AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 3
0001 13 April 2010
W912PL
CONTRACTING DIVISION
P.O. BOX 532711
LOS ANGELES, CA 90053-2325
SEE ITEM 6
W912PL-09-R-0053
26 March 2010
Replace page 00110-4 of Section 00110 and 00120-4 of Section 00120.
The first sentence of the Tab # 1 Factor #1 description shall read: "Offeror shall identify a minimum of two or more (2) Design Build and one or more (1) Design-Bid-Build projects of a similar scope, dollar minimum magnitude of $5,000,000.00 and complexity it has successfully completed within the past five years."
00110-4 Amendment 0001
TAB #1
FACTOR 1: EXPERIENCE ON SIMILAR DESIGN BUILD
AND DESIGN-BID-BUILD CONTRACTS, SPECIFICALLY
CONSTRUCTION INCLUDING BUT NOT LIMITED TO
OFFICE BUILDINGS, HANGERS, FACILITIES,
UNMANNED AERIAL SYSTEMS, FLIGHT SIMULATORS,
WING HEADQUARTERS, AND OTHER CONSTRUCTION
SUBFACTOR NO. 1a: Design and Construction Processes SUBFACTOR NO. 1b: Construction Safety Methods
TAB #2 FACTOR 2: TECHNICAL APPROACH, METHODS AND
PROCEDURES
TAB #3
FACTOR 3: PAST PERFORMANCE ON SIMILAR
CONTRACTS, SPECIFICALLY CONSTRUCTION
INCLUDING BUT NOT LIMITED TO OFFICE BUILDINGS,
HANGERS, FACILITIES, UNMANNED AERIAL SYSTEMS,
FLIGHT SIMULATORS, WING HEADQUARTERS, AND
OTHER CONSTRUCTION
TAB #4
FACTOR 4: CORPORATE/MANAGEMENT STRUCTURE
SUBFACTOR NO. 4a: Capability to Manage & Control Project SUBFACTOR NO. 4b: Key Personnel SUBFACTOR NO. 4c: Offeror’s Workload SUBFACTOR NO. 4d: Offeror’s succession plan
(a) Detailed Submission Requirements for the Technical Proposal: Submit detailed response to the evaluation factors under each of the tabs as follows:
TAB #1 FACTOR 1: EXPERIENCE ON SIMILAR DESIGN BUILD AND DESIGN-BID-
BUILD CONTRACTS, SPECIFICALLY CONSTRUCTION INCLUDING BUT NOT
LIMITED TO OFFICE BUILDINGS, HANGERS, FACILITIES, UNMANNED AERIAL
SYSTEMS, FLIGHT SIMULATORS, WING HEADQUARTERS, AND OTHER
CONSTRUCTION
Offeror shall identify a minimum of two or more (2) Design Build and one or more (1) Design- Bid-Build projects of a similar scope, dollar minimum magnitude of $5,000,000.00 and complexity it has successfully completed within the past five years. Provide a description of the project, total dollar value of the contract at the time of award and at the time of completion, the completion date of the award and the name, address and telephone number of the client. In the case of a federal, state or local government project, provide the name, address, and telephone number of the contracting officer. Offeror may include projects completed by predecessor companies.
SUB-FACTOR NO. 1a, DESIGN and CONSTRUCTION PROCESSES. This sub-factor will be evaluated on the basis of demonstrated knowledge and experience performing Design Build and Design-Bid-Build projects requiring design and construction requirements.
00120-4 Amendment 0001 other impacts on the evaluation.
Material omission(s) may cause the technical proposal to be rejected as unacceptable.
(b) The adjectival rating, of the Technical Proposal may be negatively affected if the specified information is not provided in the specified location in accordance with the submission instructions in Section 00 01 10.
(c) The adjectival rating of the Technical Proposal may be negatively affected if the proposals are generic, vague, or lacking in detail.
(d) The degree of risk to the Government inherent in the offerors technical proposal will be a consideration under this factor.
(e) The Government may consider a proposal based on a deficient offer if the Government elects to enter into discussions with offerors and all deficiencies are remedied in revised proposals.
I. LIST OF EVALUATION FACTORS, SUB-FACTORS AND SPECIFIC TECHNICAL
EVALUATION CRITERIA
In order to be considered technically acceptable, technical proposals must meet the following minimum requirements:
TAB #1 FACTOR 1: EXPERIENCE ON SIMILAR DESIGN BUILD AND DESIGN-BID-
BUILD CONTRACTS, SPECIFICALLY CONSTRUCTION INCLUDING BUT NOT
LIMITED TO OFFICE BUILDINGS, HANGERS, FACILITIES, UNMANNED AERIAL
SYSTEMS, FLIGHT SIMULATORS, WING HEADQUARTERS, AND OTHER
CONSTRUCTION
Offeror shall identify a minimum of two (2) or more Design Build and one or more (1) Design- Bid-Build projects of a similar scope, dollar minimum magnitude of $5,000,000.00 and complexity it has successfully completed within the past five years. Provide a description of the project, total dollar value of the contract at the time of award and at the time of completion, the completion date of the award and the name, address and telephone number of the client. In the case of a federal, state or local government project, provide the name, address, and telephone number of the contracting officer. Offeror may include projects completed by predecessor companies.
SUB-FACTOR NO. 1a, DESIGN and CONSTRUCTION PROCESSES. This sub-factor will be evaluated on the basis of demonstrated knowledge and experience performing Design Build and Design-Bid-Build projects requiring design and construction requirements.
SUB-FACTOR NO. 1b, CONSTRUCTION SAFETY METHODS. This sub-factor will be evaluated on the basis of demonstrated successful performance of Design Build and Design-Bid-Build projects while employing safety protocols.
Standard for Acceptability: This standard is met when the Offeror can identify two (2) or more completed Design Build and one (1) or more completed Design-Bid-Build
| W912PL-09-R-0053 Amendment 0001.pdf |
| SF30 |
| Section 00650 Wage Rates |
| Section 00100.pdf |
| 52.0000-4010 INQUIRIES |
| 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998) |
| 52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION INFORMATION SYSTEM (ASSIST) (JAN 2006) |
| 52.211-4 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) |
| 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991) |
| 52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991) |
| 52.0214-4583 TELEGRAPHIC BIDS/OFFERS ARE NOT ACCEPTABLE |
| 52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004) |
| 52.0215-5001 DIRECTIONS FOR SUBMITTING OFFERS (MAR 2002) |
| 52.216-1 TYPE OF CONTRACT (APR 1984) |
| 52.217-5 EVALUATION OF OPTIONS (JUL 1990) |
| 52.225-11 BUY AMERICAN ACT --CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (AUG 2007) ALTERNATE I (AUG 2007) |
| 52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT-- CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (JAN 2005) ALTERNATE II (AUG 2007) |
| 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008) |
| 52.228-4507 BID GUARANTEE FORM AND AMOUNT |
| 52.232-38 SUBMISSION OF ELECTRONIC FUNDS TRANSFER INFORMATION WITH OFFER (MAY 1999) |
| 52.233-2 SERVICE OF PROTEST (SEP 2006) |
| 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995) |
| 52.236-28 PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997) |
| 252.247-7022 REPRESENTATION OF EXTENT OF TRANSPORTATION BY SEA (AUG 1992) |
File details come from the government source that posted it. Updated .