CIVIL/OPS/ENVIRONMENTAL BR

ATTN: ADYSON MEDLEY

600 DR M L KING JR PL RM 821

LOUISVILLE KY 40202-2236

W22W9K11672745

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912QR21Q0072 to provide tow ing services of the crane barge Henry M. Shreve is hereby amended as follow s:

a. The Scope of Work (SOW) and Price Breakout Schedule have been modified in accordance w ith the Customer's request.

b. The due date is hereby extended from 10:00AM 05 August 2021 to 10:00AM 06 August 2021.

c. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR21Q0072

X 9B. DATED (SEE ITEM 11)

22-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Jul-2021

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE 964860

FACILITY CODECODE

EMAIL:TEL:

W912QR21Q0072

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 05-Aug-2021 12:00 AM to 06-Aug-2021 10:00 AM.

The following have been modified:

PRICE BREAKOUT SCHEDULE

Line

Item DESCRIPTION Unit QTY. TOTAL COST

Item for:

TOWING LD777 100’wide x 300’ long 5’-9” Draft, LD780 100’wide x 34’ long 5’-9” Draft, and up to two 54’ x 140’ flat deck equipment barges.

FROM McAlpine Locks and Dam, Louisville, KY, Louisville Repair Station (LRS) - Ohio River Mile

606.8. Or any site between LRS and Olmsted. The

projected pickup date is 1 Sept 2011 at 0700 hours.

Contractor will be called by government representative to set specific date.

TO Olmsted Locks and Dam, Olmsted, IL, Ohio River Mile 964.6 Right Descending Bank delivery 4 days after pickup. Location of dropoff at the site will determined by gov’t representative on the Shreve. JOB 1

Item for:

TOWING LD777 100’wide x 300’ long 5’-9” Draft, LD780 100’wide x34’ long 5’-9” Draft, and up to two 54’ x 140’ flat deck equipment barges.

FROM Olmsted Locks and Dam, Olmsted, IL, Ohio River Mile 964.6 Right Descending Bank pick up during the month of October 2021. Contractor will be called by government representative to set specific date.

TO McAlpine Locks and Dam, Louisville, KY, Louisville Repair Station (LRS) - Ohio River Mile 606.8, delivery 4 days after pickup at Olmsted. JOB 1

Item is to reimburse the contractor of all costs associated with the mobilization of a towboat to McAlpine (LRS) from the contractor’s fleet. JOB 1

Item is to reimburse the contractor of all costs associated with the demobilization of a towboat from LRS to return the towboat to their fleet after the SHREVE and LD-780 have been delivered. JOB 1

Optional Item is for additional days due to unforeseen delays or scheduling conflicts. Bid item is for one day and may be awarded up to 5 times. Option may be awarded up to the end of the period of performance in the contract. ls 1

TOTAL BASE:

TOTAL BASE PLUS OPTION:

SCOPE OF WORK

SCOPE OF SERVICES FOR

RENTAL OF ONE TOWBOAT WITH OPERATING PERSONNEL

1. General The object of these specifications is to secure towing of the crane barge Henry M. Shreve for the US Army, Corps of Engineers, Louisville District, from Louisville Repair Station located immediately upstream of McAlpine Locks and Dam to Olmsted Locks and Dam by renting one towboat with all necessary operating personnel. There may be commercial barges in the tow provided there are no stops to interrupt the delivery of the Shreve and the towboat can fleet the Shreve and barges into its tow unaided. The contractor’s towboat shall have a minimum horsepower of 4000 horsepower (HP). The towboat will tow the Heavy Lift Crane Henry M.

Shreve (SHREVE) LD-777 and Barge LD 780, and up to two 54’ x 140’ flat deck equipment barges to the destinations listed in the bid schedule.

a. The dates given in the bid schedule are the projected pickup and delivery dates at the given locations. Actual pickup and delivery dates and times may change. The Government reserves the right to adjust this date to meet its repair project schedule. Notice of such a change will be given as soon as possible, with a goal of notifying the contractor not later than 14 days prior to any new delivery date.

b. The SHREVE is a heavy lift crane permanently affixed to a 300 foot long by 100 foot wide by 14 foot molded depth hull. A barge, LD-780, is coupled to the stern of the SHREVE during towing. The LD-780 is 34 foot long by 100 foot wide by 8 foot molded depth. The towing draft of the SHREVE is 5 feet 9 inches. There is extremely limited forward visibility for the pilot when the SHREVE is in tow due to the height of the crane and gate stowage structure (see photo at end of specifications). A dedicated lookout shall be stationed at the head of the tow during towing operations. The SHREVE’s gate stowage structure blocks signals from towboat mounted radar antennas. The SHREVE has an enclosed lookout station on the front of the crane barge Questions concerning technical details of the SHREVE may be directed to the technical representative, Brian Holcomb at (502) 315-6702.

c. High steel of the SHREVE is the top of the three spuds at 61 feet 0 inches (based on a 5 foot 9 inch draft).

Spuds can be lowered and dogged at 55 feet 0 inches for transiting under low objects, but this increases the draft of the vessel. The fixed high steel of the SHREVE is the storage racks at 55 feet 0 inches to the top of the handrail.

d. Priority lockage shall be given at all locks in route on the Ohio River during mobilization and while the Shreve is in tow. Priority lockage will not be given while returning to port.

2. Inspection of Equipment.

a. After award and prior to the tow, the Contracting Officer or his/her authorized representative will make an inspection of the contractor’s towboat (noted by name and horsepower with the bid) to determine the condition and suitability for the service for which it will be used. The contractor will contact the technical representative at the telephone number above immediately after award to coordinate inspection. If it is found that the equipment offered is not suitable for the purpose intended, or that it is not in good mechanical condition, it will not be accepted and the contractor shall provide a towboat that meets the requirements stated herein. If deficiencies are of a minor nature and may be easily repaired, the contractor will be given three days to correct all deficiencies found. If the deficiencies are not corrected within the three-day period, the contract may be terminated. Towboats must meet the requirements as outlined in the latest edition of the U.S. Army Corps of Engineers’ Safety and Health Requirements Manual (EM 385-1- 1). This inspection will not relieve the Contractor from the satisfactory operation of the equipment during the period of the contract or any extension thereof.

3. Insurance

a. Evidence of insurance shall be submitted to the Contracting Officer or his/her authorized representative within two days after award. Certificate of Insurance shall be for the duration of the contract.

b. Workmen’s Compensation. Workmen’s Compensation and Occupation Disease Coverage as legally required by the State wherein the work is being performed.

c. Comprehensive General Liability Insurance (to include government furnished or contractor furnished vessel usage). Bodily injury coverage with minimum limits of $500,000 per occurrence shall be required.

Property damage coverage with a minimum limit of $100,000 per occurrence shall be required. Property damage coverage with a minimum limit of $100,000 per occurrence shall be required. THUS, THE

COMBINED SINGLE LIMIT SHALL BE AT LEAST $600,000.

d. Marine Liability Insurance. The contractor shall procure and maintain marine insurance, including Hull and Protection and Indemnity in the minimum amount of $40,000,000 for the Shreve, Barge LD-780, and the two flat deck barges and equipment, per occurrence (including Jones Act and Collision and Towers liability insurance). Notwithstanding the foregone, the Contractor shall assure that it has sufficient marine liability insurance to cover the value of any damage to or loss of the vessels being towed.

4. Delivery and Release.

a. The towboat shall arrive at the above specified pickup points at the dates and times indicated. The towboat shall then tow the SHREVE and Barge LD-780 to the designated delivery point by the date and time specified.

b. The towboat shall be released after mooring the SHREVE at the designated site.

5. Payments.

a. Payments will be made after receipt of a proper invoice. Invoices shall be sent electronically to the technical representative. Brian.L.Holcomb@usace.army.mil

b. No payment will be made for lost time due to breakdowns or for any causes due to the fault or negligence of the Contractor or his employees.

c. Delays encountered in route beyond the control of the Contractor: There are currently no expectations of delays to be encountered in route beyond the control of the contractor, such as high water limiting passage of the crane barge under bridges, river closures or the like. However, if such delays are encountered, they will be evaluated for accuracy and paid for under the bid item for such delays.

e. Lost Time. Lost time will be considered as the time when the boat is inoperative because of breakdowns and/or other causes due to the fault or negligence of the Contractor or his employees. Time lost for minor repairs and/or adjustments to the boat which, in the opinion of the contracting officer, does not interfere with or result in loss of operating time, will not be charged as lost time to the Contractor.

6. Performance of Plant.

a. Award of the Contract and acceptance of the towboat does not relieve the Contractor from responsibility for the satisfactory performance of the boat. Time is of the essence in the delivery of services under the Contract; “Best possible speed for conditions” will be maintained by the towboat used. Strict compliance with the delivery schedule is essential and untimely delivery of the services required under the Contract, or other unsatisfactory performance, will jeopardize the interests of the Government.

7. Control and Responsibility.

a. The operation of the towboat shall at all times be under the direction of the Contractor or designated employees.

8. Supervision.

a. Proper supervision will be maintained on the towboat by the Contractor to ensure compliance with the terms of the contract. The Contractor's authorized representatives will be designated in writing at the time of delivery of the boat and at any time thereafter when such authorized representatives may be changed

9. EM 385-1-1, SAFETY AND HEALTH REQUIREMENTS.

a. EM 385-1-1, Safety and Health Requirements Manual, revised 15 September 2008, is part of this scope.

The contractor shall comply by all pertinent provisions. No separate payment will be made for compliance with Safety and Health Requirements. EM 385-1-1 can be downloaded from, http://www.usace.army.mil/CESO/Pages/EM385-1-1,2008NEW!.aspx

10. Expenses of Operation and Repair.

a. Except as hereinafter provided, the Contractor shall furnish at his own expense all operator(s) labor, lubricating oils, greases, appliances, appurtenances, equipment, materials, and bear all expenses incidental to the efficient operation of the towboat in connection with the work under the contract. The Contractor shall also bear all direct overhead and collateral expenses incidental to the operation, upkeep, and repair of the boat; shall maintain the boat in a good state of repair and shall arrange for a supply of renewal parts to be on hand when needed for the boat.

11. Subsistence and Quarters for Government Personnel.

a. Two Government personnel will be aboard during transit periods. The Contractor shall furnish 3 meals per day and quarters for the two Government personnel. Quarters include separate beds with bedding, towels and bathing facilities.

12. Personnel

a. Upon delivery of the towboat, the Contractor shall furnish the SHREVE Master a complete list of all contractor employees who will be working in any capacity on the towboat along with their schedule of work. Updates will be required anytime a change in personnel or work schedule occurs.

b. Crew. The Contractor shall furnish and pay all necessary crew required for the satisfactory and efficient operation of the towboat. The Contractor shall be responsible for compliances with all marine laws pertaining to labor on the towboat.

c. Licensed Personnel. The Contractor shall furnish and pay a sufficient number of towboat pilots and/or masters, engineers, and deckhands to operate the towboat the required number of hours. The pilots furnished shall be competent and satisfactory to the Contracting Officer, shall possess a current Operator of Uninspected Towing Vessel upon the Western Rivers (Radar Observer) or Master of Towing Vessel issued by the U.S. Coast Guard for the type, size, tonnage, and horsepower of the boat proposed to be furnished, and for the waters in which it will be operated. Operators shall be alert at all times.

13. Towboat.

a. The hull of the towboat shall be steel construction, flat bottom, suitable for operation on the Ohio River and

Mississippi River. It shall be capable of being easily handled in swift currents and maneuvered in close places. The towboat shall at all times comply with the current rules and regulations of the U.S. Coast Guard and shall be currently certified for operation in the waters specified. BIDS ON TUGBOATS

WILL BE CONSIDERED NONRESPONSIVE.

b. The towboat shall be propelled by two or more diesel marine engines with a total manufacturer rating of not less than 4000 continuous horsepower (flywheel) for all engines operated at the manufacturer's rated continuous rpm. The contracting officer will use the current Inland River Record to verify horsepower of the towboat being bid. If the horsepower in the Inland River Record does not correlate with the horsepower required by this specification, the bidder must submit with its bid, additional information from the engine manufacturer that evidence that the equipment bid meets the horsepower required of this specification. If additional data is not provided with your bid, your bid may be determined non-responsive.

c. The towboat shall have at least one steering and two flanking rudders working in conjunction with each propulsion shaft and propeller. The power-actuated steering and flanking rudders shall be capable of independent operation and shall be seaworthy and in good mechanical condition. Z-drive vessels are also acceptable and meet this specification at the same horsepower rating.

d. The towboat shall be equipped with two electric generators, one for standby.

e. The pilothouse shall be equipped with adequate windows to allow the operator good visibility in all directions.

f. The towboat shall have a minimum of two towing knees permanently affixed to the bow.

g. The towboat shall be equipped with ample deck fittings and at least two power operated winches.

e. The contractor shall furnish sufficient ratchets, wire, and fittings to make up tow to the SHREVE.

i. The towboat shall arrive to tow the SHREVE with a sufficient amount of fuel to allow for continuous operation between destinations.

j. No-smoking within the interior of the towboat should be encouraged to the greatest extent possible.

14. Anti-Terrorism & Operational Security

a. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

b. The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

c. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

The HM SHREVE and Barge LD780 are in tow by the mv J.C. Thomas. The SHREVE has been placed at the head of tow with the Barge LD780 at the stern of the SHREVE.

The SHREVE is 300’ x 100’ barge with an air draft of 61’.

The Barge LD 780 is 34’ x 100’.

The mv J.C. Thomas is 150’ x 42’ with a 36’ height of eye for the pilots.

(End of Summary of Changes)