LAS_LB_Industry Day Slides_18_20NOV2026.pdf
PDF 5 MB Posted
- Solicitation number
- W912PL27S0003
About this file
This document is a presentation from a US Army Corps of Engineers Los Angeles District Reverse Industry Day event held November 18-20, 2026, in Las Vegas and Long Beach, California.
The event introduced the military construction (MILCON) Other Transaction (OT) authority under 10 U.S.C. § 2808a and presented 15 planned projects across multiple fiscal years (FY27-FY30) valued between $10 million and $500 million. The initiative uses Progressive Design-Build (PDB) and Construction Management at Risk (CMAR) delivery methods to streamline project execution. Key projects include the Sentinel Re-Entry Vehicle Facility at Vandenberg Space Force Base ($100-250M, OTA-CMAR), Launch Support Infrastructure ($25-100M, OTA-PDB), Air Traffic Control Tower Fire Station Operations Facility ($100-250M, OTA-PDB), and Collaborative Combat Aircraft Hangar at Creech Air Force Base ($100-250M, OTA-PDB). The presentation emphasized that OT agreements avoid standard Federal Acquisition Regulation (FAR) compliance requirements including Competition in Contracting Act mandates, certified cost or pricing data submissions, Cost Accounting Standards, and Project Labor Agreement mandates, while remaining subject to Davis-Bacon labor law, OSHA safety requirements, environmental compliance, and payment/performance bonds. All contract terms are negotiable, and cost transparency uses "open book estimates" with living documents updated as design progresses. The document includes detailed program overviews, schedules for each project phase, and architectural renderings for select facilities. A draft solicitation for the RSRV Sentinel project with articles and white paper expectations was available for industry review and feedback.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Las Vegas Attendee List - 18NOV2026.pdf | ||
| Las Vegas Attendee List - 18NOV2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OTA Reverse Industry day
US Army Corps of Engineers Los Angeles District
18 & 20 NOV 2026
“Delivering Bold Solutions to Serve and Strengthen All Communities”
Agenda (Las Vegas)
• 0730 – 0830: Sign In, network, take seats
• 0830 – 0840: Commander's Welcome
• 0840 – 0845: Rules for Industry Day
• 0845 – 0930: OTA-PDB/CMAR & Open Book Est.
• 0930 – 0945: Break (Be seated by 0945)
• 0945 – 0955: Articles & OTA Process
• 0955 – 1020: RSRV Solicitation & Articles
• 1020 – 1030: Break (Be seated by 1030)
• 1030 – 1100: RSRV Pitch Presentations
• 1100 – 1105: Special Presentation
• 1105 – 1115: Break (Be seated by 1115)
• 1115 – 1200: General Q&A
• 1200 – 1330: Lunch
1330 – 1400: Program Brief 1400 – 1430: White Paper Expectations (thanks)
Breakout Room #1 (Chancellor Room)
• 1430 – 1630: Meet the Primes
Breakout Room #2 (Ambassador Room)
• 1430 – 1630: 1:1 OTA-PDB Industry Feedback
Sessions with USACE – By Invitation Only
• 1630 – 1700: Final Networking
• 1700: Adjourn, wrap up and clean up
Morning Session Afternoon Session
Agenda (Long Beach)
1330 – 1400: Program Brief 1400 – 1430: White Paper Expectations (thanks)
Breakout Room #1 (Large Room)
• 1430 – 1630: Meet the Primes
Breakout Room #2 (Classroom #1)
• 1430 – 1630: 1:1 OTA-PDB Industry Feedback
Sessions with USACE – By Invitation Only
Breakout Room #3 (Classroom #2)
• 1430 – 1630: 1:1 OTA-PDB Industry Feedback
Sessions with USACE – By Invitation Only
• 1630 – 1700: Final Networking
• 1700: Adjourn, wrap up and clean up
Morning Session Afternoon Session
• 0800 – 0900: Sign In, network, take seats
• 0900 – 0910: Director – LA Regional SBDC
• 0910 – 0920: Commander's Welcome
• 0920 – 0925: Rules for Industry Day
• 0925 – 0945:OTA-PDB/CMAR & Open Book Est.
• 0945 – 1000: Break (Be seated by 1000)
• 1000 – 1015: Articles & OTA Process
• 1015 – 1100: RSRV Solicitation & Articles
• 1100 – 1110: Break (Be seated by 1125)
• 1110 – 1125: RSRV Pitch Presentations
• 1125 – 1200: General Q&A
• 1200 – 1330: Lunch
Opening Remarks
RULES FOR REVERSE INDUSTRY DAY
• All information shared here today is Unofficial and Non-binding.
• Please hold your questions until the end of the presentation during the Q&A portion.
• Information shared in this briefing are for informational purposes only and shall not be construed as a commitment by the Government to solicit or award any requirement.
End-to-End Process for MILCON Projects
Thank you
Decision Gateway to Phase 2
• The USACE Los Angeles District has a requirement to build a new, highly-specialized cybersecurity training facility. Speed, innovation, and cost control are critical. Instead of a traditional, FAR based process, under 2808(a) authority, the Government utilizes an Other Transaction approach to compete, down-select to the top 3 firms, and selects design-build firm, “ABC Ltd.," to develop the project under a Progressive Design-Build model.
• The design-build firm, “ABC Ltd.,” was selected based on their superior qualifications and expertise, amongst qualified firms, not a low bid or proposal
6. Qualifications Based Selection
(QBS)
• Government Selects
Best Qualified Offeror
PRE-AGREEMENT: PLANNING, SOLICITATION, & AWARD
1. Project Requirements
• Mission Need
• Performance Objectives
• Industry Outreach /
Market Intelligence
• SCO OTA Approval
3. Statement of Qualifications
(SOQs)
• Industry Submits SOQs
• Government Evaluation
4. Down-Select
• Government
Selects Best Qualified Offers
• Invite Firms to Pitch Presentations
7. Negotiate OT (Phase 1) Services
• Scope of Ph 1 Design/ Preconstruction Services
• Performance Metrics
8. Award OT (Phase 1)
Agreement
• Award Other
Transaction Agreement
2. Request for Qualifications
(RFQ)
• Finalize Requirements
Package
• Industry Day / Notice
• Publish Solicitation
5. Pitch Presentations
• Offeror Presentations / Meetings / Interviews
• Q&A
• Site Visit, if applicable
Example Scenario
KICKOFF & ALIGNMENT SCHEMATIC DESIGN BUDGET LOCK DESIGN DEVELOPMENT DECISION GATEWAY TO
PHASE 2
AGREEMENT PHASE 1 – DESIGN & PRECONSTRUCTION SERVICES (OT Agreement using MILCON Design Funds)
PRECONSTRUCTION
READINESS
Risk Informed Project Alignment Meeting
• Goals & Objectives
• Risk Workshop
• Success Metrics
• Communication Plan
Concept Solutions
• Further Alternates
• Innovation Opportunities
• Risk Reduction
Schematic Design Development
• Develop Design
Concepts
• Evaluate Systems
• Confirm Approach
Budget Estimate Submission
• Level 3 Cost Estimate
• Cost Confidence Package
• Scope/Schedule Validation
Advance Design (Technical Development)
• Tailored Design
• Engineer Analysis
• Constructability Reviews
Integrated Schedule Development
• Long Lead Item Identification
• Resource Planning
Execution-Ready Integrated Solution
• Coordinate Estimate
• Constructability
• Risk Mitigation
Government Decision
• Scope Confirmed
• Cost Validated
• Risk Accepted
• Negotiate Phase 2:
Construction
Pre-Construction Work
• BCOES
• Permitting
• Early Submittals
• Site Readiness
Open Book Estimate / Price ScheduleOpen Book Estimate / Price Schedule
Switch to Firm-Fixed Price
OFF RAMP
DECISION POINT
OFF RAMP
DECISION POINT
AGREEMENT PHASE 1 – DESIGN & PRECONSTRUCTION SERVICES (OT Agreement using MILCON Design Funds)
ABC Ltd. begins with the SPLs initial concept design. At this stage, there is no fixed price for construction. Instead, the firm will present an initial "Open Book Estimate" that becomes a living document as the design progresses.
“The Green Line” Agreement Phase 1 – Design & Construction Services
An "open book estimate" for a Progressive Design-Build project is a transparent and collaborative pricing model.
Instead of the design-builder providing a single, fixed price (a "closed book"), the firm opens their financial records to the government.
The design-builder shares all cost information as the design progresses, including:
Direct Costs: All subcontractor bids, material supplier quotes, and labor rates.
Indirect Costs: Estimates for project management, field office overhead, and other general conditions.
Fee/Profit: A pre-negotiated and clearly defined fee, which can be a fixed amount or a percentage of the final construction cost.
This provides the Government with an understanding of key project's cost drivers and can work with the design-builder to make informed decisions
What is an open book estimate?
Example Project: SPL Cybersecurity Training Facility Estimate Version: 1.0 (Based on 30% Design) Date: 6 Oct 2026
Open Book Estimate – 30% Design
Basis of EstimateEstimated CostCost Category
1. Direct Construction Costs (Subcontractor & Materials)
Based on preliminary geotechnical report and historical data for similar sites.
$1,500,000Site Work & Utilities
Volumetric estimate based on initial massing model. High variability.
$4,000,000Concrete & Steel Structure
Allowance based on 2 concepts. Decision needed by 60% design review.
$2,500,000High-Performance Facade
System not yet selected. Estimate based on high-efficiency Variant Refrigerant Flow (VRF) system.
$3,500,000Specialized HVAC/Mechanical
High-risk item. Includes significant allowance for shielded cabling and redundant power. Needs input from SPL IT Security team.
$5,000,000Electrical & Data Infrastructure
Allowance pending detailed requirements from
SPL.
$2,000,000Security Systems (SCIF, etc.)
Allowance based on $/SF for similar training facilities.
$1,800,000Interior Finishes
High-Performance Facade: 2 Options presented: a pre-cast panel system and a modern metal-and-glass system. The design-builder shows the actual quotes for both, along with the pros and cons (energy performance, aesthetics, schedule). The SPL team, seeing the real costs, chooses the metal-and-glass system as the more cost-effective and accelerated schedule option, and the estimate is updated with that hard quote.
Electrical & Data Infrastructure: The design-builder facilitates a meeting between their electrical subcontractor and the SPL IT security experts.
Together, they refine the requirements for the shielded cabling. The subcontractor provides a detailed, updated quote based on this collaborative session. The "High-risk item" note is removed, as the scope is now clearly defined and cost is reduced.
Basis of EstimateEstimated Cost
Cost Category
1. Direct Construction Costs (Subcontractor & Materials)
Allowance based on 2 concepts. Decision needed by 60% design review.
$2,500,000High-Performance Facade
High-risk item. Includes significant allowance for shielded cabling and redundant power. Needs input from SPL IT Security team.
$5,000,000Electrical & Data Infrastructure
Open Book Estimate – 60% Design
Project Cost Limitation: The project has a budgetary limit of $19,600,000. The Open Book Estimate is showing $20,000,000, which is $400,000 over budget.
Cost reduction measures are employed.
Target Value Design: The updated estimate shows the project is tracking slightly over SPL’s initial budget. The entire team (FED, Design-Builder, Stakeholders) holds a workshop. They look at the "open book" and decide to change the interior finish specifications in non-critical areas from high-end to a more durable, mid-range option, saving approximately $400,000. The Target Value Design is now within budget at $19,600,000.
Basis of EstimateEstimated Cost
Cost Category
1. Direct Construction Costs (Subcontractor & Materials)
Allowance based on $/SF for similar training facilities.
$1,800,000Interior Finishes
Open Book Estimate – 60% Design
OTA Structure What to expect?
The Evolution of Authorities Strategic Role & Operational IntentPrimary Mission FocusStatutory Authority
The foundational authority. Used for dual-use technology exploration where commercial partners own the underlying intellectual property. It avoids FAR compliance to encourage early-stage innovation and collaborative R&D.
Basic, Applied, & Advanced Research10 U.S.C. § 4021 (Research OTs)
The primary tool for modern defense modernization. Authorizes physical or virtual prototype development. Crucially, successful completions can transition directly into non-competitive follow-on production agreements. Novel approach if for construction.
Prototype Projects & Production Transition10 U.S.C. § 4022 (Prototype OTs)
The New Frontier via 2026 NDAA.
Expands the OT model directly into military construction even when the construction methods being used are not novel or experimental.
Military Construction & Facility Modernization
10 U.S.C. § 2808a (MILCON OTs)
All Terms are Legally Negotiable
All Applicable Laws Still Apply
• Fiscal - Fiscal law / Anti-Deficiency Act compliance
• Criminal
• General Laws
What Laws Don’t Apply? - Procurement Specific Laws
OTA StatusTraditional FAR Contract RequirementStatute / Regulation
Does Not Apply . Agencies only need to compete the agreement "to the maximum extent practicable" using flexible, streamlined procedures .
Mandates "full and open competition" via rigid bidding tiers and formal Justifications & Approvals (J&As) .Competition in Contracting Act (CICA)
Does Not Apply . Negotiators are free to use commercial pricing terms, market research, or custom metrics .
Requires contractors to submit certified cost or pricing data during negotiations .Truthful Cost or Pricing Data Act (TINA)
Does Not Apply. Dispute resolution must be custom-negotiated and written directly into the OTA terms .
Mandates a highly structured, slow process for filing contractor claims and appeals.Contract Disputes Act (CDA)
Does Not Apply . Companies can use their existing commercial accounting systems instead of expensive government-compliant systems.
Dictates precise, rigid accounting rules for how companies measure and allocate costs .Cost Accounting Standards (CAS)
Does Not Apply. Intellectual property and data rights are fully negotiable from scratch .
Standardizes strict default rules giving the government licensing rights in technical data and software.Bayh-Dole Act & Rights in Technical Data
Not Applicable. Because the FAR does not govern OTs, the regulatory mandate for PLAs does not apply.
Mandatory for federal construction projects with an estimated value of $35 Million or more.Project Labor Agreements (PLA)
The OT Agreement
• How will it be formed?
• What is still applicable to construction that we used to have in our FAR-Base contracts?
• Who is involved?
• How long will it take?
Construction Laws Still Apply
• Davis-Bacon / applicable labor law compliance
• OSHA & EM 385-1-1 safety requirements
• Environmental compliance
(NEPA/UFC/installation standards)
• Payment & Performance bonds
• Security
What does it look like?
RSRV Sentinel DRAFT to Industry
• DRAFT Solicitation Review
• Articles (Attachment 3)
• Pitch Presentation for Shortlisted Firms (Attachment 2)
• White Paper Expectations (Attachment 1)
NOTE: White Paper Expectations will be reviewed at 1330hrs
OTA PROGRAM PRESENTATIONS
• Program Overview
• Sentinel Re-Entry Vehicle Facility
• Launch Support Infrastructure
• Air Traffic Control Tower Fire Station Operations Facility
• CCA Unit Ops and Hangar
• Disaster Resiliency Program Phase 4
• Mission Support Facility
• Warrior Fitness Center
• F-35 Data Lab
• CAF Next Gen Cyber Capabilities Center
• Human Performance Training and Aquatics Center
PROGRAM OVERVIEW
Aqc TypeNAICSFAR 36.204 /
DFARS 236.204
Range
TitleLocationProgServiceP2PY
OTA
CMAR236220$100-250MFY25 Sentinel Re-Entry Vehicle FacilityVandenberg SFBMILCONSF50957427 OTA-PDB236220$25-100MLaunch Support Infrastructure Vandenberg SFBMILCONSF58315028 OTA-PDB236220$100-250MATCT Fire Station Ops FacilityVandenberg SFBMILCONSF56854228 OTA-PDB236220$100-250MCollaborative Combat Aircraft (CCA) Unit Ops and HangarCreech AFBMILCONAF57566528 OTA-PDB236220$25-100MDisaster Resiliency Program Phase 4Creech/Grand Forks AFBOTHERAF58294528 OTA-PDB236220$25-100MMission Support FacilityCreech AFBMILCONAF50741029 OTA-PDB236220$25-100MWarrior Fitness FacilityCreech AFBMILCONAF50626129 OTA-PDB236210$25-100MADAL Corrosion Control B5255Davis Monthan AFBMILCONAF57150929 OTA-PDB237310$25-100MImprove Road and Infrastructure to SLC-9Vandenberg SFBMILCONAF800181229 OTA PDB 236220$250-500MICOE Headquarters and Training CenterFt HuachucaMILCONA57069330 OTA-PDB236220$25-100MConsolidated Human Performance Training Center/Aquatic Training CenterDavis Monthan AFBMILCONAF57124230 OTA-PDB236220$10-25M Fire Station 43Vandenberg SFBMILCONSF57683830 OTA-PDB236220$10-25M F-35 Data Lab Support FacilityNellis AFBMILCONAF57980430 OTA-PDB236220$25-100MNext Gen Cyber Capabilities CenterNellis AFBMILCONAF51032530 OTA-PDB236220$25-100MGila Bend Consolidated Crash Fire Rescue/ATCT/Base Ops FacilityLuke AFBMILCONAF56906030
SCHEDULE
• Design Instruction Q4 FY26
• RFQ Q1 FY27
• Phase 1 Agreement Q2 FY27
• Phase 2 Agreement Q4 FY27
Sentinel Re-Entry Vehicle Facility
FEATURES
• ~25ksf Facility, Industrial + Admin
• Vehicle Through Bay
• Processing Bays
• Post-Boost Altitude Control Module & Mass
Properties Maintenance Areas
• Multiple 5-ton Overhead Cranes
• ICD/ICS 705 Construction w/Shielding
SCOPE
Program Year: FY27 Type: OTA-CMAR
NAICS: 236220
FAR Range: $100M-$250M Location: Vandenberg SFB
• Design Instruction Q1 FY27
• RFQ Q2 FY27
• Phase 1 Agreement Q4 FY27
• Phase 2 Agreement Q3 FY28
Launch Support Infrastructure
FEATURES
• (3) Requirements Combined
• Telecommunication Lines South to North Base
• 3+ mi of Comm Horz Directional Drilling
• Improve Road and Infrastructure to SLC 5
• Utility & Transpo corridor improvements
• South base Entry Control Facility
• Inspection lanes, Inspection Shelter, Gatehouse, and
Overwatch Tower
SCOPE
Program Year: FY28 Type: OTA-PDB
NAICS: 237310
FAR Range: $25M-$100M
• Design Instruction Q1 FY27
• RFQ Q2 FY27
• Phase 1 Agreement Q4 FY27
• Phase 2 Agreement Q3 FY28
Air Traffic Control Tower Fire Station Operations Facility
FEATURES
• ~36ksf Facility
• Integrated Ops Center, Fire Station, and ATCT
• ~29ksf Multiple Facility Demolition
• +150ft Tall Tower
• Airfield Apron
SCOPE
Program Year: FY28 Type: OTA-PDB
NAICS: 236220
COLLABORATIVE COMBAT AIRCRAFT (CCA) HANGAR
FEATURES
• +65ksf Aircraft Maintenance Hangar w/AMU
• +500ksf Airfield Apron
• Demolition of Existing Hangar 726
• Backup Power
• Overhead Hangar Cranes
• ICD/ICS 705 Construction
• Aircraft Sunshades
SCHEDULE
• Design Instruction Q1 FY27
• RFQ Q2 FY27
• Phase 1 Agreement Q4 FY27
• Phase 2 Agreement Q2 FY28
SCOPE
Program Year: FY28 Type: OTA-PDB
NAICS: 236220
Location: Creech AFB
DISASTER RESILIENCY PROGRAM PHASE 4
• Improvements/Expansion to Existing LOLA, M&I, and Storage Facilities - Creech
• New LOLA Construction, Improvements/Expansion to Existing M&I and Storage Facilities–Grand Forks
• Aircraft Shade Structures
• Airfield Pavements
• ICD/ICS 705 Construction
SCHEDULE
• Design Instruction Q1 FY27
• RFQ Q2 FY27
• Phase 1 Agreement Q4 FY27
• Phase 2 Agreement(s) Q3 FY28
SCOPE
Program Year: FY28 Type: OTA-PDB
NAICS: 236220
Location: Creech & Grand Forks AFBs
MISSION SUPPORT FACILITY
• +36ksf Office Admin Facility
• Central Facility for Mission Support and Force Support Squadron Functions
• Manpower, Finance, Airmen/Family Readiness
• Auditorium Space
• AP Portion of Facility will be ICD/ICS 705
Construction
SCHEDULE
• Design Instruction Q1 FY27
• RFQ Q3 FY27
• Phase 1 Agreement Q2 FY28
• Phase 2 Agreement(s) Q1 FY29
SCOPE
Program Year: FY29 Type: OTA-PDB
NAICS: 236220
WARRIOR FITNESS FACILITY
• Weight Room
• (2) Basketball & Racquetball Courts
• Class Exercise Rooms
• Second Floor 1/8mi Running Track
• Admin Areas
SCHEDULE
• Design Instruction Q1 FY27
• RFQ Q3 FY27
• Phase 1 Agreement Q2 FY28
• Phase 2 Agreement(s) Q1 FY29
SCOPE
Program Year: FY29 Type: OTA-PDB
NAICS: 236220
F-35 DATA LAB
• +10ksf Secure Space Facility
• Server Room
• Lab and Clean Room Spaces
• ICD/ICS 705 Construction
• Admin Areas
SCHEDULE
• Design Instruction Q2 FY27
• RFQ Q3 FY27
• Phase 1 Agreement Q1 FY28
• Phase 2 Agreement(s) Q1 FY30
SCOPE
Program Year: FY30 Type: OTA-PDB
NAICS: 236220
FAR Range: $10M-$25M Location: Nellis AFB
CAF NEXT GEN CYBER CAPABILITIES CENTER
• +22ksf Facility
• Demolition of Bldg 595
• CITBN Server and Vault, Primary Base POP
• Admin, Conference, and Multi-Purpose Spaces
SCHEDULE
• Design Instruction Q2 FY27
• RFQ Q3 FY27
• Phase 1 Agreement Q1 FY28
• Phase 2 Agreement(s) Q1 FY30
SCOPE
Program Year: FY30 Type: OTA-PDB
NAICS: 236220
Location: Nellis AFB
CONSOLIDATED HUMAN PERFORMANCE TRAINING & AQUATIC
CENTER
FEATURES
• +32ksf Human Performance Training Center
• ~20ksf Aquatic Training Center
• ~2ksf Covered Storage
• Dive Simulator
• Offices
• Classrooms
• Exterior Multipurpose Training Area
SCHEDULE
• Design Instruction Q2 FY27
• RFQ Q3 FY27
• Phase 1 Agreement Q1 FY28
• Phase 2 Agreement(s) Q1 FY30
SCOPE
Program Year: FY30 Type: OTA-PDB
NAICS: 236220
Location: Davis Monthan AFB
RSRV Sentinel DRAFT to Industry
• DRAFT Solicitation Review
• Articles (Attachment 3)
• Pitch Presentation for Shortlisted Firms (Attachment 2)
• White Paper Expectations (Attachment 1)
Questions & Thank You
Thank you for your interest in USACE Projects and we look forward to your input!