QUESTIONS AND ANSWERS 24 January 2019
QUESTION #1: Did the submission date change?
RESPONSE #1: I will update this in FBO.gov. The submission date is February 15, 2018. The response date shown was an estimated timeframe for the pre-solicitation notice that no longer applies.
QUESTION #2: Is this solicitation regarded as an RFQ or RFP?
RESPONSE #2: The solicitation is regarded as a Construction requirement below the Simplified Acquisition Threshold as a RFQ.
QUESTION #3: Do you have a form that you would want our pricing and business information put on to submit?
RESPONSE #3: There is no particular form to use. We recommend using the CLIN structure within the solicitation to fill out your pricing. Please review the solicitation in full for any other information on what is required for quote submittal purposes.