W912PP18R0038_Amend_01.pdf

PDF 189 KB Posted

Attached to
FY 18 BUILDING 27496 BLAST DOORS, KIRTLAND AIR FORCE BASE, BERNALILLO COUNTY, NEW MEXICO
Solicitation number
W912PP18R0038
Issued by

About this file

W912PP18R0038 - Amendment 1

View the file

Other files

File Type Posted
W912PP18R0038_Bldg_27496_Hydraulic_Doors_Amendment_0003.pdf PDF
W912PP18R0038_Amend_02.pdf PDF
site_visit_attendees.pdf PDF
W912PP18R0038.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

PROJECT: DESIGN-BUILD FY18 BUILDING 27496 HYDRAULIC DOORS -- KIRTLAND AIR FORCE BASE, BERNALILLO

COUNTY, NEW MEXICO

1. This is Amendment No. 0001 to Solicitation No. W912PP18R0038; 7 September 2018. The following revisions shall be incorporated into the specifications. All other provisions shall remain unchanged.

U.S. ARMY ENGINEER DISTRICT, ALBUQUERQUE

CORPS OF ENGINEERS

4101 JEFFERSON PLAZA, N.E.

ALBUQUERQUE, NEW MEXICO 87109-3435

J

W912PP18R0038

1 2

09/07/2018

08/14/2018

W912PP18R0038

AMENDMENT No. 0001

2. SPECIFICATIONS: Delete the following listed pages and substitute the pages attached hereto. On the revised pages, for convenience, changes are emphasized by STRIKETHROUGH for deletions and UNDERLINE for additions from the previous issue. All portions of the revised (or new) pages shall apply whether or not changes have been indicated.

Delete Page Insert Page

Section 00 22 16, Page 19 Section 00 22 16, Page 19

////////LAST ITEM////////

W912PP18R0038

Page 19 of

N/A Vol 2 Tab 8 JV Agreement (if applicable) and/or Corporate, Partnership, Joint Venture Certificate

Not Rated

*A RATING OF UNACCEPTABLE ON ANY FACTOR/SUBFACTOR WILL RESULT IN AN OVERALL

RATING OF UNACCEPTABLE.

3.0.1 Where the word “project(s)” appears, it is understood to mean a project(s), contract(s), task order(s), or any other contract document provided for in the Federal Acquisition Regulation (FAR 2.101). Examples of projects submitted by the Prime Construction Contractor may be projects performed for a State or Federal Government Agency; or for a commercial or private sector customer.

3.0.2 Where the word “recent” appears it is understood to mean a construction type project for which construction is at least 70% complete (measured by performance period days) as of the RFP closing date or a construction type project that has been completed within 7 years of the RFP closing date. Projects completed more than 7 years before the RFP closing date will not be considered for evaluation purposes.

3.0.3 Where the word “relevant” appears it is understood to mean that project experience submitted is similar to the context of this solicitation in terms of scope and magnitude of effort and complexity as described and required in this RFP. For this RFP, “relevant” projects are defined as projects that are similar in terms of:

scope (maintenance bunker facilities), type (underground structures and operations of hydraulic blast door systems and operation), complexity (hydraulic door and lift operations within a highly classified and secure complex) magnitude ($5 Million or above).

4.0 FACTOR 1: TECHNICAL – SUBFACTOR A: RELEVANT CONTRACTOR EXPERIENCE

4.1 SUBMISSION REQUIREMENTS

4.1.1 The Offeror shall submit examples of construction projects which best illustrate the experience of the construction contractor on relevant projects of similar in scope, type, complexity, and magnitude as defined in section 3.03 above.

A minimum three (3) projects, but not more than 5, are to be submitted for the Prime Contractor. No more than two (2) are to be submitted for the design firm.

Each project example shall include a project narrative, discussing the project and providing specifics as noted herein. If a Joint Venture (JV) is proposing, provide examples for each prime contractor in the JV within the five project examples allowed.

4.1.2 Indefinite-Delivery, Indefinite Quantity (IDIQ) Contracts, where numerous Task Orders are summed to meet the minimum construction dollar value identified herein, are not acceptable.

4.1.3 The government preference is that project examples submitted be of completed projects (i.e. construction complete). Projects still under construction will be evaluated only if they are more than 70 percent complete.

4.1.4 Information is to be compiled on the Contract Description Forms provided at the end of section 00 22 16 and will be used to evaluate contractor experience. Responses to this factor should take into account experience of the management team proposed for the contract, timeliness of performance, safety and health record, customer satisfaction and cost control. Offerors are invited, but not required, to submit photographs of successful projects in conjunction with this section. Project experience submitted by the Offeror as a subcontractor will not be evaluated.

4.1.5 Each project example narrative should include the following information:

Project title and location