QA_Sources Sought.pdf

PDF 106 KB Posted

Attached to
Sources Sought: PN 103069 Net-Zero Carbon – Unaccompanied Personnel Facility
Solicitation number
W912PM24R0003
Issued by

About this file

This document contains questions and answers from a sources sought notice regarding a net-zero carbon unaccompanied personnel facility project. The U.S. Army Corps of Engineers Engineering District Wilmington is seeking information on contractors' experience and qualifications to support an upcoming solicitation for an integrated design and construction project delivering a net-zero carbon barracks. Respondents are asked to provide details on relevant past performance projects from the last six years including descriptions of their teaming relationships, contract structures, and contributions to final design quality. Subcontractor information is also requested pertaining to the past performance projects submitted.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers Sources Sought – Integrated Design and Construction (IDaC) Net-Zero Barracks

1. In the sources sought notice, experience is requested to be within the past 6 years. Would USACE consider expanding this to 10 years? Our firm is currently performing a $80+M Barracks complex and are excited for this opportunity but opening up the experience to 10 years would really allow our firm to utilize large barrack experience which is comparable to the UPF planned barracks.

ANSWER 1: In order to determine current capability, it is important to evaluate projects that are recent; therefor, the 6-year requirement will remain as stated in the notice.

2. Can we expand the past performance project relevance time to 12 years in lieu of 6 years?

ANSWER 2: In order to determine current capability, it is important to evaluate projects that are recent; therefor, the 6-year requirement will remain as stated in the notice.

3. You are asking for us to identify our key subcontractors including their experience and qualifications. Are you asking for any key subcontractors we would use on this new pursuit or should we list the key subcontractors on the projects we are showing for past performance?

ANSWER 3: Please provide information pertaining to subcontractors utilized on the relevant projects submitted for past projects.

4. Under the qualifications paragraph, you are asking for us to “Describe the teaming relationship and contract structure between the Construction Contractor, the Owner and the Designer of Record, and how the Construction Contractor improved the quality of the final design.” You are looking for a description for each of the past performance jobs we are providing in the SS response correct?

ANSWER 4: Yes, that is correct.