This solicitation is for a firm-fixed-price design/bid/build contract to construct an Automated Multipurpose Machine Gun (MPMG) Range at Devens Reserve Forces Training Area in Massachusetts. The project includes a 4-lane light MPMG range with targetry out to 800 meters, as well as range operations and control facilities, classrooms, storage buildings, covered mess, ammunition building, and restrooms. Supporting facilities incorporate site work, utilities, security measures, and information systems. The contract duration is estimated at 740 calendar days from notice to proceed. This is a small business set-aside acquisition conducted by the Department of the Army Corps of Engineers Louisville District. The North American Industry Classification System code is 236220 and the business size standard is $36.5 million.

View the file

Other files

File Type Posted
Bid Opening Results W912QR21B0014.docx DOCX document
W912QR21B0014-0002.pdf PDF
W912QR21B0014_Plans-0001.pdf PDF
Site Visit Roster 1.jpg JPG image
Site Visit Roster 2.jpg JPG image
W912QR21B0014_Specs-0000.pdf PDF
W912QR21B0014_Plans_Vol1-0000.pdf PDF
Devens Multi- Contractor Pass request.pdf PDF
Devens Visitors Pass Request.pdf PDF
W912QR21B0014_Plans_Vol2-0000.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912QR21B0014 for the Construction of an MPMG Range at Devens Reserve Forces Training Area, MA is hereby amended as follow s:

See summary of changes:

1. CONTRACT ID CODE PAGE OF PAGES

1 20

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR21B0014

X 9B. DATED (SEE ITEM 11)

25-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Sep-2021

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912QR21B0014-0001

W912QR21B0014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMDMT 1 SUMMARY OF CHANGES

SUMMARY OF CHANGES

DRAWINGS:

1. The following Drawings have been replaced in their entirety:

CS531 – Previous General Note #4 was deleted.

CS533 – General Note #7 was added.

ES517 – Change to Material requirements 3MH110 – Change to louver and fan schedule requirements 4A200 – Pre-finished metal wall panel note added

SPECIFICATIONS:

2. The following Specification Sections have been edited in their entirety:

DIVISION 00

Section 00 08 00.00 06 Special Provisions

Part 1 Section 1.21 Part 1 Section 1.30.c

DIVISION 08

Section 08 71 00 Door Hardware

Door Hardware Set Attachment

3. Wage Determination MA20210008 is hereby removed and replace by Wage Determination MA20210002 Modification 6, dated 17 September 2021:

4. The E-Submission Instructions are modified to change the Bid Opening call in information:

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

E-SUBMISSION INSTRUCTIONS

Bid Opening All sealed bids must be delivered electronically per the instructions contained within this solicitation. The bid opening will be conducted telephonically via the below conference call-in number. Bids must be received by the time specified in the solicitation, otherwise they will be deemed late and unacceptable. The bid opening teleconference will begin promptly thirty (30) minutes after the bid submission time. The conference call-in number is as follows:

Conference Call-In Number: (844) 800-2712

Access Code: 964 051 25

The Contracting Officer with assistance from the assigned Contract Specialist will download all of the bid submissions and record all of the pertinent information prior to the conference call.

The bid opening teleconference will begin promptly 30 minutes after the submission time and at that time the bid opening officer will 1) read the names of the submitting contractors and their bids, and 2) read the independent government estimate. Once the information has been disseminated, the call will come to an end. The bid abstract will be posted to the beta.sam website by close of business of the day bids are opened.

Immediately following the bid opening, and upon notice by the Contracting Officer, the apparent low offeror will be requested to mail in their original bid and original bid bonds, respectively.

NOTE: Due to the potential of no Government Personnel being available to inspect the original bonds, the Contracting Officer may contact the bonding company to verify the information in the bond is accurate and complete

Bids: ALL SUBMISSIONS TO THIS BID ANNOUNCEMENT SHALL BE SUBMITTED ELECTRONICALLY THROUGH DOD SAFE. No paper copies, CD-ROMs or facsimile submissions will be accepted. Electronic Bid Submission is required through the Army’s Electronic File Sharing Service, DOD SAFE (https://safe.apps.mil). The DOD SAFE Application is used to send large files to individuals that would normally be too large to send via email.

There are no user accounts for SAFE. Authentication is handled via email. Anyone has access to DOD SAFE, and the application is available for use by anyone. The SAFE “Getting Started Guide” has information on how to utilize the system (https://safe.apps.mil/about.php).

Instructions for uploading are as follows:

1. Send an email to the Contracting Officer and Contract Specialist to receive the link to drop off your proposal. This will need to be completed five (5) business days prior to uploading your bid.

a. Josh Gitchel, Contract Specialist at joshua.gitchel@usace.army.mil

b. Jesse Scharlow, Contracting Officer at jesse.e.scharlow@usace.army.mil

2. You will receive an email with the link to submit your drop-off. The link will be provided no later than two (2) business days prior to the bid date.

3. Short Note to the Recipients: Click the Add Files or Drag and Drop your files. For file description, enter W912QR21B0014-FIRMNAME.

4. Click Upload button to send documents.

Guest users will need to check their email to verify their email address before the recipients will be notified.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

WAGE RATES

"General Decision Number: MA20210002 09/17/2021

Superseded General Decision Number: MA20200002

State: Massachusetts

Construction Types: Heavy (Heavy and Dredging)

HEAVY CONSTRUCTION PROJECTS; AND

MARINE CONSTRUCTION PROJECTS

County: Worcester County in Massachusetts.

HEAVY CONSTRUCTION PROJECTS; AND MARINE CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/01/2021 1 02/12/2021 2 04/02/2021 3 04/30/2021 4 08/20/2021 5 09/10/2021 6 09/17/2021

ASBE0006-005 09/01/2020

Rates Fringes

Insulator/asbestos worker Includes the application of all insulating materials, protective coverings, coating, and finishes to all types of mechanical systems..........$ 49.00 31.75

* BOIL0029-001 01/01/2021

Rates Fringes

BOILERMAKER......................$ 45.87 29.02

BRMA0001-002 08/01/2020

SPRINGFIELD/PITTSFIELD CHAPTER WORCESTER (Warren County)

Rates Fringes

Bricklayer, Cement Mason, Plasterer & Stonemason...........$ 44.16 33.63

BRMA0001-014 02/01/2021

WORCESTER CHAPTER

WORCESTER (Auburn Barre, Blackstone, Berlin, Bolton, Boylston, the Brookfields, Charlton, Clinton, Douglas, Dudley, Grafton, Hardwick, Holden, Leicester, Mendon, Millbury, Milville, New Braintree, Northboro, Northbridge, Oakham, Oxford, Paxton, Rutland, Shrewbury, Southbridge, Spencer, Sturbridge, Sutton, Upton, Uxbridge, Webster, Westboro, West Boylston, Worcester)

Rates Fringes

Bricklayer, Cement Mason, Plasterer & Stonemason...........$ 53.61 35.94

BRMA0001-015 02/01/2021

LOWELL CHAPTER

WORCESTER (Hopedale, Milford, Southboro)

Rates Fringes

Bricklayer, Cement Mason, Plasterer & Stonemason...........$ 53.61 35.94

BRMA0001-023 02/01/2021

LOWELL CHAPTER

WORCESTER (Ashburhanm, Athol, Fitchburg, Gardner, Harvard, Hubbardston, Lancaster, Leominster, Lunenburg, Petersham, Phillipston, Princeton, Royalston, Sterling, Templeton, Westminster, Winchendon)

Bricklayer, Cement Mason, Plasterer & Stonemason...........$ 53.61 35.94

BRMA0003-001 02/01/2021

Rates Fringes

Marble & Tile Finisher...........$ 42.57 32.00 Marble, Tile & Terrazzo Workers..........................$ 54.69 33.80

TERRAZZO FINISHER................$ 55.77 34..47

CARP0056-004 08/01/2020

Rates Fringes

DIVER TENDER.....................$ 49.07 35.57

DIVER............................$ 68.70 35.57

CARP0056-008 08/01/2020

Rates Fringes

PILEDRIVERMAN....................$ 49.07 35.57

CARP0336-002 03/01/2020

WORCESTER (Except Gilbertville, Harwick, Warren, West

Brookfield)

Carpenter/Lather.................$ 42.40 29.10

CARP0336-007 03/01/2020

WORCESTER (Gilbertville, Hardwick, Warren, West Brookfield)

Rates Fringes

Carpenter/Lather.................$ 42.40 29.10

CARP1121-004 01/06/2020

Rates Fringes

MILLWRIGHT.......................$ 36.71 31.15

ELEC0096-002 09/06/2020

WORCESTER (Warren)

Rates Fringes

ELECTRICIAN......................$ 44.42 29.07

ELEC0104-001 09/03/2017

Rates Fringes

Line Construction:

Cableman....................$ 38.45 18.42+A Equipment Operator..........$ 38.45 22.50+A Groundman...................$ 24.88 10.24+A Lineman.....................$ 45.23 25.71+A

A. PAID HOLIDAYS: New Year's Day; Memorial Day;

Independence Day; Labor Day; Thanksgiving Day; Christmas Day and Columbus Day, provided the employee has been employed 5 working days prior to any one of the listed holidays.

ELEV0041-002 01/01/2020

Rates Fringes

ELEVATOR MECHANIC................$ 54.85 34.765+a+b

FOOTNOTE:

a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.

b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

ENGI0004-003 06/01/2020

WORCESTER (Except Athol, Barre, Brookfield, East Brookfield, Hardwick, New Braintree, North Brookfield, Oakham, Petersham, Phillipston, Royalston, Strutbridge, Templeton, Warren, West Brookfield, Winchendon)

Power equipment operators:

BUILDING, HEAVY & MARINE

GROUP 1....................$ 48.73 29.25

Group 1....................$ 49.33 29.75

GROUP 2....................$ 48.23 29.25

Group 2....................$ 48.81 29.75

GROUP 3....................$ 32.47 29.25

Group 3....................$ 32.72 29.75

GROUP 4....................$ 39.89 29.25

Group 4....................$ 40.30 29.75

GROUP 5....................$ 23.08 29.25

Group 5....................$ 23.13 29.75

GROUP 6....................$ 27.64 29.25

Group 6....................$ 27.79 29.75

FOOTNOTE FOR POWER EQUIPMENT OPERATORS:

A. PAID HOLIDAYS: New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Patriot's Day, Columbus Day, Veteran's Day, Thanksgiving Day, Christmas Day

HOURLY PREMIUM FOR BOOM LENGTHS (Including Jib):

Over 150 ft. +2.18 Over 185 ft. +3.84 Over 210 ft. +5.39 Over 250 ft. +8.16 Over 295 ft. +11.29 Over 350 ft. +13.14

POWER EQUIPMENT OPERATORS CLASSIFICATIONS BUILDING AND HEAVY

CONSTRUCTION

GROUP 1: Power shovel; crane; truck crane; derrick; pile driver; trenching machine; mechanical hoist pavement breaker; cement concrete paver; dragline; hoisting engine;

three drum machine; pumpcrete machine; loaders; shovel dozer; front end loader; mucking machine; shaft hoist;

steam engine; backhoe; gradall; cable way; fork lift;

cherry picker; boring machine; rotary drill; post hole hammer; port hole digger; asphalt plant on job site;

concrete batching and/or mixing plant on job site; crusher plant on job site; paving concrete mixer; timber jack GROUP 2: Sonic or vibratory hammer; grader; scraper; tandem scraper; bulldozer; tractor; mechanic - maintenance; York rake; mulching machine; paving screed machine;stationary steam boiler; paving concrete finishing machine; grout pump; portable steam boiler; portable steam generator;

roller; spreader; asphalt paver; locomotives or machines used in place thereof; tamper (self propelled or tractor-draw); cal tracks; ballast regulator;rail anchor machine; switch tamper; tire truck GROUP 3: Pumps (1-3 grouped); compressor; welding machines (1-3 grouped); generator; sighting plant; heaters (power driven, 1- 5); syphon-pulsometer; concrete mixer; valves controlling permanent plant air steam, conveyor, wellpoint system (operating) GROUP 4: Assitant engineer (fireman) GROUP 5: Oiler (other than truck cranes and gradalls) GROUP 6: Oiler (on truck cranes and gradalls)

POWER EQUIPMENT OPERATORS CLASSIFICATIONS MARINE CONSTRUCTION

GROUP 1: Shovel; crane; truck crane; cherry picker; derrick;

pile driver; two or more drum machines; lighters; derrick boats; trenching machines; mechanic hoist pavement breakers; cement concrete pavers; draglines; hoisting engines; pumpcrete machines; elevating graders; shovel dozer; front end loader; backhoe; gradall; cable ways;

boring machine; rotary drill; post hole hammer; post hole digger; fork lift; timber jack; asphalt plant (on site);

concrete batching and/or mixing plant (on site); crusher plant (on site); paving concrete mixer GROUP 2: Portable steam boiler; portable steam generator;

sonic or vibratory hammer; grader; scraper; tandem scraper;

concrete pump; bulldozer; tractor; York rake; mulching machine; roller; spreader; tamper (self-propelled or tractor-drawn); asphalt paver; concrete mixer with side loader; mechanic - maintenance; cal tracks; ballast regulator; switch tamper; rail anchor machine; tire truck GROUP 3: Pumps (1-3 grouped); comressor; welding machines (1-3 grouped); generator; lighting plant; heaters (power driven 1-5); syphon-pulsometer; concrete mixer; valves controlling permanent plant air or steam; conveyor; well point systems; auger (powered by independent engines and attached to pile drivers); hydraulic saws GROUP 4: Fireman GROUP 5: Assistant engineer (other than truck crane and gradall) GROUP 6: Assistant engineer (on truck crane and gradall)

ENGI0098-005 12/01/2016

Rates Fringes

Power equipment operators:

Group 1....................$ 33.68 23.96+A Group 2....................$ 33.37 23.96+A Group 3....................$ 33.15 23.96+A Group 4....................$ 32.54 23.96+A Group 5....................$ 29.92 23.96+A Group 6....................$ 28.80 23.96+A Group 7....................$ 26.86 23.96+A Group 8....................$ 305.95 23.96+A Group 9....................$ 230.69 23.96+A Group 10....................$ 35.17 23.96+A Group 11....................$ 38.18 23.96+A Group 12....................$ 39.68 23.96+A Group 13....................$ 40.68 23.96+A Group 14....................$ 41.68 23.96+A Group 15....................$ 43.18 23.96+A

HAZARDOUS WASTE PREMIUM $2.00

FOOTNOTE FOR POWER EQUIPMENT OPERATORS:

Group 8 and Group 9 are per day wages.

A. Paid Holidays: New year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day and Christmas Day

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

Group 1: Shovels; crawlers and truck cranes including all tower; self-propelled hydraulic cranes 10 tons and over;

draglines; clam shells; cableways; shaft hoists; mucking machines derricks; backhoes; bulldozers; gradalls;

elevating graders; pile drivers; concrete pavers; trenching machines; front end loaders- 5 1/2 cu yds and over; dual drum paver; automatic grader-excavator(C.M.I. or equal);

scrapers towing pan or wagon; tandem dozers or push cats(2 units in tandem); shotcrete machine; tunnel boring machine;

combination backhoe/loader 3/4 cu yd hoe or over; jet engine dryer; tree shredder; post hole digger; post hole hammer; post extractor; truck mounted concrete pump with boom; roto-mill; Grader; Horizontal Drilling Machine; John Henry Rock Drill and similar equipment.

Group 2: Rotary drill with mounted compressor; compressor house (3 to 6 compressors); rock and earth boring machines (excluding McCarthy and similar drills); front end loaders 4 cu yds to 5 1/2 cu yds); forklifts-7 ft lift and over 3 ton capacity; scraper 21 yds and over (struck load); sonic hammer console; reclaimers road planer/milling machine; cal tracks; ballast regulators; rail anchor machines; switch tampers, asphalt pavers; mechanic; welder and transfer machine.

Group 3: Combination backhoe/loader up to 3/4 cu yd;

scrapers up to 21 cu yd (struck load, self propelled or tractor drawn); tireman; front end loaders up to 4 yds;

well drillers; engineer or fireman on high pressure boiler;

self-loading batch plant; well point operators electric pumps used in well point system; pumps, 16 inches and over (total discharge); compressor, one or two 900 cu ft and over; powered grease truck; tunnel locomotives and dingys;

grout pumps; hydraulic jacks; boom truck; hydraulic cranes-up to 10 ton.

Group 4: Asphalt rollers; self-powered rollers and compactors; tractor without blade drawing sheepsfoot roller; rubber tire roller; vibratory roller or other type of compactors including machines for pulverizing and aerating soil; york rake.

Group 5: Hoists; conveyors; power pavement breakers;

self-powered concrete pavement finishing machines; two bag mixers with skip; McCarthy and similar drills; batch plants (not self loading); bulk cement plants; self-propelled material spreaders; three or more 10 KW light plants; 30 KW or more generators; power broom.

Group 6: Compressor (one or two) 315 cu ft to 900 cu ft;

pumps 4 inches to 16 inches (total discharge).

Group 7: Compressors up to 315 cu ft; small mixers with skip; pumps up to 4 inches; power heaters; oiler; A-frame trucks; forklifts-up to 7 ft. lift and up to 3 ton capacity; hydro broom; stud welder.

Group 8: Truck crane crews Group 9: Oiler Group 10: Master Mechanic Group 11: Boom lengths over 150 feet including jib Group 12: Boom lengths over 200 feet including jib Group 13: Boom lengths over 250 feet including jib Group 14: Boom lengths over 300 feet including jib Group 15: Boom lengths over 350 feet including jib

* IRON0007-012 09/16/2021

Rates Fringes

IRONWORKER.......................$ 49.83 34.81

LABO0022-001 06/01/2018

Rates Fringes

Laborers: (HEAVY CONSTRUCTION)

GROUP 1.....................$ 33.25 22.92

GROUP 2.....................$ 33.50 22.92

GROUP 3.....................$ 34.00 22.92

GROUP 4.....................$ 34.25 22.92

GROUP 5.....................$ 21.50 22.92

GROUP 6.....................$ 34.25 22.92

LABORERS CLASSIFICATIONS

GROUP 1: Laborers; carpenter tenders; cement finisher tenders, plasterer tenders

GROUP 2: Asphalt raker; fence and guard rail erector; laser beam operator; mason tender; pipelayer; pneumatic drill operator; pneumatic tool operator; wagon drill operator, jack hammer operator, pavement breaker, carbide core drilling machine, chain saw operator, barco type jumping tampers, concrete pump, motorized mortar mixer, ride-on-motorized buggy

GROUP 3: Air track operator; block paver; rammer; curb setter, hydraulic and similar self powered drills

GROUP 4: Blaster; powderman

GROUP 5: Flagger

GROUP 6: Asbestos Abatement; Toxic and Hazardous Waste Laborers

LABO0022-013 06/01/2018

Rates Fringes

Laborers:

(FREE AIR OPERATION):

SHIELD DRIVEN AND LINER

PLATE IN FREE AIR)

GROUP 1....................$ 39.40 21.80+a GROUP 2....................$ 39.40 21.80+a

(OPEN AIR CASSONS,

UNDERPINNING AND TEST

BORING INDUSTRIES):

TEST BORING & WELL DRILLING

Driller....................$ 39.35 24.30+A Laborer....................$ 37.95 24.30+A

(OPEN AIR CASSONS,

UNDERPINNING AND TEST

BORING INDUSTRIES):

OPEN AIR CASSON,

UNDERPINNING WORK & BORING

CREW

Bottom man.................$ 39.10 24.30+A Laborers; Top man..........$ 37.95 24.30+A

(TUNNELS, CAISSON &

CYLINDER WORK IN

COMPRESSED AIR)

GROUP 1....................$ 39.75 24.70+a GROUP 2....................$ 42.30 24.70+a GROUP 3....................$ 42.30 24.70+a GROUP 4....................$ 42.30 24.70+a GROUP 5....................$ 42.30 24.70+a

GROUP 6....................$ 44.30 24.70+a

CLEANING CONCRETE AND

CAULKING TUNNEL (Both New & Existing) GROUP 1....................$ 39.40 21.80+a GROUP 2....................$ 39.40 21.80+a

ROCK SHAFT, CONCRETE

LINING OF SAME AND TUNNEL

IN FREE AIR

GROUP 1....................$ 36.85 21.80+a GROUP 2....................$ 39.40 21.80+a GROUP 3....................$ 39.40 21.80+a GROUP 4....................$ 39.40 21.80+a GROUP 5....................$ 41.40 21.80+a

LABORERS CLASSIFICATIONS for TUNNELS, CAISSON & CYLINDER WORK

IN COMPRESSED AIR

GROUP 1: Powder watchman; Top man on iron bolt; change house attendant

GROUP 2: Brakeman; trackman; groutman; tunnel laborer;

outside lock tender; lock tender; guage tender

GROUP 3: Motorman, miner

GROUP 4: Blaster

GROUP 5: Mucking machine operator

GROUP 6: Hazardous Waste work within the ""HOT"" zone. (A premium of two dollars $2.00 per hour over the basic wage rate.

LABORERS CLASSIFICATIONS for (FREE AIR OPERATION): SHIELD

DRIVEN AND LINER PLATE IN FREE AIR

GROUP 1: Miner; miner welder; conveyor operator; motorman;

mucking machine operator; nozzle man; grout man-; pumps, shaft and tunnel steel and rodman; shield and erector arm operators, mole nipper, outside motorman, burner, TBM operator, safety miner; laborer topside; heading motormen;

erecting operators; top signal men

GROUP 2: Brakeman; trackman

LABORERS CLASSIFICATIONS FOR CLEANING CONCRETE AND CAULKING

TUNNEL (Both New & Existing)

GROUP 1: Concrete workers; strippers and form movers (wood & steel), cement finisher

GROUP 2: Form erector (wood & steel and all accessories)

LABORERS CLASSIFICATIONS for ROCK SHAFT, CONCRETE LINING OF

SAME AND TUNNE IN FREE AIR

GROUP 1: Change house attendants

GROUP 2: Laborers, topside, bottom men (when heading is 50

ft. from shaft) and all other laborers

GROUP 3: Brakeman; trackman; tunnel laborers; shaft laborers

GROUP 4: Miner; cage tender; bellman

GROUP 5: Hazardous Waste work within the ""HOT"" zone. (A premium of two dollars $2.00 per hour over the basic wage rate)

FOOTNOTE FOR LABORERS:

A. PAID HOLIDAYS: New Year's Day, Washington's Birthday, Patriot's Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, and Christmas Day

LABO1421-003 06/01/2018

Rates Fringes

Laborers:

Group 1.....................$ 38.15 24.10 Group 2.....................$ 38.90 24.10 Group 3.....................$ 39.15 24.10 Group 4.....................$ 34.15 24.10 Group 5.....................$ 37.25 24.10 Group 6.....................$ 38.15 24.10

Group 1: Adzeman, Wrecking Laborer.

Group 2: Burners, Jackhammers.

Group 3: Small Backhoes, Loaders on tracks, Bobcat Type Loaders, Hydraulic ""Brock"" Type Hammer Operators, Concrete Cutting Saws.

Group 4: Yardman (Salvage Yard Only).

Group 5: Yardman, Burners, Sawyers.

Group 6: Asbestos, Lead Paint, Toxic and Hazardous Waste.

PAIN0035-006 07/01/2019

PAINTER

NEW CONSTRUCTION:

Bridge.....................$ 50.66 30.90 Brush, Taper...............$ 39.86 30.25 Spray, Sandblast...........$ 41.26 30.25

REPAINT

Bridge.....................$ 50.66 30.90 Brush, Taper...............$ 37.92 30.25 Spray, Sandblast...........$ 39.32 30.25

PAIN0035-021 01/01/2019

Rates Fringes

GLAZIER..........................$ 39.86 30.25

PLUM0004-002 03/01/2021

WORCESTER (Except Hopedale and Southboro)

Rates Fringes

Plumbers and Pipefitters.........$ 47.85 26.92

PLUM0012-002 03/01/2019

WORCESTER (Hopedale and Southboro)

Rates Fringes

PLUMBER..........................$ 56.69 29.93

ROOF0033-001 02/01/2021

Rates Fringes

Roofers:

All Tear-off and/or removal of any types of roofing and all spudding, sweeping, vacuuming and/or cleanup of any and all areas of any type where a roof is to be relaid........$ 46.60 29.33

SFMA0669-002 04/01/2021

Rates Fringes

SPRINKLER FITTER.................$ 43.14 27.48

SHEE0017-004 08/01/2020

WORCESTER (Harvard, Lancaster)

Sheet metal worker...............$ 50.67 41.84

SHEE0063-002 01/01/2020

WORCESTER (Except Harvard & Lancaster)

Rates Fringes

Sheet metal worker...............$ 35.49 31.04

TEAM0379-003 08/01/2020

Rates Fringes

Truck drivers:

Group 1.....................$ 34.98 26.6325+A+B Group 2.....................$ 35.15 26.6325+A+B Group 3.....................$ 35.22 26.6325+A+B Group 4.....................$ 35.34 26.6325+A+B Group 5.....................$ 35.44 26.6325+A+B Group 6.....................$ 35.73 26.6325+A+B Group 7.....................$ 36.02 26.6325+A+B

TRUCK DRIVERS CLASSIFICATIONS

Group 1: Station wagons; panel trucks; and pickup trucks

Group 2: Two axle equipment; & forklift operator

Group 3: Three axle equipment and tireman

Group 4: Four and Five Axle equipment

Group 5: Specialized earth moving equipment under 35 tons other than conventional type trucks; low bed; vachual;

mechanics, paving restoration equipment

Group 6: Specialized earth moving equipment over 35 tons

Group 7: Trailers for earth moving equipment (double hookup)

POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK

(UNDERGROUND ONLY) $.40 DIFFERENTIAN BY AXLE HAZARDOUS

MATERIALS (In Hot Zone Only) $2.00 premium

FOOTNOTES: A. PAID HOLIDAYS: New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Patriot's Day, Columbus Day, Veteran's Day, Thanksgiving Day, & Christmas Day

B. PAID VACATION: Employees with 4 months to 1 year of service receive 1/2 day's pay per month; 1 week vacation for 1 - 5 years of service; 2 weeks vacation for 5 - 10 years of service; and 3 weeks vacation for more than 10 years of service

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

(End of Summary of Changes)

Devens MPMGR 015314

SECTION 00 80 00.00 0 6

SPECIAL PROVISIONS

02/20

AMENDMENT 0001

PART 1 GENERAL

Attachments to this specification are as follows:

Construction Project Sign Details Project Submittal Register

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C1153 (2010 R15) Standard Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-600-01 (2016; with Change 2, 2018) Fire Protection Engineering for Facilities

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations

U.S. ARMY (DA)

AR 530-1 Operation Security

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

ER 415-1-15 Construction Time Extensions for Weather

ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.59 Hazard Communication

1.2 SUBMITTALS

Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for information

DOCUMENT 00 80 00.00 06 Page 1 only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with LRL Section 01 33 00.00 06

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Labor, Equipment, and Material Report; G

Daily Equipment Report; G

Radioactive Material/Equipment; G

SD-04 Samples

Equipment Warranty Identification Tags; G

SD-05 Design Data

SF1413 Statement and Acknowledgement

Local Agency Check

Progress Photographs

SD-07 Certificates

Warranty of Construction

NO ASBESTOS - CONTAINING MATERIAL (ACM) CERTIFICATION

Sales and Use Tax

SD-11 Closeout Submittals

Preliminary (Working) As-Built Drawings; G

Final As-Built Drawings; G

CAD Working As-Built Drawings; G

Contour Map; G

Equipment-in-Place List

Maintenance and Parts Data

Warranty Management Plan; G

1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

Refer to FAR 52.211-12 "LIQUIDATED DAMAGES" in Section 00 70 00 for the amount of Liquidated Damages for the project.

Refer to FAR 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 00 for a notification of significant contract dates.

DOCUMENT 00 80 00.00 06 Page 2

1.3.1 Additional Requirements/Clarifications of Work Included Within the Contract

a. The time stated in FAR 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 00 for completion shall include installation of Government-furnished furniture as well as as-built drawings, O&M manuals, operational tests/reports/training/instructions, equipment lists.

b. If the Contractor fails to meet the requirements in paragraph "Requirements for Completion of Designated Areas Prior to Furniture Installation", by the Contractor's accepted scheduled Furniture Installation Start Date,the Contractor shall pay liquidated damages to the Government in the amount of $1,455 for each week of the delay until the requirement is fulfilled. The liquidated damages contained in this paragraph are independent of and in addition to those references in FAR 52.211-12 "Liquidated Damages - Construction".

Changes to the Contractor's Scheduled Furniture Installation Start Date and Construction Completion Date must be received and accepted no later than forty-nine (49) calendar days prior to the Contractor's current Scheduled Furniture Installation Start Date in order to avoid liquidated damages associated with the furniture installation.

Commencement of furniture installation on or after the Contractor's scheduled Furniture Installation Start Date prior to the fulfillment of these requirements does not relieve the Contractor of their liquidated damages obligation.

Amendment 0001***********************************************************

c. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB

DOCUMENT 00 80 00.00 06 Page 3 are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training.

The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

DOCUMENT 00 80 00.00 06 Page 4

************************************************************Amendment 0001

1.3.2 Requirements for Completion of Designated Areas Prior to Furniture Installation

a. The Contractor is responsible for access to the building, security and ownership during the furniture and IT/Telecom equipment installation.

Facility operation and maintenance during the furniture and IT/Telecom equipment installation is the responsibility of the Contractor.

b. The Government will be installing IT/Telecom equipment, including the telephone switch and individual telephone sets, during the furniture installation period.

c. The Contractor shall be responsible for coordination with its subcontractors and the Government furniture and IT/Telecom installation contractors, as necessary, to accommodate the furniture and IT/Telecom equipment installation.

d. The exterior roads, parking areas, walks, and building entrances shall be sufficiently complete to support the delivery of furniture products by semi-tractor trailers and made available for use to the Government furniture and IT/Telecom installation contractors.

e. All interior building finishes of areas receiving furniture, including all furniture entries, pathways, staging, and storage areas shall be complete. Completed building finishes shall include all flooring materials and base, interior walls, ceilings, lighting, HVAC systems and controls, doors, doorframes, and trim. All areas are to be cleaned, vacuumed, and an initial waxing applied as appropriate for the installation of furniture.

f. All utilities and systems serving the building shall be fully operational. The HVAC system(s) must be in operation, fully balanced and commissioned. The elevator(s) shall be operable and certified for use by the approving agency prior to the delivery of the furniture package and must be made available, at no additional cost, for use by the furniture and IT/Telecom equipment installation contractors.

g. The pre-final building punch inspections shall be performed and punch list items corrected by the Contractor prior to the Government Furniture and IT/Telecom installations.

h. During installation of the furniture and IT/Telecom, the Contractor shall participate in inspections as noted above in paragraph "Additional Requirements/Clarifications of Work Included Within the Contract"(b). Repairs to any damaged areas shall be performed at no additional cost to the Government by the appropriate party as determined by the Government during these inspections.

i. The Contractor shall be responsible for the electrical hookup of the power feed(s) and phone/data wiring to-as well as providing all data/com faceplates and jacks for-all powered modular systems furniture. This work may be coordinated with the Government Furniture and IT/Telecom installation contractors to occur while they continue their installations.

j. The Contractor shall perform the final buffing and waxing of areas after the furniture and IT/Telecom installation contractors have

DOCUMENT 00 80 00.00 06 Page 5 indicated either installation in those areas is complete or that the final buffing and waxing should be performed in certain areas prior to the placement of furniture. The final buffing and waxing of corridors shall be performed by the Contractor after the furniture and IT/Telecom installation contractors have indicated installation is complete for the building.

k. After furniture and IT/Telecom installation by the Government, the Contractor shall perform a complete final cleaning in all impacted areas. Final Inspection and Acceptance may occur only after all furniture and IT/Telecom installation by the Government is complete.

1.4 NOT USED

1.5 NOT USED

1.6 CONTRACT DRAWINGS AND SPECIFICATIONS

In addition to DFARS 252.236-7001 "Contract Drawings and Specifications" in Section 00 70 00 the following will apply:

a. After Award or no later than Notice to Proceed (NTP), the Government will furnish the Contractor a compact disk containing all technical contract documents in electronic media only. This disk will include a complete set of drawing files and technical specification files which have all amendments included. The disk will contain drawing files in PDF format along with technical specifications in PDF format. These PDF files are the contract documents that represent the construction requirements of the contract, and are being provided for the Contractor's use in printing paper copies of contract documents.

b. In addition, native CAD files(this includes, but not limited to, all source files, models, custom fonts and linestyles, plot files, and images used to create the contract drawings) are provided in accordance with the "AS-BUILT DOCUMENTS" paragraph for the Contractor's use in maintaining and preparing as-built plans. If another CAD Program is used other than the Using Agency's System, all native CAD files that were generated with that software and all support files will also be included. Only native files are to be used for As-Built preparation and information.

c. Native files are to be used for As-Built preparation only. The PDF files are the contract documents that represent the construction requirements of the contract.

1.7 AS-BUILT DOCUMENTS FOR DESIGN BID BUILD PROJECTS

1.7.1 General

This section covers the completion of final as-built drawings, as a requirement of the contract. The Contractor is responsible for maintaining paper copy working as-built drawings during the construction phase. These paper copy drawings will be used by the Contractor to prepare, maintain and submit the final as-built drawings

1.7.1.1 As-Built Drawings

An as-built drawing is a contract construction drawing revised to reflect the final as-built conditions of the project because of modifications, DOCUMENT 00 80 00.00 06 Page 6 changes, corrections to the project design required during construction, submittals and extensions of design. The terms "drawings," "contract drawings," "drawing files," "working as-built drawings" and "final as-built drawings" refer to contract drawings that are revised to be used for the "RECORD DRAWING AS-BUILTS".

1.7.1.2 Government-Furnished Files

a. The Contractor will be provided electronic files at the beginning of construction for use during the construction phase which are to…