONS $

NOTE: Option 3 may be exercised up to 100 times.

Scope of Work

Taylorsville Lake 2825 Overlook

Road Taylorsville, KY 40071

The contractor will furnish all personnel, equipment, supplies and materials necessary. Prices should include mobilization & de-mobilization, fuel, labor, material, and equipment for the renovation of existing Yates Log House and Ashes Creek Schoolhouse located at Taylorsville Lake in Spencer County, Kentucky. The contractor’s work and responsibility will include all planning, programming, administration, management, supervision, communications, and inspection necessary to assure that all work is conducted in accordance with the contract requirements and all applicable Federal, State and Local laws and regulations. All work will be performed in strict compliance with the attached specifications and all other terms and conditions incorporated herein.

Taylorsville Lake will furnish access to necessary water supply, restroom facilities, and needed electrical outlets.

Prior to the commencement of work, a pre-construction meeting shall be held with a Corps of Engineers representative and the contractor.

Contractor shall commence work within 30 calendar days from the issuance of the Notice to Proceed (NTP) and complete the work no later than 180 calendar days from the issuance of the NTP.

The building is sited to face the North. On the North and South elevation lowest log is identified as the sill log, then the #1 log above and then #2 and on to # 10 at the top. # 10 is also the bearing log for the rafters On the East and West elevations the lowest log bears on the sill logs. The lowest log is identified as #1 and then # 2 and on to the top # 10.

Contractor shall verify dimensions of all timbers, window, door and other openings prior to manufacturing or installing any such item. Contractor shall verify the actual size required for each opening. Retain any elements of building that are removed during demolition and renovation process and retain for reuse when reconstructing. Any elements that cannot be salvaged, the contractor will match original in design, material and finish.

All materials that were removed for replacement shall be cleaned up and removed at the contractor’s expense.

Unless specified, replacement wood should be naturally rot resistant species such as White Oak or Walnut. Wood lap siding can consist of Western Red Cedar or similar rot resistant species.

Base Item: Selective log replacement/repair, installation of lap siding, and construction of north side porch.

North Side:

1. Remove the three-sided stone steps.

2. Remove all daubing, metal mesh, insulation, and fill materials between the logs.

3. Replace the entire sill log and install borate impel rods in the lower side as per product specifications, typically along the center line every 18 inches.

4. Replace the entire log #1 to the left and right of the door.

5. Treat the entire exterior surface with wood preservative, insect repellant, and a D/2 biological solution, as per product specifications to remove and retard biological growth.

6. Construct a porch that runs the entire width of the north side and extends eight (8) feet out from the front of the cabin. The roof structure shall be permanently attached to the Cabin between the upper and lower windows and have a minimum slope of ¼’ per foot. The roof rafters shall be constructed out of 2”x4” rough-cut White Oak lumber with 12” spacing. The floor joists shall be constructed out of 2”x8” #2 pressure treated pine lumber. The floor decking shall be constructed out of 1” thick rough-cut White Oak lumber. The posts shall be rough cut White Oak 6”x”6 and spaced no more than 8’ apart in any direction. The foundation of the porch shall rest on stacked stone piers that are adequately spaced to support the entire porch and match the existing stone foundation. All fasteners such as nails, screws, bolts, etc. shall be coated or galvanized. The roof covering of the porch shall be 5V galvanized metal and have a minimum 2” drip edge. Steps shall be constructed centered with the front door with a total minimum width of 4’, maximum 7” riser height, and handrail consistent with the building materials listed above.

7. Replace door sill/threshold plate. Replace all exterior trim around the existing door.

Match original sill in all respects. Once completed, the door shall be weather tight and shut/lock without any problems. Exterior refers to any woodwork that is directly exposed to weather elements.

8. Replace the sill/threshold and all trim work around the exterior of each of the 2 lower windows. Ensure all sills have adequate slope to allow for drainage away from the window. Remove, repair, and repaint window sash and reglaze windows as necessary.

Once completed, the windows shall be weather tight. Exterior refers to any woodwork that is directly exposed to weather elements.

9. Replace all daubing below the roof structure with Natural Hydraulic Lime cement and river sand or at least a sand with similar coloration. The backing should be stainless steel (ss) expanded metal, nailed or screwed with ss fasteners. The daubing for exterior logs should be sloped outward from behind the upper log face to the edge of the lower log face.

10. Install wood lap siding on the entire exterior surface above the newly installed front porch. No finger jointed siding is allowed. The lap siding must be primed with oil alkyd primer on all sides before installation and a second coat applied after installation, brush application only. Use 15# felt to flash at corners, windows, and doors prior to installation. When siding goes over a door or window install metal flashing. To allow for movement put only one nail through siding. Using stainless steel or galvanized ring shank nails, nail just high enough so the nail does not penetrate the siding below. Siding should be tightly butted. Cut 4” x 6” strips of 15# felt to insert beneath all butt to butt joints. It should lap over lower siding to direct any water back to the exterior. Caulk all vertical joints, no horizontal joints will be caulked.

11. Replace the sill/threshold and all trim work around the exterior of each of the 2 upper windows. Ensure all sills have adequate slope to allow for drainage away from the window. Remove, repair, and repaint window sash and reglaze windows as necessary.

Once completed, the windows shall be weather tight. Exterior refers to any woodwork that is directly exposed to weather elements.

12. Install an adequate trim piece/flashing where the trim meets the new roof.

East Side:

1. Remove all daubing, metal mesh, insulation, and fill materials between the logs.

2. Remove the board and batten siding and the horizontal framing.

3. Repair deterioration along the bottom edge and butt end on the south end of the #1 log.

4. Treat the entire exterior surface with wood preservative, insect repellant, and a D/2 biological solution, as per product specifications to remove and retard biological growth.

5. Install wood lap siding on the entire exterior surface. No finger jointed siding is allowed. The lap siding must be primed with oil alkyd primer on all sides before installation and a second coat applied after installation, brush application only. Use

15# felt to flash at corners, windows, and doors prior to installation. When siding goes over a door or window install metal flashing. To allow for movement put only one nail through siding. Using stainless steel or galvanized ring shank nails, nail just high enough so the nail does not penetrate the siding below. Siding should be tightly butted. Cut 4” x 6” strips of 15# felt to insert beneath all butt to butt joints. It should lap over lower siding to direct any water back to the exterior. Caulk all vertical joints, no horizontal joints will be caulked.

6. Replace the sill/threshold and all trim work around the exterior of the window. Ensure all sills have adequate slope to allow for drainage away from the window. Remove, repair, and repaint window sash and reglaze windows as necessary. Once completed, the windows shall be weather tight. Exterior refers to any woodwork that is directly exposed to weather elements.

South Side:

2. Replace the entire sill log and install borate impel rods in the lower side as per product specifications, typically along the center line every 18 inches. This sill is three lapped pieces, replace with a full-length sill.

3. Replace log #1, #2, and #3 to the left of the door.

4. Replace log #1 and #3 to the right of the door.

5. Repair deterioration in log #7.

6. Replace log #8.

7. Treat the entire exterior surface with wood preservative, insect repellant, and a D/2 biological solution, as per product specifications to remove and retard biological growth.

8. Replace door sill/threshold plate. Replace all exterior trim around the existing door to match the door on the North side. Match original sill in all respects. Once completed, the door shall be weather tight and shut/lock without any problems. Exterior refers to any woodwork that is directly exposed to weather elements.

9. Install wood lap siding on the entire exterior surface above the newly installed front porch. No finger jointed siding is allowed. The lap siding must be primed with oil alkyd primer on all sides before installation and a second coat applied after installation, brush application only. Use 15# felt to flash at corners, windows, and doors prior to installation. When siding goes over a door or window install metal flashing. To allow for movement put only one nail through siding. Using stainless steel or galvanized ring shank nails, nail just high enough so the nail does not penetrate the siding below. Siding should be tightly butted. Cut 4” x 6” strips of 15# felt to insert beneath all butt to butt joints. It should lap over lower siding to direct any water back to the exterior. Caulk all vertical joints, no horizontal joints will be caulked.

West Side:

2. Remove the board and batten siding and the horizontal framing.

3. Replace log #1, #2, and #4 to the right of the chimney.

4. Repair the #6 log to the right of the chimney with epoxy stabilization along its exposed lower edge.

5. Repair the #6 and #7 logs to the left of the chimney with epoxy stabilization near the chimney.

6. Treat the entire exterior surface with wood preservative, insect repellant, and a D/2 biological solution, as per product specifications to remove and retard biological growth.

7. Install wood lap siding on the entire exterior surface. No finger jointed siding is allowed. The lap siding must be primed with oil alkyd primer on all sides before installation and a second coat applied after installation, brush application only. Use 15# felt to flash at corners, windows, and doors prior to installation. Flash along all joints of the chimney. To allow for movement put only one nail through siding.

Using stainless steel or galvanized ring shank nails, nail just high enough so the nail does not penetrate the siding below. Siding should be tightly butted. Cut 4” x 6” strips of 15# felt to insert beneath all butt to butt joints. It should lap over lower siding to direct any water back to the exterior. Caulk all vertical joints, no horizontal joints will be caulked.

All Sides:

1. The contractor is responsible for ensuring that the stacked stone foundation is secured, tightly stacked with no loose or missing stones, and is adequate to support the foundation structure.

2. Replacement logs must be treated with a non-toxic wood treatment to “age” the new wood to help blend with the old. The selected treated must be coordinated with project staff.

3. All products/materials must be installed and/or applied using manufacturers recommendations.

Option 1: Roof Replacement Yates Log House

1. Remove existing wood shingle roof, nails, and 15# building felt.

2. Modify the roof overhang on all sides to extend to a minimum of 24” on all edges.

The overhang can be modified by scabbing on to the existing structure. Add 1” thick sheeting to the extended overhang that is consistent with the rest of the roof.

3. Install 15# building felt or similar moisture barrier on the entire surface of the decking.

4. Install a 12”-16” strip of EDPM (rubber) over the ridge of the roof on top of the 15# felt.

5. Flash and seal all joints surrounding the chimney.

6. Install 1” thick by 24” long butt shingles with 10” exposure and 1.5” overhang on all sides per manufacturers recommendations. It is recommended to use Western Red Cedar but other hardwood species may be used with approval from the Project Manager.

7. Gable ends of the roof must be trimmed out using a similar wood species.

Option 2: Roof Replacement Ashes Creek Schoolhouse

1. Remove existing wood shingle roof, nails, and 15# building felt.

2. Install 15# building felt or similar moisture barrier on the entire surface of the decking.

3. Install a 12”-16” strip of EDPM (rubber) over the ridge of the roof on top of the 15# felt.

4. Flash and seal all joints surrounding the chimney.

5. Install 1” thick by 24” long butt shingles with 10” exposure and 1.5” overhang on all sides per manufacturers recommendations. It is recommended to use Western Red Cedar but other hardwood species may be used with approval from the Project Manager.

6. Gable ends of the roof must be trimmed out using a similar wood species.

Option 3: Roof Decking, Inspection, Replacement, and Preparation Yates Log House & Ashes Creek Schoolhouse

1. A thorough inspection of the 1” skip decking shall be conducted and all wood that is damaged shall be replaced in kind. Rotten/Damaged decking boards encountered will be paid for according to the Contractors total per board.

2. The contractor will locate, mark, and measure any rotten or damaged roof decking after removing existing wood shingles and notify the Project Manager for a visual inspection and confirmation of the rotten or damaged area before removal.

3. Once the Project Manager confirms the damage the contractor will prepare a written estimate of the total 1” skip decking boards to be replaced.

NOTE: This will be done prior to the replacement decking.

4. Once approved, the contractor can then proceed to replace the damaged decking.

5. The price given on the contractors quote sheet multiplied by the number of 1” skip decking boards used will be added to the contractor’s final payment.

NOTE: The contractor will track the number of boards used to replace rotten or damaged roof decking for payment.

Site visits are not required but highly recommended. Please contact the POC below to schedule.

All inquiries and correspondence concerning this job shall be directed to the following.

Evan McKinney U.S. Army Corps of Engineers Taylorsville Lake 2825 Overlook Road Taylorsville, KY 40071 Phone: 502-477-8882 Email: evan.s.mckinney@usace.army.mil

TAYLORSVILLE LAKE YATES HISTORICAL LOG HOUSE AND ASHES

CREEK SCHOOLHOUSE RENOVATION TABLE OF CONTENTS

SPECIFICATIONS/DESCRIPTION

1 Project Information 2 Performance Work Statement 3 Pre-Work Conference 4 Working Hours 5 Contractor Submittals 6 Permits and Licenses 7 Identification of Contract Employees and Vehicles 8 Safety Requirements 9 Required Security Training and Planning 10 Accident Reporting 11 Damage Reports 12 Contractor Employees’ Conduct and Competency 13 Damage or Loss of Contractor’s Supplies and Property 14 Supervision 15 Environmental Program 16 Contract Discrepancy Report (CDR) NOT APPLICABLE.

17 Meetings 18 Quality Control NOT APPLICABLE.

19 Quality Assurance

20 Deficiencies 21 Interruptions to Systems 22 Government Furnished Materials and Equipment 23 Contractor Furnished Items 24 Safeguarding Government Property 25 Minimum Manpower Requirements 26 Minimum Personnel Qualifications 27 Cooperation with other Contractors, Lessees, and Volunteers 28 Reports 29 Applicable Publications 30 Warranty 31 Wage Rates 32 Definitions 33 Contract Drawings 34 Index of Exhibits

SPECIFICATIONS/DESCRIPTION

1. Project Information.

Yates Log House and Ashes Creek Schoolhouse Renovation at Taylorsville Lake, Taylorsville, Kentucky.

2. Performance Work Statement.

The contractor will furnish all personnel, equipment, supplies and materials necessary. Prices should include mobilization & de-mobilization, fuel, labor, material and equipment for the renovation of existing Yates’s historical log house to include selective demolition of sill log and misc. logs, repair work on chinking and daubing, and complete replacement of all window/door trims and thresholds at the Taylorsville Lake Yate’s Log House located at Taylorsville Lake in Spencer County, Kentucky. The contractor’s work and responsibility will include all planning, programming, administration, management, supervision, communications and inspection necessary to assure that all work is conducted in accordance with the contract requirements and all applicable Federal, State and Local laws and regulations. All work will be performed in strict compliance with the attached specifications and all other terms and conditions incorporated herein.

3. Pre-Work Conference:

Prior to the commencement of work, the contractor will be required to attend a pre-construction meeting with a Corps of Engineers representative during which the Contractor’s plan of work, safety procedures, start date and other items in this contract will be discussed.

4. Working Hours.

a. Normal working hours, except as otherwise specified herein, will be Monday through Friday, 7:00 a.m. to 4:00 p.m. Eastern Time. Work inside Government buildings or other secured areas will be performed during the above referenced work hours. Work that interferes with other ongoing functions at the project will be scheduled around normal working hours, as specified by the Project Manager.

Holiday Work. The eleven Federal holidays observed are:

New Year's Day (January 1st) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Juneteenth National Independence Day (June 19th) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)

When one of the above designated holidays falls on a Sunday, the following Monday is observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Work will be scheduled around the above listed Federal holidays except as specified herein or as approved by the point of contact (POC) Evan McKinney.

b. Inclement Weather Work: The Contractor will maintain the schedule of services regardless of inclement weather. Exceptions may be approved by the POC when severe conditions make it impractical or dangerous to perform the work.

5. Contractor Submittals.

Unless otherwise specified, the Contractor will submit the following information to the POC prior to the pre-work conference for this contract:

a. Contractor Representatives. List of names of Contractor Representatives.

b. Accident Prevention Plan (APP). A suggested outline for the Contractor’s Accident Prevention Plan Appendix A of EM 385-1-1 See Section C-1.9 for APP requirements. Exhibit D.

c. Emergency Contacts. A prioritized list, including phone numbers, of those persons (normally Contractor Representatives) to call in case of emergencies.

d. Operators. A list of names of qualified equipment/vehicle operators, including experience, training and qualification to operate specific equipment.

e. Certificate of Insurance.

f. Security Requirements.

6. Permits and Licenses.

The Contractor will obtain, at own expense, any required licenses, permits or certifications necessary to perform the specified services. Required licenses, permits and certifications will be kept current during the period the work is performed. The Contractor is also responsible for any and all costs associated with the training of Contractor personnel to acquire and maintain valid licenses, permits or certifications necessary to perform the contract services specified herein. The Contractor, Contractor personnel and any persons acting on behalf of the Contractor will comply with all applicable Federal, State and local laws and regulations, including any subsequent changes to these laws and regulations.

Minimum Personnel and Training Requirements. The Contractor will provide an adequate number of fully trained and qualified personnel to perform the work specified herein. Contractor personnel will be properly trained to perform their assigned work in a safe and effective manner.

Training will include but is not limited to instruction on the proper and safe use and operation of Contractor equipment and any Contractor provided tools, supplies and materials required to perform the specified services. Only properly trained and qualified employees will be used in the performance of services specified herein. The Contractor will also assume responsibility for training or Orienting Contractor personnel to perform the services specified in the contract. In the event the Contracting Officer or his/her Authorized Representative determines that the Contractor does not have a qualified employee performing the specified work, the Contractor will be required to provide qualified personnel, or subcontract the work to a person or persons who are trained and qualified to perform the work. The Contractor acknowledges that the employment of undocumented migrant workers to perform services under this contract will not be permitted.

7. Identification of Contract Employees and Vehicles.

All Contractor employees will be in good appearance while performing services. Employees must wear long pants, shirt with no vulgar or obscene graphics with at least sleeves equivalent of a t-shirt, and durable work type shoes. Vehicles and any motorized equipment utilized for transportation will be in good operating condition with no display of obscene or vulgar material such as stickers, flags, or etc. Vehicles will be maintained in accordance with federal, state, and local laws.

8. Safety Requirements.

a. General. Performance of all services will assure complete safety to public visitors, Contractor employees, and all other persons in the area. The Contractor will comply with any pertinent requirements contained in the Corps of Engineers Safety Manual (EM 385-1-1), current at the time of award and any subsequent revisions to that document. Furthermore, the Contractor will comply with pertinent occupational safety and health standards for general industry (29 CFR Part 1910) as required by the Occupational Safety and Health Administration (OSHA). If the Contractor fails or refuses to promptly comply with safety and security requirements as specified herein, the POC or any other project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage will be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.

b. The Contractor will comply with the Occupational Safety and Health Act (OSHA), the Corps of Engineers Manual, EM 385-1-1, https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf or latest version and as otherwise stated herein. Special attention will be given to the requirements for safety meetings.

The Contractor will inform the POC a minimum of 7 calendar days prior to a Contractor monthly safety meeting, to permit a Government representative to attend.

c. Accident Prevention Plan (APP). The Contractor will prepare an Accident Prevention Plan to assure that requirements of the safety program are provided as specified. This plan must be accepted by the Contracting Officer prior to commencement of any work. One copy of the Accident Prevention Plan will be provided to the Contracting Officer and the POC one week prior to the pre-work conference. The Accident Prevention Plan must be in the outline and form prescribed in Appendix A of EM 385-1-1.

d. Activity Hazard Analysis (AHA). The Contractor will use Activity Hazard Analyses (AHA’s) as one of many tools to insure safe performance of work. It is the Contractor’s responsibility to prepare the AHA. Sample AHA’s may be available at the project office for review and use by the Contractor to assist in the development of site specific Activity Hazard Analyses prior to the Contractor performing the job. The Contractor is encouraged to revise or add to these sample AHA’s as necessary to address changing conditions. Prior to performing jobs with inherent hazards, the Contractor will review, at a “Tool Box” safety meeting, the approved AHA’s with those employees who will perform that work each time the work is ordered. The Government may request advanced notification of the time and date of the above AHA “Tool Box” safety meeting for Contractor employees so that the Government may attend such reviews.

The Government will require the Contractor to prepare an AHA for any jobs for which an adequate AHA does not already exist. A copy of this AHA will be submitted to the POC and must be accepted before the Contractor starts the job. This copy of the AHA will become the property of the Government. Guidance is included, which will be used by the Contractor as a guide for the preparation of required AHA's.

A copy of the approved AHA’s will be available at all times to workers at each associated job site and a copy will be provided to the Government.

e. Public Safety. The Contractor will ensure that reasonable precautions are taken to protect the public at all times where work is being performed. The Contractor will immediately report to the POC any potential hazards found by his employees on the project. The Accident Prevention Plan will include procedures to be taken to provide for public safety. Additionally, the Contractor will not allow any persons, except employees, into work areas that are not otherwise open to the public; nor will the Contractor transport in Contractor work vehicles any persons, except employees, during times the Contractor is on the project performing work under a contract.

f. Personal Protective Apparel and Equipment. Protective apparel and equipment, as identified in the AHA, will be provided to eliminate or minimize hazards to personnel. As a minimum, each employee will wear a short-sleeved shirt, long trousers, and appropriate footwear during all contract work. Face shields, spectacles with side-shields, or goggles, and hearing protection will be worn by employees when required by safety manual. Fire extinguisher(s) and first aid kit(s) meeting the Safety Manual standards will also be provided and easily accessible to all employees.

g. Contractor Employees Certified in First Aid & CPR. The Contractor will schedule employees so the appropriate numbers of certified personnel are on duty to administer First Aid and CPR as required by the Safety Manual.

Copies of their certification will be provided in accordance with regulations. Two people per crew will be trained in First Aid and CPR. Individuals working alone will be trained in First Aid.

h. Hazard Communication Program. The Contractor will be responsible for implementing a hazard communication program for Contractor employees, as required by the Safety Manual.

The Contractor will provide Material Safety Data Sheets (MSDS) and/or Safety Data Sheets (SDS) for review by the POC prior to use of any hazardous substance on the project and provide a plan for the proper handling, transportation, storage and usage of hazardous substances on the project.

9. Required Security Training and Planning.

a. General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations.

Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

b. Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index

(commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.

Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

c. Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See

Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

d. Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.

Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

10. Accident Reporting.

The Contractor is responsible for reporting all accidents to the Project Manager immediately.

Prompt action will be taken to ensure immediate and appropriate medical treatment. The Contractor will maintain an accurate record of any accidents in the manner and on the forms prescribed by the Project Manager. For property damage accidents of $2,000 or more, the Contractor will complete and submit to the Project Manager a copy of ENG Form 3394. The Contractor will maintain an OSHA 300 Log of On – The – Job injuries and first aid treatments. The Contractor will also provide a monthly record of all exposure and accident experience incidental to the performance of services under the contract. This reporting requirement includes exposure and accident experience of both the Prime Contractor and any subcontractor(s). A Monthly Record of Work-Related Injuries/Illnesses & Exposure form will be available from the Project Manager. The Monthly Record of Work-Related Injuries/Illnesses & Exposure report will be provided to the Project Manager by the 5th working day of the month for the previous month.

11. Damage Reports.

All instances where Government materials, supplies, property, and/or equipment are damaged will be reported immediately to the Project Manager. When the damage was caused by contract employees, a written report of the incident and extent of such damage will be submitted to the Project Manager, within 2 work days (less weekends and holidays) of occurrence. For property damage accidents of $2,000 or more the Contractor will complete and submit to the Project Manager a copy of ENG 3394.

12. Contractor Employees’ Conduct and Competency.

All contract employees will conduct themselves in a proper and courteous manner at all times.

Since the majority of work is performed in the presence of the general public, the conduct of all employees is critical and will be closely monitored. Contract employees will comply with all provisions of Title 36, Chapter III, Part 327, CFR and obey all posted signs and regulations in the performance of the work under this contract. Being under the influence of or consuming alcoholic beverages or controlled substances by the Contractor or employees while on duty is prohibited.

a. Employee Dismissal. The Contractor expressly agrees to dismiss any employee or subcontractor employee whose continued employment is deemed by the Project Manager to be inconsistent with the best interests of the public or the U.S. Army Corps of Engineers. The Contracting Officer (KO) or the Project Manager may require the Contractor to immediately remove from the work site any employee or subcontractor who is incompetent, endangers persons or property, or whose physical or mental condition would impair their ability to satisfactorily perform the work. Notification to the Contractor will be promptly made in writing if time and circumstances permit.

Otherwise, notification will be verbal and confirmed in writing as soon as possible. No removal will reduce the Contractor's obligation to perform all work required under this contract nor be the basis for time extension. Immediate replacement of the employee will be made.

13. Damage or Loss of Contractor’s Supplies and Property.

The Contractor is responsible for taking the action necessary to protect Contractor supplies, materials and equipment, and the personal property of Contractor employees from loss, damage or theft. The Government assumes no responsibility for theft, damage, etc., of the above. The Government is not responsible for providing storage areas or facilities for the storage of Contractor supplies, materials and equipment. With prior approval, the Project Manager may provide a location for the temporary storage of large equipment to prevent the transportation of such equipment to/from the work site while a particular service is being performed. However, the Government assumes no liability for the loss or destruction of Contractor equipment while it is stored on Government property.

14. Supervision.

The POC will be Evan McKinney. The Contractor is responsible for providing on-site supervision and quality control inspections of work performed under the contract. The level of supervision and inspections will be sufficient to assure that services are performed in accordance with contractual requirements and all applicable Federal, state and local laws and regulations.

The Contractor or a Contractor Representative will personally supervise the work, or be readily available by phone or other means of communication to respond to any contract issue that may arise when work is in progress. The Contractor Representative(s) will conduct overall management coordination and be the central point of contact with the Government for performance of all work under the contract.

Contractor Representative will have full authority to contractually commit the Contractor for prompt action on all matters pertaining to administration of this contract, and will be the on-site Contractor employee who is responsible for safety.

15. Environmental Program.

The Contractor will comply with Federal, State, and local laws, regulations and standards regarding environmental protection. All environmental protection matters will be coordinated with the POC. Any of the facilities operated by the Contractor may be inspected by the POC, or other Federal, State and local officials without advance notice. Access for inspection will be granted upon request.

Citations against Government facilities operated by the Contractor for non-compliance with environmental standards are a matter for resolution between the Government and the issuing office.

The Contractor will conduct all operations and maintenance activities in a manner to prevent contamination of Government land and property. The Contractor will ensure all lubricants, petroleum products, paints, cleaning materials, or any other hazardous substances are not spilled, leaked, or disposed of on Government property and are disposed of in accordance with environmental regulations. If spills or contamination occur, the Contractor will be responsible for cleanup and any associated costs in accordance with Federal, State and Local Law. Such spills will be reported to the POC immediately.

16. Contract Discrepancy Report (CDR). NOT APPLICABLE.

17. Meetings.

The Contractor is required to attend a pre-work meeting to be scheduled by the POC. A tour of the work site will be conducted following the discussions. It is recommended that the Contractor’s on-site representative or superintendent also attend this meeting. During the pre- work conference, the Contractor will also provide any required submittals not previously submitted.

18. Quality Control. NOT APPLICABLE.

19. Quality Assurance.

The Government will monitor the Contractor's performance in each functional area under this contract and reserves the rights to use whatever additional surveillance procedures are deemed appropriate. The Government will keep a record of all complaints received by the public concerning Contractor performance. Upon receipt of a written complaint by the public, the Government will attempt to verify the complaint and furnish the Contractor a copy of the findings.

A Government employee will not be considered an Inspector unless he identifies himself as such to the Contractor or the Contractor Representative. No Inspector is authorized to change any provision of the specifications without written authorization of the Contracting Officer nor will the presence or absence of an inspector relieve the Contractor from any requirements of the Contract.

20. Deficiencies.

If the Contractor fails to perform, or if performance in any area is judged unsatisfactory by the POC, the Government will take corrective action. If any of the services do not conform to contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements, at no cost to the Government.

21. Interruptions to Systems.

Contractor will…