PERFORMANCE WORK STATEMENT (PWS)
JOHN H. KERR DAM AND RESERVOIR –TIMBER HARVEST
CULTURAL RESOURCES ASSESSMENT SURVEY OF
IDENTIFIED TIMBER HARVEST AREAS AT JOHN H. KEER
LAKE PROJECT
11 AUGUST 2016
Part 1
General Information
1.0 GENERAL: This is a non-personal services contract to provide cultural resources assessment surveys related to the Timber Harvesting activities at John H. Kerr Dam and Reservoir (JHK). The Government will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn shall be responsible to the Government.
1.1 Description of Services/Introduction: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the cultural resources assessment surveys of selected timber harvest areas within the JHK area of potential effect (APE) as defined in this Performance Work Statement (PWS), except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
1.2 Background: The U.S. Army Corps of Engineers, Wilmington District (the Corps) plan to conduct various timber harvesting operations around the JHK property. The purpose of this contract is to conduct required cultural resource assessments in compliance with sections 106 and 110 of the National Historic Preservation Act. In addition, surveys need to be in compliance with various State regulations (Virginia and North Carolina) depending on the location of the planned timber harvest area. Because timber harvesting involves activities including road construction, dragging of material on skids, and other general ground-disturbing activities that have the potential to adversely affect previously unidentified historic properties, a cultural resource assessment is required to identify any significant historic properties that may potentially be adversely affected by such activities. Additionally, a cultural resources assessment will also be used to identify and protect previously identified cultural resources within the APE that are eligible or potentially eligible for listing in the National Register of Historic Places (NRHP).
Cultural resources studies that have been previously conducted for the JHK and are available through State preservation offices.
1.3 Objectives: Cultural resources assessment survey under this contract is designed to identify and evaluate the significance of any resources that may be impacted from proposed timber harvesting activities. The survey report shall identify the location and boundaries of any identified cultural resources, evaluate the resources for significance under National Register criteria and propose commendations to avoid or minimize impacts to these resources. In addition, the Contractor shall provide a GIS layer showing the location of shovel tests, newly identified cultural resources and their boundaries.
1.4 Scope: This PWS details the Contractor’s requirements to provide cultural resource assessment survey associated with timber harvesting activities undertaken within the JHK APE as defined in Technical Exhibit 4. The APE encompasses lands owned by the US Army Corps of Engineers. Work performed under this PWS shall include the following tasks:
• Locating previously identified cultural resource sites within the APE that are eligible or potentially eligible for listing in the NRHP.
• Testing various timber harvesting areas according to required State standards.
• Evaluating all identified resources within the various APEs for eligibility under the National Register of Historical Resources eligibility criteria.
• Providing clear boundaries for all resources identified with clear mapping and appropriate GIS data. (Trees along the boundary parameter shall be marked by white paint to indicate areas where logging should not be conducted)
• Providing recommendations for avoidance or minimization of impacts to identified resources that fall within identified timber harvesting areas.
• Produce a GIS layer showing the location of shovel tests, newly identified cultural resources and their boundaries.
• Producing monthly field summaries to include findings and progress, as well an executive summary, draft and final reports.
1.5 Period of Performance (POP): The period of performance shall be for one (1) Base Year of 12 months and one (1) 12-month option year, not to exceed 2 years.
1.6 General Information
1.6.1 Quality Control: The Contractor shall develop and maintain an effective quality control (QC) program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program is the means by which the Contractor assures that the work complies with the requirement of the contract. After acceptance of the quality control plan, the Contractor shall receive the Contracting Officer’s (KO) acceptance in writing of any proposed change to this QC system. Note: As part of this QC program, the Contractor shall pay specific attention to ensure protection of materials removed during excavations. Safeguards are to be implemented to ensure that all materials are protected from accidental destruction or loss. Loss or destruction of materials will be sufficient grounds for termination of the contract and an unsatisfactory evaluation.
1.6.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards, and defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.6.3 Hours of Operation: The Contractor is expected to provide services parallel to JHK hours of operations. The Contractor is required to meet with JHK point of contact (POC) staff to confirm a schedule. A scheduling meeting will be coordinated between the Contractor, JHK staff, the Contracting Officer’s Representative (COR), and/or the Contracting Officer (KO) upon notice to proceed (NTP) to determine the work schedule. Additional scheduling meetings will be held on a quarterly basis between the Contractor, JHK POC, COR, and/or the KO to coordinate the work schedule as needed.
1.6.4 Place of Performance: The work to be performed under this contract shall be performed at the Contractor’s facility, at libraries and archives (public, private, and Tribal), and within the JHK APEs, as shown in Technical Exhibit 4.
1.6.5 Type of Contract: The Government will award a Firm Fixed Price contract.
1.6.6 Security Requirements: RESERVED
1.6.6.1 Physical Security: RESERVED
1.6.6.2 Key Control: RESERVED
1.6.7 Special Qualifications: Agencies, institutions, corporations, associations, or individuals shall be considered qualified when they meet the minimum criteria given in section 1.6.11 below. The Contractor shall submit with the proposal package the qualifications, including academic and work experience, for the Principal Investigator (PI) and the key employees to the KO. Any change to these employees during the performance of this contract must have the prior written approval of the KO.
1.6.8 Post Award Conference/Periodic Progress Meetings: The Contractor shall to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The KO, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the KO will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues.
These meetings shall be at no additional cost to the Government.
1.6.9 Contracting Officer Representative (COR): The COR will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including government drawings, designs, specifications; monitor Contractor's performance and notifies both the KO and Contractor of any deficiencies; coordinate availability of Government furnished property; and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.6.10 Key Personnel: The following personnel are considered key personnel by the Government: Principal Investigator (PI) and/or Project Manager (PM), and Project Archaeologist. The contract proposal shall include documentation (i.e. curriculum vitae) demonstrating that all key personnel meet or exceed the Secretary of Interior’s Professional Qualifications Standards as specified in 36 CFR Part 61 and 48 Federal Register 44738- 44739. The PI, PM, and Project Archaeologist for the contract shall be, at minimum, an archaeologist at the MA level with at least two years of professional experience in cultural resources management and the administration of multi-disciplinary surveys/excavations within the states of North Carolina and Virginia. The PI shall be responsible for overall supervision of work and services to be performed under this contract, and shall be responsible for the validity of the material presented and reports produced under this contract. The PI and PM may be the same individual.
The KO and COR shall be informed if any sub-contractors or third party vendors are anticipated to be used. If sub-contractors are to perform work, appropriate documentation demonstrating that all sub-contractors meet the Secretary of Interior’s Professional Qualifications Standards as specified above shall be also included in the contract proposal. Documentation shall include curriculum vitae, resume, and/or certifications pertinent to qualifications. In addition, the COR will approve in advance all changes in key personnel during the period of contract services.
1.6.11 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall also ensure that all documents or reports produced are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.6.12 Contractor Travel: The Contractor shall be required to mobilize to and from the various JHK APEs to perform work under this contract.
Reimbursable travel costs include transportation, lodging, meals, and incidental expenses as defined in Part 31.205-46 of the Federal Acquisition Regulation. Costs for transportation will be reimbursed based on the prevailing General Services Administration (GSA) mileage reimbursement rate. Costs for lodging, meals, and incidental expenses will be reimbursed in accordance with the Joint Travel Regulations, based on the prevailing GSA per diem rate for the area. These costs shall be incorporated into the required cost proposal.
1.6.13 Other Direct Costs: RESERVED.
1.6.14 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract will be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials shall not be used or sold by the Contractor without written permission from the KO. All materials supplied to the Government will be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.6.15 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to, or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.), or perform evaluation services which may create a current or subsequent Organizational Conflict of Interest (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated. The KO may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.6.16 Phase In/Phase Out Period: RESERVED
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS:
2.1.1. CONTRACTOR. A supplier or vendor having a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An
employee of the U.S. Government appointed by the Contracting Officer to administer the contract. Such appointment will be in writing and will state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5. DELIVERABLE. Anything that can be physically delivered but may include non-physical items such as meeting minutes.
2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8. QUALITY ASSURANCE. The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An
organized written document specifying the surveillance methodology to be used for surveillance of Contractor performance.
2.1.10. QUALITY CONTROL. All necessary measures taken by the
Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.12. WORK WEEK. Is defined as Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement APE Area of Potential Effects AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial Off the Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer NRHP National Register of Historic Places NTP Notice to Proceed OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PI Principal Investigator PIPO Phase In/Phase Out PM Project Manager POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SHPO State Historic Preservation Officer TE Technical Exhibit
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND
SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Services: The Government will provide ArcView shapefiles of the various timber harvest APEs to be tested for cultural resources. The Government will NOT provide any other services or personnel to assist with production set up.
3.2 Facilities: The Government will NOT provide facilities.
3.3 Utilities: The Government will NOT provide utilities.
3.4 Equipment: The Government will NOT provide equipment.
3.5 Materials: The Government will NOT provide any materials.
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS. All GPS equipment shall be of such design and in such condition and adjustment that results obtained will be within a sub-meter range of accuracy. The Contractor shall ensure that no trash, flagging (note site boundaries will require marking though) or other materials are left behind in the areas while working. Access gates shall remain in the position in which there are found.
4.2 Secret Facility Clearance: RESERVED
4.3. Materials: The Contractor shall provide office and field supplies to meet the requirements under this PWS.
4.4. Equipment: The Contractor shall provide office, safety, and field equipment to meet the requirements of this PWS:
PART 5
SPECIFIC TASKS
5. Specific Tasks:
5.1. Basic Services: The Contractor shall supply the necessary personnel, facilities, supplies, materials, and other equipment required to conduct a cultural resources assessment survey of the identified parcels. The Contractor shall be responsible for coordinating entry and obtaining the necessary access to gates with the Forest Managers. The Contractor shall be responsible for securing an Archaeological Resource Protection Act (ARPA permit from the Corps).
The Contractor shall be responsible for providing a safe working environment for all persons in his/her employ as prescribed by EM 385-1-1, “Safety and Health Requirements Manual,” dated 28 November 2014. The Contractor shall be responsible for all damages to persons and property that occur in connection with the work and services performed under this Contract, without recourse against the Government. The Contractor shall be responsible for having adequate insurance coverage for all activities required under this Contract.
During survey of the JHK areas requiring survey, any necessary work stoppages shall be coordinated with the COR and/or the KO. All parties shall make every effort to not affect the work schedule or the costs due to delays in survey portion of the Project.
5.2. Previously Identified Cultural Resource Sites: If previous existing sites exist within any of the identified timber harvest areas the Contractor shall reassess their significance and provide and update on the National Register eligibility of the resource.
5.3. Cultural Resource Assessment Survey: Field survey methods shall include initial reconnaissance survey, a survey of the project area for historic resources in the built environment – including canals, ditches, levees, and other features and structures that may be greater than 50 years in age – and subsurface archaeological testing. The intensity of archaeological testing varies in accordance with the designated zones of high, moderate, and low site potential as determined during preparation of the research design and as noted in the field. In most instances, systematic shovel testing along transects supplemented by judgmental shovel tests is most efficient. Techniques employed in the assessment survey will vary depending on such factors as terrain, vegetation, land use, hydrology, and the locations where various types of cultural resources (archaeological and other) may be expected or predicted.
Where cultural resources are anticipated or evident on the surface, it is necessary to undertake some subsurface testing to more precisely delineate boundaries and, where necessary, to obtain sufficient information for preliminary site evaluation. Historic and cultural resources within the built environment should also be recorded, assessed, and evaluated. Testing of high, medium, and low probability zones should follow the guidelines for density and spacing as needed to meet any state standards in which the zone falls.
In the event that new archaeological sites are identified, either as a result of surface reconnaissance or subsurface testing, additional subsurface testing shall be carried out to determine site boundaries, horizontal and vertical extent(s), and cultural affiliation. Appropriate forms shall be completed for all new sites recorded and all previously recorded sites revisited, along with appropriate location and sketch maps as required by each state. Newly recorded sites and other resources will require new resource numbers, assigned by each state. Site and resource numbers should be assigned before completion and submittal of the draft report, and official site numbers should be used to reference resources.
The Contractor shall revisit and evaluate all previously recorded cultural resources within the project areas. Unless explicitly directed otherwise, Contractors are to consider and treat all previously recorded resources as newly recorded resources except during evaluation: all previously recorded resources shall be revisited, investigated, recorded, boundaries established, and content determined. Review of previous investigation data may inform methodology and shall be reviewed before field investigation, particularly to identify any resources that may contain human remains, for which unique methodologies should be established in coordination with the COR.
Archaeological sites shall be shovel tested as described below, and historic resources shall be sufficiently photographed, sketched, and/or recorded appropriate to type. In evaluating the resource(s), the results of previous investigations shall be described, cited, and incorporated into the evaluation and recommendation of significance and eligibility of the resource(s) for listing on the National Register of Historic Places. In no event is a previously recorded resource to be excluded from the investigation, either during fieldwork or in evaluation and report preparation, unless explicitly directed by the COR, which shall be referenced in the report.
The field assessment survey shall:
1) Identify and define areas of site and resource probability (where the potential for presence of cultural resources is low, medium, or high probability);
2) Conduct systematic subsurface archaeological investigation according to probability zones as determined by the probability model;
3) Identify new and previously documented cultural resources based on surface inspection and/or subsurface testing or assessment of historic resources, as appropriate to the resource type;
4) For archaeological sites, employ a systematic subsurface testing strategy consistent with the predicted probability model, supplemented where appropriate by judgmental subsurface testing, utilizing appropriate state standards for shovel tests all excavated soils screened through ¼-inch mesh, with the testing strategy and probability model updated according to field conditions;
5) Recover data allowing the Contractor to fully describe and define newly and previously identified resources within the project area as possible, including information on type, period(s) of occupation, and location. Both horizontal and vertical boundaries for archaeological sites with subsurface components shall be defined utilizing shovel tests include an assessment of any historic buildings or other historic structures or resources within the project area, including ditches and canals as appropriate;
6) Allow further predictions to be made about the distribution, density and potential significance of cultural resources within the general project study area.
Records shall be kept of the specific area(s) and method(s) of survey (surface inspection or subsurface testing), the content of each shovel test (soil type, color, etc.), and the precise location of all cultural resources that have been identified. Locations of subsurface testing shall be recorded with a GPS unit with at least sub-meter accuracy, and the UTMs for each testing location shall be recorded and reported along with testing results. “Writing off” of any shovel test locations due to disturbance is not acceptable; shovel tests shall still be conducted in disturbed areas, with vertical extent of disturbance recorded in field notes.
It is essential that the Contractor fully develop a probability model before beginning fieldwork in order to conduct fieldwork according to these requirements.
The field survey and Contractor must comply with Federal, State, and local laws and regulations.
If the Contractor encounters any problems in accessing any portions of the property, or if the Contractor encounters any other problems in the process of implementing contract requirements, the Contractor shall contact the COR and KO immediately to resolve the issues as quickly as possible.
The Contractor shall be responsible for identification and avoidance of all utilities, andshall be responsible for all impacts by the Contractor to any utilities.
Deliverables (see Technical Exhibit 2):
• Monthly monitoring updates (email).
• Executive Summary (email).
• Draft report (Five bound copies, and one electronic copy).
• Final report (Five bound copies, and one electronic copy).
5.4. Inadvertent Discoveries: N/A
5.5 Period of Performance: The POP is to parallel construction contracts for the JHK, but no longer than a total of four years. The Contractor will be required to meet with the COR and/or the KO to determine the work schedule upon NTP. This contract will be initially awarded for a total of 12 months (Base Year), with one additional 12 month option period awarded as Option
1. If Phase I archeological investigations are required as a result of the Corps requiring additional timber harvest areas to be investigated, this contract may be amended within the Base Year or Option Period to include additional timber harvest areas.
The schedule is as follows:
1) Development of probability model and determination of high probability zones.
2) Commence cultural resource survey to identify sites within the APE that are eligible or potentially eligible for listing in the NRHP.
3) The Contractor shall provide a monthly executive summary detailing activities and progress undertaken within the last calendar month. The executive summary can be transmitted electronically within seven days of the prior month’s activity.
4) Five hard copies and one electronic copy of the draft report shall be delivered to the COR within 90 days after survey is complete or after all Options have been executed, whichever comes first. If deemed acceptable by the Government, the draft report shall be used for SHPO and Tribal consultation.
5) Reviews of the draft reports will be provided to the Contractor within 60 calendar days after receipt of the draft report.
6) Five bound copies, and one electronic copy (on compact disc) of the final reports shall be delivered to the COR within 14 calendar days after receipt by the Contractor of the Government's review comments on the report draft. The electronic report copy shall include a copy the complete artifact catalog (compatible with Microsoft Excel).
5.5. Payment and Deliverables:
The Contractor shall assign a Contract Project Manager (CPM) to ensure that task budgets are being strictly adhered to and that deliverables are submitted to the Corps on time in accordance with the dates specified in the Payment and Deliverables Schedule. The PI and/or PM may be designated as the CPM.
The CPM shall be fully responsible for the performance of the Contractor’s team, including subcontractors, for this Work Order. Invoicing may be submitted to the COR after the completion of each task designated below, including any necessary updates and/or reporting that occurred during the task. Invoices shall include a breakdown of costs (time and materials) for each task and associated reporting.
Base Year Cultural Resource Survey of the following timber harvest areas Option 1 Cultural Resource Survey of the following timber harvest areas
At a minimum, associated deliverables within each option year shall include:
1) Weekly monitoring status reports e-mailed to the COR. These are expected to be brief status updates (areas worked and general results).
2) Monthly executive summary detailing monitoring activities and progress undertaken within the last calendar month. The executive summary shall be transmitted electronically within seven days of the prior month’s monitoring (one electronic .pdf copy).
3) ArcGIS shapefile(s) and feature class(es) with any sites and/or features, including boundaries of archaeological sites and other cultural resources identified during monitoring. Resources identified within a study area shall be represented in two ways: 1) shapefile(s) inclusive of all resources within the project area of that type (point, line, or polygon), AND 2) each individual resource shall be represented by a separate and unique shapefile for ease of transmission to SHPO. Note that no single resource shall contain multiple entries for boundary or location (e.g., multiple polygons representing a single site); for exceptions (e.g., networks of canals and ditches), discuss with COR in advance of submitting deliverables.
4) Completed site forms for all archaeological sites and historic resources recorded during the project, including the required topographic location and sketch maps; these shall be provided in both electronic format and hard copy, separate from their inclusion in the report.
5) Completed Survey Log and associated maps, in both electronic and hard copy, separate from inclusion in the report.
6) Five hard copies and one electronic copy of the draft monitoring report shall be delivered to the Wilmington District within 90 days after monitoring is complete or after all Options have been executed, whichever comes first. All information collected shall be compiled to produce a graphically illustrated, scientifically acceptable report which conforms to the Secretary of Interior’s Standards and Guidelines.
Information shall be presented in textual, tabular, and graphic forms, whichever is most appropriate, effective, and advantageous to communicate necessary information. All tables shall have a number, title, appropriate explanatory notes, and a source note. Oversize drawings or plates shall normally not have an image larger than 11 inches by 14 inches with sufficient margin for binding on the left side and shall have a graphic scale and a north arrow. No logos shall be used anywhere in the report. The draft report will be used for consultation.
Since Section 106 of the National Historic Preservation Act provides all of the consulting parties 30 days to review, the review period for the draft report is anticipated to take 60 days.
7) The Contractor shall address and/or incorporate any comments made by the Wilmington District, and any other reviewers designated by Wilmington District into the revised final report. The Final Report shall address and resolve the reviewer’s comments and shall be submitted
(along with a reproducible master copy of the original text, drawings, and plates) within 14 calendar days after receipt by the Contractor of the Government's review comments.
5.6 Inspection and Acceptance of Deliverables:
As work is in progress, any inspection of the work by the KO or her/his representative shall be solely at her/his option. All work, and all of the Contractor's office, equipment, and personnel engaged in the work, shall be subject to and available for inspection by the KO or her/his duly authorized representative (COR) upon receiving a two week notice of the inspection. The Corps’ Cultural Resources Manager may visit the field site at their individual discretion and without prior notice to the Contractor.
The COR will accept or reject the deliverables in writing. In the event of rejection of any deliverable, the Contractor will be notified in writing by the COR, giving the specific reason(s) for rejection. The Contactor shall have (5) working days to make corrections to the rejected deliverable(s) and resubmit to the COR.
Review and acceptance of delivered work will be the basis of final payment for the work. The Contractor shall be responsible for the professional quality and technical accuracy of the reports, maps, forms, logs, questionnaires, and other documents furnished under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in reports, maps, forms, logs, or questionnaires.
PART 6
APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
6.1. The Contractor shall abide by all applicable regulations, publications, manuals, and local policies and procedures including, but, not limited to, Secretary of the Interior's Standards and Guidelines for Archaeology and Historic Preservation, EM 385-1-1, Safety and Health Requirements Manual, dated 15 September 2008, and the American Antiquity Style Guide.
PART 7
ATTACHMENT/TECHNICAL EXHIBIT LISTING
7. Attachment/Technical Exhibit List:
7.1 Attachment 1/Technical Exhibit 1 – Performance Requirements
Summary
7.2 Attachment 2/Technical Exhibit 2 – Deliverables Schedule
7.3 Attachment 3/Technical Exhibit 3 – List Timber Harvest Areas by Option.
7.4 Attachment 4/Technical Exhibit 4 – Location of project area.
TECHNICAL EXHIBIT 1
Performance Requirements Summary The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective
(The Service required— usually a shall statement)
Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)
Method of Surveillance
PRS # 1.
Probability model and determination of high probability zones. (PWS 5.2)
Model and probability zones for testing will meet all state requirements for the location of the timber harvest area.
Zero deviation from standard.
Periodic review (weekly e-mail and monthly status summary reports, site visits, and review of draft report.
PRS # 2
Cultural Resource Survey (PWS 5.3)
Archaeological survey of timber deliverables will be conducted in accordance with the
PWS.
Zero deviation from standard.
Periodic review (weekly e-mail and monthly status summary reports, site visits, and review of draft report.
PRS # 3
Draft Report
(PWS 5.4)
Draft Cultural Resource Assessment Survey report in accordance with the PWS. This report will be sufficient for the Government to use in project planning and for consultation with the SHPO, Tribes, and other interested parties.
Minor revisions to a single draft report
Periodic review (weekly e-mail and monthly status summary reports, site visits, and review of draft report.
PRS # 4
Final Report
(PWS 5.5)
All comments made on the Draft Report will be adequately addressed.
No revisions needed.
Review of final report.
TECHNICAL EXHIBIT 2
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Form at Submit To
Probability model and determination of high probability zones
As Needed N/A Field inspection
Charles.A.Ope t@usace.army.
mil Chuck Opet
John H. Kerr Lake
1930 Mays Chapel Rd.
Boydton VA 23917
Status Report Monthly 1 Electronic
Charles.A.Ope t@usace.army.
mil Executive Summary
30 Days after survey work is complete or after Option has been executed, whichever comes first.
1 Electronic Charles.A.Ope t@usace.army.
mil
Draft Report 90 days after survey work is complete or after Option has been executed, whichever comes first.
6 5 hard copies 1 electronic
Charles.A.Ope t@usace.army.
mil Chuck Opet
John H. Kerr Lake
1930 Mays Chapel Rd.
Deliverable Frequency # of Copies Medium/Form at Submit To
Final Report 14 days following review
6 5 hard copies 1 electronic
Charles.A.Ope t@usace.army.
mil Chuck Opet
John H. Kerr Lake
1930 Mays Chapel Rd.
TECHNICAL EXHIBIT 3
List of Timber Harvest Areas by Option.
Base Year:
1. Westcare - 175 acres
2. Greenwood - 150 acres
3. Buffalo WMA - 60 acres
4. Keats Peninsula - 165 acres
5. Merifield WMA - 120 acres
6. Hwy 92 Steel Bridge - 65 acres
7. North Banister WMA - 79 acres
Option 1:
1. South Banister WMA - 64 acres
2. North Steel Bridge - 61 acres
3. Beaver Pond WMA - 48 acres
4. Voodoo - 30 acres
5. North Buffalo - 205 acres
6. Tuscarora - 129 acres
7. Cedar Grove WMA - 132 acres
TECHNICAL EXHIBIT 4
Locations and Acreage of Timber Harvest Areas.