W912QR20Q0040.pdf

PDF 2 MB Posted

Attached to
W912QR21Q0040 - Carr Creek Herbicide Application
Solicitation number
W912QR21Q0040
Issued by

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W912QR21Q0040 22-Mar-2021

b. TELEPHONE NUMBER

502.315.6172

8. OFFER DUE DATE/LOCAL TIME

11:00 AM 05 Apr 2021

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912QR9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

ADYSON MEDLEY

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

W22W9K10565134

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESS

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

502.315.6195 OR 6193FAX:

TEL: 502.315.6172 SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$8,000,000

NAICS:

561730

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

X

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF64

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W912QR21Q0040

Section SF 1449 - CONTINUATION SHEET

SPECIAL INSTRUCTIONS

This Request for Quote (RFQ) is for the contractor to furnish all materials, supplies, tools, parts, equipment, transportation, labor, supervision, communication, and quality control to complete the work listed below, at the areas specified, at Carr Creek Lake, located in Knott County, Kentucky.

Location:

United States Corps of Engineers Carr Creek Lake 843 Sassafras Creek Road Sassafras, KY 41758

This procurement is 100% set-aside for Small Business, NAICS 561730 (Size Determination $8,000,000).

Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.

Note: The contract award will be based on Lowest Price. One firm-fixed price services contract will be made from this RFQ. In addition to the completed price breakout schedule/quote, the Offeror must complete and submit the Representations and Certifications located within the solicitation.

Quotes are due on 05 April 2021 at 11:00 am Eastern Time. Email submissions will be accepted. Please submit quotes to adyson.medley@usace.army.mil. Fax submittals will not be accepted.

Contractor must fill out Representations and Certifications (Reps and Certs) section and submit along with RFQ.

All contractors must be registered in the System for Award Management (www.SAM.gov) prior to sumbitting a quote. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier (formerly DUNS number) for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov.

Refer to www.SAM.gov for information formerly found in CCR, EPLS, ORCA and FedReg.

Please begin the registration process immediately in order to avoid delay of the contract award should your firm be selected. SAM Registrations must be active at the time quotes are submitted in accorance with 52.204-7.

ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.

Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) within 30 days of activation or the vendor risks no longer being active in SAM.

Vendors can check whether an account is active by performing a query by their CAGE or Unique Entity Identifier (known as DUNS). The new registration process may now take several weeks, so vendors are highly encouraged to begin registering as soon as possible to avoid any possible delays in future contract awards. Remember, there is no cost to use SAM.

To find out additional information about the changes of the SAM registration process, contractors should visit the Frequently Asked Questions (FAQ) link located at the top of the SAM homepage (www.sam.gov).

PLEASE NOTE: SAM is completely free of charge for both registrants and users.

Note: Page numbering in this document may not be accurate.

PRICE BREAKOUT SCHEDULE

Jesse Saylor is the local Point of Contact (POC), Technical Representative at Carr Creek Lake, for the contract.

Jesse.B.Saylor@usace.army.mil

(606) 642-3308

Item No.

Description Quantity Unit Price Total

0001 BASE: Apply Herbicide at Shingle Branch 2 Job $_______ $ ______

TOTAL BASE $ ______

0002 OPTION 1: Apply Herbicide at Damsite Right Abutment 2 Job $______ $ ______

OPTION 2: Apply Herbicide at Defeated Creek Sediment Dam 2 Job $______

0004 OPTION 3: Apply Herbicide at Littcarr Sediment Dam 2 Job $______ $______

0005 OPTION 4: Apply Herbicide at Marina 2 Job $______ $______

0006 OPTION 5: Apply Herbicide at Smith’s Branch 2 Job $______ $______

0007 OPTION 6: Apply Herbicide at Deerlick Branch 2 Job $______ $______

0008 OPTION 7: Apply Herbicide at Littcarr 2 Job $______ $______

TOTAL OPTIONS

TOTAL BASE + ALL OPTIONS

REPS & CERTS

COMPANY NAME AND ADDRESS: __________________________________________

PHONE NUMBER _____________________ FAX NUMBER _____________________

EMAIL ADDRESS ________________________________________________________

BUSINESS SIZE (select one) Large Business _____ Small Business_____ HUBZone Business_____ 8A _____ Woman-Owned ____ Service-Disabled Veteran-Owned ____ Contractor is registered with SAM: _____ YES _____ NO (See FAR 52.204-7)

TAX ID # ______________________

INDICATE Unique Entity Identifier (previously DUNS NUMBER) ___________________ (This is 9 digit numeric code) CAGE NO. _________ (Note: See Unique Entity Identifier (FAR 52.204-7)

SCOPE OF WORK

Dated 22 February 2021 Herbicide Application

U.S. Army Corps of Engineers Carr Creek Lake

843 Sassafras Creek Road, Sassafras, KY 41758 606-642-3308

TP-1.1 GENERAL:

a. Description. The contractor shall furnish all materials, supplies, tools, parts, equipment, transportation, labor, supervision, communication, and quality control to complete the work listed below, at the areas specified, at Carr Creek Lake, located in Knott County, Kentucky.

b. Work shall be provided in accordance with all Terms, Conditions, General, Specific and Technical Provision, Exhibits, Attachments, Drawings, etc. contained herein or incorporated by Reference. All distances and measurements given are approximate. Each bidding contractor is urged to visit the job site to assess quantities, critical dimensions, and work conditions. All work will be done according to standard industry practices. Access to the work area is controlled and appointments to look at the site shall be coordinated with the Project Manager. This includes all mandatory provisions of the Federal Acquisition Regulation (FAR), whether referenced or not, current at time of award.

c. Contractor Responsibility. Contractor’s work and responsibility shall include, but are not limited to supply of equipment/materials, all planning, programming, administration, management, supervision, and inspection required to assure all equipment/materials are acquired and services are conducted in accordance with the contract and all applicable laws, regulations, or directives. The Contractor shall insure all work meets or exceeds specifications. The prime Contractor shall be responsible for ensuring all subcontractors comply with the provisions of this contract.

d. Performance Required: Special consideration of the Contractor is directed to the fact that the required accuracy, thoroughness, safety, and progress of this work are essential to the intended purpose. The contractor must be cognizant of the difficulties involved and of the contingencies which may arise, and must make certain that their personnel, equipment, transportation facilities and supply of materials are adequate at all times to ensure complete compliance with all provisions of these specifications. The work shall be done under professional supervision by competent employees. All contract services shall be in accordance with the submitted documents, and any additions, revisions or deletions must be approved by the Contracting Officer or his/her authorized representative.

e. Completion of Work: Completion of work shall include acceptable performance of all aspects of this contract.

f. Conditions:

1. Pre-Work Conference: The contractor will be required to attend a pre-work conference, scheduled at least one week prior to beginning work, where the Contractors plan of work, safety plan, security plan, start-up date, and other items included in this contract will be briefly discussed. The contractor will also be required to supply the necessary proof of liability insurance (copy of insurance forms) at that time. In addition, a copy of the MSDS sheets will be given to the government at this time and reviewed to ensure contractor compliance. This area is a secure area and the contractor will need to supply the government with a list of contractor personnel that will be working on-site.

2. Damages: The contractor shall be responsible for all damages to government or private property during the course of this contract. The contractor shall have appropriate insurance to cover liability and damages.

3. Hours and Days of Work: Work may be conducted at Carr Creek Lake between the hours of 7:00 a.m. and 4:30 p.m. EST, Monday through Friday. No work shall be performed outside of these times, or on Saturday or Sunday or on Federal Holidays, unless approved by the Technical Representative at Carr Creek Lake.

January 1 - New Year’s Day

January 18 - Birthday of Martin Luther King, Jr.

January 20 - Inauguration Day

February 15 - Washington’s Birthday

May 31 - Memorial Day

July 4 - Independence Day

September 6 - Labor Day

October 11 - Columbus Day

November 11 - Veterans Day

November 25 - Thanksgiving Day

December 25 - Christmas Day

4. Payment Procedure/Additional Work. At no time should the contractor do additional work without prior authorization of the Contracting Officer, and no work shall be performed that will cause the Contractor to exceed the contract price. Work performed without a binding contract document authorizing such work shall result in the Contractor not being paid for that work performed. During the course of the contract, any additional work determined to be needed may be requested by the Park Manager to the Contracting Officer for a Contract Modification.

5. Contract Start and Completion Dates: Work under this contract shall begin no later than 30 calendar days after the award being issued and must be completed NLT 60 calendar days later.

Additional time may be granted for inclement weather, when coordinated with and approved by the Park Manager. This includes delay of work that may occur during excessive rainfall or wet periods.

6. Wage Rates: Department of Labor wage rates apply to this work and are included. The contractor, if requested, is required to provide payroll documents for all work performed under this contract.

7. The Contractor shall, at all times prior to delivery, take care to protect and preserve all materials, supplies, and equipment of every description (including material and property which may be Government owned) and all work performed. All reasonable requests of the Technical Representative or his/her authorized representative to enclose or specially protect such property shall be complied with. If so determined by the Technical Representative, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payment due to them.

8. The contractor shall become familiar with all details of the work, verify and be responsible for all critical measurements, dimensions in field, and shall advise the TECHNICAL REPRESENTATIVE of any discrepancy prior to performing work.

9. The Contractor will notify the Contracting Officer or his/her authorized representative, upon commencement of work activities, and difficulties, interruption, or suspension of work, and when the required work has been completed. The Contractor shall update the Contracting Officer, or their authorized representative, no less than once weekly on status of work being done.

TP-1.2 CONTRACTOR SUBMITTAL: Unless otherwise specified, the Contractor shall submit the following information to the TECHNICAL REPRESENTATIVE prior to the pre-work conference for this contract:

a. Safety Plans. The Contractor shall submit, for acceptance by the TECHNICAL REPRESENTATIVE, an accident prevention plan and Activity Hazard Analysis (AHA) in accordance with the requirements of the Corps of Engineer’s Safety and Health Requirements Manual, EM385-1-1, hereinafter referred to as the Safety Manual, current at the time of award.

b. Certification of Employees Qualified to Administer First Aid and CPR. The Contractor shall submit proof the appropriate number of employees, as required in the Safety Manual, are certified to administer First Aid and CPR.

TP-1.3 SAFETY:

a. General Safety. The Contractor shall comply with the safety standards contained in Corps of Engineers Manual, EM 385-1-1, “Safety and Health Requirements Manual”, current at the time of award, as well as all current provisions of the Occupational Safety and Health Act (OSHA).

b. Safety Manual Requirements. The Contractor and employees shall comply with all pertinent sections of the Corps of Engineer’s Safety and Health Requirements Manual, EM 385-1-1, current at the time of award, and any subsequent revisions. This manual will be available on the Internet at:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

The Contractor’s safety plan must be submitted in writing and can be turned in at the same time as the pre-work conference.

c. Personal Protective Apparel and Equipment. Protective apparel and equipment, as identified in the AHA, shall be provided to eliminate or minimize hazards to personnel. As a minimum, each employee shall wear a sleeved shirt, long trousers and safety-toe shoes or boots during all contract work. Hard hats, face shields, safety glasses with side-shields, or goggles, and hearing protection shall be worn by employees when required by safety manual. Fire extinguisher(s) and first aid kit(s) meeting the Safety Manual standards shall also be provided and easily accessible to all employees.

d. Contractor Employees Certified in First Aid & CPR. The Contractor shall schedule employees so the appropriate numbers of certified personnel are on duty to administer First Aid and CPR as required by the Safety Manual. Copies of their certification shall be provided before work begins under this contract.

TP-1.4 ACCIDENT REPORTING. The Contractor shall maintain accurate accident records and report accidents as prescribed by the TECHNICAL REPRESENTATIVE. Accidents shall be reported within 24 hours of occurrence, and all serious accidents (those resulting in death or injury requiring medical attention or lost time) shall be reported immediately.

TP- 1.5 DAMAGE REPORTS. In all instances where Government property, equipment, natural features, landscape, or trees are damaged by contract employees, an immediate notification shall be made to the TECHNICAL REPRESENTATIVE. A full report of the incident and extent of such damage shall be submitted to the TECHNICAL REPRESENTATIVE within two working days of occurrence, excluding weekends and holidays.

TP-1.6 CONTRACT EMPLOYEES. All contract employees shall conduct themselves in a proper and courteous manner at all times. Contract employees shall comply with all provisions of Title 36, Chapter III, Part 327, CFR and obey all posted signs and regulations in the performance of the work under this contract. Being under the influence of or consuming alcoholic beverages or controlled substances by the Contractor or employees while on duty is prohibited.

TP- 2.1 SPECIAL REQUIREMENTS:

a. Security:

1. Access and General Protection/Security Policy and Procedures. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

2. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the TECHNICAL REPRESENTATIVE NLT 5 calendar days after the completion of the training.

3. Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the TECHNICAL REPRESENTATIVE no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

b. Unique Entity Identifier Number and SAM Registration: Contractors will be required to register in the SAM (System of Award Management) in order to be awarded the contract. Please visit https://www.sam.gov/ for government information or to register. For assistance in registering on the SAM and other required web sites visit: http://www.aptac-us.org/new. (NOTE: Pay careful attention when typing in the SAM website address on your browser). In order to register with SAM, you must have a Unique Entity Identifier number. If you are unsure of your Unique Entity Identifier number, or have questions regarding this, you can call 1-800-333-0505 for assistance.

c. Failure to provide all information requested on the quote sheet and to complete SAM registration may be grounds for considering the quote unresponsive.

d. Special Considerations:

TP-3.1 GENERAL SPECIFICATIONS:

CLIN 0001 (Base): Apply Herbicide at Shingle Branch

The work will consist of the following methods as specified herein:

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in accordance with the manufactures recommended application rate.

2. All herbicide treatment rates, mixtures, and timing will be per manufacturer’s recommendation to ensure maximum efficiency of the kill rate.

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with a second treatment. Hand operated pump sprayers or a tank mounted sprayer on a vehicle may be used when spraying.

To minimize the need for retreatment:

Foliar herbicide application should not occur when rain is anticipated within four hours of treatment site

4. All work done will be within the vicinity of water will be accomplished with the following special considerations to minimize contamination: Use an Aquatic safe herbicide OR adhere to the following bulleted restrictions.

Herbicide shall not be applied to surface waters.

Herbicide shall not be applied near water in a manner that will allow seepage of herbicide into the water.

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, is not permissible in the recreation areas, near open water, or close to wells. Empty herbicide containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material. Containers shall not be stored for disposal at a later date. The water source should be from a domestic supply so as not to reduce the efficacy of the herbicide.

6. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment should begin after 15 May and be completed by 30 May and the second treatment should begin after 01 September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment.

After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 20 September for payment.

CLIN 0002 (Option 1): Apply Herbicide at Damsite Right Abutment

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in accordance with the manufactures recommended application rate.

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with a second treatment. Hand operated pump sprayers or a tank mounted sprayer on a vehicle may be used when spraying.

4. All work done will be within the vicinity of water will be accomplished with the following special considerations to minimize contamination: Use an Aquatic safe herbicide OR adhere to the following bulleted restrictions.

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, is not permissible in the recreation areas, near open water, or close to wells. Empty herbicide containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material.

Containers shall not be stored for disposal at a later date. The water source should be from a domestic supply so as not to reduce the efficacy of the herbicide.

6. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment should begin after 15 May and be completed by 30 May and the second treatment should begin after 01 September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment. After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 20 September for payment.

CLIN 0003 (Option 2): Apply Herbicide at Defeated Creek Sediment Dam

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with

4. All work done will be within the vicinity of water will be accomplished with the following special

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material. Containers shall not be

6. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment

September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment.

After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project

CLIN 0004 (Option 3): Apply Herbicide at Littcarr Sediment Dam

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in accordance with the manufactures recommended application rate.

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with

4. All work done will be within the vicinity of water will be accomplished with the following special

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material. Containers shall not be

6. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment

September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment.

After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project

CLIN 0005 (Option 4): Apply Herbicide at Marina

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with

4. All work done will be within the vicinity of water will be accomplished with the following special

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material. Containers shall not be

6. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment

September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment.

After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project

CLIN 0006 (Option 5): Apply Herbicide at the Smith’s Branch

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with

4. All work done will be within the vicinity of water will be accomplished with the following special

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material. Containers shall not be

6. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment

September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment.

After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project

CLIN 0007 (Option 6): Apply Herbicide at Deerlick Branch

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with

4. All work done will be within the vicinity of water will be accomplished with the following special

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material. Containers shall not be

6. Access to this site must occur via boat as its location is across lake from Ky. Hwy 160. All applicable safety gear such as life jackets must be worn while accessing the work site.

7. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment

September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment.

After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project

CLIN 0008 (Option 7): Apply Herbicide at Littcarr

1. Techniques used for treatment will be done as specified below. Herbicide application rates will be in

3. There must be a 100% kill rate at target areas. Failure to meet the kill rate will require follow up with

4. All work done will be within the vicinity of water will be accomplished with the following special

5. Mixing and Container Disposal: Mixing as well as cleaning of equipment and, cleaning of clothing, containers shall be disposed of at landfill on the same or next day after use and containers most be disposed of at a landfill authorized to dispose of this type of waste material. Containers shall not be

6. Access to this site must occur via boat as its location is across lake from Ky. Hwy 160. All applicable safety gear such as life jackets must be worn while accessing the work site.

7. Two herbicide treatments will be required to satisfy the terms of this contract. The first treatment

September and be completed no later than 15 September. After completion of the first spraying, an invoice should be delivered to the Carr Creek Lake project office no later than 05 June for payment.

After completion of the second spraying, an invoice should be delivered to the Carr Creek Lake project

TP 3.2 GOVERNMENT INSPECTION: The method of government surveillance used will be Planned Sampling or 100% inspection. Surveillance by planned sampling is designed to inspect some part, but not all of the contract services requirements being monitored. Surveillance by 100% inspection requires that every occurrence of a performed service be monitored. Contract requirements using these evaluations are generally those that occur infrequently, or are essential, or are costly to perform, or at the Government's discretion. These results are then compared to the specific performance standards. When an area of vegetation removal and spraying is finished, the contractor will ensure that all logs and work records for that section have been completed before the Technical Representative is notified to perform the Quality Assurance (QA) Inspection. The contractor will not move into another section to perform contract services until the Technical Representative has instructed them to do so.

Typically, this will require completion of the QA inspection of the area and acceptance of the work. However, in some circumstances, the contractor may be allowed to begin work in subsequent areas with the understanding that they may be required to return to an area if work is not accepted by the government.

-End of Specifications-

BASE – Shingle Branch (approximately .6 acres)

Option 1 – Right Abutment of Dam (approximately .6 acres)

Option 2 – Defeated Creek Sediment Dam (approximately 1.15 acres)

Option 3 – Littcarr Sediment Dam (approximately .70 acres)

Option 4 – Marina (approximately .85 acres)

Option 5 – Smith’s Branch (approximately 2.5 acres)

Option 6 – Deerlick Branch (approximately 1 acre)

Option 7 – Littcarr (approximately .4 acres)

CLAUSES INCORPORATED BY REFERENCE

52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.209-6 Protecting the Government's Interest When Subcontracting

With Contractors Debarred, Suspended, or Proposed for Debarment

JUN 2020

52.212-1 Instructions to Offerors--Commercial Items JUN 2020 52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.217-5 Evaluation Of Options JUL 1990 52.219-6 (Dev) Notice of Total Small Business Set-Aside (DEVIATION

2020-O0008).

NOV 2020

52.222-3 Convict Labor JUN 2003 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-41 Service Contract Labor Standards AUG 2018 52.222-50 Combating Trafficking in Persons OCT 2020 52.222-55 Minimum Wages Under Executive Order 13658 NOV 2020 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

SEP 2013

52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-10 Waste Reduction Program MAY 2011 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

AUG 2018

52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving

JUN 2020

52.223-19 Compliance with Environmental Management Systems MAY 2011 52.223-20 Aerosols JUN 2016 52.223-21 Foams JUN 2016 52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

OCT 2018

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

DEC 2013

52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.237-1 Site Visit APR 1984 52.237-2 Protection Of Government Buildings, Equipment, And

Vegetation

APR 1984

52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

NOV 2011

252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

DEC 2019

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

JAN 2021

252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials

SEP 2014

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

252.232-7010 Levies on Contract Payments DEC 2006 252.237-7010 Prohibition on Interrogation of Detainees by Contractor

Personnel

JUN 2013

252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JAN 2021 252.247-7023 Transportation of Supplies by Sea FEB 2019

CLAUSES INCORPORATED BY FULL TEXT

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (AUG 2020)

(a) Definition. As used in this provision--

Commercial and Government Entity (CAGE) code means—

(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity by unique location; or

(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.

(b) The Offeror shall provide its CAGE code with its offer with its name and location address or otherwise include it prominently in its proposal. The CAGE code must be for that name and location address. Insert the word "CAGE" before the number. The CAGE code is required prior to award.

(c) CAGE codes may be obtained via--

(1) Registration in the System for Award Management (SAM) at www.sam.gov. If the Offeror is located in the United States or its outlying areas and does not already have a CAGE code assigned, the DLA Commercial and Government Entity (CAGE) Branch will assign a CAGE code as a part of the SAM registration process. SAM registrants located outside the United States and its outlying areas shall obtain a NCAGE code prior to registration in SAM (see paragraph (c)(3) of this provision).

(2) The DLA Commercial and Government Entity (CAGE) Branch. If registration in SAM is not required for the subject procurement, and the Offeror does not otherwise register in SAM, an Offeror located in the United States or its outlying areas may request that a CAGE code be assigned by submitting a request at https://cage.dla.mil.

(3) The appropriate country codification bureau. Entities located outside the United States and its outlying areas may obtain an NCAGE code by contacting the Codification Bureau in the foreign entity's country if that country is a member of NATO or a sponsored nation. NCAGE codes may be obtained from the NSPA at https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx if the foreign entity's country is not a member of NATO or a sponsored nation. Points of contact for codification bureaus, as well as additional information on obtaining NCAGE codes, are available at http://www.nato.int/structur/AC/135/main/links/contacts.htm.

(d) Additional guidance for establishing and maintaining CAGE codes is available at https://cage.dla.mil.

(e) When a CAGE code is required for the immediate owner and/or the highest-level owner by Federal Acquisition Regulation (FAR) 52.204-17 or 52.212-3(p), the Offeror shall obtain the respective CAGE code from that entity to supply the CAGE code to the Government.

(f) Do not delay submission of the offer pending receipt of a CAGE code.

(g) If the solicitation includes FAR clause 52.204-2, Security Requirements, a subcontractor requiring access to classified information under a contract shall be identified with a CAGE code on the DD Form 254. The Contractor shall require a subcontractor requiring access to classified information to provide its CAGE code with its name and location address or otherwise include it prominently in the proposal. Each location of subcontractor performance listed on the DD Form 254 is required to reflect a corresponding unique CAGE code for each listed location unless the work is being performed at a Government facility, in which case the agency location code shall be used. The CAGE code must be for that name and location address. Insert the word "CAGE" before the number. The CAGE code is required prior to award.

(End of Provision)

52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)

(a) Definitions. As used in this clause--

Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.

Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).

Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

Safeguarding means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

(End of clause)

52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO

SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020)

The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services-- Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Items. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.

(a) Definitions. As used in this provision-

Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition.

(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .