This is a Draft Project Solicitation for a Progressive Design-Build Other Transaction (OT) Agreement to repair and renovate the High Speed Test Track (HSTT) at Holloman Air Force Base, New Mexico.
The U.S. Army Corps of Engineers (USACE) Albuquerque District is seeking a qualified Design-Build Team to execute this project under the authority of Title 10 U.S.C. § 2808a. The total project funding is not-to-exceed $291,000,000, covering design, construction, and commissioning activities. The project scope includes repairs to the 15,536 linear meter rail system track, partial girder and track replacement, concrete girder repairs, roadway pavement work, utility replacements (power, communications, water), vehicle bridge replacement, and new relay towers. The facility must have at least 30,000 feet operational by 2030, and testing operations must continue during construction with minimal downtime. Delivery will follow a Progressive Design-Build model with Phase 1 consisting of design and pre-construction services, and Phase 2 consisting of final design and construction contingent upon successful negotiation of a Guaranteed Maximum Price within a fixed-price model, subject to Congressional authorization and funding availability. The Government reserves an off-ramp provision allowing discontinuation if a fair and reasonable price cannot be negotiated.
The competitive selection process consists of two steps: Step 1 requires White Paper submissions due December 1, 2026, evaluated on qualifications including bonding capacity (minimum $291M single project), corporate leadership strategy, execution strategy, past relevant experience (with at least one project involving heavy-duty continuous welded rail), and team composition. A target of three qualified teams will be invited to Step 2 Pitch Meetings (January 12-14, 2027) for final evaluation. The selected Design-Build Team will be issued post-selection Phase 1 Proposal Instructions to negotiate Phase 1 terms. Submissions must be made via PIEE (Procurement Integrated Enterprise Environment) and comply with strict formatting requirements including 12-page limitations. The Government anticipates award by end of FY2027. CMMC Level 2 cybersecurity compliance is required. Performance and Payment Bonds of at least $291,000,000 are mandatory. Small business participation is encouraged but not required.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT PROJECT SOLICITATION
Progressive Design-Build (PDB) Other Transaction (OT) for FY28 High Speed Test Track (HSTT), Holloman Air Force Base, Otero County, New Mexico (NM)
W912PP279A001
PROJECT SOLICITATION OVERVIEW INFORMATION
Federal Agency Name:
U.S. Army Corps of Engineers (USACE), Albuquerque District (SPA)
Project Title: High Speed Test Track
Announcement Type:
Initial Announcement and Request for White Papers
Project Solicitation Number:
W912PP279A001
Project Need:
The Air Force requires repairs to the High Speed Test Track and needs to reclaim ability to use entire length of the sled track. The work includes renovating supporting infrastructure (roads, water, electric, communications) to increase data collection capability (faster and larger data collection and distribution to support hypersonic testing) and to facilitate efficient test operations.
Project Location:
Holloman AFB, New Mexico (NM)
Authority for Award:
Title 10 U.S.C. § 2808a
Type of Instrument:
Other Transaction (OT) Agreement for Progressive Design-Build. Phase 1 will be for Design and Pre-Construction Services. Phase 2 may be added by modification(s) for final design and construction upon successful negotiation(s) of a Guaranteed Maximum Price (GMP) within a Fixed Price model subject to authorization, approvals, and availability of funds.
Delivery Model: Progressive Design-Build (PDB)
NAICS Code: 237990 (other heavy and civil construction)
PSC Code: Y1BZ – Construction of Other Airfield Structures
Total Project Funding:
Not-to-Exceed (NTE) $291,000,000.00
Anticipated Award:
Single OT award intended. The Government reserves the right to select, not select, or continue discussions with any Design-Build Team at any phase.
This announcement, including all stated attachments and any websites incorporated by reference, constitutes the entire solicitation and forms the basis for all content resulting in the OT.
Solicitation POCs:
Diana Keeran; Diana.M.Keeran@usace.army.mil Leslie Molina; Leslie.M.Molina@usace.army.mil
ANTICIPATED SCHEDULE
Note: This schedule is subject to change at the Government's discretion.
Milestone Dates/Time - All Times are Central
Time Zone (CT)
Special Notice Posting 27 October 2026 (actual)
Draft Project Solicitation and Attachments 13 November 2026
Industry Day (Virtual) 16 November 2026
Draft Project Solicitation and Attachment Comments Due:
19 November 2026
Request for White Papers 23 November 2026
White Papers Due 1 December 2026
Notifications and Request for Pitch Meetings On or around 8 December 2026
Site Visit by invite only 18 December 2026
Pitch Meetings 12-14 January 2027
Selection / Proposal / Negotiations 20 Jan – 21 Feb 2027
Agreement Award TBD, FY2027
The Government anticipates completing the competitive selection process and making an award within approximately four (4) months of release of the Request for White Papers.
Companies that are interested in proposing but unable to meet the approximate timeline may be removed from consideration for award.
Attachments:
Attachment 1 – Request for White Papers (Step 1) Attachment 2 – HSTT Requirement Overview and Anticipated Structural Requirements
(Step 1) *Attachment 3 – Current 65% design package (Step 2) *Attachment 4 – Invitation for Pitch Meeting (Step 2) (Final Competitive Evaluation
Step) (Provided to Design-Build Team(s) by Invitation only)
*Attachment 5 – Model OT Agreement Template **Attachment 6 – Post-Selection Phase 1 Proposal Instructions (Provided only to the selected Design-Builder after completion of the competitive selection process)
*NOTE 1: Attachments 3 through 5 will be provided at a future date, as appropriate, to Design- Build Team(s) selected to participate in Step 2.
**NOTE 2: Attachments 6 will be provided at a future date, as appropriate, to the Design-Build Team selected as the most advantageous to the Government.
1.0 PROJECT INFORMATION
1.1 The U.S. Army Corps of Engineers (USACE) Albuquerque District (SPA), on behalf of the Air Force Civil Engineering Center (AFCEC), is seeking to identify a Design-Build Team for repairs to the High Speed Test Track (HSTT), Holloman Air Force Base, New Mexico.
1.2 Project Goals:
Project Goal / Objective
Description / Key Focus Areas
Collaborative Project Development
Facilitate early and continuous collaboration between the design-builder, stakeholders, and the Government to jointly develop the project's design, cost, and schedule in a non-adversarial environment.
Innovation, Speed, and Flexibility
Leverage the OT framework outside traditional FAR constraints to emphasize speed, innovation (in materials, methods, and delivery), and optimal mission outcomes.
Qualifications- Based Selection
Prioritize the selection of a Design-Build Partner based on proven past performance, team merit, and technical approach rather than detailed construction price proposals at this initial stage.
Risk Management & Feasibility
Ensure the chosen team has a deep understanding of complex Military Construction (MILCON) requirements, coupled with proactive risk identification and mitigation strategies.
Integrated Team Execution
Establish a cohesive Progressive Design-Build (PDB) team structure (including Prime, Designer of Record, Key Subcontractors, and the Government) that demonstrates clear reporting lines, continuity, and collaborative execution capabilities.
1.3 The total project funding for this project, including design, construction, and commissioning activities, may not exceed $291M. This affordability cap is a material requirement. White Papers, Pitch Meeting responses, and the selected Design-Build Team’s post-selection Phase 1 Proposal must demonstrate a credible approach to developing and delivering the project within this affordability constraint. The Government will not require a competitive Phase 2 construction price, GMP within a fixed price model, at the time of initial selection.
1.4 The Government intends to utilize a Progressive Design-Build (PDB) project delivery method following Design-Build Institute of America (DBIA) best practices. This approach emphasizes early collaboration, qualifications-based selection, open-book pricing, and shared risk management between the Government and the Design-Build Team.
2.0 ACRONYMS AND DEFINITIONS
A/E (Architect-Engineer): The licensed professional, firm, or team responsible for the planning, design, and technical drawings/specifications for the facility.
CUI (Controlled Unclassified Information): Information that requires safeguarding or dissemination controls pursuant to and consistent with applicable law, regulations, and government-wide policies, but is not classified under Executive Order 13526 or the Atomic Energy Act, as amended.
FFP (Firm-Fixed-Price): A pricing structure where the price is not subject to any adjustment on the basis of the design-builder’s cost experience in performing the contract. This places maximum risk on the design-builder and provides full responsibility for all costs and resulting profit or loss.
GMP (Guaranteed Maximum Price): A pricing structure commonly used in Progressive Design-Build where the parties collaboratively develop the design, scope, and pricing prior to establishing a final construction price. Once negotiated and incorporated into the Agreement through a modification, the GMP functions as a Firm- Fixed-Price (FFP) commitment for the defined scope of work. The Design-Builder assumes the risk for completing the work within the negotiated GMP and is generally responsible for cost overruns, except for Government-directed changes, differing site conditions, or other authorized modifications that formally adjust the GMP.
HAFB HSTT (High Speed Test Track): The specific project facility, located at Holloman Air Force Base, New Mexico, where the Department performs rail-mounted ground-based testing at estimated speeds up to Mach 10.
Model OT Agreement Template: The Government’s baseline OT agreement template that will be provided as Attachment 4. The Model OT Agreement Template identifies anticipated terms and conditions for the resulting Phase 1 OT Agreement and future Phase 2 modification, as applicable. The final agreement will be completed after selection and negotiation with the selected Design-Builder.
Off-Ramp: Refers to a contractual mechanism that allows the Government to discontinue the Progressive Design-Build relationship if a fair and reasonable GMP or FFP for construction cannot be achieved. Upon off-ramp, the Government retains rights to the completed design to continue the project through another delivery method or design-builder.
Open Book: A transparent cost estimating methodology used during the Progressive Design-Build process where the Design Builder shares complete, detailed, and auditable cost information with the Government. This includes, but is not limited to, direct and indirect costs, subcontractor quotes, and fee structures, for the purpose of collaboratively validating and negotiating a final construction price.
OT (Other Transaction) Agreement: A legally binding instrument other than a standard contract, grant, or cooperative agreement. OTs are not subject to the Federal Acquisition Regulation (FAR) and provide significant flexibility in tailoring the procurement process and terms to the needs of a project.
PDB (Progressive Design-Build): A two-stage project delivery method where the owner selects a Design-Build team based on qualifications. The team then works collaboratively with the owner during "Phase 1" to develop the design and establish a price for "Phase 2" (final design and construction).
Post-Selection Phase 1 Proposal Instructions: The instructions issued only to the selected Design-Build Team after completion of the competitive selection process. These instructions identify the information required to support negotiation of the Phase 1 Design and Pre-Construction Services OT Agreement, which may include proposed scope, level of effort details, fee, schedule, assumptions, and related proposal information. This document is not a competitive Step 2 evaluation attachment.
SAM (System for Award Management): The official U.S. government website where all entities must be registered to do business with the federal government.
UEI (Unique Entity Identifier): The 12-character alphanumeric identifier assigned to all entities (public and private companies, individuals, institutions, or organizations) who register to do business with the federal government in the System for Award Management (SAM).
USACE (U.S. Army Corps of Engineers): The federal agency, acting as the engineering and construction agent for the Department of Defense, responsible for managing this solicitation and the resulting OT agreement.
3.0 THE OT PDB PROCESS
The OT PDB model is a collaborative project delivery approach in which the Government, designer, and constructor work together from the early stages of design to refine scope, reduce risk, and improve cost and schedule certainty. Under this OT, the process will be executed in two parts:
Phase 1: Design and Pre-Construction Services
Scope: The selected Design-Build team shall collaborate with the Government to advance the design, perform site investigations, validate and refine project requirements, and develop progressively more detailed cost and schedule information.
Design Advancement: This phase will begin at award with the initiation of the design and will continue through an agreed-upon design milestone to establish GMP under a fixed price model for construction.
Purpose: The purpose of Phase 1 is to de-risk the project, resolve key technical and scope issues, and align the parties on a common path forward before establishing the final construction price.
Open Book Costing: During Phase 1, the Design-Build Team shall develop a transparent, "Open Book" cost estimate, sharing subcontractor quotes, labor, equipment, material, and detailed pricing data to support cost reconciliation and scope validation with the Government to inform the final construction price. Develop construction cost estimates using the Micro Computer Aided Cost Estimating System (MCACES MII) with the embedded Work Breakdown Structure (WBS) Military Uniformat II. Develop any contingency in support of Cost and Schedule Risks using Oracle Crystal Ball Software.
Pricing & Negotiation: Upon completion of the agreed design milestone(s) in Phase 1, the Design-Build Team will submit a formal GMP proposal for Phase 2 based on the "Open Book" cost model. The Agreements Officer will lead a formal negotiation with the Design-Build Team to finalize a fair and reasonable price.
Award: If the parties successfully negotiate a fair and reasonable price, the Government may modify the Phase 1 OT to authorize the awardee to complete the Phase 2 final design and construction activities.
Phase 2: Full Design and Construction
Scope: Phase 2 consists of the completion of the final design and all physical construction activities required to deliver the fully functional facility.
The Off-Ramp: The Government is not obligated to award Phase 2. The OT includes an off-ramp provision allowing the Government, if unable to reach an agreement on a fair and reasonable price for Phase 2, a lack of sufficient funds, or any other reason determined (in its sole discretion), to use the completed design and associated project information to pursue another acquisition approach, including a competitive solicitation for final design completion and construction.
4.0 OT PROCESS
The Government will conduct a two-step qualifications-based competitive selection process to identify the most qualified Design-Build Team for this PDB project. The competitive selection process consists of Step 1, White Paper evaluation, and Step 2, Pitch Meeting evaluation. The Pitch Meeting will serve as the final competitive evaluation step.
Step 1: White Paper Submission and Evaluation
Interested Design-Build Teams shall submit a White Paper in accordance with Attachment 1.
The Government will evaluate White Papers to identify the most qualified Design-Build Teams to proceed to Step 2.
Step 2: Pitch Meeting Phase — By Invitation Only
A target of three of the most highly qualified Design-Build Teams from Step 1 will be invited to participate in a Pitch Meeting in accordance with Attachment 3. The Pitch Meeting will evaluate the Design-Build Team’s qualifications, project understanding, collaborative approach, communication, problem-solving capability, risk awareness, design-build management approach, and ability to serve as the Government’s long-term Design-Build Team.
The Government may select the most advantageous Design-Build Team based on the totality of the Step 1 White Paper and Step 2 Pitch Meeting evaluation.
Post-Selection Phase 1 Proposal and Negotiation
After completion of the competitive Qualifications Based Selection (QBS) process, the Government will issue Attachment 5 – Post-Selection Phase 1 Proposal Instructions only to the selected Design-Build Team. The selected Design-Build Team will submit a Phase 1 Proposal for Design and Pre-Construction Services.
The Phase 1 Proposal may include the proposed Phase 1 scope of services, staffing plan, labor categories, level of effort details, fee, schedule, assumptions, exclusions, and other direct costs and/or information necessary to support negotiation of the Phase 1 OT Agreement.
Attachment 4 – Model OT Agreement Template will serve as the baseline agreement template for negotiation and award of the Phase 1 OT Agreement.
Attachment 5 is not part of the competitive Step 2 evaluation and will not be issued to all shortlisted Design-Build Teams. It is a post-selection negotiation document used only with the Design-Build Team selected.
If the Government and selected Design-Build Team cannot reach agreement on fair and reasonable Phase 1 terms, the Government reserves the right to discontinue negotiations and take any action in the Government’s interest, including engaging another highly qualified Design-Build Team, revising the acquisition approach, or cancelling the solicitation.
Award
Phase 1 — Design and Pre-Construction Services: The selected Design-Build Team may be awarded an OT Agreement for Phase 1 after successful negotiation of fair and reasonable Phase 1 terms. No construction activities will be authorized under Phase 1.
Subject to the availability of funding, Phase 1 will be funded with appropriated funds for planning, design, and preconstruction services, as applicable.
Phase 2 —Design and Construction: Phase 2 may be added by modification to the OT Agreement upon successful negotiation of a fair and reasonable FFP or GMP at a future design milestone. Phase 2 is subject to statutory authorization, required approvals, availability of Military Construction funds on or around FY28, and the Government’s determination that progression to construction is in the Government’s interest.
5.0 SUBMISSION REQUIREMENTS
Step 1: White Paper
Design-Build Teams shall submit their White Paper in accordance with Attachment 1.
Compliance: The White Paper must address all requirements outlined in Attachment 1.
Incomplete submissions may be deemed non-conforming and disqualified from further consideration. Additionally, as discussed in Attachment 1, submissions that do not demonstrate the required bonding capacity will be disqualified from further consideration.
Step 2: Invitation for Pitch Meeting (By Invitation Only)
Invited Design-Build Teams shall participate in the Pitch Meeting in accordance with Attachment 3 (provided to the selected teams). The Pitch Meeting will serve as the final competitive evaluation step. The Government will evaluate the Design-Build Team’s qualifications, technical/project understanding and approach, collaborative approach, problem-solving capability, risk management and budget control, innovation and schedule optimization and ability to serve as the Government’s Design-Build Team.
The official requirements for the pitch meetings in Step 2 will be provided to the selected design-builders in Attachment 3 to this solicitation.
The Government intends to select the most qualified Design-Build Team based on the Step 1 White Paper and Step 2 Pitch Meeting evaluation.
Negotiations: Post-Selection Phase 1 Proposal
After selection, the Government will issue Attachment 5 – Post-Selection Phase 1 Proposal Instructions only to the selected Design-Build Team. The selected Design-Build Team’s Phase 1 Proposal will be used to support negotiation of the Phase 1 OT Agreement and may include the proposed design and preconstruction scope, staffing plan, labor categories, hourly rates, fee, schedule, assumptions, exclusions, and other information necessary to establish fair and reasonable Phase 1 terms.
The Post-Selection Phase 1 Proposal is not a separate competitive evaluation step and will not be issued to all shortlisted Design-Build Teams.
The Phase 1 Proposal will not establish the final Phase 2 construction price, FFP, or GMP. The Phase 1 proposal may include preliminary cost information, cost approach, labor rates, level of effort, fee, assumptions, and other information necessary to negotiate Phase 1 and support future open-book cost development. Any target construction price, FFP, or GMP for Phase 2 will be developed later during Phase 1 and negotiated at a future design milestone.
Attachment 4 provides the Model OT Agreement Template for informational and negotiation purposes. The final OT Agreement will be completed after selection and negotiation of Phase 1 terms with the selected Design-Build Team.
6.0 EVALUATION CRITERIA — STEP 1 AND STEP 2
Each company will be evaluated using a qualifications-based selection methodology. Please refer to Attachment 1 for the evaluation criteria.
Step 1 White Paper Evaluation and Step 2 Pitch Meeting Evaluation will both be considered for the final selection decision of the most advantageous Design-Build Team. Step 1 evaluates the Design-Build Team’s bonding, and written qualifications based on corporate leadership strategy, execution strategy, and team composition and organization as described in Attachment 1. Step 2 evaluates the Design-Build Team’s technical understanding, collaborative capability, communication, problem-solving ability, risk awareness, and ability to serve as the Government’s long-term Design-Build Team. The Government may select the most qualified Design-Build Team based on the totality of the Step 1 and Step 2 evaluations. No competitive price, Phase 2 construction price, FFP, GMP, Conceptual Design submission, or Scope of Services submission will be evaluated during the competitive selection process.
Within Step 1, the evaluation factors are: Corporate Leadership Strategy, Execution Strategy, Past Relevant Experience, and Team Composition and Organization. The Request for White Papers, Attachment 1, addresses the components of these factors and the evaluation of the qualifications.
Within Step 2, the Government will consider the Design-Build Team’s technical understanding, collaborative capability, communication, problem-solving ability, risk awareness, PDB management approach, and ability to support Phase 1 design development and open-book cost development.
Only the most qualified Design-Build Team(s) identified in Step 1 will be invited to proceed to Step 2. Each participant(s) will receive formal notification of their selection or non-selection.
Progressive Design-Build (PDB) evaluation process:
Strength is defined as a feature of the Design-Build Team’s submission that meaningfully increases the Government’s confidence in the Design-Build Team’s ability to successfully deliver the project. Strengths reflect aspects such as a clear and executable corporate strategy for successful partnering, demonstrated experience on heavy-duty continuously welded rail projects, strong team qualifications, effective collaboration strategies, and a well-thought-out plan for managing cost, schedule, constructability, and risk during preconstruction and execution.
Weakness is defined as a flaw or omission in the submission that reduces the Government’s confidence in the Design-Build Team’s ability to successfully perform under the agreement. Weaknesses may include lack of clarity in the proposed approach, insufficient detail in planning or execution strategies, limited or less relevant experience, unclear organizational structure or staffing approach, or gaps in understanding of project requirements or constraints.
Relevancy is defined as the level of connection between the Design-Build Team’s qualifications to the requirements of the HSTT Project. The more closely related, the higher the relevancy.
Risk is defined as a condition or aspect of the submission that introduces uncertainty regarding the Design-Build Team’s ability to meet cost, schedule, quality, or performance objectives. Unlike a Weakness, a Risk does not necessarily represent a deficiency but rather highlights an area where the outcome is uncertain and may require further clarification, mitigation, or management during the Progressive Design-Build preconstruction phase. Risks may arise from assumptions, interface challenges, sequencing approaches, or unresolved design and construction considerations that could affect project success if not properly addressed.
Evaluation Rating Scale
Outstanding The response demonstrates exceptional understanding, approach, and confidence of successful performance. Strengths significantly outweigh any weaknesses or risks.
Good The response demonstrates a strong understanding and approach.
Strengths outweigh weaknesses or risks, and the Progressive Design Build Team provides a high level of confidence.
Acceptable The response meets the Government’s requirements and provides an adequate level of confidence. Weaknesses or risks are not significant or are reasonably mitigated.
Marginal The response only partially meets the Government’s requirements.
Weaknesses or risks reduce confidence in successful performance.
Unacceptable The response fails to meet the Government’s requirements or contains significant deficiencies that create unacceptable risk.
7.0 COMMUNICATIONS AND SUBMISSION INSTRUCTIONS
Bidding Inquiry System: All questions regarding this Project Solicitation must be submitted through the ProjNet Suite Bidder Inquiry System at https://www.projnet.org/projnet.
o Solicitation Number: W912PP279A001 o Bidder Inquiry Key: U84MCF-UTG2SX o Inquiry Deadline: ProjNet will be closed to new inquiries on the date and time identified in the Anticipated Schedule.
o The Government will post answers to questions received. Companies are encouraged to monitor ProjNet for updates.
o The Step 2 Pitch Meeting inquiry process, if applicable, will be provided only to
Design-Build Teams invited to Step 2. Any post-selection Phase 1 Proposal questions will be handled directly with the selected Design-Build Team during post-selection negotiation.
White Paper Submission:
o Due Date: White Papers are due no later than the time and date specified in the overview schedule.
o Submission POCs: Diana Keeran (Diana.M.Keeran@usace.army.mil) and Leslie
Molina (Leslie.M.Molina@usace.army.mil) via PIEE Solicitation Module. The PIEE link to access the step-by-step instructions and other attachments are posted on SAM.gov. ONLY PIEE submissions will be accepted for required competitive submissions, unless otherwise instructed by the Government.
Step 2 Pitch Meeting logistics and any required materials will be provided to invited Design-Build Teams in Attachment 3. The post-selection Phase 1 Proposal process will be provided only to the selected Design-Builder in Attachment 5.
o File Formats: Only .pptx, .pdf, .doc, .docx, .xlsx, or .xls attachments are permitted. Files ending in .zip or .exe will not be accepted.
NOTE: Submissions that are generic, boilerplate, or fail to demonstrate project-specific understanding may be assessed with lower confidence. Greater consideration will be given to
Companies that demonstrate proven success in DB Processes, collaborative Progressive Design- Build (PDB) delivery, and experience with complex, secure, or mission-critical facilities.
8.0 SPECIAL CONSIDERATIONS
8.1 Governing Documents and Registration
This announcement, its stated attachments, and any websites incorporated by reference constitute the entire solicitation. In the event of a discrepancy between the announcement, the attachments, or the websites, this main solicitation announcement shall take precedence.
Prospective Design-Build Teams may submit responses to the Request for White Papers without being formally established in System for Award Management (SAM) or as a joint venture entity.
All Design-Build Teams must be registered in SAM at www.sam.gov and possess a valid Unique Entity Identifier (UEI) to be eligible for award. Progressive Design-Build Teams (PDBT) must also ensure that team members who currently possess security clearances applicable for a project of this nature are maintained. The selected Design-Build Team shall maintain an active SAM registration during contract performance and through final payment of the OT.
As of the time of publication of this solicitation, all proposal submissions are anticipated to be unclassified.
8.2 Cybersecurity Requirements
(a) Authority & Applicability: The Department of War (DoW) has established the Cybersecurity Maturity Model Certification (CMMC) project, as codified in 32 CFR Part 170, to ensure that entities handling government information implement appropriate cybersecurity standards. As a matter of DoW policy, the principles of the CMMC project are applicable to the OT resulting from this solicitation. Performance under the resulting Agreement will require the handling of Federal Contract Information (FCI).
(b) Required Level & Scope: The Government has determined that this project requires the implementation of cybersecurity practices equivalent to CMMC Level 2. The CMMC Level 2 requirements apply to all information systems owned or operated by the Design-Builder (and its subcontractors) that will process, store, or transmit CUI in the performance of the OT.
(c) Security Controls: At a minimum, the Design-Builder must implement the 110 cybersecurity controls that constitute CMMC Level 2. These controls focus on safeguarding information through access control, identification and authentication, media protection, physical protection, and system and information integrity. The final OT will list these specific controls.
(d) Self-Assessment and Attestation (Condition of Award): Prior to the award of the OT, the successful Design-Builder must conduct a self-assessment of their information systems against the CMMC Level 2 security controls. The Design-Build Team shall provide a signed attestation affirming that they have successfully implemented all CMMC Level 2 controls. A completed positive self-assessment and attestation are required to be eligible for the OT award. The Government may request additional information regarding the assessment at its discretion.
(e) Flow-Down to Subcontractors: The successful Design-Build Team will be responsible for ensuring that any subcontractor, teaming partner, or vendor handling CUI in support of this project also meets the CMMC Level 2 requirements.
8.3 Government-Provided Resources for Cybersecurity and Contracting
The U.S. Government provides several no-cost resources to assist businesses in navigating the federal marketplace and strengthening their cybersecurity posture. Design-Build Teams are encouraged to explore these projects.
APEX Accelerators (Government Contracting Assistance): APEX Accelerators (formerly PTAP) offer free, expert guidance to businesses seeking to enter or expand their work within the government sector. Their mission is to help build a strong U.S. supply chain through confidential, one-on-one coaching (e.g., SAM.gov registration, finding opportunities, proposal processes). Find your local APEX Accelerator:
https://www.apexaccelerators.us/#/
Project Spectrum (Cybersecurity Compliance Support): Project Spectrum is a DoD-funded, vendor-neutral initiative dedicated to helping businesses in the Defense Industrial Base (DIB) improve cybersecurity readiness. They provide tools, training, and individualized dashboards to help small and medium-sized businesses meet DoD requirements, including CMMC. Access resources: https://www.projectspectrum.io/#/
8.4 Project-Specific Terms and Conditions
(a) Congressional Authorization Limitation: Construction under any resulting OT is contingent upon statutory authorization and appropriation of funds. No construction activities shall be initiated unless and until the project is authorized in the National Defense Authorization Act (NDAA) and funded through applicable appropriations. Initial performance will be limited to planning and design activities (Phase 1), which may proceed using MILCON Design funds following Congressional notification. Transition to construction (Phase 2) is contingent upon satisfaction of these requirements. The Government is not obligated to proceed with construction, and performance of Phase 1 shall not be construed as a commitment to do so.
(b) Performance and Payment Bonds: The successful Design-Builder must demonstrate the capability to provide single project Performance and Payment Bonds of at least $291,000,000.
(c) Commitment to Small Business Participation: Small business participation is encouraged, but not required for award eligibility under 10 U.S.C. § 2808a. Design-Build Teams have full flexibility to structure their teams in a manner that best supports successful project performance.
If a Design-Build Team identifies a small business partner, the partner’s role should be clearly described and may be incorporated into the resulting Agreement, as applicable.
(d) Site Visit: Site visit information and logistics may be provided to Design-Build Teams invited to Step 2 Pitch Meetings or to the selected Design-Build Team during post-selection Phase 1 proposal development and negotiation, as determined by the Government. The Government reserves the right to control timing, access, attendance limitations, and security procedures for any site visit. USACE will not reimburse the Design-Build Team for costs associated with the Site Visit.
(e) PDB Approach — Step 1, Step 2, Post-Selection Phase 1 Proposal, and Phase 1 Performance: This requirement will be executed using a PDB model under OT pursuant to 10 U.S.C. § 2808a. The Government intends to establish a collaborative, integrated team environment where the selected Design-Build Team works closely with the Government to refine requirements, advance the design, validate scope, manage risk, and align cost and schedule within the established affordability constraints.
(f) INFORMATIONAL PURPOSES ONLY / REFERENCE ONLY
SPECS/DRAWS/REPORTS ATTACHMENTS:
TBD
INFORMATIONAL PURPOSES ONLY / REFERENCE ONLY:
TBD
9.0 WHITE PAPER CONTENT
Issuance of this solicitation is a Request for White Papers only, the required Attachment 1 – Request for White Paper (Step 1) is the only submission required to be submitted by the solicitation closing date stated in the posting.
***End of Section***
ATTACHMENT 1
STEP 1: Request for White Papers for Other Transaction (OT)
Progressive Design-Build (PDB) via Other Transaction (OT)
SECTION 1: OVERVIEW
The U.S. Army Corps of Engineers (USACE) is seeking qualified Design-Build Team(s) to participate in a PDB via OT agreement for the High Speed Test Track (HSTT) at Holloman AFB, NM. This request for white papers allows interested Design-Build Teams to submit qualification packages as the first step in a competitive, two-step selection process.
This acquisition emphasizes:
Qualifications-Based Selection: Design-Build Team(s) will be selected based on partnering approach, experience, capability, and teaming strategy, not a price proposal.
Collaborative Project Development: The selected Design-Build Team will work directly with USACE and Air Force partners to develop the project design and price.
Speed and Flexibility: The Government will evaluate White Papers based on the criteria identified in this announcement using a qualifications-based, collaborative evaluation process. The evaluation is intended to identify the Design-Build Team(s) best suited to partner with the Government to further develop the project scope, technical solution, and agreement terms during subsequent phases of the process.
SECTION 2: STEP 1 – WHITE PAPER SUBMISSION REQUIREMENTS
The Government reserves the right, at its sole discretion, to determine that a response which does not conform to the requirements or instructions contained in this announcement is ineligible for further consideration.
Design-Build Teams that submit White Papers determined to be the most advantageous to the Government, based on the evaluation criteria identified in this announcement, may be invited to participate in Step 2 – Pitch Meetings.
Interested parties should prepare their White Papers in a clear, concise, and organized manner that enables the Government to efficiently evaluate the proposed approach. To facilitate an efficient review, responses shall be prepared in accordance with the instructions and formatting requirements contained in this announcement. Failure to comply with these requirements may increase the risk that the response will not be considered for further evaluation.
a. White Papers will be evaluated using the criteria identified in this announcement. Only those responses determined to be the most advantageous to the Government may be invited to proceed to Step 2.
GENERAL SUBMISSION REQUIREMENTS
White Paper Submission, Page Limitations, and Format Requirements (MANDATORY):
The White Paper shall be submitted by the time and date as specified in the Solicitation. All submissions should be in Adobe PDF format with Optical Character Recognition (OCR) applied to all documents that will enable word searches to be conducted using Adobe-compatible PDF software.
Offers must be submitted electronically via Procurement Integrated Enterprise Environment (PIEE) Solicitation at https://piee.eb.mil/. Respondents must be registered in PIEE before they can submit a proposal.
The page limitation for the White Paper is 12-pages. Title Sheet, letter from the bonding company agent, formal teaming agreements, CPARS, and Past-Performance Questionnaires (PPQ) are not included in the page limitation and should not be numbered. A one-page cover sheet or title sheet is recommended identifying your firm’s name, the file’s title, and describing any applicable design-build team arrangements. Any extraneous information or cover letters that provide additional information about your firm that is not requested by this Request for White Papers will not be reviewed or evaluated.
All text shall be at least 10 pt. font and easily read (e.g., Arial, Times New Roman, or Calibri).
All text shall be typed and single-spaced. Each page shall be 8-1/2” x 11” (charts/graphics are the only documents that may be submitted on an 11” x 17”). Margins should be no less than 1” (right, left, top, and bottom).
Pages that exceed the page limitation will not be reviewed and the information contained on those pages will not be considered for evaluation.
Restriction on Disclosure and Use of Data:
Respondents that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall-
(1) Mark the title page with the following legend:
This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, an agreement is awarded to this respondent because of, or in connection with, the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting agreement. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend:
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
Instruction:
The Government reserves the right to not consider responses, in part or in full, that fail to adhere to the pro-forma criteria listed above at its sole discretion
REGISTER FOR ACCESS TO PIEE:
Every Vendor must register in the Procurement Integrated Enterprise Environment for the specific applications they wish to use. During registration, respondents will need to register for the solicitation module with the relevant role (Proposal Manager).
To use an application in the Procurement Integrated Enterprise Environment system, you must establish a personal account in the system.
This account is activated by your Government Administrator or the Procurement Integrated Enterprise Environment Customer Support Center.
You will need to take several steps to establish your personal account:
On the PIEE Home Page, click the Help/Training button in the upper right-hand corner for steps needed to complete before registering.
Complete your Vendor activation requirements (See Vendors Getting Started section on the Help/Training page).
Set up your PC to use the applications (See Machine Setup link on the Help/Training page).
Self-register as "Vendor" or your Contractor role for your CAGE codes (See the demo below for help with Self Registration).
Have your GAM activate your account.
Additional registration instruction and step-by-step walkthrough can be found at:
https://pieetraining.eb.mil/wbt/xhtml/wbt/portal/overview/vendorRegister.xhtml
UPLOADING PROPOSAL TO PIEE:
Detailed instructions on the uploading of proposals can be found at:
https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtml
PIEE Web based training: https://pieetraining.eb.mil/wbt/
In the event a respondent is unable to register for a PIEE account or otherwise is unable to upload their proposal to PIEE, the respondent shall email the individuals identified below no later than 48 business hours prior to the offer due date and time, stating the issue they are having with PIEE, and request instructions for an alternate method to submit their proposal. This alternate method will be in the form of email to the following recipients:
Bernadette Gronewold Bernadette.l.gronewold@usace.army.mil Leslie Molina Leslie.M.Molina@usace.army.mil
For the purposes of determining whether the proposal was received "late", the date and time the file(s) are received by the USACE Outlook Server or uploaded into the PIEE Solicitation website as identified in the PIEE Solicitation notification e-mail sent to the Contract Specialist(s)/ Contracting Officer will be the time and date the Government received the proposal. Do not assume that electronic communication is instantaneous. Please make allowances for delays in transmittal.
b. OT FRAMEWORK
This acquisition will be conducted pursuant to the authority provided under 10 U.S.C. § 2808a using an Other Transaction (OT) agreement. The OT framework provides the Government with the flexibility to establish a collaborative, qualifications-based approach tailored to the complexity and requirements of this project.
The OT approach:
Enables a collaborative Progressive Design-Build (PDB) process that encourages early engagement among the Government, Design-Build Team, and other project stakeholders.
Supports selection of a highly qualified Design-Build Team based on demonstrated experience, capabilities, collaborative teaming approach, and ability to achieve project objectives.
the Government and selected Design-Build Team to establish tailored agreement terms addressing project risks, schedule requirements, performance expectations, and other mission needs.
Facilitates innovative acquisition approaches focused on speed, flexibility, and successful mission outcomes.
Is not subject to FAR-based procurement procedures; however, applicable federal laws and requirements, including fiscal law requirements, remain applicable.
c. WHITE PAPER CONTENT (REQUIRED SECTIONS)
1. BONDING CAPACITY (Excluded from the Page Count)
The submission shall include a letter from your bonding company agent certifying the current maximum bonding capacity per project and the aggregate.
2. CORPORATE LEADERSHIP STRATEGY
Instruction:
Identify the Design-Builder’s corporate leadership actions to execute philosophies and strategies related to partnering, issue resolution, and the approach to alternative delivery methods. In the White Paper submission, the Design-Builder should correlate their philosophies and strategies with the actions utilized to execute on the relevant projects provided in Section 3. Also, identify what the Design-Builder’s corporate definition is of successful project execution.
Include the following:
1. Corporate approach(es) utilized to partner with Owners and industry
2. Approach(es) enacted to facilitate issue resolution with subsequent outcomes
3. Corporate definition of project execution success
4. Approach(es) and qualification(s) to lead the HSTT Project through a Progressive
Design-Build delivery process of unprecedented magnitude and complexity for USACE.
Expectation:
Evidence based responses provide proven partnership approaches and demonstrate mature corporate experience that is advantageous to successful execution of the HSTT project.
3. EXECUTION STRATEGY (HIGH-LEVEL)
Instruction:
This is not a design submittal. Keep submission at a high level and demonstrate how the approaches and strategies have been enacted on past projects.
Include the following:
1. Understanding of project objectives
2. Approach to Progressive Design-Build Collaboration
3. Risk Identification and Mitigation Strategy
4. Means of constructing direct fixation track on concrete girder with continuously welded rail
5. Budget Management Strategies
6. Innovation Approaches (materials, methods, delivery)
Prior Execution Strategy:
All interested parties are informed that prior to this solicitation, design work for this project had been underway by separate contract. The Government has completed an initial partial design to the 65% design submittal through a separate effort with Huitt-Zollars Mason & Hanger Joint Venture (hereinafter referred to as the "Incumbent Designer"). The complete Baseline Design package is provided as Government-Furnished Information (GFI) in Attachment 3 to ensure all Offerors in Step 2 have equal access to all technical data generated to date.
The Offeror’s proposed execution strategy may or may not use any portion of the prior execution strategy and there is no preference during evaluation as to the extent of the use of the prior execution strategy.
Expectation:
Responses demonstrate feasibility, credibility, and understanding of project complexity, and project execution collaboration.
4. PAST RELEVANT EXPERIENCE
Instruction:
Demonstrate experience by submitting up to three (3) projects that include relevant experience as it relates to the HSTT project. At least one project must include heavy-duty continuous welded rail. The submission must summarize performance clearly and factually.
Expectation:
Provide evidence of consistent, successful project delivery on requirements relevant to the HSTT project.
Required information (USE FOR EACH PROJECT):
Project Name & Location:
Client and Contact Information:
Final Contract Value:
Delivery Method:
Key Features & Relevance:
o Description of the aspects of the projects that are relevant to the HSTT project Solicitation.
o Successful collaboration and integration o Federal/DoD experience on military installations (preferred, but not required)
Outcomes: Budget Performance (Cost), adherence to schedule, performance, and quality of work.
Reference Information: Company, POC, email, phone Performance Assessment (Federal: CPARS, Non-federal: Other) [Does not count against page limit]
5. TEAM COMPOSITION & ORGANIZATION
Instruction:
The submission of the organizational chart and narrative should clearly identify the full team structure used by the Design-Builder. Avoid marketing language—focus on roles and relationships. Identify personnel as noted below. Additional roles may be identified in the organizational chart, but do not identify the actual personnel other than those required below.
Provide:
Prime Entity (legal name), if Joint Venture or other teaming arrangement – see below.
Designer of Record Key Design Team / Trade Partners (If applicable, discipline or name) Methods used to conduct local labor market analysis
General subcontract strategy and vetting process used to resource projects.
Required Roles (at minimum): The White Paper submission should identify personnel for the three roles listed below. The submission should include a short narrative on each individual’s experience and qualifications as it relates to their role in the HSTT project.
Project Executive (Identify) Senior Project / Project Manager (Identify) Design Manager (Identify)
Include Organizational Chart:
The organizational chart shall depict the complete project delivery organization and clearly demonstrate the proposed management structure for execution of the project. At a minimum, the chart shall identify:
Corporate leaders supporting the project.
Project-level management structure.
Lines of authority, responsibility, and communication.
The relationship among the Prime Design-Builder, Designer of Record, key design disciplines, major trade partners, and other principal team members.
Any joint venture, mentor-protégé, or other teaming relationships, if applicable.
The organizational chart should clearly demonstrate how the Design-Build Team is organized to effectively manage, coordinate, and deliver a project of this size, complexity, and technical scope.
Additional Requirement:
Provide a short narrative description of:
Team integration Prior working relationships (if applicable) Ability to execute collaboratively Experience / Qualifications
Joint Ventures (JVs) & Teaming Agreements, if applicable:
Incumbent Designer Availability Offerors are permitted, but not required, to team with or subcontract to the Incumbent Designer to complete the design-build effort. Offerors will not be evaluated more or less favorably solely based on their decision to utilize or not utilize the Incumbent Designer.
Non-Exclusivity of Incumbent Designer In the interest of promoting maximum competition, the Incumbent Designer is permitted to participate as a design partner, subcontractor, or team member on more than one Offeror’s proposal. Prime Offerors are strictly prohibited from requiring or enforcing exclusive teaming agreements with the Incumbent Designer for this solicitation.
Multi-Offeror Participation Should the Incumbent Designer elect to participate on multiple Offeror teams, the Incumbent Designer must establish and maintain strict internal Organizational Conflict of Interest (OCI) firewalls. The Incumbent Designer shall not share, disclose, or cross-pollinate proprietary construction methodologies, pricing, schedule strategies, or technical innovations between competing Prime Offerors. Each Proposal that includes the Incumbent Designer must include a signed Non-Exclusivity and Firewall Certification executed by the Incumbent Designer.
Deferred Finalization of Joint Ventures / Teaming Agreements
(a) Proposal-Stage Teaming Flexibility: Utilizing the flexibility afforded under this Other Transaction (OT) solicitation, Offerors are not required to submit a fully executed Joint Venture (JV) agreement, consortium agreement, or binding subcontract with their Designer of Record at the time of initial proposal submission.
(b) Required Proposal Documentation: In lieu of a finalized partnership or JV agreement at the time of proposal submission, Offerors shall submit a Statement of Intent (SOI) signed by both the Prime Design-Build Offeror and the proposed Design Firm.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .