Lake ONeill Dredging_Bid Abstract_W912PL-09-B-0005.pdf
PDF 18 KB Posted
- Solicitation number
- W912PL-09-B-0005
About this file
_Bid Abstract
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AM04.pdf | ||
| Am03.pdf | ||
| Lake O'Neill sign-in sheet for Pre-Bid Walk of10 Sep 2009.PDF | ||
| Am2.pdf | ||
| Am01.pdf | ||
| W912PL-09-B-0005_Spec.pdf | ||
| W912PL-09-B-0005_Attachments.pdf | ||
| W912PL-09-B-0005_Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CJW Construction $5,984,680
JND Thomas Co., Inc $8,184,937 Furby Construction Co., Inc $8,777,700 Cutting Edge Concrete Services $9,330,710
Government Estimate $8,429,976
Summary of Bids
Number of Amendments: 4
BID ABSTRACT
IFB W912PL-09-B-0005
Lake O'Neill Dredging and Recharge Pond Rehabilitation
San Diego County, CA
HUBZone Set-Aside
Marine Corps Base - Camp Pendleton
23 September 2009
Bid Opening Date: 9/23/09
CJW Construction, Inc.
841 East Washington Avenue, Suite B Santa Ana, CA 92701
1 Mobilization and Demobilization 1 Job Lump Sum $584,000.00
2 Clear & Grub Ponds 4 -7 & Settling Pond Preparation 1 Job Lump Sum $150,000.00
3 Material Excavation from Ponds 4 - 7 257,000 Cubic Yards $4.00 $1,028,000.00
4 Re-Handling of Excavated Material 257,000 Cubic Yards $0.01 $2,570.00
5 Final Construction of Pond 6 & 7 Levee 147,000 Cubic Yards $3.00 $441,000.00
6 Install 30-inch CMP Culverts 6 Each $4,000.00 $24,000.00
7 Place Crushed Rock on Levee 1,700 Ton $65.00 $110,500.00
8 Rip Rap Placement 2 Ton $500.00 $1,000.00
9 Dredge Lake O'Neill 361,000 Cubic Yards $10.00 $3,610,000.00
10 Re-Handle Dredge Material 361,000 Cubic Yards $0.01 $3,610.00
11 SWPPP Development and Compliance 1 Job Lump Sum $20,000.00
12 Temporary Water Delivery 1 Job Lump Sum $10,000.00
$5,984,680.00
Unit Price Total Amount
Total Bid Amount
Item # Description Estimated Quantity
Unit of Measure
W912PL-09-B-0005
4 Amendments
San Diego County, California
Lake O'Neill Dredging and Recharge Pond Rehabilitation Marine Corps Base - Camp Pendleton
JND Thomas Co., Inc 22052 W Everett Riverdale, CA 93656
1 Mobilization and Demobilization 1 Job Lump Sum $647,759.00
2 Clear & Grub Ponds 4 -7 & Settling Pond Preparation 1 Job Lump Sum $65,790.00
3 Material Excavation from Ponds 4 - 7 257,000 Cubic Yards $1.64 $421,480.00
4 Re-Handling of Excavated Material 257,000 Cubic Yards $4.94 $1,269,580.00
5 Final Construction of Pond 6 & 7 Levee 147,000 Cubic Yards $1.29 $189,630.00
6 Install 30-inch CMP Culverts 6 Each $5,336.00 $32,016.00
7 Place Crushed Rock on Levee 1,700 Ton $27.51 $46,767.00
8 Rip Rap Placement 2 Ton $1,900.00 $3,800.00
9 Dredge Lake O'Neill 361,000 Cubic Yards $5.09 $1,837,490.00
10 Re-Handle Dredge Material 361,000 Cubic Yards $8.81 $3,180,410.00
11 SWPPP Development and Compliance 1 Job Lump Sum $222,860.00
12 Temporary Water Delivery 1 Job Lump Sum $267,355.00
$8,184,937.00
W912PL-09-B-0005
Marine Corps Base - Camp Pendleton San Diego County, California
Total Bid Amount
4 Amendments
Item # Description Estimated Quantity
Unit of Measure Unit Price Total
Furby Construction Co., Inc.
801 Civic Center Drive National City, CA 91950
1 Mobilization and Demobilization 1 Job Lump Sum $1,500,000.00
2 Clear & Grub Ponds 4 -7 & Settling Pond Preparation 1 Job Lump Sum $259,900.00
3 Material Excavation from Ponds 4 - 7 257,000 Cubic Yards $5.10 $1,310,700.00
4 Re-Handling of Excavated Material 257,000 Cubic Yards $1.00 $257,000.00
5 Final Construction of Pond 6 & 7 Levee 147,000 Cubic Yards $3.00 $441,000.00
6 Install 30-inch CMP Culverts 6 Each $2,500.00 $15,000.00
7 Place Crushed Rock on Levee 1,700 Ton $35.00 $59,500.00
8 Rip Rap Placement 2 Ton $1,300.00 $2,600.00
9 Dredge Lake O'Neill 361,000 Cubic Yards $5.00 $1,805,000.00
10 Re-Handle Dredge Material 361,000 Cubic Yards $7.00 $2,527,000.00
11 SWPPP Development and Compliance 1 Job Lump Sum $300,000.00
12 Temporary Water Delivery 1 Job Lump Sum $300,000.00
$8,777,700.00
Marine Corps Base - Camp Pendleton San Diego County, California
Unit of
Cutting Edge Concrete Services, Inc.
18020 National Trails Hwy. PO Box 398 Oro Grande, CA 92368
1 Mobilization and Demobilization 1 Job Lump Sum $575,000.00
2 Clear & Grub Ponds 4 -7 & Settling Pond Preparation 1 Job Lump Sum $165,000.00
3 Material Excavation from Ponds 4 - 7 257,000 Cubic Yards $3.75 $963,750.00
4 Re-Handling of Excavated Material 257,000 Cubic Yards $4.57 $1,174,490.00
5 Final Construction of Pond 6 & 7 Levee 147,000 Cubic Yards $3.50 $514,500.00
6 Install 30-inch CMP Culverts 6 Each $6,000.00 $36,000.00
7 Place Crushed Rock on Levee 1,700 Ton $45.00 $76,500.00
8 Rip Rap Placement 2 Ton $500.00 $1,000.00
9 Dredge Lake O'Neill 361,000 Cubic Yards $10.70 $3,862,700.00
10 Re-Handle Dredge Material 361,000 Cubic Yards $4.57 $1,649,770.00
11 SWPPP Development and Compliance 1 Job Lump Sum $97,000.00
12 Temporary Water Delivery 1 Job Lump Sum $215,000.00
$9,330,710.00
Marine Corps Base - Camp Pendleton San Diego County, California
Unit of
Government Estimate
1 Mobilization and Demobilization 1 Job Lump Sum $126,432.00
2 Clear & Grub Ponds 4 -7 & Settling Pond Preparation 1 Job Lump Sum $41,378.00
3 Material Excavation from Ponds 4 - 7 257,000 Cubic Yards $2.87 $737,590.00
4 Re-Handling of Excavated Material 257,000 Cubic Yards $2.87 $737,590.00
5 Final Construction of Pond 6 & 7 Levee 147,000 Cubic Yards $6.32 $929,040.00
6 Install 30-inch CMP Culverts 6 Each $1,609.00 $9,654.00
7 Place Crushed Rock on Levee 1,700 Ton $69.00 $117,300.00
8 Rip Rap Placement 2 Ton $920.00 $1,840.00
9 Dredge Lake O'Neill 361,000 Cubic Yards $7.47 $2,696,670.00
10 Re-Handle Dredge Material 361,000 Cubic Yards $8.05 $2,906,050.00
11 SWPPP Development and Compliance 1 Job Lump Sum $68,963.00
12 Temporary Water Delivery 1 Job Lump Sum $57,469.00
$8,429,976.00
Marine Corps Base - Camp Pendleton San Diego County, California
Unit of
| Summary |
| CJW |
| JND Thomas |
| Furby |
| Cutting Edge |
| Government estimate |