AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

A. Provide updates to specif ications.

B. All other terms and conditions remain unchanged. The due date and time for bid opening has NOT changed as a result of this amendment.

C. See Summary of Changes.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 30-Jul-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PM19B0005

X 9B. DATED (SEE ITEM 11)

23-Jul-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

30-Jul-2019

CODE

U S ARMY CORPS OF ENGINEERS, WILMINGTON

69 DARLINGTON AVE.

WILMINGTON NC 28403

W912PM 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PM19B0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The Issued By organization has changed from

U S ARMY CORPS OF ENGINEERS, WILMINGTON

WILMINGTON DISTRICT

ATTN: CONTRACTING DIVISION

69 DARLINGTON AVE

WILMINGTON NC 28403-1343

to

U S ARMY CORPS OF ENGINEERS, WILMINGTON

CONTRACTING - WILMINGTON DISTRICT

69 DARLINGTON AVENUE

WILMINGTON NC 28403

(End of Summary of Changes)

W912PM19B0005

Amendment 0001

Technical Summary of Changes

SPECIFICATIONS:

35 20 23 – DREDGING

Delete existing Attachment 1 – Enclosure in its entirety and replace with revised enclosed Page.

NOTE:

Text that is added or revised by this amendment is identified in Track changes shown as RED.

The text changes may have necessitated reformatting of subsequent text or pages. If this is the case, those pages have also been issued as amended pages but are not underlined or bold text.

DRAWINGS:

Delete sheet CN102 in its entirety and replace with enclosed revised Sheet.

-- End of Summary of Changes-

Encls As Stated

Required Cubic Yards Allowable Total Cubic Channel Reach Depth (FT) to Required Depth Overdepth Yards

Base Bid Items Section 2 Tangent F - Browns Inlet Crossing 12 18,000 32,000 50,000 Tangents 1 & 2, Channels to Jacksonville 11 90,000 60,000 150,000 Section 2 Tangents I & J – New River Inlet Crossing 12 44,000 46,000 90,000 Section 4 Tangent 1 – Carolina Beach Inlet Crossing 12 20,000 30,000 50,000 Section 4 Tangent 1 & Section 5 Tangents 3, 4 & 4A – Snows Cut 12 40,000 45,000 85,000 Tangent 11 – Lockwoods Folly Inlet Crossing 12 60,000 15,000 75,000

Total Base Bid Items 272,000 228,000 500,000

Optional Bid Items Range F - Core Creek Landcut 12 6,000 11,000 17,000 Tangent 19 – Shallotte Inlet Crossing 12 15,000 15,000 30,000 Lockwoods Folly Inlet Widener 12 112,000 23,000 135,000 Oak Island USCG Basin & Channels 10 15,000 12,000 27,000

Total Optional Bid Items 148,000 61,000 209,000

Totals 420,000 289,000 709,000

Notes:

1. Allowable overdepth is 2' for all reaches except the Oak Island USCG Basin & Channels which is 1'

2. Quantities are based on volumes present at the time of the surveys indicated on the contract drawings plus shoaling anticipated before dredging begins.

Amendment 0001

Technical Summary of Changes