B1 - Bid Abstract Final Signed.pdf

PDF 341 KB Posted

Attached to
FY26 AIWW Dredge Material Placement Facility (DMPF) Improvements 2
Solicitation number
W912PM26BA002
Issued by

About this file

This is an Abstract of Bids for the U.S. Army Corps of Engineers Wilmington Contracting Office, solicitation number W912PM26BA002 for AIWW Dredge Material Placement Facility (DMPF) Improvements 2, issued January 27, 2026, and opened March 5, 2026. The contract is a 100% Small Business Set-Aside with three addenda issued. The project involves dredge material placement facility improvements across multiple placement areas (DA-64, DA-214, DA-94, and DA-308) and includes work packages for equipment mobilization/demobilization, clearing and grubbing, survey work, structural work on outfall pipes and risers, earthwork and embankment backfill, site cleanup and seeding, and payment and performance bonds. The government estimate for all line items totals $5,653,795.00 for mandatory items (0001-0014) and ranges up to $15,011,750.00 including all options (0015-0026).

Five offerors submitted bids: TKTMJ, Inc. ($5,962,000.00 total); Three Oaks Construction, Inc. ($5,653,795.00); US Aqua Services LLC ($10,454,298.00); Scrimgeours Farm All, LLC ($6,410,222.87); Bering Straits Construction Solutions, LLC ($6,952,609.00); and DK Business Solutions ($6,226,339.42). All bidders acknowledged amendments and provided 20% bid security. The Contracting Officer is Rosalind Shoemaker. Bid pricing varied significantly across offerors, with individual line item costs ranging from approximately $12,000 to over $1.5 million depending on the specific work package and contractor.

View the file

Other files

File Type Posted
B1 - Bid Opening Attendance Sheet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF BIDS 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)

I CERTIFY that I have opened, read, and recorded on this abstract all offers received SIGNATURE

69 Darlington Ave. In response to this solicitation.

Wilmington, North Carolina 28403

PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. BIDDERS

(Check A, B or C and complete D, E and F.)

A. OFFEROR A. OFFEROR

A. HIRED LABOR

B. REASONABLE CONTRACT B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount)

(WITHOUT PROFIT)

NUMBER OF ADDENDA ISSUED 3 C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

(INCLUDING PROFIT)

0001 Equipment Mobilization and Demobilization (DA-64) 1 Job $161,705.00 $161,705.00 $500,000.00 $500,000.00 $1,250,000.00 $1,250,000.00 0002 Placement Area 64 - Clearing and Grubbing 1 Job $90,875.00 $90,875.00 $75,000.00 $75,000.00 $400,000.00 $400,000.00 0003 Placement Area 64 - Pre and Post Construction Survey Work 1 Job $55,415.00 $55,415.00 $75,000.00 $75,000.00 $90,000.00 $90,000.00 0004 Placement Area 64 - Outfall Pipe and Riser Structural Work 1 Job $445,225.00 $445,225.00 $300,000.00 $300,000.00 $1,230,000.00 $1,230,000.00 0005 Placement Area 64 - Earthwork and Embankment Backfill 1 Job $718,280.00 $718,280.00 $450,000.00 $450,000.00 $1,590,000.00 $1,590,000.00 0006 Placement Area 64 - Site Cleanup and Seeding 1 Job $75,125.00 $75,125.00 $150,000.00 $150,000.00 $250,000.00 $250,000.00 0007 Payment and Performance Bonds: DA 64 1 Job $18,600.00 $18,600.00 $22,000.00 $22,000.00 $120,000.00 $120,000.00 0008 Equipment Mobilization and Demobilization (DA-214) 1 Job $159,110.00 $159,110.00 $500,000.00 $500,000.00 $1,250,000.00 $1,250,000.00 0009 Placement Area 214 - Clearing and Grubbing 1 Job $83,060.00 $83,060.00 $75,000.00 $75,000.00 $250,000.00 $250,000.00 0010 Placement Area 214 - Pre and Post Construction Survey Work 1 Job $50,925.00 $50,925.00 $75,000.00 $75,000.00 $90,000.00 $90,000.00 0011 Placement Area 214 - Outfall Pipe and Riser Structural Work 1 Job $399,400.00 $399,400.00 $300,000.00 $300,000.00 $1,142,000.00 $1,142,000.00 0012 Placement Area 214 - Earthwork and Embankment Backfill 1 Job $476,765.00 $476,765.00 $215,000.00 $215,000.00 $906,000.00 $906,000.00 0013 Placement Area 214 - Site Clean up and Seeding 1 Job $45,700.00 $45,700.00 $150,000.00 $150,000.00 $300,000.00 $300,000.00 0014 Payment and Performance Bonds: DA 214 1 Job $14,600.00 $14,600.00 $20,000.00 $20,000.00 $120,000.00 $120,000.00 0015 Option 1: Equipment Mobilization and Demobilization (DA 94) 1 Job $163,620.00 $163,620.00 $500,000.00 $500,000.00 $625,000.00 $625,000.00 0016 Option 2: Placement Area 94 - Clearing and Grubbing 1 Job $97,000.00 $97,000.00 $75,000.00 $75,000.00 $185,000.00 $185,000.00 0017 Option 3: Placement Area 94 - Pre and Post Construction Survey Work 1 Job $55,415.00 $55,415.00 $75,000.00 $75,000.00 $26,000.00 $26,000.00 0018 Option 4: Placement Area 94 - Outfall Pipe and Riser Structural Work 1 Job $510,080.00 $510,080.00 $330,000.00 $330,000.00 $1,360,000.00 $1,360,000.00 0019 Option 5: Placement Area 94 - Earthwork and Embankment Backfill 1 Job $688,760.00 $688,760.00 $830,000.00 $830,000.00 $1,385,000.00 $1,385,000.00 0020 Option 6: Placement Area 94 - Site Clean up and Seeding 1 Job $58,665.00 $58,665.00 $150,000.00 $150,000.00 $160,000.00 $160,000.00 0021 Option 7: Placement Area 94 - Payment and Performance Bonds DA 94 1 Job $19,000.00 $19,000.00 $30,000.00 $30,000.00 $37,250.00 $37,250.00 0022 Option 8: Equipment Mobilization and Demobilization (DA 308) 1 Job $161,325.00 $161,325.00 $500,000.00 $500,000.00 $625,000.00 $625,000.00 0023 Option 9: Placement Area 308 - Clearing and Grubbing 1 Job $156,830.00 $156,830.00 $75,000.00 $75,000.00 $385,000.00 $385,000.00 0024 Option 10: Placement Area 308 - Post Construction Survey Work 1 Job $60,815.00 $60,815.00 $75,000.00 $75,000.00 $48,375.00 $48,375.00 0025 Option 11: Placement Area 308 - Outfall Pipe and Riser Structural Work 1 Job $872,500.00 $872,500.00 $400,000.00 $400,000.00 $1,150,000.00 $1,150,000.00 0026 Option 12: Placement Area 308 - Payment and Performance Bonds 1 Job $15,000.00 $15,000.00 $15,000.00 $15,000.00 $37,125.00 $37,125.00

$2,794,785.00 $2,907,000.00 $8,988,000.00 Total Amount of Line Items 0015 - 0021 $1,592,540.00 $1,990,000.00 $3,778,250.00 Total Amount of Line Items 0022 - 0026 $1,266,470.00 $1,065,000.00 $2,245,500.00 Total Amount of Line Items 0001 - 0026 $5,653,795.00 $5,962,000.00 $15,011,750.00

W912PM26BA002 27-Jan-26 5-Mar-26

Yes

AIWW Dredge Material Placement Facility (DMPF) Imrpovements 2 -100% Small Business Set-Aside

TKTMJ, Inc.

109 Arthur St.

Natchitoches, LA 71457

20%

Total Amount of Line Items 0001-0014

Yes

U. S. Department of the Army, Corps of Engineers Wilmington Contracting Office

Rosalind Shoemaker, Contracting Officer

X 20%

Three Oaks Construction, Inc.

515 S. Flynn St.

North Sioux City, SD 57049

Electronic Equivalent OF1419

PROJECT TITLE 13. BIDDERS

A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount)

NUMBER OF ADDENDA ISSUED 3 C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

0001 Equipment Mobilization and Demobilization (DA-64) 1 Job $140,000.00 $140,000.00 $353,450.21 $353,450.21 $1,072,075.00 $1,072,075.00 0002 Placement Area 64 - Clearing and Grubbing 1 Job $70,710.00 $70,710.00 $159,050.37 $159,050.37 $41,914.00 $41,914.00 0003 Placement Area 64 - Pre and Post Construction Survey Work 1 Job $35,000.00 $35,000.00 $27,343.33 $27,343.33 $24,000.00 $24,000.00 0004 Placement Area 64 - Outfall Pipe and Riser Structural Work 1 Job $350,000.00 $350,000.00 $413,911.07 $413,911.07 $321,810.00 $321,810.00 0005 Placement Area 64 - Earthwork and Embankment Backfill 1 Job $784,000.00 $784,000.00 $289,908.13 $289,908.13 $886,904.00 $886,904.00 0006 Placement Area 64 - Site Cleanup and Seeding 1 Job $70,000.00 $70,000.00 $430,966.42 $430,966.42 $1,509,945.00 $1,509,945.00 0007 Payment and Performance Bonds: DA 64 1 Job $28,994.00 $28,994.00 $15,309.00 $15,309.00 $30,226.00 $30,226.00 0008 Equipment Mobilization and Demobilization (DA-214) 1 Job $140,000.00 $140,000.00 $474,200.46 $474,200.46 $1,064,720.00 $1,064,720.00 0009 Placement Area 214 - Clearing and Grubbing 1 Job $35,237.00 $35,237.00 $159,886.53 $159,886.53 $59,227.00 $59,227.00 0010 Placement Area 214 - Pre and Post Construction Survey Work 1 Job $35,000.00 $35,000.00 $27,343.33 $27,343.33 $24,000.00 $24,000.00 0011 Placement Area 214 - Outfall Pipe and Riser Structural Work 1 Job $350,000.00 $350,000.00 $413,910.20 $413,910.20 $319,210.00 $319,210.00 0012 Placement Area 214 - Earthwork and Embankment Backfill 1 Job $336,000.00 $336,000.00 $243,463.61 $243,463.61 $407,435.00 $407,435.00 0013 Placement Area 214 - Site Clean up and Seeding 1 Job $56,000.00 $56,000.00 $234,170.76 $234,170.76 $1,167,224.00 $1,167,224.00 0014 Payment and Performance Bonds: DA 214 1 Job $19,045.00 $19,045.00 $15,309.00 $15,309.00 $23,919.00 $23,919.00 0015 Option 1: Equipment Mobilization and Demobilization (DA 94) 1 Job $140,000.00 $140,000.00 $338,514.35 $338,514.35 $146,556.00 $146,556.00 0016 Option 2: Placement Area 94 - Clearing and Grubbing 1 Job $81,538.00 $81,538.00 $142,910.43 $142,910.43 $65,827.00 $65,827.00 0017 Option 3: Placement Area 94 - Pre and Post Construction Survey Work 1 Job $35,000.00 $35,000.00 $22,473.59 $22,473.59 $24,000.00 $24,000.00 0018 Option 4: Placement Area 94 - Outfall Pipe and Riser Structural Work 1 Job $350,000.00 $350,000.00 $425,407.62 $425,407.62 $324,569.00 $324,569.00 0019 Option 5: Placement Area 94 - Earthwork and Embankment Backfill 1 Job $700,000.00 $700,000.00 $232,032.03 $232,032.03 $804,042.00 $804,042.00 0020 Option 6: Placement Area 94 - Site Clean up and Seeding 1 Job $42,000.00 $42,000.00 $513,492.91 $513,492.91 $780,502.00 $788,502.00 0021 Option 7: Placement Area 94 - Payment and Performance Bonds DA 94 1 Job $26,971.00 $26,971.00 $16,364.00 $16,364.00 $17,422.00 $17,422.00 0022 Option 8: Equipment Mobilization and Demobilization (DA 308) 1 Job $140,000.00 $140,000.00 $477,028.73 $477,028.73 $162,613.00 $162,613.00 0023 Option 9: Placement Area 308 - Clearing and Grubbing 1 Job $270,489.00 $270,489.00 $319,581.40 $319,581.40 $588,100.00 $588,100.00 0024 Option 10: Placement Area 308 - Post Construction Survey Work 1 Job $35,000.00 $35,000.00 $32,418.31 $32,418.31 $24,000.00 $24,000.00 0025 Option 11: Placement Area 308 - Outfall Pipe and Riser Structural Work 1 Job $700,000.00 $700,000.00 $617,391.08 $617,391.08 $545,138.00 $545,138.00 0026 Option 12: Placement Area 308 - Payment and Performance Bonds 1 Job $22,910.00 $22,910.00 $14,386.00 $14,386.00 $10,920.00 $10,920.00

$2,449,986.00 *Actual: $3,258,222.42 $3,258,222.41 $6,952,609.00 Total Amount of Line Items 0015 - 0021 $1,375,509.00 *Actual: $1,691,194.93 $1,691,194.92 $2,170,918.00 Total Amount of Line Items 0022 - 0026 $1,168,399.00 $1,460,805.52 $1,330,771.00 Total Amount of Line Items 0001 - 0026 $4,993,894.00 *Actual: $6,410,222.87 $6,410,222.85 $10,454,298.00

Should be As read at bid opening

Yes

20% 20%

US Aqua Services LLC 4406 Higway 14 New Iberia, LA 70560

Scrimgeours Farm All, LLC 12965 NW 110th Ave.

Bering Straits Construction Solutions, LLC

3301 C ST STE 400

Total Amount of Line Items 0001-0014

Reddick, FL 32686 Anchorage, AL 99503

20%

Yes Yes

PROJECT TITLE 13. BIDDERS

A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount)

NUMBER OF ADDENDA ISSUED 3 C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

0001 Equipment Mobilization and Demobilization (DA-64) 1 Job $330,975.89 $330,975.89 0002 Placement Area 64 - Clearing and Grubbing 1 Job $57,015.81 $57,015.81 0003 Placement Area 64 - Pre and Post Construction Survey Work 1 Job $50,442.93 $50,442.93 0004 Placement Area 64 - Outfall Pipe and Riser Structural Work 1 Job $424,879.15 $424,879.15 0005 Placement Area 64 - Earthwork and Embankment Backfill 1 Job $683,781.14 $683,781.14 0006 Placement Area 64 - Site Cleanup and Seeding 1 Job $27,229.63 $27,229.63 0007 Payment and Performance Bonds: DA 64 1 Job $12,394.00 $12,394.00 0008 Equipment Mobilization and Demobilization (DA-214) 1 Job $293,866.66 $293,866.66 0009 Placement Area 214 - Clearing and Grubbing 1 Job $90,185.87 $90,185.87 0010 Placement Area 214 - Pre and Post Construction Survey Work 1 Job $50,442.93 $50,442.93 0011 Placement Area 214 - Outfall Pipe and Riser Structural Work 1 Job $418,620.63 $418,620.63 0012 Placement Area 214 - Earthwork and Embankment Backfill 1 Job $372,271.39 $372,271.39 0013 Placement Area 214 - Site Clean up and Seeding 1 Job $14,995.72 $14,995.72 0014 Payment and Performance Bonds: DA 214 1 Job $12,394.00 $12,394.00 0015 Option 1: Equipment Mobilization and Demobilization (DA 94) 1 Job $341,720.92 $341,720.92 0016 Option 2: Placement Area 94 - Clearing and Grubbing 1 Job $102,865.06 $102,865.06 0017 Option 3: Placement Area 94 - Pre and Post Construction Survey Work 1 Job $47,921.19 $47,921.19 0018 Option 4: Placement Area 94 - Outfall Pipe and Riser Structural Work 1 Job $429,648.95 $429,648.95 0019 Option 5: Placement Area 94 - Earthwork and Embankment Backfill 1 Job $574,849.59 $574,849.59 0020 Option 6: Placement Area 94 - Site Clean up and Seeding 1 Job $28,505.40 $28,505.40 0021 Option 7: Placement Area 94 - Payment and Performance Bonds DA 94 1 Job $12,394.00 $12,394.00 0022 Option 8: Equipment Mobilization and Demobilization (DA 308) 1 Job $343,016.92 $343,016.92 0023 Option 9: Placement Area 308 - Clearing and Grubbing 1 Job $715,391.12 $715,391.12 0024 Option 10: Placement Area 308 - Post Construction Survey Work 1 Job $19,588.84 $19,588.84 0025 Option 11: Placement Area 308 - Outfall Pipe and Riser Structural Work 1 Job $758,547.68 $758,547.68 0026 Option 12: Placement Area 308 - Payment and Performance Bonds 1 Job $12,394.00 $12,394.00

$2,839,495.75 Total Amount of Line Items 0015 - 0021 $1,537,905.11 Total Amount of Line Items 0022 - 0026 $1,848,938.56 Total Amount of Line Items 0001 - 0026 $6,226,339.42

Wilmignton, NC 28409

20%

DK Business Solutions 6013 Sweet Gum DR

Total Amount of Line Items 0001-0014

Yes

2026-03-05T16:20:25-0500
SHOEMAKER.ROSALIND.MARIE.1395095168

File details come from the government source that posted it. Updated .