A21 - REV1-W912PM25BA003_AMDT0002_PACKAGE.pdf
PDF 17 MB Posted
- Attached to
- Maintenance Dredging, Wilmington Harbor Inner Ocean Bar Federal contract opportunity
- Solicitation number
- W912PM25BA003
About this file
This document is an Amendment (Amendment 0002) to a federal solicitation for maintenance dredging services for the Wilmington Harbor Inner Ocean Bar in Brunswick County, North Carolina. The amendment modifies several key aspects of the original solicitation, including updating the wage determination (NC20250019 dated 02-21-2025), revising technical specifications for dredging, and changing beach placement area details. Specifically, the amendment updates Section 00 01 15 (List of Drawing Sheets) to include a new wage determination document and modifies Section 00 21 00 (Instructions).
The dredging project involves removing approximately 1,350,000 cubic yards of shoaled material from multiple channel areas, including Baldhead Shoal Reach 1, Baldhead Shoal Reach 2, Smith Island Channel, and other specified locations. The beach placement will occur at Caswell and Oak Island beaches, with an environmental window for material placement from 16 November 2025 to 30 April 2026. Dredging depths are specified between -44 and -46 feet MLLW, including paid overdepth. The project requires an ocean-certified hydraulic pipeline dredge, and the contract will be firm fixed price with an estimated value between $10 million and $25 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B1 - WH IOB Bid Abstract.pdf | ||
| A21 - W9129M25BA003-AMDT0003-PACKAGE.pdf | ||
| A21 - W912PM25BA0030002_FY25WHIOB -AMDT0002 - Final Conformed Copy.pdf | ||
| A21 - WAGE DETERMINATION - NC20250019 - Dated 02-21-2025.pdf | ||
| A2 - Smith Island Channel_Historical_1998-2023.pdf | ||
| A2 - Smith Island Channel_2023_Vibracores.pdf | ||
| A2 - Baldhead_Shoal_Reach_2_Historical_1998-2008.pdf | ||
| A2 - Baldhead_Shoal_Reach_1_Historical_1998-2012.pdf | ||
| A21 - W912PM25BA003_FY25WHIOB-AMDT0001-Conformed Copy.pdf | ||
| A21 - W912PM25BA003_FY25WHIOB-AMDT0001-PACKAGE - Final.pdf | ||
| A21 - LOCKED_WHIOB_RTA Set_UpdatedFEB25.pdf | ||
| A21 - RTA-SPECS1-W912PM24BA003-FY26WHIOB.pdf | ||
| A21 - UnLocked_WHIOB_RTA Set_UpdatedFEB25.pdf | ||
| A21 - Solicitation - W912PM25BA003.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section 00 01 15 - List of Drawing Sheets
The attachments table has changed from:
No prior attachments
To:
Identifier Attachment Name Attachment Description Reference Identifier Date Line Item # Of Pages
WAGE DETERMI
NATION -
NC20250019,
Dated 02-21-2025
Wage Determination 21 Feb 2025 6
The following contract documents were added:
WAGE DETERMINATION - NC20250019, Dated 02-21-2025
The following contract documents page counts were changed:
ATTACHMENT PAGE COUNTS
Attachment Name Current Previous
WAGE DETERMINATION - NC20250019, Dated 02-21-2025 6 none
Miscellaneous text in this section has been added to:
WAGE DETERMINATION - NC20250019, Dated 02-21-2025
Section 00 21 00 - Instructions
Miscellaneous text in this section has been modified to:
k7ctdddc Cross-Out
TOTAL AMOUNTS
TOTAL AMOUNT OF LINE ITEMS 0001 - 0004 $___________________
TOTAL AMOUNT OF OPT BID ITEM 1, LINE ITEMS 0005-0006 $___________________
TOTAL AMOUNT OF OPT BID ITEM 2, LINE ITEMS 0007-0008 $___________________
TOTAL AMOUNT OF OPT BID ITEM 3, LINE ITEMS 0009-0010 $___________________
TOTAL AMOUNT OF LINE ITEMS 0001-0010 $___________________
NOTE 1: Please be sure to include unit prices rounded to two (2) decimal places.
NOTICE TO BIDDERS
NOTE 1: EVALUATION OF OPTIONS
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
NOTE 2: AVAILABILITY OF FUNDS
The exercise of any and all optional bid items shall be subject to the availability of funds.
NOTE 3: EXERCISE OF OPTIONS
The Government reserves the right to exercise optional bid items 0005 to 0008 within 90 days of contract award and optional bid items 0009-0010 by 28 April 2026.
NOTE 4: ENVIRONMENTAL WINDOW
The environmental window for dredging with hopper dredges will be limited to the period of 01 December through 15 April.
The environmental window for cutterhead dredging will occur from 16 November through 30 April.
The environmental window for beach placement is 16 November through 30 April.
NOTE 5: COMMENCEMENT OF WORK
Commencement of work will be initiated with the issuance of a Notice to Proceed (NTP).
NOTE 6: COMPLETION OF WORK
Completion of all work shall be 30 April 2026.
NOTE 7: WAGE DETERMINATION (WD)
WD number NC20250019, dated 02-21-2025 does not include hopper dredging. If there are any class of laborers or mechanics which are not listed in the wage determination and which are to be employed under the contract, they shall be classified in conformance with wage determination NC20250019. Contractors can request additional classes and rates after contract award by submitting an SF 1444 to the Contracting Officer. (The SF-1444 can be downloaded from the "Library" section on the WDOL website (http://www.wdol.
gov) and it is in the FAR at 48 C.F.R. 53.301-1444)
(END OF NOTICE TO BIDDERS)
HANDCARRIED BIDS/PROPOSALS
1. If bids/proposals are hand carried, deliver them to the U. S. Army Corps of Engineers, Wilmington District, Attn: Diana Curl or Rosalind M. Shoemaker, 69 Darlington Avenue, Wilmington, North Carolina, 28403.
All bids/proposals must be received in the Contracting Office not later than the exact time specified for bid opening or time specified for receipt of proposals. No electronic copies of bids will be accepted.
2. Due to security measures at the Wilmington District Office, you should allow sufficient time for delivery of the bid/proposal to ensure it is received timely.
(End)
INFORMATION TO ALL CONTRACTORS
System for Award Management (SAM) and Electronic Funds Transfer (EFT)
1. All contractors must register in the System for Award Management (SAM) database before they can be awarded a contract. You may register at http://www.sam.gov. SAM information or help is also available by calling 866-606-8220.
2. Public Law 104-134 requires the use of Electronic Funds Transfer (EFT) for all Federal payments. EFT information will be pulled from your SAM by the USACE FINANCE CENTER, 5720 INTEGRITY DRIVE, MILLINGTON, TN 38054-5005 for contractor payments.
(End)
PRE-AWARD INFORMATION
1. Contracts shall be awarded to responsible prospective contractors only. Before award, to be determined responsible, a prospective contractor must:
a. Have adequate financial resources to perform the contract, or the ability to obtain them;
b. Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and government business commitments;
c. Have a satisfactory performance record;
d. Have a satisfactory record of integrity and business ethics;
e. Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them;
f. Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
g. Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
2. Each Bidder shall, upon request of the Contracting Officer, furnish information on any or all of the above areas so that the Contracting Officer can make an affirmative determination of responsibility or nonresponsibility.
3. A contract shall be awarded to a responsible prospective contractor.
Before award, to be determined responsible, a prospective contractor must submit the following information within three (3) days of request:
a. Current Financial Statement
b. Furnish a completed Small Business Subcontracting Plan (LARGE BUSINESS ONLY)
(End of Paragraph)
BID OPENING
Bidders who choose to attend the bid opening in person, may do so at the scheduled time. The bid opening will also be read via a teleconference line.
TOLL FREE: 1-844-800-2712
ATTENDEES ACCESSCODE: 43382789
(End)
Section 00 70 00 - Conditions of the Contract
Additional Information/Notes
The following clauses were modified:
52.217-7 Option for Increased Quantity-Separately Priced Line Item. Mar 1989 hereby reads as follows:
Option for Increased Quantity-Separately Priced Line Item (Mar 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor for optional bid items 0005 to 0008 within 90 days of contract award and for optional bid items 0009-0010 by 28 April 2026. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
Section 00 73 00 - Supplementary Conditions
Miscellaneous text in this section has been modified to:
EQUIPMENT & OWNERSHIP
(a) This special contract requirement does not apply to terminations. See Federal Acquisition Regulation (FAR) part 49.
(b) Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region III. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the simplified acquisition threshold (SAT), the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
(End of Clause)
ELECTRONIC SOFTWARE
CONTRACTOR SUPPLY ANDUSE OF ELECTRONIC SOFTWARE FOR PROCESSING WAGE RATE
REQUIREMENTS STATUTECERTIFIED LABOR PAYROLLS (APR 2011)
(a) The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.
(b) If the contractor elects to use an electronic payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with the Wage Rate Requirements statute. When the contractor uses an electronic payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.
(c) The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the Federal Acquisition Regulation
(FAR);
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export in an Excel spreadsheet to be imported into the contractor's Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government's RMS;
(5) demonstrated security of data and data entry rights;
(6) ability to produce contractor-certified electronic versions of weekly payroll data;
(7) ability to identify erroneous entries and track the date/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
(8) capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.
(d) All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.
(End of clause)
SAFETY & HEALTH REQUIREMENTS
This paragraph applies to contracts and purchase orders that require the contractor to comply with EM 385-1-1 (e.g., contracts that include the Accident Prevention clause at FAR 52.236-13 and/or other safety provisions). EM 385-1-1 and its changes are available athttp://www.publications.usace.army.mil/usacepublications/engineermanuals.aspx .The Contractor shall be responsible for complying with the current edition and all changes posted on the web through the date that is 10 calendar days prior to the date offers are due. If the solicitation is amended to extend the time set for receipt of offers, the 10 calendar days rule stated above shall be applied against the amended date. (For example, if offers are due on 10 April, all changes posted on or before 31 March shall apply to the contract. If the time for receipt of offers is extended from 10 April to 20 April, all changes posted on or before 10 April shall apply to the contract.)
(End)
REQUIRED INSURANCE
(a) The Contractor shall procure and maintain during the entire period of his performance under this contract the following minimum insurance:
1. Comprehensive and Employer's Liability Insurance: Coverage in an amount not less $100,000 or in the amount required by the State law in which the work is to be performed under this contract, whichever is greater.
2. Comprehensive General Liability Insurance: Coverage in an amount not less than $500,000 per occurrence.
3. Automobile Liability Insurance: $200,000 per person and $500,000 per occurrence for bodily injury liability and $20,000 property damage liability.
4. Vessel liability: When contract performance involves use of vessels, the contracting officer shall require vessel collision liability and protection and indemnity liability insurance.
(b) Prior to the commencement of work hereunder, the Contractor shall furnish to the Contracting Officer a certificate or written statement of the above-required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation, or any material change in the policies adversely affecting the interests of the Government in such insurance, shall not be effective for such period as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than 30 days after written notice thereof to the Contracting Officer.
(c) The Contractor agrees to insert the substance of this clause, including this subparagraph (c), in all subcontracts hereunder.
(End)
BASIS FOR SETTLEMENT
Basis for Settlement of Proposals
Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under Federal Acquisition Regulation (FAR) 49.206-2(b). In evaluating a termination settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(b) If equipment costs have been allocated toa contract using predetermined rates, those charges will be adjusted to actual costs.
(c) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.
(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation
(FAR) 31.205-11).
(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.
(End of clause)
UNAUTHORIZED INSTRUCTIONS
UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL
The Contractor shall not accept any instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer or the Contracting Officer's Representative (COR) acting within the limits of the COR's Authority. See the Contracting Officer's Representative clause of this contract.
(End of Instruction)
UAI 5122.1302-100
Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13and Department of Labor regulations, U.S. Army Corps of Engineers (USACE)contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S.
veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
-U.S. Department of Labor Veterans' Employment and Training Service (VETS):https://www.dol.gov/vets/
-Federal Veteran Employment Information: https://www.fedshirevets.gov/
-Veterans Opportunity to Work (VOW) Program: https://www.benefits.va.gov/vow/
-U.S. Army Warrior Transition Command Employment Index:
https://wct.army.mil/modules/employers/index.html
-Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes
(End of special contract requirement)
WAGE DETERMINATION
"General Decision Number:NC20250019 02/21/2025
Superseded General Decision Number:NC20240019
State: North Carolina
Construction Type: Heavy Dredging
Counties: North Carolina Statewide.
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR5.1(a)(1).
|If the contract is entered |. Executive Order 14026 |
|into on or after January 30, | generally applies to the |
|2022, or the contract is | contract. |
|renewed or extended (e.g., an |.The contractor must pay |
|option is exercised) on or | all covered workers at |
|after January 30, 2022: | least $17.75 per hour (or |
| | the applicable wage rate |
| | listed on this wage |
| | determination, if it is |
| | higher) for all hours |
| | spent performing on the |
| | contract in 2025. |
|If the contract was awarded on. Executive Order 13658 |
|or between January 1, 2015and| generally applies to the |
|January 29, 2022, and the | contract. |
|contract is not renewed or |. The contractor must pay all|
|extended on or after January | covered workers at least |
|30, 2022: | $13.30 per hour (or the |
| | applicable wage rate listed|
| | on this wage determination,|
| | if it is higher) for all |
| | hours spent performing on |
| | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the
Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/03/2025
1 02/21/2025
* ENGI0025-002 10/01/2024
Rates Fringes
Dredging : (Hydraulic Dredges
Over 20"")
CLASS A1....................$ 47.07 15.34+a
CLASS A2....................$ 41.94 14.99+a
CLASS B1....................$ 40.71 14.90+a
CLASS B2....................$ 38.31 14.73+a
CLASS C1....................$ 37.26 14.66+a
CLASS C2....................$ 36.07 14.57+a
CLASS D.....................$ 29.96 14.15+a
Hydraulic Dredges Under20""
Cook........................$ 8.11 ** 1.73+b
Deckhand....................$ 7.77 ** 1.73+b
Engineer....................$ 9.59 ** 1.73+b
Launchman...................$ 8.19 ** 1.73+b
Leverman....................$ 10.03 ** 1.73+b
Mate........................$ 8.82 ** 1.73+b
Mess Cook...................$ 7.71 ** 1.73+b
Messman & Janitor...........$ 7.53 ** 1.73+b
Oiler & Fireman.............$ 8.11 ** 1.73+b
Shoreman....................$ 7.82 ** 1.73+b
Spider Barge Operator.......$ 8.68 ** 1.73+b
Spill Barge Operator........$ 8.68 ** 1.73+b
Welder......................$ 9.79 ** 1.73+b
CLASSIFICATIONS:
CLASS A1: Deck Captain, Leverman, Mechanical Dredge Operator.
Licensed Tug Operator over 1000 HP
CLASS A2: Crane Operator (360swing)
CLASS B1: Derrick Operator (180swing), Spider/Spill Barge
Operator, Timber Fork Operator, Dozer Operator, Engineer, Blaster/Driller, Fill Placer, Electrician, Licensed Boat
Operator, Licensed Crew Boat Operator.
CLASS B2: Certified Welder.
CLASS C1: Mate, Drag Barge Operator, Welder, Assistant Fill
Placer, Steward.
CLASS C2: Boat Operator.
CLASS D: Shoreman, Deckhand, Rodman, Scowman, Cook, Messman, Oiler, Janitor, Drill Oiler
PREMIUMS: Additional 20% for hazardous material work
FOOTNOTE APPLICABLE TO ABOVECRAFTS:
a. New Year's Day, Good Friday, Memorial Day, Independence
Day, Labor Day, Thanksgiving Day and Christmas Day.
Vacation Contribution of 8% of straight time rate multiplied by the total hours worked.
b. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. Plus Vacation contribution of 8% of straight time pay for all hours worked.
INCENTIVE PAY : (Add to Hourly Rate)
Operator (NCCCO License/Certification) $1.80; Licensed Tug
Operator over 1000 HP (Assigned as Master) USCG licensed
Master of Towing Vessels (MOTV) $1.80; Licensed Boat
Operator (assigned as lead boat captain) USCG licensed boat operator $1.30; Engineer (QMED and Tankerman endorsement or licensed engineer (USCG) $1.80; Oiler QMED and Tankerman endorsement (USCG) $1.80; All classifications Tankerman endorsement only (USCG) $1.55; Deckhand or Mater AB w/Lifeboatman only (USCG) $1.80; Welder (ABS certification)
$1.55
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order14026 ($17.75) or 13658
($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706,Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who isa victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
""SU"",""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e. Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate isa single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance(additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should bidirected to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mailto:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email todba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
Solicitation # W912PM25BA003 Date: 19-MARCH-2024 Project Title – MAINTENANCE DREDGING, WILMINGTON HARBOR
INNER OCEAN BAR
BRUNSWICK COUNTY, NORTH CAROLINA
Amendment No. 0002
TECHNICAL SUMMARY OF CHANGES
1. REVISIONS TO SPECIFICATIONS. Revised section to the specification with revision mark “***AMENDMENT 0002***” is shown on each revised page.
A. 35 20 23 – DREDGING & BEACH PLACEMENT WORK
a. REVISED BY DELETION:
i. 2.1 CHARACTER OF MATERIAL
1. The material is to be removed from the maintenance dredging areas is predominantly composed of shoaled material, which has accumulated since dredging was conducted. The shoaled material is believed to consist primarily of sand, silt and clay but may also include wood, metal and other sunken debris that may have become lodged in the channel by recent storms. Site conditions are not fully characterized, but the channels have been subject to routine periodic dredging.
Historic subsurface investigation data from previous dredging contracts is available upon request. It is the responsibility of the Contractor to familiarize themselves with the existing data, conduct their own investigations if necessary, and decide for themselves the site conditions and character of materials prior to commencing the work. The Government shall not be liable for the Contractor's failure to properly prepare to deal with the existing geologic conditions at each dredging area. The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made.
Remove hard material as needed to achieve the required template.
b. REVISED BY ADDITION
i. 3.5.15 Dredging Requirements
1. 2) Dredge Area 3
a) As determined by the results of a hydrographic survey monitoring, the Government will direct the Contractor to dredging areas within Smith Island Channel. Dredging depths at this area will be between plus or minus -44 and plus or minus -46 feet MLLW including paid overdepth, unless otherwise stated in the layout drawing.
2. b) Material placement will be the Caswell and Oak Island Beach site.
Solicitation # W912PM25BA003 Date: 19-MARCH-2024 Project Title – MAINTENANCE DREDGING, WILMINGTON HARBOR
INNER OCEAN BAR
BRUNSWICK COUNTY, NORTH CAROLINA
Amendment No. 0002
2. REVISIONS TO DRAWINGS. Revision mark “***AMENDMENT 0002***” is shown on each revised page.
A. The design for Wilmington Harbor Inner Ocean Bar originally showed a gap in the beach placement on Caswell Beach between Construction Stations 30+00 and 70+00.
Amendment 002 now shows beach material being placed at this location. Additionally, the construction berm width for the entire project has been reduced 20’ to account for the additional material being placed in that location. All the plan sheets that show the beach placement area and dimensions have been updated to reflect the changes.
i. DRAWINGS:
1. GI01 - INDEX OF DRAWINGS, PROJECT VICINITY MAP AND
PROJECT SITE PLAN
2. CN104 - CASWELL BEACH PLACEMENT AREA STA. 0+00 TO STA.
106+00
3. CN105 - CASWELL BEACH AND OAK ISLAND PLACEMENT
AREA STA. 106+00 TO STA. 219+00
4. CN106 - OAK ISLAND PLACEMENT AREA STA. 219+00 TO STA.
254+00
5. CN301 - BEACH PLACEMENT AREA TYPICAL SECTIONS
6. CN302 - BEACH FILL CROSS-SECTIONS STA. 5+00 TO STA. 60+00
7. CN303 - BEACH FILL CROSS-SECTIONS STA. 65+00 TO STA.
120+00
8. CN304 - BEACH FILL CROSS-SECTIONS STA. 125+00 TO STA.
180+00
9. CN305 - BEACH FILL CROSS-SECTIONS STA. 185+00 TO STA.
240+00
10. CN306 - EACH FILL CROSS-SECTIONS STA. 245+00 TO STA.
250+00
…end of summary…
FY25 WILMINGTON HARBOR INNER OCEAN BAR FY26WHIOB
AMENDMENT 0002 W912PM25BA003
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00.10 38 8/17 SUPPLEMENTARY SPECIAL CONTRACT
REQUIREMENTS
01 32 01.00 10 02/15 PROJECT PROGRESS SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL
01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
DIVISION 02 - EXISTING CONDITIONS
02 21 00 09/22 CONSTRUCTION SURVEYS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 08/20 DREDGING & BEACH PLACEMENT WORK
35 20 23.33 02/22 NATIONAL DREDGING QUALITY MANAGEMENT
PROGRAM - PIPELINE HYDRAULIC DREDGE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS
SECTION TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 20 23
DREDGING & BEACH PLACEMENT WORK
08/20
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 DESCRIPTION OF WORK
1.3 WORK COVERED BY CONTRACT PRICE
1.4 REFERENCES
1.5 DEFINITIONS
1.5.1 Maintenance Material
1.5.2 New Work Material
1.5.3 Hard Material
1.6 SUBMITTALS
1.7 BEACH PLACEMENT OPERATIONS AND WORK PLAN
1.7.1 Federal Channels
1.7.1.1 Caswell and Oak Island Beach Federal Channels
1.7.2 Beach Placement
1.8 METHOD OF COMMUNICATION
1.9 LOCAL OFFICE
1.10 OTHER DREDGING OPERATIONS
1.10.1 PLANT LOCATION
1.10.2 PLANT
1.11 ENVIRONMENTAL COMPLIANCE AND PROTECTION
1.12 BASIS FOR BIDS
1.13 NOTICES
1.13.1 NOTICE TO THE GOVERNMENT
1.13.2 NOTICE TO MARINERS
1.13.3 SEAGOING BARGE ACT
1.14 NAVIGATION AIDS
1.15 TIDE DATA
1.15.1 Kinematic Tidal Datum
1.15.2 RTK GPS Disputes
1.15.3 Real Time Kinematic (RTK) GPS
PART 2 PRODUCTS
2.1 CHARACTER OF MATERIAL
PART 3 EXECUTION
3.1 FLOATING PLAN INSPECTION AND CERTIFICATION
3.2 FENDER TIRES
3.3 REPORTING REQUIREMENT
3.4 COMPLIANCE WITH APPLICABLE NAVIGATION RULES AND REGULATIONS,
MARINE EQUIPMENT
3.4.1 Vessels
3.4.2 Obstructions
3.4.3 Contractor Responsibility
SECTION 35 20 23 Page 1
3.5 DREDGING
3.5.1 Order of Work
3.5.2 Work Plan
3.5.3 Dredging Plan
3.5.4 Acceptance Sections
3.5.5 Interference with Navigation
3.5.6 Dredging in Progress
3.5.7 Lights
3.5.8 Navigation Warnings
3.5.9 Ranges, Gages, and Lines
3.5.10 Dredge Plant and Equipment
3.5.11 Dredge Positioning System
3.5.12 Dredge Certification
3.5.13 Layout of Work
3.5.13.1 Overdepth Dredging
3.5.13.2 Side Slopes
3.5.13.3 Excessive Dredging
3.5.14 Obstructions and Debris
3.5.15 Dredging Requirements
3.5.16 Quality Control
3.5.17 Skimming of Hoppers
3.5.18 Salvaged Material
3.5.19 Safety of Structures
3.6 PLACEMENT OPERATIONS
3.6.1 Dredged Material Placement Plan
3.6.2 Method of Placement
3.6.3 Beach Placement Operations Plan
3.6.4 Placement in Indicated Site(s)
3.6.5 Contract Placement Areas
3.6.5.1 Beach Placement
3.6.5.1.1 Placement of Material for Beach Placement
3.6.5.1.2 Objectionable Matter
3.6.5.1.3 Beach Compatible Sediments
3.6.5.1.4 Discharge Points
3.6.5.1.5 Longitudinal Dikes
3.6.5.1.6 Fills Adjustment for Beach Placement
3.6.5.1.7 Placement Tolerances
3.6.5.1.8 Equipment Staging, Storage and Demobilization
3.6.6 Beach Tilling
3.6.7 Construction and Grade Stake Recovery Plan
3.6.8 Misplaced Dredged Material
3.6.9 Pipeline Routes
3.6.9.1 Pedestrian Access
3.6.9.2 Dune Protection
3.6.10 Submerged Pipelines
3.6.11 Pipeline Leakage
3.6.12 Booster Pumps
3.7 QUALITY CONTROL
3.8 WATER POLLUTION CONTROL
3.8.1 Contamination of Water
3.8.2 Placement of Materials
3.9 MEASUREMENT AND PAYMENT
3.9.1 Dredging Volume of Material Removed from Channels and Basins
3.9.2 Contract Drawings
3.9.3 Monthly Partial Payments
3.9.4 Method of Survey - Channels and Basins
3.9.5 Singlebeam Surveying Method - Channels and Basins
3.9.6 Survey Lines - Channels and Basins
3.10 FINAL EXAMINATION AND ACCEPTANCE
SECTION 35 20 23 Page 2
3.11 PLACEMENT AREA AND BEACH PLACEMENT ACCEPTANCE
3.12 PLANT REMOVAL
-- End of Section Table of Contents --
SECTION 35 20 23 Page 3
SECTION 35 20 23
DREDGING & BEACH PLACEMENT WORK
08/20
PART 1 GENERAL
1.1 GENERAL INFORMATION
This Section covers furnishing suitable dredging plant and performing all work required to remove the specified materials from within the prescribed work area limits as indicated, and placement of the dredge material within the prescribed material placement areas. The Contractor is responsible for making their own investigation of submerged, surface, and overhead structures in the work areas and other locations they find necessary to traverse. The exact location, depths, and heights of various structures including, but not limited to submarine cables, pipes, highlines, docks, piers, bulkheads, and bridges (as applicable), are not known and it will be necessary for the Contractor to ascertain interference problems and notify the respective owners in advance of dredging operations. The Contractor is responsible for making necessary arrangements with the respective owners of the structure(s) to assure satisfactory completion of dredging in the vicinity with a minimum interruption of service, and shall perform their operations in such a manner as will avoid damage to these facilities.
1.2 DESCRIPTION OF WORK
The work consists of furnishing plant, labor, materials, and equipment to perform dredging, placing beach quality sand on beach, constructing the beach placement sections, and associated work as required by these specifications and drawings for Wilmington Harbor Inner Ocean Bar, Brunswick County, North Carolina.
1.3 WORK COVERED BY CONTRACT PRICE
The contract price per cubic yard as listed for "Dredging - Dredging - Smith Island Channel, Dredging - Baldhead Shoal Reach 1, Dredging - Baldhead Shoal Reach 2" of the BIDDING SCHEDULE shall include the cost of all plant, material, supplies, labor, and incidental expenses in connection with the dredging, excavating, transporting, placing and shaping the beach placement material; temporary safety fencing, temporary warning signs, all diking, embankments, temporary bulkheading needed for control and confining the material and discharge fluid; surveys for the layout and control of the dredging work and for the beach placement work surveys described in Section 01 10 00.10 38: SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS, paragraph, BEACH SURVEYS AND SURVEY PERSONNEL, repairs, and its final inspection and acceptance. The Contractor shall be required to place the beach material in accordance with the drawings.
The contract price, as listed for "Mobilization and Demobilization" of the BIDDING SCHEDULE shall include the cost of transporting and assembling all plant, material, supplies, equipment, pipeline, labor, and incidental expenses in connection with performing the required work listed within the specifications and contract plans. The contactor shall be required to remove all plant, material, equipment, pipeline, supplies, and other incidental items prior to final payment for "Mobilization and
SECTION 35 20 23 Page 4
Demobilization".
1.4 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual
1.5 DEFINITIONS
1.5.1 Maintenance Material
Maintenance material is defined as that comprising shoaling which has occurred since the channel areas were last dredged.
1.5.2 New Work Material
New work material is defined as previously undredged material.
1.5.3 Hard Material
Hard material is defined as material requiring blasting or the use of special equipment for economical removal, and includes boulders or fragments too large to be removed in one piece by the dredge.
1.6 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Work Plan , G
Dredge Material Placement Plan , G
Preconstruction Video Survey
Pipeline Route ; G, A
Beach Placement Operations and Work Plan ; G, A
Beach Placement Operations Plan , G
SD-02 Shop Drawings
Dredging Plan , G
Dredged Material Placement Plan , G
SECTION 35 20 23 Page 5
Construction and Grade Stake Recovery Plan , G SD-06 Test Reports
Daily Observer Reports , G
SD-07 Certificates
Protection Plan
1.7 BEACH PLACEMENT OPERATIONS AND WORK PLAN
1.7.1 Federal Channels
The Contractor shall develop and submit a Beach Placement Operations and Work Plan for all Federal Channels. The work plan shall delineate work areas within the Federa; Channels that will be worked thoroughly before moving to the next work area. In addition to the soundings, the post-dredging surveys of the Federal Channels shall show the work areas, limits, the location of anomalies, and the location of unacceptable material. The Contractor shall begin dredging in the portion of the Federal Channels as indicated in the plans for each area. Upon the depletion of material within the area being dredged by the Contractor or when directed by the Contracting Officer or his/her designated representative, the Contractor will proceed to dredge in another area of the Federal Channel.
The Contractor shall develop and submit a beach placement operations plan for the Contracting Officer's Approval. See Section 01 10 00.10 38 :
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS, paragraph, FINAL EXAMINATION AND ACCEPTANCE OF BEACH PLACEMENT for beach placement acceptance requirements. Placement of the beach material within the fill section can begin at the start of the project, the end of the project, or points in between, however, once placement begins at a particular point and in a certain direction, placement will continue in that direction until the end of the project is reached. Placement of beach material on any beach shall not begin until beach placement has been completed on the current beach or as directed the Contracting Officer or his/her designated representative.
1.7.1.1 Caswell and Oak Island Beach Federal Channels
The Federal Channels that are shown on the contract drawings shall be the source of all beach placement material for the Wilmington Harbor Inner Ocean Bar Maintenance Dredging Project.
1.7.2 Beach Placement
The Contractor shall develop and submit a beach placement operations plan for the Contracting Officer's Approval. See Section 01 10 00.10 38 :
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS, paragraph, FINAL EXAMINATION AND ACCEPTANCE OF BEACH PLACEMENT for beach placement acceptance requirements. Placement of the beach material within the placement section can begin at the start of the project, the end of the project, or points in between, however, once placement begins at a particular point and in a certain direction, placement will continue in that direction until the end of the project is reached. Placement of material on any beach shall not begin until beach placement has been completed on the current beach or as directed the Contracting Officer or his/her designated representative.
SECTION 35 20 23 Page 6
1.8 METHOD OF COMMUNICATION
The Contractor shall furnish and maintain a radio telephone and a cellular phone on the dredge(s) throughout the period of the contract. The plant will not be allowed to begin work until the VHF marine band radio is installed and in good working order and a properly operating cellular phone is on board. The radio telephone shall be capable of operation from the dredge's main control station and capable of transmitting and receiving on a frequency or frequencies within the 156-162 megahertz band using the classes of emissions designated by the Federal Communications Commission. Continuous radio contact shall be maintained between the dredge control room and the inspectors of the placement areas as well as the inspectors patrolling the pipeline.
1.9 LOCAL OFFICE
The Contractor shall maintain a land based office in the immediate vicinity of the project. This office shall be equipped with at least one operable telephone and fax machine, which provides both local and long distance service. The numbers for this equipment shall be provided to the Contracting Officer's Representative during the preconstruction conference, and the telephone shall be monitored and answered by contractor personnel during working hours. This requirement may be waived by the Contracting Officer or his/her designated representative if suitable facilities are available on the dredge.
1.10 OTHER DREDGING OPERATIONS
The Contractor should anticipate the possibility of concurrent dredging operations, adjacent to or nearby the dredge and placement areas in this contract.