This document package includes an amendment to a solicitation and related specifications for a federal construction project. The U.S. Army Corps of Engineers is seeking bids to upgrade chain link security and safety fencing for the Survivability, Vulnerability, and Assessment Directorate at White Sands Missile Range in New Mexico. The amendment provides revisions to specifications covering special project procedures, quality control, environmental protection, and digging permits for work on the restricted military installation. Bidders must acknowledge receipt of the amendment by the specified date and time. The specifications outline requirements for contractor access, waste disposal, utility outages, road closures, and anticipated roadblocks during testing missions. The quality control plan must be submitted within 10 days of notice to proceed and include organization charts and testing procedures.

View the file

Other files

File Type Posted
site visit attendees.pdf PDF
W912PP22B0017_SV Fence Upgrades_RTA.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

W912PP

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SVAD Fence Upgrades, White Sands Missile Range, New Mexico.

1.This is Amendment No. 0001 to Solicitation No. W912PP22B0017. The following revisions shall be incorporated into the specifications. All other provisions shall remain unchanged.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

U.S. ARMY ENGINEER DISTRICT, ALBUQUERQUE

CORPS OF ENGINEERS

4101 JEFFERSON PLAZA, N.E.

ALBUQUERQUE, NEW MEXICO 87109-3435

See Item 6

J

9A. AMENDMENT OF SOLICITATION

NO.

W912PP22B0017

1 2

06/17/2022

9B. DATED (SEE ITEM 11)

05/26/2022

W912PP22B0017

AMENDMENT No. 0001 Page

2. SPECIFICATIONS: Delete the following listed pages and substitute the pages attached hereto. On the revised pages, for convenience, changes are emphasized by STRIKETHROUGH for deletions and UNDERLINE for additions from the previous issue. All portions of the revised (or new) pages shall apply whether or not changes have been indicated.

Delete Page Insert Page

01 35 20.00 44 SPECIAL PROJECT

PROCEDURES FOR WHITE SANDS MISSILE

RANGE, ENTIRETY

01 35 20.00 44 SPECIAL PROJECT

PROCEDURES FOR WHITE SANDS MISSILE

RANGE, ENTIRETY

01 45 00.00 10 QUALITY CONTROL,

ENTIRETY

01 45 00.00 10 QUALITY CONTROL,

ENTIRETY

3. DRAWING CHANGES: The following drawings have been revised and the sequence number changed to indicate such revision:

Delete Page Insert Page

NA

////////LAST ITEM////////

SV Fence Upgrades W912PP22B0017 WSMR, NM Amendment 0001

SECTION 01 35 20.00 44

SPECIAL PROJECT PROCEDURES FOR WHITE SANDS MISSILE RANGE

7/2008

PART 1 GENERAL

1.1 NOTICE OF RESTRICTED ACCESS TO WHITE SANDS MISSILE RANGE

White Sands Missile Range is a restricted area in its entirety. Access to the Range by foreign nationals is not authorized unless approved on a case-by-case basis by the commander. The Contractors shall present to the Contracting Officer or his representative acceptable evidence of United States citizenship or bona fide immigrant alien status for each Contractor or sub-contractor employee who will perform work at this installation.

Requests for foreign national access shall be presented to the Contracting Officer at least 14 days prior to the desired access date. The following information must be included in each visit request: Name in full, security clearance, official title or position, nationality, visa, passport, order number, or serial number, date(s) desired and purpose of visit.

1.2 CONTRACTOR ACCESS PROGRAM

Contractors must complete and submit the attached Form 5000 for employee access. The current Access Control requirements published on the WSMR Directorate of Emergency Services website are as follows:

1.2.1 ACCESS CONTROL

All visitors to White Sands Missile Range (WSMR) must have a valid need for access and a White Sands Missile Range Point of Contact (POC) or sponsor for that visitor. The exception for this is to visit the Missile Park and Museum (in this case access will be restricted to the area of the museum).

When visitors arrive they must have a valid state or federal ID, a WSMR sponsor or POC and provide that information to the access clerks or guards at the gate.

Entry Requirements for person without a Valid DOD ID Card requesting unescorted access:

1. A valid purpose for entering the installation; (Attend Meeting, visit Museum, Job interview, etc.)

2. Valid driver's license

3. Current vehicle registration (If operating a vehicle)

4. Proof of current insurance (If operating a vehicle)

5. License plate number

6. Provide the destination, name of facility, building number, street address, or unit name/designation

The visitor's POC/sponsor will be contacted and the visitor will be ran through the NCIC-III database and a determination will be made for acceptability.

Once acceptability has been determined a Temporary Gate Pass will be

SECTION 01 35 20.00 44 Page 1 issued for short visits not to exceed 14 days.

For visits that exceed this time frame the visitors MUST have a SPONSOR and complete the Form 5000. The Form 5000 contains personal information and it must be protected. DO NOT transmit over open e-mail. Protect the document with a password and send the two forms over separate e-mails or provide information to the POC/Sponsor who will submit with an encrypted email" and 102 for Main Post and/or Up Range.

A pass completed by this method can be up to 365 days from the completed NCIC-III Check. (Done with the Form 5000 or a Temporary Gate Pass). The request forms must be submitted by the POC/Sponsor and not the requestor.

Once acceptability has been determined, the Form 102 will be returned to the POC/Sponsor and the visitor will be granted a temporary pass to go to the WSMR access badge processing center.

For more information, please contact the Installation Physical Security Section at: 575-678-7626/5414/7905

For this Contract, the USACE Contracting Officer's Representative (COR) shall serve as the Government POC/Sponsor.

1.2.2 Background Checks

The Contractor may be requested to furnish information to conduct background checks for each employee to the Security Directorate and/or Pass & Badge Office prior to access to the installation.

1.2.3 Identification of Employees

The Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the work to display, identification as approved and directed by the Contracting Officer. Prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon release of any employee. When required, the Contractor shall obtain and provide fingerprints of persons employed on the project. Contractor and subcontractor personnel shall wear identifying markings on hard hats clearly identifying the company for whom the employee works. Contractor personnel shall wear visible Contractor-furnished employee identification badges while physically on the Installation. Each badge shall include, as a minimum, the company name, employee name, photograph, Contract Title, Contract Number, and the expiration date of the badge.

1.2.4 Utility Outages

Although no outages are anticipated, the following guidelines are provided: Utility outage permits are required. The contractor is responsible for the coordination and submitting all forms and sketches required for any outage. Utility, road and railroad closures require a minimum ten(10) working days advance written notice and will be subject to WSRO approval. In the case of a road closure a sketch shall be in accordance with the Manual on Uniform Traffic Control Devices, and shall be provided at no additional cost to the government.

1.2.5 General Requirements

The Contractor is responsible for daily clean-up and complete restoration of the area once the contract is complete. Work shall be accomplished in accordance with all applicable contract documents.

SECTION 01 35 20.00 44 Page 2

1.2.6 Environmental Concerns

The Contractor is responsible for getting all Environmental approvals (SWPPP's, etc…..). The Contractor shall prepare a SWPPP for review by the Government and shall be a co-permittee on the NPDES permit. Once the Government has reviewed and accepted the Contractor's submitted SWPPP, the Contractor shall submit a Notice Of Intent (NOI) and provide a copy to the Government no later than 5 days prior to earth disturbance. See Section 01 57 20.20 10 ENVIRONMENTAL PROTECTION FOR WHITE SANDS MISSILE RANGE for more detail.

SWPPP: All work shall be in accordance with the National Pollutant Discharge Elimination System Manual (NPDSM) December 2003. The Contractor is responsible for installing and maintaining all erosion and sediment control devices until permanent stabilization of the disturbed site has occurred. All erosion and sediment control devices shall be inspected weekly and after every storm and repairs made if necessary. At the completion of construction and after the vegetation has been established, the Contractor shall remove all temporary erosion and sediment control devices. The Contractor shall construct or install temporary and permanent erosion and sediment control best management practices (BMPs) in accordance with UFSWF Guide Specification Section 01 57 23 STORM WATER

POLLUTION PREVENTION MEASURES.

Unexploded Ordinance (UXO): The project does not have any historical documentation of any incidences of Unexploded Ordinance (UXO's). However, WSMR is an active range and all Contractor employees must have WSMR provided UXO training. No one is allowed on WSMR range areas without the training. No one shall disturb any suspicious object or item that could be a UXO and it should be immediately reported to (575) 678-7588 or (575) 678-3411.

Information on projected roadblocks, lockouts, and lock-ins can be obtained by calling (575) 678-1178 (recording) and/or (575) 678-2222 (office).

1.3 Demolition Waste

All non-hazardous solid waste resulting from demolition operations (construction and demolition, C&D, debris) on WSMR shall be recycled and/or disposed of at an approved off-site solid waste or recycling facility. The contractor shall segregate and recycle, at a minimum, all scrap metal including, but not limited to, steel, aluminum, copper, copper wire, brass, and pipes. The contractor shall report to the WSMR Garrison Environmental Division Solid Waste Program Manager, the tons and type of material recycled and disposed, identify the recycling and disposal facility and provide the information to the government. The contractor shall be responsible for proper collection and disposal of all other non-hazardous solid waste (trash) generated at the job site. Cardboard, paper, aluminum cans, soda and water bottles should be recycled in any available blue recycling trailer conveniently located on main post.

As an alternative to off-site disposal and recycling of C&D debris, the contractor is authorized to recycle scrap metal, asphalt, concrete and clean fill on-site. The contractor must coordinate with the WSMR Garrison Environmental Division Solid Waste Manager (678-2415) and complete and submit the WSMR Diverted/Stockpiled Materials Monthly Report Form. The contractor is authorized to dispose of other acceptable C&D debris at the on-site C&D landfill. The attached WSMR C&D Waste Turn-In Inspection

SECTION 01 35 20.00 44 Page 3

Sheet identifies C&D debris accepted at the on-site C&D landfill. The contractor shall report the tons and type of material recycled and disposed to the government. The contractor is authorized to recycle all scrap metal including, but not limited to, steel, aluminum, copper, copper wire, brass, and pipes at the on-site scrap metal yard, Monday through Thursday, 7:30am to 11:30am and 12:30pm to 2:30pm.

Concrete shall be crushed in accordance with WSMR and New Mexico Air Quality regulations and government specifications. The contractor shall apply for a General Construction Permit (GCP) through New Mexico Environment Department. The contractor shall comply with the provisions (one of them is the use of water spray). Out of state contractors will need to provide a relocation notice from wherever they came from to New Mexico Environment Department as part of the GCP application. The contractor will coordinate with WSMR Garrison Environmental Division Air Quality Program Manager (678-2225) at the planning stage before crushing operation begins.

"A satellite accumulation point (SAP) must be established by the contractor for accumulation of lead-based paint and asbestos waste generated during removal and abatement on WSMR. Contact the Hazardous Waste Management Center (HWMC), 678-4641, for further guidance. A SAP may also be required for proper management and disposal of paint related waste when other than latex or acrylic paint is used. An inventory of products to be used on WSMR, along with the manufacturer's SDS/MSDS, shall be provided to the HWMC prior to start of work.

1.4 DIGGING PERMIT AND UTILITY LOCATES

For all project activities requiring excavation, soil borings, or other subsurface work, the Contractor shall complete the attached WSMR Digging Permits in accordance with the Digging Permit Processes contain therein.

The Contractor is responsible for completing BOTH Digging Permits and obtain all required signatures/approvals to ensure all potential underground utilities and communication lines are identified. The Contractor shall allow a minimum of 45 calendar days for the WSMR Digging Permit Process from submission to Government Approval.

For the INFORMATION MANAGEMENT DIRECTORATE TRANSMISSION SECTION (WG-G6-DTE) EXCAVATION PERMIT, the form is to be filled out and e-mailed to Mr. Adam Carruth (adam.m.carruth.civ@mail.mil) and Mr. Danny Apodaca (daniel.d.apodaca2.civ@mail.mil). The WSMR Commo Group will mark/flag the commo lines in the area per the information provided, and when completed, e-mail the signed document back to the POC that submitted the locate request. The Commo group also signs the WSMR Digging Permit once the Commo Locate form and process has been completed.

For locates of utilities that do not belong to White Sands Missile Range, the Contractor shall submit a request through the website https://geocall.nm811.org/geocall/portal.

1.5 ANTICIPATED ROADBLOCKS

Test missions at White Sands Missile Range involve required road closures to meet safety protocols. Accordingly, the Contractor shall anticipate eight (8) roadblock delays per month that may interrupt transportation into and from White Sands Missile Range, as well as travel within the White Sands Missile Range installation. Each roadblock has a duration up to two

(2) hours.

SECTION 01 35 20.00 44 Page 4

For locations of roadblocks on public roads, information is available at https://www.wsmr.army.mil/Pages/WhiteSandsRoadBlockSchedule.aspx .

To access information for the latest roadblock information, contact (575) 675-1178. The information is updated each weekday in the afternoon for the following day.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 35 20.00 44 Page 5

SECTION 01 45 00.00 10

QUALITY CONTROL

11/16

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D3740 (2019) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction

ASTM E329 (2020) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection

1.2 PAYMENT

Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable CLIN Schedule item.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Contractor Quality Control (CQC) Plan ; G

SD-06 Test Reports

Verification Statement

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction. QC consist of plans, procedures, and organization necessary to produce an end product

SECTION 01 45 00.00 10 Page 1 which complies with the Contract requirements. The QC system covers all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the Contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent maintains a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN

Submit no later than 10 days after receipt of notice to proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements FAR 52.246-12 Inspection of Construction. Construction will be permitted to begin only after acceptance of the CQC Plan applicable to the particular feature of work to be started.

3.2.1 Content of the CQC Plan

Include, as a minimum, the following to cover all construction-operations, both onsite and offsite, including work by subcontractors fabricators, suppliers and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.

c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Furnish copies of these letters to the Contracting Officer.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. These procedures must be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer are required to be used.)

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking construction deficiencies from identification

SECTION 01 45 00.00 10 Page 2 through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of the specifications can generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.

3.2.2 Acceptance of Plan

Acceptance of the Contractor's plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Government reserves the right to require the Contractor to make changes in the Contractor Quality Control(CQC) Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2.3 Notification of Changes

After acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

3.3 COORDINATION MEETING

After the Preconstruction Conference, before start of construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system.

During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations,, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There can be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings or address deficiencies in the CQC system or procedures which can require corrective action by the Contractor.

3.4 QUALITY CONTROL ORGANIZATION

3.4.1 Personnel Requirements

The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, and sufficient number of additional qualified personnel to ensure safety and Contract compliance. The Safety and Health Manager reports directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of

SECTION 01 45 00.00 10 Page 3 the CQC organization. The Contractor's CQC staff maintains a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure Contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the CQC organization. The CQC organization is responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.

3.4.2 CQC System Manager

Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC System Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of five years construction quality control experience on construction similar to this contract, or a person with a minimum of ten years construction experience, of which a minimum of five years experience must be in construction quality control on construction similar to this contract. This CQC System Manager is on the site at all times during construction and is employed by the prime Contractor. The CQC System Manager is assigned no other duties .

may also serve as the Superintendent, provided the person meets the specified qualifications for both positions. Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.

3.4.3 Additional Requirement

In addition to the above experience and education requirements, the Contractor Quality Control(CQC) System Manager and Alternate CQC System Manager are required to have completed the Construction Quality Management (CQM) for Contractors course. If the CQC System Manager does not have a current certification, obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the various locations within the Corps of Engineers Fort Worth District geographical area. For locations and schedules of training courses, please connect to the following link:

http://www.swf.usace.army.mil/BusinessWithUs/ConstructionQualityManagementTraining.aspx Registration is required; call the Contracting Officer's Representative for times and reservations. There is no charge for the course; however the Contractor will pay for travel and per diem costs.

The Construction Quality Management Training certificate expires after 5 years. If the CQC System Manager's certificate has expired, retake the course to remain current.

3.4.4 Organizational Changes

Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.

SECTION 01 45 00.00 10 Page 4

3.5 SUBMITTALS AND DELIVERABLES

Submittals, if needed, have to comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements.

3.6 CONTROL

CQC is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows:

3.6.1 Preparatory Phase

This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.

b. Review of the Contract drawings.

c. Check to assure that all materials and equipment have been tested, submitted, and approved.

d. Review of provisions that have been made to provide required control inspection and testing.

e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the Contract.

f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

g. Review of the appropriate activity hazard analysis to assure safety requirements are met.

h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.

i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.

j. Discussion of the initial control phase.

k. The Government needs to be notified at least 72 hours in advance of beginning the preparatory control phase. Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the

SECTION 01 45 00.00 10 Page 5 definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

3.6.2 Initial Phase

This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:

a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.

b. Verify adequacy of controls to ensure full contract compliance.

Verify required control inspection and testing are in compliance with the contract.

c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards.

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The Government needs to be notified at least 24 hours in advance of beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases.

g. The initial phase for each definable feature of work is repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.

3.6.3 Follow-up Phase

Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

3.6.4 Additional Preparatory and Initial Phases

Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

SECTION 01 45 00.00 10 Page 6

3.7 TESTS

3.7.1 Testing Procedure

Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements.

Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and acceptance tests when specified. Procure the services of a Corps of Engineers approved testing laboratory or establish an approved testing laboratory at the project site. Perform the following activities and record and provide the following data:

a. Verify that testing procedures comply with contract requirements.

b. Verify that facilities and testing equipment are available and comply with testing standards.

c. Check test instrument calibration data against certified standards.

d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.

e. Record results of all tests taken, both passing and failing on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports are submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated results in nonpayment for related work performed and disapproval of the test facility for this Contract.

3.7.2 Testing Laboratories

All testing laboratories must be validated by the USACE Material Testing Center (MTC) for the tests to be performed. Information on the USACE MTC with web-links to both a list of validated testing laboratories and for the laboratory inspection request for can be found at:

https://mtc.erdc.dren.mil/ .

3.7.2.1 Capability Check

The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel is required to meet criteria detailed in ASTM D3740 and ASTM E329.

3.8 COMPLETION INSPECTION

3.8.1 Punch-Out Inspection

Conduct an inspection of the work by the CQC System Manager and the CQC staff near the end of the work, or any increment of the work established by a time stated in Contract FAR 52.211-10 Commencement, Prosecution, and

SECTION 01 45 00.00 10 Page 7

Completion of Work, or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection.

3.8.2 Pre-Final Inspection

The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.

3.8.3 Final Acceptance Inspection

The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative is required to be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands can also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the Contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance FAR 52.246-12 Inspection of Construction.

3.9 DOCUMENTATION

3.9.1 Quality Control Activities

Maintain current records providing factual evidence that required quality control activities and tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:

a. The name and area of responsibility of the Contractor/Subcontractor.

b. Operating plant/equipment with hours worked, idle, or down for repair.

c. Work performed each day, giving location, description, and by whom.

When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.

SECTION 01 45 00.00 10 Page 8

d. Test and control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.

e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.

f. Submittals and deliverables reviewed, with Contract reference, by whom, and action taken.

g. Instructions given/received and conflicts in plans and specifications.

3.9.2 Verification Statement

Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the Contract. Furnish the original and one copy of these records in report form to the Government daily within 24 hours after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days need to be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports need to be signed and dated by the Contractor Quality Control(CQC) System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report.

3.10 NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer can issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

-- End of Section --

SECTION 01 45 00.00 10 Page 9

SF 30
AMEND
01 35 20.00 44 - SPECIAL PROJECT PROCEDURES FOR WHITE SANDS MISSILE RANGE
PART 1 GENERAL
1.1 NOTICE OF RESTRICTED ACCESS TO WHITE SANDS MISSILE RANGE
1.2 CONTRACTOR ACCESS PROGRAM
1.2.1 ACCESS CONTROL
1.2.2 Background Checks
1.2.3 Identification of Employees
1.2.4 Utility Outages
1.2.5 General Requirements
1.2.6 Environmental Concerns
1.3 Demolition Waste
1.4 DIGGING PERMIT AND UTILITY LOCATES
1.5 ANTICIPATED ROADBLOCKS
PART 2 PRODUCTS NOT APPLICABLE
PART 3 EXECUTION NOT APPLICABLE
01 45 00.00 10 - QUALITY CONTROL
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 CONTRACTOR QUALITY CONTROL CQC PLAN
3.2.1 Content of the CQC Plan
3.2.2 Acceptance of Plan
3.2.3 Notification of Changes
3.3 COORDINATION MEETING
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
3.4.2 CQC System Manager
3.4.3 Additional Requirement
3.4.4 Organizational Changes
3.5 SUBMITTALS AND DELIVERABLES
3.6 CONTROL
3.6.1 Preparatory Phase
3.6.2 Initial Phase
3.6.3 Follow-up Phase
3.6.4 Additional Preparatory and Initial Phases
3.7 TESTS
3.7.1 Testing Procedure
3.7.2 Testing Laboratories
3.7.2.1 Capability Check
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
3.8.2 Pre-Final Inspection
3.8.3 Final Acceptance Inspection
3.9 DOCUMENTATION
3.9.1 Quality Control Activities
3.9.2 Verification Statement

3.10 NOTIFICATION OF NONCOMPLIANCE