This document is a solicitation for Hazardous Tree Removal & Right of Way Corridor Clearing services at Barren River Lake in Kentucky. The U.S. Army Corps of Engineers, Louisville District is seeking a contractor to furnish all materials, equipment, labor, and supervision to complete the required work. The contract will be awarded to the lowest priced offer from a qualified small business, with a NAICS code of 561730 and size standard of $9.5 million.
The work includes removing hazardous trees and clearing right-of-way corridors across several recreation areas at Barren River Lake. The contractor will be required to mobilize and demobilize, as well as comply with all federal, state, and local laws and regulations. The period of performance is 120 calendar days from the date of award. Interested contractors are strongly encouraged to conduct a site visit on September 18, 2024 at 9:00 AM Central Time. Quotes are due on September 20, 2024 by 2:00 PM Eastern Time and must be submitted electronically. Any questions must be submitted by September 18, 2024 at 10:00 AM Eastern Time.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W912QR24Q0128 10-Sep-2024
b. TELEPHONE NUMBER
502.315.7494
8. OFFER DUE DATE/LOCAL TIME
02:00 PM 20 Sep 2024
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912QR9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MAXWELL S WILLIAMS
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W22W9K42395601
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE H270A00 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
LOGISTICS MANAGEMENT
600 DR. MLKJ PLACE P.O. BOX 59 ROOM 172D
LOUISVILLE KY 40201-0059
TEL: FAX:
FAX:
TEL: 502.315.7494 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$9,500,000
NAICS:
561730
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF46
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W912QR24Q0128
Section SF 1449 - CONTINUATION SHEET
SPECIAL INSTRUCTIONS
Prices should include mobilization & de-mobilization, fuel, labor, material, equipment and any applicable permits.
The contractor’s work and responsibility shall include all planning, programming, administration, management, supervision, communications and inspection necessary to assure that all work is conducted in accordance with the contract requirements and all applicable Federal, State and Local laws and regulations.
All work shall be performed in strict compliance with the attached specifications and all other terms and conditions incorporated herein. Work under this contract shall begin within 10 calendar days of Award being issued and must be completed within 120 calendar days of Award.
The work under this request for quote is 100% set aside for small business. NAICS Code 561730 (Size Standard, $9.5 Million).
One award will be made from this Solicitation. The contract award will be based on Lowest Price.
Note: A site visit is HIGHLY ENCOURAGED. It is strongly encouraged that each interested contractor visit the job site and assume responsibility for quantities, materials, critical dimensions, and work conditions used to calculate a quote. This site visit will be held on 18 September @ 0900 Central Time. The POC’s contact information is as follows:
Dan Taylor, Lead Ranger daniel.r.taylor@usace.army.mil Barren River Lake 11088 Finney Rd.
Glasgow, KY 42141 270-646-2055
Submit Quotes to Maxwell Williams. Quotes are due on 20 September 2024 at 02:00 PM Eastern Time. Fax submittals will not be accepted. Electronic submittals will be accepted and may be emailed to maxwell.s.williams@usace.army.mil. All questions must be submitted to maxwell.s.williams@usace.army.mil by 18 September 2024 at 10:00 AM Eastern Time.
All contractors must be registered in the System for Award Management (www.SAM.gov) prior to award of a contract. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http:// www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov.
Please begin the registration process immediately to avoid delay of the contract award should your firm be selected.
ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.
Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) with 30 days of activation or the vendor risks no longer being active in SAM.
PLEASE NOTE: SAM is completely free of charge for both registrants and users.
All inquiries and correspondence concerning this solicitation shall be directed to the email listed above.
PRICE BREAKOUT SCHEDULE
Price Breakout Schedule
Dated 23 August 2024 Hazardous Tree Removal & Right of Way Corridor Clearing
U.S. Army Corps of Engineers Barren River Lake 11088 Finney Rd.
Glasgow, KY 42141
CLIN Description Unit Price
Unit of
Issue
Qty TOTAL
0001 (Base): Tree Removal - Bailey’s Point Campground, Tailwater Campground, Port Oliver Recreation Area, Beaver Creek Recreation Area
$ EA 1 $
0002 (Option 1): Tree Removal – Bailey’s Point C-Showerhouse & Trails
$ EA 1
Total of Base
0003 (Option 2): Tree Removal – Lower Storage Area
$ EA 1 $
0004 (Option 3): Right-of-Way Corridor Clearing – Bailey’s Point REC Area
$ EA 1 $
0005 (Option 4): Right-of-Way Corridor Clearing – Port Oliver REC Area
$ EA 1 $
0006 (Option 5): Right-of-Way Corridor Clearing – Beaver Creek REC Area
$ EA 1 $
0007 (Option 6): Right-of-Way Corridor Clearing – Tailwater REC Area
$ EA 1 $
0008 (Option 7): Right-of-Way Corridor Clearing – Narrows REC Area
$ EA 1 $
Total of Options
Total of All CLINs
CLIN Description:
CLIN 0001 (Base): Tree Removal - Bailey’s Point Campground, Tailwater Campground, Port Oliver Recreation Area, Beaver Creek Recreation Area CLIN 0002 (Option 1): Tree Removal – Bailey’s Point C-Showerhouse & Trails CLIN 0003 (Option 2): Tree Removal – Lower Storage Area CLIN 0004 (Option 3): Right-of-Way Corridor Clearing – Bailey’s Point REC Area CLIN 0005 (Option 4): Right-of-Way Corridor Clearing – Port Oliver REC Area CLIN 0006 (Option 5): Right-of-Way Corridor Clearing – Beaver Creek REC Area CLIN 0007 (Option 6): Right-of-Way Corridor Clearing – Tailwater REC Area CLIN 0008 (Option 7): Right-of-Way Corridor Clearing – Narrows REC Area
SCOPE OF WORK
Performance Work Statement
Dated 23 August 2024 Hazardous Tree Removal & Right of Way Corridor Clearing
U.S. Army Corps of Engineers Barren River Lake 11088 Finney Rd.
Glasgow, KY 42141
TP-1.1 GENERAL:
a. Description. The contractor shall furnish all materials, supplies, tools, parts, equipment, transportation, labor, supervision, communication, and quality control to complete the work listed below, at the areas specified at Barren River Lake, located in Barren and Allen Counties, Kentucky.
b. Work shall be provided in accordance with all Terms, Conditions, General, Specific and Technical Provision, Exhibits, Attachments, Drawings, etc. contained herein or incorporated by reference. All distances and measurements given are approximate. Each interested contractor is urged to visit the job site to assess quantities, critical dimensions, and work conditions. All work will be done according to standard industry practices. Access to the work area is controlled and appointments to look at the site shall be coordinated with the Technical Representative. This includes all mandatory provisions of the Federal Acquisition Regulation (FAR), whether referenced or not, current at time of award.
c. Contractor Responsibility. Contractor’s work and responsibility shall include but are not limited to supply of equipment/materials, all planning, programming, administration, management, supervision, and inspection required to assure all equipment/materials are acquired and work is conducted in accordance with the contract and all applicable laws, regulations, or directives. The Contractor shall ensure all work meets or exceeds specifications.
The prime Contractor shall be responsible for ensuring all subcontractors comply with the provisions of this contract.
d. Performance Required. Special consideration of the Contractor is directed to the fact that required accuracy, thoroughness, safety, and progress of this work are essential to the intended purpose. The contractor must be cognizant of the difficulties involved and of the contingencies which may arise, and must make certain that their personnel, equipment, transportation facilities and supply of materials are adequate at all times to ensure complete compliance with all provisions of these specifications. The work shall be done under professional supervision by competent employees. All contract work shall be in accordance with the submitted documents, and any additions, revisions or deletions must be approved by the Contracting Officer or his/her authorized representative.
e. Completion of Work. Completion of work shall include acceptable performance of all aspects of this contract.
f. Conditions.
1. Pre-Work Conference: The contractor will be required to attend a pre-work conference, scheduled at least one week prior to beginning work, where the Contractors plan of work, safety plan, security plan, start-up date, and other items included in this contract will be briefly discussed. The contractor will also be required to supply the necessary proof of liability insurance (copy of insurance forms) at that time. In addition, a copy of the Safety Data Sheet will be given to the government at this time and reviewed to ensure contractor compliance. This area is a secure area and the contractor will need to supply the government with a list of contractor personnel that will be working on-site.
2. Damages. The contractor shall be responsible for all damages to government or private property during the course of this contract. The contractor shall have appropriate insurance to cover liability and damages.
3. Hours and Days of Work. Work may be conducted between the hours of 6:30 a.m. and 7:00 p.m. Central Time (CT), Monday through Friday (only during daylight hours), when campgrounds are closed to the public, and in day use areas. Work may be conducted between the hours of 8:00 a.m. and
7:00 p.m. CT, Monday through Thursday and 8:00 AM through 2:00 PM on Fridays within the campgrounds when they are open to the public. No work shall be performed outside of these times, on Saturdays or Sundays, or on federal Holidays, unless approved by the Technical Representative, or as otherwise noted below.
a. Due to the fact that some of the work may be done around open campsites that are being used, the contractor will have to coordinate the work ahead of time with the Corps project office to ensure the work can be done safely and with minimal impact to the campers renting the affected campsite. Campers will not be asked to vacate an occupied site in order to complete work under this contract.
b. The campground at the Bailey’s Point Campground opens April 18, 2025, Tailwater Campground opens May 2, 2025, and Narrows Campground opens May 16, 2025. When working in a closed area the entry gate to the area must be kept closed, and the gate must be locked as the Contractor leaves the area for breaks and at the end of each workday.
4. Payment Procedure/Additional Work. At no time should the contractor do additional work without prior authorization of the Contracting Officer, and no work shall be performed that will cause the Contractor to exceed the contract price. Work performed without a binding contract document authorizing such work shall result in the Contractor not being paid for that work performed. During the course of the contract, any additional work determined to be needed may be requested by the Technical Representative to the Contracting Officer for a Contract Modification.
5. Contract Start and Completion Dates. Work under this contract shall begin within 10 calendar days of Award being issued and must be completed within 120 calendar days of Award.
Additional time may be granted for inclement weather, when coordinated with and approved by the Technical Representative. This includes delay of work that may occur during excessive rainfall or wet periods. The Options within this scope of work can be exercised at any point during the Period of Performance (PoP) and shall not constitute an extension to the PoP.
6. Wage Rates: Department of Labor wage rates apply to this work and are included. The contractor is required to provide payroll documents for all work performed under this contract.
7. The Contractor shall, at all times prior to delivery, take care to protect and preserve all materials, supplies, and equipment of every description (including material and property which may be Government owned) and all work performed. All reasonable requests of the Contracting Officer or his/her authorized representative to enclose or specially protect such property shall be complied with. If so determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payment due.
8. The Contractor will notify the Technical Representative or his/her authorized representative, upon commencement of work activities, and difficulties, interruption, or suspension of work, and when the required work has been completed. The Contractor shall update the Technical Representative, or their authorized representative, no less than once weekly on status of work being done. Work will commence when the funds are allocated, and work orders have been received from the Contracting Officer or his/her authorized representative.
9. Strongly Encouraged Site Visit: The Scope of Work only contains a detailed list of tree locations, but site conditions vary per location. It is strongly encouraged that each interested contractor visit the job site and assume responsibility for quantities, materials, critical dimensions, and work conditions used to calculate a quote. This site visit will be held on 18 September @ 0900 Central Time. The POC’s contact information is as follows:
Dan Taylor, Lead Ranger daniel.r.taylor@usace.army.mil Barren River Lake 11088 Finney Rd.
Glasgow, KY 42141 270-646-2055
TP-1.2 CONTRACTOR SUBMITTAL. Unless otherwise specified, the Contractor shall submit the following information to the Technical Representative prior to the pre-work conference for this contract:
a. Safety Plans. The Contractor shall submit, for acceptance by the Technical Representative, an accident prevention plan and Activity Hazard Analysis (AHA) in accordance with the requirements of the Corps of Engineer’s Safety and Health Requirements Manual, EM385-1-1, hereinafter referred to as the Safety Manual, current at the time of award.
b. Certification of Employees Qualified to Administer First Aid and CPR. The Contractor shall submit proof the appropriate number of employees, as required in the Safety Manual, are certified to administer First Aid and CPR.
TP-1.3 SAFETY.
a. General Safety. The Contractor shall comply with the safety standards contained in Corps of Engineers Manual, EM 385-1-1, “Safety and Health Requirements Manual”, current at the time of award, as well as all current provisions of the Occupational Safety and Health Act (OSHA).
b. Safety Manual Requirements. The Contractor and employees shall comply with all pertinent sections of the Corps of Engineer’s Safety and Health Requirements Manual, EM 385-1-1, current at the time of award, and any subsequent revisions. This manual will be available on the Internet at:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf The Contractor’s safety plan must be submitted in writing and can be turned in at the same time as the pre-work conference.
c. Personal Protective Apparel and Equipment. Protective apparel and equipment, as identified in the AHA, shall be provided to eliminate or minimize hazards to personnel. As a minimum, each employee shall wear a sleeved shirt, long trousers and safety-toe shoes or boots during all contract work. Hard hats, face shields, safety glasses with side-shields, or goggles, and hearing protection shall be worn by employees when required by safety manual. Fire extinguisher(s) and first aid kit(s) meeting the Safety Manual standards shall also be provided and easily accessible to all employees.
d. Contractor Employees Certified in First Aid & CPR. The Contractor shall schedule employees so the appropriate numbers of certified personnel are on duty to administer First Aid and CPR as required by the Safety Manual. Copies of their certification shall be provided before work begins under this contract.
TP-1.4 ACCIDENT REPORTING. The Contractor shall maintain accurate accident records and report accidents as prescribed by the Technical Representative. Accidents shall be reported within 24 hours of occurrence, and all serious accidents (those resulting in death or injury requiring medical attention or lost time) shall be reported immediately.
TP-1.5 DAMAGE REPORTS. In all instances where Government property, equipment, natural features, landscape, or trees are damaged by contract employees, an immediate notification shall be made to the Technical Representative. A full report of the incident and extent of such damage shall be submitted to the Technical Representative within two working days of occurrence, excluding weekends and holidays.
TP-1.6 CONTRACT EMPLOYEES. All contract employees shall conduct themselves in a proper and courteous manner at all times. Contract employees shall comply with all provisions of Title 36, Chapter III, Part 327, CFR and obey all posted signs and regulations in the performance of the work under this contract. Being under the influence of or consuming alcoholic beverages or controlled substances by the Contractor or employees while on duty is prohibited.
TP- 2.1 SPECIAL REQUIREMENTS:
a. Security
1. General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
2. Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
3. Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something):
All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
4. Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.
Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
SUPPLEMENTAL SECURITY REQUIREMENTS
All Contractors and subcontractor employee(s) working on this contract who require access to any Louisville District Lake Projects and Lock and Dam Projects shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12). The
Louisville District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Louisville District Security Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Louisville District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.
FOR ALL LOUISVILLE DISTRICT CONTRACTS:
Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Louisville District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted access to Louisville District facilities.
The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working, (2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) US Citizens Security Access Form each employee working on site must have a background investigation form submitted directly to the Louisville District Security Office.
The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.
Contractors shall have background checks completed for their employees annually in the case of Contracts with an initial period of performance (POP) greater than 1 year and those Contracts with Options or Modifications Which Extend the POP beyond 1 year. For instance, if the employee was cleared in May of 2022, they shall be cleared again in May of 2023. It is the Contractor’s responsibility to ensure that each employee’s security is up to date. Failure to comply may lead to possible removal from the project/jobsite.
The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S.
Army Corps of Engineers (USACE), they must process the employee through the Louisville District USACE Security Office for background purposes.
FOR CONTRACTORS REQUIRING DOD COMMON ACCESS CARDS (CAC)
The documents listed below are required:
SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). Fingerprints are captured electronically at the closest Army Recruiting Station to the contractor’s home of record or at the USACE, Louisville District Security Office.
Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.
Following submission of paperwork, the Louisville District Security Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Louisville District Security Office will make recommendations to the PCO or their Designated Representative. The Louisville District Security Office cannot give approval due to unfavorable report(s). The Louisville District Security Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.
FOREIGN NATIONALS
The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign
Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N- 550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I- 688A), etc.
In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Louisville District Security Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation, or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Louisville District Security Office by phone, letter, or email at the following numbers/addresses:
CELRL-SM
600 Martin Luther King Jr. Pl Louisville, KY 40202
Primary Email: DLL-CELRL-Security-SM@usace.army.mil
Alternate (if no response in 72 hours):
James R. Milner, phone (502) 315-6916; James.R.Milner@usace.army.mil Jason Almodovar, phone (502) 315-6754; Jason.Almodovar@usace.army.mil
b. Payment: Payment will be made by Electronic Funds Transfer (EFT), upon acceptance of the completed work and providing final invoice and labor records.
c. Qualifications: The contractor shall have at least five (5) years experience in the requirements for this Scope of Work.
TP-3.1 GENERAL SPECIFICATIONS:
a. CLIN 0001 (Base): Tree Removal - Bailey’s Point Campground, Tailwater Campground, Port Oliver Recreation Area, Beaver Creek Recreation Area
The work will consist of the following methods as specified herein for CLIN 0001 (Base) and CLIN 0002 - 0003 (Options 1 & 2):
1. Hazardous trees will be removed at three (6) Areas in Allen and Barren Counties at Barren River Lake, KY. See attached spreadsheet (Sheets 1-3) for exact locations.
2. All trees identified to be removed are described in the attached spreadsheet and have been identified with a blue metal tag at eye level on the trunk. Each tag has a unique number stamped on it, coordinating with the attached spreadsheet. The spreadsheet will delineate which trees should be cut down and removed.
3. All trees requiring complete removal are dead or dying and should be cut to within 3-4” of the ground. All debris shall be taken to the closest burn area on government property designated by the Project Manager and placed in piles suitable for burning by government personnel at a later date. The designated burn areas are located at Bailey’s Point, The Narrows, and Tailwater.
4. Hazardous limbs (limbs greater than ¾” in diameter) which are damaged, dead, or dying should be removed. Limbs will be cut back to the collar of the tree where the limb meets the base of the tree and removed from designated trees. Any limbs which the contractor considers questionable should be brought to the attention of the technical representative for a decision as to whether removal is necessary. Cut limbs shall be taken to the closest burn area on government property designated by the park manager and placed in piles suitable for burning by government personnel at a later date. Hazardous limbs removed from trail areas may be left to the sides of the trails, but no closer than 5’ from trail’s edge. These trees will not block the trail.
5. Trees requiring complete removal that lie outside of designated mowing areas or in wooded areas will be cut down to within 3-4” of ground level and left in the woods. Any trees in this category will be labeled as such on the attached spreadsheet. (All trees located on trails fall under this category). If the felled tree is blocking a trail or dropped within a mowed area, that portion in the maintained area must be cut to a manageable size and moved to the wooded area.
6. Recreation area roadways will be kept clean of debris and contractor equipment will not block the roadway or campsites, except when necessary, during the cutting and removal process. Contractor shall use appropriate traffic control and pedestrian access restrictions to keep visitors out of the work area and to ensure their safety. Equipment used to access trail areas must be approved by a Government Representative prior to work.
7. Trees that are felled that contain saw logs may be removed from government property for personal use ONLY. The removal of saw logs shall not result in the sale of marketable timber by the contractor.
8. For CLIN 0001 (Base), there are a total of 51 trees to be cut and removed or limbed. Inventory and locations of where work is to be accomplished is referenced in the table below.
b. CLIN 0002 (Option 1): Tree Removal – Bailey’s Point C-Showerhouse & Trails
1. Refer to specs in TP-3.1(a): There are a total of 19 trees to be cut and removed or limbed.
Inventory and locations of where work is to be accomplished is referenced in the table below. For Trail locations see Figures 1-3.
c. CLIN 0003 (Option 2): Tree Removal – Lower Storage Area
1. Refer to specs in TP-3.1(a): There are a total of 6 trees to be cut and removed or limbed.
Inventory and locations of where work is to be accomplished is referenced in the table below.
d. CLINS 0004-0008 (Options 3-7): Right-of-Way Corridor Clearing CLIN 0004 (Option 3): Right-of-Way Corridor Clearing – Bailey’s Point REC Area CLIN 0005 (Option 4): Right-of-Way Corridor Clearing – Port Oliver REC Area CLIN 0006 (Option 5): Right-of-Way Corridor Clearing – Beaver Creek REC Area CLIN 0007 (Option 6): Right-of-Way Corridor Clearing – Tailwater REC Area CLIN 0008 (Option 7): Right-of-Way Corridor Clearing – Narrows REC Area
The work will consist of the following methods as specified herein for CLINS 0004 – 0008 (Options 3 thru 7):
1. Right-of-Way clearing will occur at five (5) Areas in Allen and Barren Counties at Barren River Lake, KY. See attached maps (Figures 4-8) for exact locations.
2. The areas to be cleared are entering Bailey’s Point Recreation Area (Figure 4 / Option 3 / .82 miles), Port Oliver Recreation Area (Figure 5 / Option 4 / .35 miles), Beaver Creek Recreation Area (Figure 6 / Option 5 / .27 miles), Tailwater Recreation Area (Figure 7 / Option 6 / .04 miles), and Narrows Recreation Area (Figure 8 / Option 7 / .48 miles).
3. The work will consist of clearing underbrush (including existing fallen trees or limbs) back 15’ from the edge of the pavement. The trees that are removed shall be less than 3” in diameter at breast height (DBH). The trees that are dead within that 15’ zone shall be felled, and the debris placed in an adjacent wood line behind the 15’ zone. If the dead tree debris cannot be placed behind the 15’ zone it shall be taken to the nearest burn area. Limbs that overhang the roadway and fall within that 15’ zone shall be cut to a height of 20’ above the roadway to ensure adequate clearance for recreational equipment to have ingress and egress into the REC areas. Trees (less than 3” DBH) and limbs that are cut adjacent to wooded areas may be deposited there, but it must be behind the 15’ clear zone. Any trees or limbs deposited in the woods shall not interfere with any adjacent recreational improvements.
Sheet 1
Sheet 2
Sheet 3
Figure 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7
Figure 8
-End of Specification-
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-22 Alternative Line Item Proposal JAN 2017 52.204-29 Federal Acquisition Supply Chain Security Act Orders--
Representation and Disclosures.
DEC 2023
52.212-1 Instructions to Offerors--Commercial Products and Commercial Services
SEP 2023
52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services
NOV 2023
52.217-5 Evaluation Of Options JUL 1990 52.222-25 Affirmative Action Compliance APR 1984 52.237-1 Site Visit APR 1984 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
SEP 2022
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors JAN 2023 252.204-7015 Notice of Authorized Disclosure of Information for Litigation
Support
JAN 2023
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7024 Notice on the Use of the Supplier Performance Risk System MAR 2023 252.223-7008 Prohibition of Hexavalent Chromium JAN 2023 252.225-7012 Preference For Certain Domestic Commodities APR 2022 252.225-7048 Export-Controlled Items JUN 2013 252.225-7055 Representation Regarding Business Operations with the
Maduro Regime
MAY 2022
252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime
JAN 2023
252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region - Representation
JUN 2023
252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region
JUN 2023
252.225-7972 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems (DEVIATION 2020-O0015)
MAY 2020
252.225-7973 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems - Representation (DEVIATION 2020- O0015)
MAY 2020
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.237-7010 Prohibition on Interrogation of Detainees by Contractor
Personnel
JAN 2023
252.244-7000 Subcontracts for Commercial Products or Commercial Services
NOV 2023
252.247-7023 Transportation of Supplies by Sea JAN 2023
CLAUSES INCORPORATED BY FULL TEXT
52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)
(a) Definitions. As used in this clause--
Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
(End of clause)
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services-- Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Products and Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.
(a) Definitions. As used in this provision-
Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."
(d) Representations. The Offeror represents that--
(1) It [ ___ ] will, [ ___ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation.