JBMDL Barracks 5502
Solicitation number
W912QR22R0061
Issued by

About this file

This federal solicitation seeks design/build construction services for a full facility restoration of an enlisted barracks building at Joint Base McGuire-Dix-Lakehurst in New Jersey. The estimated construction cost is between $10-25 million. The project involves renovating an existing 39,770 square foot three-story barracks building to provide 56 two-person sleeping rooms, day rooms, laundry facilities, and mechanical/electrical spaces. The scope includes structural, mechanical, electrical and fire protection system upgrades, as well as interior and exterior finish renovations. A HUBZone price evaluation preference applies. The Army Corps of Engineers is the contracting agency. Offerors must register in the System for Award Management and comply with various proposal, bonding and CCR/ORCA requirements specified in the solicitation. Technical inquiries should be submitted through the ProjNet website. Funds have not been appropriated for this acquisition so no contract award will be made until funds become available.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CIVIL/OPS/ENVIRONMENTAL BR

ATTN: ADAM WANTLAND

600 DR M L KING JR PL RM 821

LOUISVILLE KY 40202-2236

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SEE CONTINUATION PAGE

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR22R0061

X 9B. DATED (SEE ITEM 11)

24-Jun-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0002

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Sep-2022

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912QR

FACILITY CODECODE

EMAIL:TEL:

W912QR22R0061_Specs-0002

W912QR22R0061

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMDT 0002

Solicitation W912QR22R0061 for the JBMDL, NJ 5502 Barracks Full Facility Restoration (FFR) project is hereby amended as follows:

1. The following Drawings have been replaced in their entirety:

AD-110 Added note 12.

A-110 Notes 10 and 15 Deleted. Revised graphic to show hi-lo drinking fountain with bottle filler.

Deleted existing door in Storage room 137. Revised note 1.

A-111 Revised Elevation A-120 Notes 10 and 15 Deleted. Revised graphic to show hi-lo drinking fountain with bottle filler.

A-130 Notes 10 and 15 Deleted. Revised graphic to show hi-lo drinking fountain with bottle filler.

Deleted note 15 form both stairs.

A-140 Added note 4 and 5.

2. The following Specification Sections have been added or replaced in their entirety:

VOLUMES 1A, 1B, and 2

DIVISION 01

Section 01 02 00.00 48 Statement of Work

- Part 1 – Design Objectives, and Functional and Area Requirements, Part 1.9.1.5 Bid Options.

- Part 1 – Design Objectives, and Functional and Area Requirements, Part 1.2.8 UFC updated.

- Part 1 – Design Objectives, and Functional and Area Requirements, Part 1.3.3.1, updated the

Responsibilities table for window blinds, washer and dryers, and televisions

- Part 6 – Architectural and Interior Design, Part 6.4.4.1 revised.

- Part 6 – Architectural and Interior Design, Part 6.4.8 revised.

- Part 13 – Fire Protection Design, Part 13.1.11, updated the requirements and prohibitions for attic access hatches.

Attachment A-Room Requirements.

-Added remarks to room 107.

-Added note to provide insulated metal panels for rooms without windows.

3. All other terms and conditions remain unchanged.

(End of Summary of Changes)

P2 #481648 Building 5502 FFR JB MDL, New Jersey

01 02 00.01 48 - 1 Amendment 0002

PART 1

DESIGN OBJECTIVES, AND FUNCTIONAL AND AREA REQUIREMENTS

1.1 SCOPE OF WORK.

The objective of this solicitation is to obtain a renovated Barracks facility that will operate efficiently and serve the Transient Training Soldiers at Joint Base McGuire-Dix-Lakehurst effectively for many years to come. The Transient Training Soldiers Barracks is a place that will house unaccompanied enlisted personnel who will be conducting training exercises at Joint Base McGuire-Dix-Lakehurst. The existing Building 5502 was originally constructed in 1954, used as a barracks, kitchen and dining hall and has had upgrades including changing the dining area into an office and storage area for the kitchen staff to use while preparing meals for troops in the field.

Currently, the facility does not meet the needs of a Transient Training Soldiers barracks but needs to be renovated to provide additional barracks, upgrade the mechanical, electrical and fire protection systems along with upgrading the finishes.

1.1.1 Requirements stated in this RFP are minimums; design and construction shall meet or exceed the requirements. The design and technical criteria contained and cited in this RFP establish minimum standards for design and construction quality. Innovative, creative, and life cycle cost effective solutions which meet or exceed these requirements are encouraged.

1.1.2 This project shall consist of the design and renovation/conversion of existing building 5502 to a Transient Training Soldiers Barracks facility complete with upgrades to the exterior finishes, a new / replacement of the existing asphalt roof, a new elevator, required utilities, communications, electric, HVAC, fire protection/alarm systems, EMCS, signage for force protection measures, exterior building mounted lighting, site improvements and grading on a Government-owned facility at Joint Base McGuire-Dix-Lakehurst, New Jersey.

1.1.3 Contractor shall provide design for furniture and equipment to be purchased and installed by the Government.

1.1.4 Bid Options. The Government has identified Option Items which may be included in the project, if available funds allow and government authorization is given. The Option Items are listed individually on the Price Breakout Schedule and described at 1.9 below.

1.2 DESIGN OBJECTIVES.

1.2.1 Applicable Criteria. Applicable design and construction criteria references are listed in this Statement of Work and in the Outline Technical Specifications. Criteria shall be taken from the most current references as of the date of issue of the RFP, unless noted otherwise.

Referenced codes and standards are minimum acceptable requirements.

1.2.1.1 This RFP and its referenced documents define the necessary criteria to plan and design the renovated barracks facility. Functional space requirements, including general lighting, communications, power, tempered air requirements, finishes, etc. are contained within the RFP and its referenced documents and design guides. Typical functional space furniture layouts and inventories are provided in the RFP drawings (these drawings are preliminary only. It is up to the contractors DOR to design to the RFP’s requirements); Contractor’s designers shall adapt these to the final floor plans.

01 02 00.01 48 - 2

1.2.1.2 Where specific manufacturer or vendor names are called out in this RFP, the intention is to provide the desired quality and salient features for the system or material. Unless the manufacturer or vendor is identified as “sole-source”, or with similar language, the Contractor may provide an equivalent or better system or material of another vendor or manufacturer

1.2.1.3 The project shall be designed and constructed using English (inch-pound) units of measurement.

1.2.2 Primary Consideration. The primary consideration of this solicitation is to obtain a fully functional renovated Barracks Facility within funds available, and to maximize design quality.

Offerors are encouraged to review the RFP to familiarize themselves with all RFP requirements.

1.2.3 Design Quality. Design quality is achieved through the optimization of interior planning, integration of the building with the site, sustainability, selection of building materials and systems for low-cost maintenance and operation, and an overall balance of esthetics and functionality. The Army Reserve encourages a project design of award-winning caliber.

1.2.4 Design Freedom. Requirements stated in this RFP are minimums. Innovative, creative, or cost-saving proposals, which meet or exceed these requirements are encouraged, and will be considered more favorably.

1.2.4.1 The project conceptual design was developed by the Army Reserve, the Corps of Engineers, and an A/E design team; this conceptual design is accepted by the Government.

1.2.4.2 The conceptual design Drawings, this Statement of Work, and the Outline Technical Specifications, along with the other information and requirements in this RFP, serve as requirements for Contractor building design and construction completion, along with other code, regulatory and professional practice requirements. The extent of development of these RFP documents in no way relieves the successful offeror from responsibility for completing the design, construction documentation, and construction of the facility in conformance with Applicable Criteria and codes.

1.2.4.3 The conceptual design illustrates desired general arrangements, orientation, and adjacencies, it is not intended to dictate the final layout and image for the project. The Contractor’s designers shall develop and refine the conceptual site and building design in their completion of the design and construction documents. Such development shall be consistent with the criteria and acceptable to the Government.

1.2.4.4 The Contractor shall accommodate minor site and building plan changes by the Government in the early stages of the design process, as a normal part of the design development process. The Contractor may adjust spaces, within the overall and specific functional area guidelines, as required to accommodate structural layout, and as necessary to provide adequate space for mechanical, electrical and communication spaces. The mechanical and electrical spaces must provide adequate space to safely and efficiently accommodate equipment operation and maintenance. The spatial relationships and adjacencies in the RFP drawings, however, must be maintained, unless the Contractor recommends changes to the Government, and the Government accepts such changes.

1.2.4.5 The Contractor shall develop and refine the exterior image and esthetics of the building as part of the design development process. The Contractor shall utilize materials, 01 02 00.01 48 - 3 detailing, fenestration, lighting and ornamentation to develop a high-quality exterior image for the facility. Refer to Parts 2 through 15 for more details that may apply.

1.2.4.6 The Contractor’s architect or interior designer shall select the final palette of colors and materials for building interior and exterior to produce a pleasing appearance, coordinated throughout. The final palette of colors and materials selection is required to be accepted by the Government. Refer to Parts 2 through 15 for more details that may apply.

1.2.5 Installation Design Guidance.

1.2.5.1 The contractor is to follow the most up to date Joint Base McGuire-Dix-Lakehurst Installation Design Guide (IDG) for the requirements for the exterior renovation.

1.2.6 Energy and Resources Conserving Features. Public Laws 102-486 and 109-58, Executive Order 13423, and Federal Regulations 10 CFR 435, require federal buildings to be designed and constructed to reduce energy consumption in a life-cycle, cost-effective manner using renewable energy sources when economical. Products designed to conserve energy and resources by controlling the amounts of consumed energy or by operating at increased efficiencies should be considered. Minimum requirements for this project are listed in this Statement of Work. Refer to Parts 2 through 15 for more details that may apply.

1.2.6.1 Energy conservation techniques shall be considered as they relate to site design, site engineering, building design, and building engineering. Techniques which conserve energy, improve functionality, and can be justified by life cycle cost analysis as cost-effective are encouraged. Integration of energy conservation systems with the building design (lighting, structure, mechanical systems, and esthetics) is essential to facilitate functionality and maximum energy savings. If an alternative energy generation method is proposed for use as the project's primary energy source, documentation shall be submitted to the Contracting Officer, verifying the system’s reliability, life-cycle cost effectiveness, and ability to meet the project’s peak demand.

1.2.7 Sustainable Design. LEED-NC 4.0 is the Government’s current criteria for sustainable design. The project shall be designed and constructed in accordance with LEED guidance. See also Part 14 of this Section and Section 01 33 29.00 06.

Amendment 0002

1.2.8 Antiterrorism and Force Protection Considerations. This Project’s design and construction shall comply with the Department of Defense Antiterrorism (AT) Standards for Buildings, UFC 4-010-01, 12 Dec 2018 (Change 2, July 30, 2022). The Project shall meet the requirements for an “Inhabited” facility located within an Installation Perimeter. Note that existing buildings located within an installation perimeter are exempt from the requirements of Standard 1, Standoff Distance. The contractor shall fill out the AT/FP checklist for each design submittal.

A blank checklist is provided in Attachment V.

Amendment 0002

1.3 CONTRACTOR RESPONSIBILITY.

1.3.1 The Contractor shall provide all labor, materials, equipment, supplies, permits, fees, and

01 02 00.01 48 - 4 consultant services to design and construct this Barracks facility. The complex shall be a complete and usable facility, meeting the requirements of this RFP. The Contractor shall develop a complete site, building and interior design package.

1.3.2 Throughout the RFP, references are made to MCAR and OMAR funds. For clarification, this refers to the funding source – either Construction funds or Operations and Maintenance funds – for the Project. The funding source has no bearing on the Scope of the Work.

1.3.3 For purposes of clarification, this RFP identifies parts of the Project for which some responsibility is borne by the Government. The responsibility for some work items addressed elsewhere in the RFP is brought to the Contractor’s attention in the following table. If not identified as Government-furnished in the table below, or elsewhere, all work required by the RFP is the responsibility of the Contractor.

1.3.3.1 For items noted with an asterisk (*) below, Contractor is responsible for design of power, data, and other necessary mechanical or electrical provisions for the item.

Item Designed by

Furnished by

Installed by

Makes final connection

Freestanding furniture Cont Govt Govt --- Window Treatments Cont Cont Cont --- Fire extinguishers (Bona Fide Need Option)

Cont Cont Cont ---

Surface Mounted Entry Mats (Bona Fide Need Option)

Cont Cont Cont ---

Washers and Dryers* Cont Cont Cont Cont Refrigerators* (Bona Fide Need Option)

Cont Cont Cont Cont

Countertop Microwave* (Bona Fide Need Option)

Cont Cont Cont Cont

Metal Utility Shelving 100lbs per shelf Cont Cont Cont --- Televisions (Bona Fide Need Option)

Cont Cont Cont Cont

Window Blinds Cont Cont Cont ---

Amendment 0002

1.4 SURVEY AND GEOTECHNICAL INFORMATION.

1.4.1 A survey has been performed by a licensed surveyor and is provided in these documents. Refer to the RFP Drawings. The Contractor shall, at its own expense, verify existing conditions and obtain any additional information required to provide a complete and useable design. Do not contact the surveyor during the preparation of proposals for the solicitation.

1.4.2 A preliminary Subsurface Characterization report has been performed and is included in

01 02 00.01 48 - 5

Attachment C of this RFP. The design parameters provided in the report are for information only. The design parameters upon which the bid is based is the responsibility of the contractor’s geotechnical engineer.

1.5 RFP DRAWINGS.

The conceptual drawings are included as a part of this RFP to provide preliminary information and criteria for the Contractor’s completion of the design.

1.6 SPECIFICATIONS.

1.6.1 The Outline Technical Specifications are provided primarily in outline format. They shall be utilized as design and submittal criteria, and minimum standards for the corresponding construction work, and shall be met or exceeded unless Contractor obtains specific Government approval for proposed reductions. These outline specifications shall not be considered complete and suitable for final construction specifications. Contractor’s designers shall expand the outline specifications to provide comprehensive, three-part, CSI-format Specifications and shall edit the Specifications to indicate actual products to be used in the construction. Final specifications shall include as a minimum, a description of the technical requirements, criteria for determining whether the criteria are met, and quality control requirements and procedures.

The standards referenced in the outline specifications establish minimum requirements for the final construction specifications.

1.6.1.1 The Outline Technical Specifications provide design and construction criteria that supplement project-specific requirements listed in Section 01 02 00.00 48 and 01 03 00.00 48.

1.6.2 Not all Outline Technical Specification sections provided in this RFP may be required for this project, and designers shall provide additional Specification Sections or items if necessitated by their final design or RFP requirements.

1.6.3 Some Outline Technical Specification Sections are more detailed and extensive than the majority; these represent the Government’s required specification approach to this project.

Contractor’s designers must still take complete responsibility for the design and specification of the project, and shall satisfy themselves that these Sections are complete and suitable for the final design. Most of the outline specification sections are adapted from typical Government Unified Facility Guides Specifications (UFGS) and reflect Army Reserve-approved approaches and products. The outline specification requirements shall be used as the basis for selection of construction materials, products, and systems. Contractor’s final specifications shall be developed from the UFGS. The use of industry prototype specifications (such as MasterSpec) is not allowed.

1.6.3.1 The following order of priority applies:

1.6.3.1.1 First select Sections specifically developed for Army Reserve facilities. Such Sections have “48” as the fifth level of their MasterFormat 2004 numbering, such as Section 07 31 13.00 48. These Army Reserve-specific (RST) Sections can be accessed from the Corps of Engineers, Louisville District, Army Reserve Customer Website. Refer to Part 2 of this Section.

1.6.3.1.2 If no RST Section exists, select a Louisville District-specific Section (LRL), accessible from the same website. Such Sections have a “06” as the fifth level of their MasterFormat 2004 numbering.

01 02 00.01 48 - 6

1.6.3.1.3 If no Section described above exists, select an Army Section. Such Sections have a “10” as the fourth level of their MasterFormat 2004 numbering.

1.6.3.1.4 If none of the above Section exist, select a unified Section. Such Sections have no fourth or fifth level in their numbering.

1.6.4 In case of conflicts between the project-specific requirements in Section 01 02 00.00 48 or 01 03 00.00 48, and the requirements in the Outline Technical Specifications, Section 01 02 00.00 48 or 01 03 00.00 48 governs. This is true for all Outline Technical Specification Sections, including the more extensive and detailed Sections.

1.7 SITE.

The site described on the RFP drawings is included as part of this solicitation and consists of a total of approximately 1.7 acres. The site lies on Alabama Avenue within Joint Base McGuire- Dix-Lakehurst (JB MDL) in Burlington county New Jersey. Site work includes all design and construction of site features described in the RFP, including but not limited to, site planning, clearing, grading, erosion control, site drainage, signage, and physical security measures.

1.7.1 Special Utilities and Supplementary Construction.

Not Used.

1.7.2 Demolition Considerations and Requirements. Site demolition for the renovation of 5502 will primarily consist of the removal of the broken sidewalk surrounding the building and all exterior stairs and handrails. There are no mature trees on site that will need to be removed as part of this RFP.

Materials shall be disposed of off government property in a state certified landfill. The contractor must obtain required demolition permits and disposal permits. Obtain approval of the disposal site from the Contracting Officer. Cleared and grubbed material will be ground for mulch and recycled with the excess disposed of offsite in an approved disposal area.

1.7.3 Environmental Considerations and Mitigation Requirements. Contractor is to review the Hazmat Report located in the attachments for location and types of asbestos materials and lead paint that will need to be removed. The Contractor shall comply with the requirements of OSHA 29 cfr 1926.62 – lead exposure in construction during building and structure demolition.

The hazardous waste criterion for lead waste is established under the federal resource conservation and recovery act (RCRA), subtitle c, as 5.0 mg/l measured with the toxicity characteristics leaching procedure (TCLP). In addition, the crushing or recycling of materials with LBP is strictly prohibited.

1.7.3.1 The Contractor shall use the following numbers in addition to the quantities found in the Hazardous Materials Survey (Attachment B). This includes any materials found in the Crawl Space as well:

Asbestos Cement Board on interior perimeter walls: 14,000 SF Unstable LBP’s throughout the facility 2,000 SF Window Caulk (Interior & Exterior): 14,800 LF ACM Waterproofing (Interior surface of exterior cmu) 6,000 SF Building Expansion Joint caulk (Exterior): 3,600 LF Bathroom Fixture Caulk PCBs: 500 LF Fluorescent Bulbs – 2ft L (PCB): 800 EA

01 02 00.01 48 - 7

Fluorescent Bulbs – 4ft L (PCB): 300 EA

1.7.3.2 In the process of demolition should the contractor uncover tar vapor barrier on the exterior wall that contains asbestos containing material, the contractor shall cover it with new wall construction. Should any additional suspected hazardous materials be encountered during site investigations or construction, the Contractor shall immediately stop work in the affected area, notify the Contracting Officer, and await Contracting Officer’s direction before proceeding with additional work in the area.

1.7.3.3 Buildings must be designed and constructed to maintain space humidity at reasonable levels to prevent mold.

1.7.4 Site Development Constraints. The project site is on U. S. government property and the normal RFP requirements associated with a U. S. government installation shall apply.

Known site development constraints include minimum AT/FP setbacks as per UFC criteria.

1.7.5 Contractor’s Use of the Site. Except for utility service provider access, required coordination with local agencies, and observation and oversight by the Government, the Contractor shall have complete use of the site within final limits of construction to be recommended by the Contractor and approved by the Government.

1.7.5.1 Security and Identification Requirements. Refer to Section 00 80 00.00 06.

1.7.5.2 Contractor’s trailers and other equipment and materials on the site shall be tied down to resist storm force winds. Contractor shall maintain the site free from debris that could represent a hazard during storm force winds.

1.7.6 Verification of Conditions. The Contractor shall field verify existing conditions prior to beginning work. The Contractor and the designers of record shall be responsible for investigating all differing site conditions, discrepancies, and field related issues that are encountered during the design and construction process. The designers of record shall be responsible for providing guidance to the Contractor for the resolution of all such issues. The Contractor shall provide notice to the Government of any such issues prior to proceeding and with sufficient time to avoid cost or schedule impacts.

1.7.7 Verification of Utilities. The Contractor and the designers of record shall be responsible for verifying the condition, location, and capacity for all utilities necessary for the project. The Contractor and designers of record shall further verify that all utilities will meet the requirements of this project.

1.7.8 Regulatory Compliance. The Contractor shall assure that the site development complies with all applicable local, State and Federal regulations. A list of known regulations is located in Part 2 of this Statement of Work. Timely acquisition of the necessary design and construction related permits shall be the responsibility of the Contractor. The Contractor, upon notice to proceed, shall immediately begin working on the permits so as not to delay completion of the project. The Contractor shall prepare permits, associated drawings, public notices, and other related documentation as necessary to successfully meet permit approval status. The Contractor shall pay for all associated permit fees.

1.8 FUNCTIONAL AND AREA REQUIREMENTS.

01 02 00.01 48 - 8

The Army Reserve’s primary criteria documents are the following: “USAR Pamphlet Design Guide Army Reserve Facilities 14 August 2020”, commonly referred to as the Design Guide or DG; and “Operational Readiness Training Complex (ORTC) Standard Design – Revision 4.6, 24 August 2012”. IT spaces are addressed in the ARNEC Infrastructure Technical Criteria, Change 3, 1 Feb 20.

1.8.1 The existing Building 5502 gross square footage is approximately 39,770. The renovation will include renovating the existing building floor plan, structural, mechanical, electrical, fire protection, communication systems, and interior finishes. The new floor plan will consist of two person barracks with a shared bathroom, mechanical room, day room, laundry and elevator on all three floors. The single story wing presently houses a dining hall that will be converted to barracks rooms. The sub-grade basement presently contains a certified weapons vault with Intrusion Detection System (IDS) and will remain but be upgraded.

1.8.2 Individual spaces shall meet the functional and environmental requirements of the above referenced criteria documents, as well as any applicable code requirements, and additional requirements in this RFP. Refer to the RFP attachment “A” for Room Requirements.

1.8.2.1 The areas shown in the “Target Net Area” column of Room Requirement Attachment “A” reflect the areas achieved on the RFP Drawings, however minor variation is allowed. It is acceptable for the actual clear area of any space to vary from the values in the table by plus or minus 5%. If space sizes are varied, functionality and furniture requirements shall be maintained.

1.8.2.1.1 The minimum width for offices shall be 9’-6”.

1.9 OPTIONS

1.9.1 Options. The Government has identified Option Items that they wish included in the project if available funds allow. The Option Items are identified in the RFP, listed individually on the Bidding Schedule, and described briefly below.

1.9.1.1 Option – New Entry Canopies. All work required to furnish and install (4) new entry canopies and frames at each entrance to Building 5502 to match the existing canopies.

1.9.1.2 Option – Fire pump and Housing. All work required to design, furnish and install a packaged fire pump and exterior enclosure to provide adequate water pressure to Building 5502.

1.9.1.3 Option – Paved Driveway. All work required to furnish and install new pavement over an existing driveway as shown on drawings and described in the RFP.

1.9.1.4 Option – Resurface Basketball Court. All work required to resurface the existing basketball court as described on the drawings and in RFP.

Amendment 0002

1.9.1.5 Option - Remove Existing Loading Dock, Canopy, and Entrance Stoop.

Replace entrance stoop with new and provide paved driveway. All work required to remove and rebuild these existing items as described on the drawings and in the RFP.

01 02 00.01 48 - 9

1.9.1.6 Option – Army Reserve (OMAR) Funded Bona Fide Need Equipment. All work required to design, furnish and install “Bona Fide Need Funded Equipment” for the facility.

*** SAFETY PAYS ***

JB MDL, New Jersey

01 02 00.06 48 -1

PART 6

ARCHITECTURAL AND INTERIOR DESIGN

6.1 DESIGN GOAL.

The overall architectural design goal for the facility is to provide a functional, visually appealing facility that is a source of pride for facility users. The RFP conceptual building drawings present a building renovation scheme which considers the Joint Base McGuire-Dix-Lakehurst (JB MDL) Barracks Building 5502 functional requirements and which has been accepted by the Govern-ment. This does not preclude the Contractor from making improvements to the design so long as such improvements are consistent with the requirements of the RFP and acceptable to the Government. The building design is conceptual; the Contractor shall finalize all elements of the design, including exact dimensions. In completing the design, the Contractor will be allowed some latitude in manipulating the plans and elevations to improve functional layout, to accom-modate structural, mechanical, electrical and other systems, and to allow flexibility for de-sign/esthetic expression. The spatial relationships and adjacencies, however, must be main-tained, unless the Contractor recommends changes to the Government, and the Government approves such changes. The Room Requirements are included in Attachment A.

6.1.1 Site Planning Objectives. Refer to Part 3 Site Civil Engineering of this Statement of Work.

6.1.2 Exterior Design Objectives. The exterior design of Building 5502 shall meet the re-quirements of the JB MDL Installation Design Guide and shall enhance the visual environment of the surrounding area. Exterior materials and detailing shall comply with the provisions of this RFP. Use durable, low-maintenance materials.

6.1.2.1 The Army Reserve and JB MDL have accepted the conceptual building plan, includ-ing the color scheme as discussed herein. Any appreciable change to the building footprint re-quires Army Reserve and JB MDL acceptance.

6.1.2.2 The existing concrete stairs, in four locations leading up to the first floor on the bar-racks are in poor condition and are spalling, cracking and falling apart. These concrete stairs and steel railings are to be removed and replaced with new concrete stairs. Refer to the RFP Drawings for the location of all the exterior stairs that will be removed and replaced.

6.1.3 Interior Design Objectives. The interior design for the building shall be to present an efficient interior space that utilizes durable materials and furnishings to convey an organized space situated around the Barracks Building functions. Finishes and furnishings shall be easily maintained and/or replaced when they have reached their useful life. Interior surfaces shall be light in color, avoiding trendy or bright color schemes. Where feasible, spaces shall be ar-ranged to allow re-arrangement of furniture to meet future needs.

6.1.3.1 The RFP provides basic finishes and a color palette for most spaces. Contractor’s designers are required to develop a more comprehensive finish and color palette for acceptance by the Government, including accent colors and finishes, especially for common-use areas of the building. Such finish and color palette shall include but are not limited to, doors, door frames and window frames.

6.1.3.2 Functional space requirements shall be as noted in this Statement of Work. The

JB MDL, New Jersey

01 02 00.06 48 -2 Amendment 0002

Contractor’s designer shall coordinate the layout with the Government. The layout shall be de-veloped in conformance with the requirements of this RFP and the Design Guide, for the ac-ceptance from the Government.

6.1.3.3 Where the Contractor provides schedules, labeling or key plans (for signage, lockset keying, electrical panel schedules, communications/data wiring, etc.), Contractor shall use final room numbers if different from construction document room numbers. Refer to UFC 4-171-05 for guidance on room numbering.

6.1.4 Material and Product Selection Criteria. Materials shall meet the requirements of this RFP, including but not limited to the Outline Technical Specifications, which establish a mini-mum quality level. Higher quality materials will be evaluated more favorably.

6.1.5 Installation Design Guide Applicability. The Joint Base McGuire-Dix-Lakehurst In-stallation Design Guide shall be followed for all exterior elements of this project.

6.2 GENERAL CONSTRUCTION REQUIREMENTS.

The goal of the renovation of Building 5502 at Joint Base McGuire-Dix-Lakehurst is to turn a run-down barracks building into a fully functional, healthy, and sustainable Barracks facility to be used for a Transient Training Barracks. The renovation includes 3 stories above ground which are currently serving as barracks and a functioning kitchen that is used to prepare meals for troops in the field training. A sub-grade basement has a fully functional arms vault but will be reduced in size by providing new walls using pre-manufactured panels that meet AR-190 re-quirements with an Intrusion Detection system. Successful renovation of the existing facility will require extensive planning and foresight, as the structure is not conducive to any major struc-tural modification. The structural shell of the building shall remain in it’s entirety, while the interi-or walls will be completely demolished. The existing facility was also built with hazardous mate-rials that will have to be mitigated. Attachment I - Historical Drawings of Similar Barracks Build-ings is provided to convey ceiling clearances and structural limitations.

The final configuration will contain 20 (2+0) barracks, a lounge area, day room, laundry room, storage, mechanical and electrical room, teleconference room, elevator, elevator machine room, storage and restroom on the first floor and 18 (2+0) barracks on the second and third floors each for a total of 56 new barracks. The second and third floor shall include a Day Room and a Laundry Room. The basement will be renovated by adding new premanufactured walls to create a new compliant arms vault. The vault is required to be separated into 4 distinct sections with caging. The Room Requirements are included in Attachment A.

The existing kitchen, office and storage rooms will be demolished and renovated with new bar-racks. The existing kitchen equipment will be removed by the contractor and delivered to Build-ing 5021 by the Contractor.

Barracks include a living/kitchenette area, and a bath area including a water closet, lavatory, and a shower. Each room may contain a mechanical closet, as well as a built-in cabinetry in-cluding a location for a residential-type microwave and 7.5 cu. ft. top-freezer refrigerator. Micro-waves and refrigerators are to be provided by the Contractor (Bona Fide Need Option). Rooms are to be T.V. cable ready but are not required to have telephone outlets.

Day Rooms are incorporated on each floor for the purpose of officer recreation: watching televi-sion, playing cards, and other recreational activities. A primary Day Room is located on the first

JB MDL, New Jersey

01 02 00.06 48 -3 Amendment 0002 floor and is sized to accommodate larger activities.

Laundry rooms on each floor shall include 4 washers and 4 dryers per floor. Space is provided for units to be side by side, but units may be stackable type as well. A laundry sink is also pro-vided within the room.

The existing stairs shall remain with the interior finishes renovated. The stairs shall have rubber tread and landings provided, the walls shall be repainted and the handrails and guardrails re-placed with shop-finished handrails and guardrails to meet NFPA 101. Concrete steps shall be repaired, so rubber stair treads will adhere properly. Contractor shall provide all design, materi-al, equipment and labor required to complete this work.

An elevator shall be incorporated into the facility, but will not serve the basement. The elevator shall be the holeless hydraulic type. The elevator will have a minimum rated load capacity of 2,500 lbs. The elevator will follow the requirements of UFC 3-490-06. The elevator may need to penetrate the concrete roof / structure and extend into the attic. Contractor may need to alter the existing wood rafters to allow for needed height for the elevator shaft. The elevator shall not ex-tend beyond the roof decking.

The existing access to the attic is provided with a ladder and hatch located in the existing third floor bathrooms. The contractor shall close up the existing openings. New fire rated access hatch and permanent wall mounted ladder shall be located in each stair well on the third floor.

As described in UFC 1-200-02: 2-2.6.2.1 Storage and Collection of Recyclables, the contractor shall provide the space for the storage and collection of recyclables.

As a bid option, the loading dock, concrete stairs & ramp, canopy, and associated roofing and flashing shall be demolished. If this option is selected, new work as part of the option shall in-clude a new stoop & stair; new fascia, soffit, and gutter; and the exposed wall shall be patched, repaired, and parged as necessary to create a consistent appearance with the rest of the build-ing.

6.2.1 The exterior walls are clad with Exterior Insulation and Finish System (EIFS). The EIFS shall be patched in areas of deficiency, a troweled on ¼” thick skim coat of EIFS applied over the entire EIFS surface and then the EIFS shall be repainted.

6.2.2 The roofing system is asphalt shingles. The roof shingles shall be removed and replaced with new shingles. The new shingles will be secured to a new layer of nail base roof insulation panels that are attached to the existing roof rafters. The soffit will be closed off and insulated.

This will allow the attic to be kept at a temperature above freezing and allow the sprinkler sys-tem to be a wet pipe throughout the building.

6.2.3 The gutters, downspouts, trim and flashing shall be replaced.

6.2.4 The exterior windows shall be replaced, and in some cases new windows shall be add-

ed. All windows shall comply with AT/FP requirements per UFC 4-010-01. Windows are typically part of a larger assembly which includes insulated metal panels. Replacement shall include the entire assembly with new insulated metal panels to match the existing. Supporting structures shall be concealed within the wall finishes.

6.3 OCCUPANCY AND BUILDING TYPE CLASSIFICATIONS.

JB MDL, New Jersey

01 02 00.06 48 -4 Amendment 0002

In accordance with UFC 3-600-01 the IBC must be utilized to determine the occupancy classifi-cation as it relates to allowable construction type, building height, building area, building separa-tion distance, occupancy separation and associated requirements, and NFPA 101 must be uti-lized to determine the occupancy classification as it relates to fire/smoke resistance rating of interior non-load bearing partitions (other than occupancy separation), means of egress, interior finish, features of fire protection (including vertical openings) and associated requirements.

6.4 EXTERIOR DESIGN.

6.4.1 Acceptable Materials and Colors. The exterior building materials shall conform to the Installation Design Guide for JB MDL.

6.4.2 Exterior Walls. The existing exterior walls for Building 5502 are EIFS. The EIFS shall be patched in areas of deficiency, a troweled on, ¼” thick skim coat of EIFS over the entire existing EIFS to provide a smooth appealing look, and the entire exterior EIFS cladding shall be repaint-

ed. An area of 1,400 sf shall be bid to repair any defective areas of the E.I.F.S. On the interior side of the exterior walls the existing sheathing and stud framing shall be removed to the struc-tural wall, and replaced with new framing and drywall sheathing. The exterior walls shall meet the Energy requirements described in this RFP.

6.4.2.1 Brick Wall Repair. Contractor to clean and remove the grout between the bottom of the brick course and steel lintel. Clean steel lintel and repaint. Contractor to install new weep holes / vents and regrout. Contractor to remove existing expansion joint between the three story building and the single story and replace with new expansion joint.

6.4.3 Roofs. The existing roof on Building 5502 is a shingle roof system. The existing roof shingles and roofing felt shall be removed to the plywood deck. A new shingle roof system shall be installed including asphalt-saturated felt underlayment and associated ice dam underlay-ment. Shingles shall meet the fire resistance requirements of UL 790 for Class A and the wind resistance requirements of ASTM D3161/D3161M, Class F. The new shingles will be secured to a new layer of nail base roof insulation panels that are attached to the existing roof rafters. This will allow the attic to be kept at a temperature above freezing and allow the sprinkler system to be a wet pipe throughout the building. The insulation thickness will be determined by R value needed for this location. The existing soffits and fascia will be enclosed and insulated. The shin-gles will be vented through the nail base roof insulation. The asphalt shingles will have a typical manufacturer 40 year warranty.

6.4.4 Trim and Flashing. Gutters, downspouts, and fascias shall be prefinished metal; com-ply with SMACNA Architectural Sheet Metal Manual. Provide manufacturer's 20-year material and finish warranty.

Amendment 0002

6.4.4.1 Provide gutters, downspouts, drain boots that tie to storm water and other roof drainage elements as appropriate to direct runoff away from the building without damage or erosion to landscaping or paving.

JB MDL, New Jersey

01 02 00.06 48 -5

6.4.5 Miscellaneous Exterior Elements.

6.4.5.1 Knox Box. Provide a Knox Box at the Barracks Facility. Location shall be coordinat-ed during the Design.

6.4.5.2 Entry Canopies. Provide new canopies at 4 side door locations, as a bid option.

Canopy frames shall be welded aluminum. Fabric shall be 100% acrylic with a fluorocarbon fin-ish warranted against fading for 5 years. Shall be bid as an option. Refer to Price Breakout Schedule.

6.4.5.3 Exterior Expansion Joints. The expansion joints between the three story building and the single story building shall be removed and replaced.

6.4.6 Exterior Signage. The following are minimum requirements. Additional exterior signage may also be provided.

6.4.6.1 Contractor shall provide exterior signage on the building at exterior doors indicating associated interior spaces. Contractor shall coordinate style, size, and text of signs with JB MDL Department of Public Works.

6.4.6.2 The exterior existing building sign with the building number shall remain. Contractor to leave in place. Provide “Do Not Enter” signs on egress only doors. Provide appropriate signs to lead all occupants and visitors to the main entry.

6.4.7 Exterior Personnel Doors and Frames.

6.4.7.1 Exterior Doors and Hardware. Contractor shall remove and replace all exterior doors and frames. Exterior doors and frames shall be insulated hollow metal; comply with ANSI A250.8/SDI 100. Doors shall be Level 3, physical performance Level A, Model 2; insulated; top edge closed flush. Frames shall be Level 3, 14 gauge, with continuously welded corners and seamless face joints. Doors and frames shall be constructed of hot dipped zinc coated steel sheet, complying with ASTM A653, Commercial Steel, Type B, minimum A40 coating weight;

factory primed. Anchors and accessories shall be zinc coated. Frames in masonry shall have bituminous back-coating, plaster guards, and shall be grouted solid. Fire-rated openings shall comply with NFPA 80 and the requirements of the labeling authority. Exit devices shall comply with Life Safety requirements of NFPA 101 and UL listed modern rim style device and shall be fail secure. The exit device shall have a dogging feature or have the ability to lock the latch in a retracted position for unrestricted building entry at times of the User’s choosing. Design of glass, glazing, frames, connections and structure shall comply with antiterrorism minimum standards and other code requirements. Refer to Part 1 paragraph 1.2.8 for implementation requirements of UFC 4-010-01 and exceptions noted for this project.

6.4.7.1.1 Hinges. ANSI/BHMA A156.1; template, full mortise, heavy duty, ball bearing, minimum size 4 1/2 inch x 4 1/2 inch, non-ferrous base metal, non-removable pins.

JB MDL, New Jersey

01 02 00.06 48 -6 Amendment 0002

6.4.7.1.2 Locksets. ANSI/BHMA A156.2; series 4000, Grade 1 cylindrical locksets, non-ferrous base metal, removable core. Specific requirements are as follows:

6.4.7.1.2.1 Entry Doors shall be Lever Handle that can be unlocked using key in outside lever. All cylinders shall be BEST Peaks 7-pin interchangeable core. Any proposed sub-stitutions must be compatible with the existing keying system and must be approved by the Government. Five sets of exterior doors shall have Mortise Lock with Magnetic Stripe from ONITY to match existing hotel lock systems used on the base. Location of the locks on exterior doors will be determined during the design meetings after award of contract. Lock system shall be reviewed and accepted by JBMDL and Contracting Officer.

6.4.7.1.3 Exit (Panic) Devices. ANSI/BHMA 156.3; heavy-duty touch-pad type, through-bolted mounting. Listed and labeled for panic protection based on UL 305.

6.4.7.1.4 Closers. ANSI/BHMA A156.4; series C02000, Grade 1, hydraulic, factory-sized, adjustable to meet field conditions. Provide for all exterior doors, all doors opening to corridors, and as otherwise required by codes. At all exterior doors provide overhead holders or closers with hold-open capability.

6.4.7.1.5 Auxiliary Hardware. ANSI/BHMA A156.16. Provide wall or floor stops for all ex-terior doors that do not have overhead holder/stops. Provide other hardware as necessary for a complete installation.

6.4.7.1.6 Thresholds. ANSI/BHMA A156.21; non-ferrous metal. Provide at all exterior doors.

6.4.7.1.7 Weatherstripping. ANSI/BHMA A156.22. Provide at all exterior doors.

6.4.7.1.8 Kick Plates. ANSI/BHMA A156.6; non-ferrous metal. Provide at all doors with closers.

Amendment 0002

6.4.8 Exterior Windows. Provide operable and non-operable aluminum windows complying with American Architectural Manufacturers Association AAMA/NWWDA 101 / I.S.2 in all dorm/sleeping rooms. Minimum performance class shall be Heavy Commercial (HC). Minimum wind load and resulting design pressure and performance grade shall be determined in accord-ance with the International Building Code (IBC). Provide windows with insulating glass and thermal break necessary to achieve a minimum Condensation Resistance Factor (CRF) of 45.

Finish shall be Architectural Class I anodic coating or AAMA 2605 organic coating. Design of glass, glazing, frames, connections and structure shall comply with antiterrorism minimum standards and other code requirements. Refer to Part 1 paragraph 1.2.8 for implementation re-quirements of UFC 4-010-01 and exceptions noted for this project. Supporting structures shall be concealed within the wall finishes. Provide operable aluminum windows complying with American Architectural Manufacturers Association AAMA/NWWDA 101 / I.S.2 in all offices, classrooms, dayrooms, laundry, stairwells and all dorm/sleeping rooms. Provide non-operable windows in storage rooms. Mechanical rooms, Electrical Rooms, and Communications rooms shall have insulated metal panels framed to mimic windows. Minimum performance class shall be Heavy Commercial (HC). Minimum wind load and resulting design pressure and

JB MDL, New Jersey

01 02 00.06 48 -7 Amendment 0002 performance grade shall be determined in accordance with the International Building Code (IBC). Provide windows with insulating glass and thermal break necessary to achieve a mini-mum Condensation Resistance Factor (CRF) of 45. Finish shall be Architectural Class I anodic coating or AAMA 2605 organic coating. Design of glass, glazing, frames, connections and structure shall comply with antiterrorism minimum standards and other code requirements. Re-fer to Part 1 paragraph 1.2.8 for implementation requirements of UFC 4-010-01 and exceptions noted for this project. Supporting structures shall be concealed within the wall finishes.

Am…