Revised Performance Work Statement

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

MAINTENANCE AND REPAIRS OF

ELECTRICAL, MECHANICAL AND SAFETY

CONTROL SYSTEMS OF AUTOMATIC

GATES IN THE USAG-ITALY, DMC AREAS

23 August 2016

Rev#1 dated 21 September 2016

TABLE OF CONTENTS

SECTION PARAGRAPH TITLE

I DESCRIPTION OF SERVICES

1.1. Scope of Work

1.2. Location of Services

1.3. Hours of Operation

1.4. Absences (Reserved)

1.5. Confidentiality (Reserved)

1.6. General Contract Services

1.7. Specific Tasks

1.8. Conduct

1.9. Payments

1.10. Safety

1.11 Contractor Manpower Reporting (CMR)

II SERVICE DELIVERY SUMMARY

III GOVERNMENT-FURNISHED PROPERTY & SERVICES

3.1 General Information (Reserved)

3.2 Government-Furnished Property (Reserved)

3.3 Contractor-FurnishedProperty

3.4 Government-Furnished Services (Reserved)

3.5 Government Provided Training (Reserved)

IV GENERAL INFORMATION

4.1. Contractor Qualifications

4.2. Contractor Personnel

4.3. Quality Control

4.4. Quality Assurance

4.5. Physical Security

4.6. Hours of Operation

4.7. Conservation of Utilities (Reserved)

4.8. Records

V TECHNICAL EXHIBITS

5.1 Workload Estimates

5.2 Publications & Forms

5.3

5.4 Required Reports Map

SECTION I

DESCRIPTION OF SERVICES

1.1. SCOPE OF WORK: Contractor shall perform the inspection; maintenance and repair on n. 15 automatic (entrance and exit) gates end two barriers and one turnstile in the USAG-ITALY, DMC Areas.

1.2. LOCATION OF SERVICES: Service shall be performed in all USAG-ITALY, DMC installation.

1.3. HOURS OF OPERATION: The normal working hours shall be from 8:00-17:00, Monday through Friday excluding Italian and U.S. Federal Holidays.

1.4. ABSENCES: RESERVED

1.5. CONFIDENTIALITY: RESERVED

1.6. GENERAL CONTRACT SERVICES: The Contractor shall accomplish the following in conjunction with the specific contract services detailed herein:

a. Contractor shall report immediately any serious incident (e.g. accidents, abuse of Government property) to the COR.

b. Contractor shall perform the service specified by these specifications in strict compliance with ISPESL (Superior Accident Prevention and Job Security Institute) standards, CEI (Italian Electrical Committee) standards Law 626 and 464.

c. All the work phases for the inspection, maintenance and repair shall be accomplished in accordance with using methods and recommendation in conformity to the machinery directive 98/37/CE and all current European EN 13241-1, EN 12453, EN 12978 and EN 12445 and USA military standards & regulations.

d. The Contractor shall furnish all labor, equipment, supervision and transportation necessary for performance of the service called by these specifications.

e. For a correct bid preparation, it is advisable that the contractors conduct a preliminary visit so that the project data may be verified and workload problems evaluated from an objective standpoint.

f. AT Level I Training. All contractor employees, including subcontractor employees, requiring access to

Army installations, facilities, and controlled-access areas will complete AT Level I awareness training within 30 calendar days after the contract start-date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor will submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, prior to issuance of Installation Access Passes. AT Level I awareness training is available online at https://atlevel1.dtic.mil/at.

According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.

g. Access and General Protection/Security Policy and Procedures: The Contractor shall obtain entry passes for each employee from the COR. The Contractor shall inform his personnel that they may be subjected to search when entering or leaving the installation at the discretion of the Installation Commander. Upon completion of the contract work or upon employee termination the Contractor shall return all passes to the Contracting Officer or the COR. Contractor and all associated sub-contractors’ employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshall Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

h. Contractor Identification: Prior to commencement of contract performance, the Contractor shall furnish the COR in writing and in triplicate, a list of the personnel identified for work under the contract.

The list shall contain:

a. Name and address of each employee.

b. Identification Document or driving license number of each employee.

c. Copy of personnel register.

d. “Centro per l’impiego” Identification Document

e. The contractor shall furnish a list of private and commercial vehicles which will be used in conjunction with contract work. The list shall be submitted together with the list of personnel and shall contain:

1. Make of vehicle;

2. Model and year of manufacture; and

3. License Plate Number.

i. iWATCH Training: The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 15 calendar days of contract award and within 10 calendar days of new employees commencing performance with the results reported to the COR NLT 10 calendar days after contract award.

1.7 SPECIFIC TASKS

1.7.1 Contractor shall provide all the necessary labor, equipment and transportation, except as otherwise provided the following specific tasks to maintain the below listed automatic gates:

LIST OF THE AUTOMATIC GATES

GATE# 9 AMMO AREA - This gate consists of:

a. One gate with engine “FAAC 844T”

b. Pedestrian Rotating Gate, ARITEC Mfg.

c. Automatic barrier DELTA Scientific Mfg.

GATE # 4 CAMP DARBY - This gate consists of:

a. Double gates “ entrance” with engine FAAC 884 and “ exit” with engine FAAC Mfg.

AUTO CRAFT # CAMP DARBY - This gates consists of:

a. Double gates “ entrance” and “ exit” with engines FAAC Mfg 220volt.

b. One entrance gates with engines FAAC Mfg 220volt.

GATE # 27 DEPOT - This gate consists of:

a. Double gates “entrance” and “exit” with engines FAAC Mfg.

GATE # 28 DEPOT - This gate consists of :

a. Double gates with engine FAAC Mfg.

GATE# 29 DEPOT - This gate consists of:

a. One gate with engine FAAC Mfg.

GATE# for 5150 - This gate consists of:

a. One gate north side FAAC 740

b. One gate west side FAAC 740

c. One gate south side “engine arms FAAC

GATE# for 5881 - This gate consists of:

d. Gates “entrance/ exit” with engine Elbox Mfg.

e. Turnstile GUNNEBO ENTRANCE CONTROL

CARABINIERI This gate consist of:

a. Barrier FAAC Mfg.

1.7.2. PLANNED WORK SCHEDULE

The Contractor shall submit a planned work schedule to COR for approval within (10) calendar days after contract award date. Reference CDRL 0004 under exhibit 5.3 of this PWS for further direction on submission.

1.7.3. LOG BOOK.

The contractor shall built and provide to the COR a log book for each automatic gate system.

Requirements for a Log Book:

BS EN 12635 requires that the log book shall contain the following:

- name and contact details of the manufacturer

- unique identification number

- door location reference

- name and contact details of the installer

- date of completion of installation

- the results of installation verification and testing

- identification of power unit

- identification of safety devices

- the results

On an ongoing basis, there should be space for the recording of:

- all maintenance and repair visits

- details of the work done

- details of significant changes or upgrades

- name, date and signature of responsible person in each instance

1.7.4. Semi-Annual Inspection and Maintenance.

For each automatic sliding system, the Contractor shall perform an inspection using methods and recommendation showed in the applicable normative and manufacture instructions.

During the inspection the contractor shall verify the integrity of all gates evaluating the operation condition and if they meet applicable and current European and USA military safety standards, laws and manufacture instructions.

All discrepancies or impairments for each Gate discovered during the semi-annual inspection shall be reported in the Log Book and planned with the Contracting Officer Representative (COR) for correction and/or modifications.

Maintenance includes but is not limited to, inspection and test of all mechanical and electrical parts, cleaning and lubrication of the sliding metal parts, fixing the transparent board sheets and safety devices, inspecting and testing the surge protective devices, Bus, grounding and all electrical parts, cleaning of the grounding connections, brushing all rusted bolts and cleaning of all manholes.

1.7.5. Scheduled and repair/replacement work:

The Contractor shall submit an estimate offer for the repair works. The COR shall verify the offer and shall forward it to the KO for approval and negotiation of the offer submitted by contractor.

The Contractor shall submit their Proposal for scheduled repairs within five working days from COR’s request.

The list of all material to be purchased and relative price list with discount will be submitted together with the repair estimate.

Each works performed during the repairs shall be recorded in the log book.

1.7.6. Emergency Repair

Emergency repairs shall be performed as soon as possible and in no case the technician should arrive in more than one working day after the emergency notification; after the estimation or bid should be provided in writing for review, negotiation and approval.

An estimate is not required for all immediate emergency repair works requested by KO. The repair works shall be completed within (4) four hours unless otherwise approved by COR. If, additional works are required to complete the emergency repair, the cost of man-hours spent for the emergency repair shall be included in the emergency repair invoice, otherwise the cost shall be invoiced.

Each works performed during the emergency repairs shall be recorded in the log book.

1.7.7. Reports. The contractor shall submit a documented report to the COR on all automatic gates system’s inspection and, maintenance work, noting discrepancies, system impairments and recommendations, within (5) calendar days after inspection. Reference CDRL 0001 under exhibit 5.3 of this PWS for further direction on submission. The written reports shall be provided in technically correct & understandable Italian and English languages. The contractor whit the COR shall review the inspection results and maintenance status of automatic gate systems included in this contract.

1.7.8. Materials required for scheduled and repair/replacement work

All materials which are reasonably used frequently such as: screws, bolts, nuts, clamps, electric wires, gear lubricant, etc shall be considered items required to accomplish the maintenance work and shall be furnished by the Contractor at no additional cost to the Government.

All Materials for repair works should be by price list with mentioned a percentage of discount as per contract award. If the Contractor shall replace a spare parts not included in the contract price list, a copy of the supplier’s relative price list or invoice will be provided to COR.

1.8. CONDUCT: The Contractor shall:

Wear a name tag (provided at Contractor cost) identifying her/himself as a Contractor, and ensure that in all correspondence the Contractor identifies her/himself as a Contractor.

1.9. PAYMENT: The Contractor will submit invoices to the COR who will certify that the services were provided and submit the invoice to the Finance Office for payment.

1.10. SAFETY: The Contractor shall be aware of local safety requirements and ensure that all reasonable efforts are made to protect all persons from harm and U.S. Government property from damage.

1.11. CONTRACTOR MANPOWER REPORTING (CMR) (CLIN 7500): The Contractor is responsible for providing input into the CMR system in accordance with the information provided herein. The Contractor is required to report all Contractor manpower required for the performance of this contract. The Contractor is required to completely fill in all the required fields in the reporting system using the following web address: https://cmra.army.mil/. The requiring activity will assist the Contractor with the reporting requirement as necessary. The Contractor may enter reports at any time during the reporting period, which is defined as the period of performance not to exceed 12 months ending 30 September of each Government fiscal year. Reporting must be completed no later than 31 Oct for every year or part of a year for which the contract is in place. Failure to comply with this reporting requirement will result in contract termination.

Contractor shall notify the COR in writing on the last business day of October of each year with status of the CMR compliance or non-compliance via E-mail. Reference CDRL 0002 under exhibit 5.3 of this PWS for further direction on submission.

SECTION II

SERVICE DELIVERY SUMMARY

REQUIRED SERVICE PWS

PERFORMANCE

STANDARD

SURVEILLANCE

PERFORMANCE

COMPLIANCE

REMEDIES

Inspections, Operational Tests, Preventive, and Corrective Maintenance of automatic Gates Systems

1.6 1.7.3 1.7.4

Automat Gate systems shall be fully operational at 99% of the time Operational tests are performed and recorded.

Discrepancies are noted.

Repairs are made when necessary and recorded in the log book.

Verification on Site (The COR will perform an inspection on each Gate after maintenance)

100% IAW CEI;

ISPESL; 46/90

100% IAW CEI;

ISPESL; 46/90

Machinery Directive

98/37/CE

European

EN 13241-1

EN 12453

EN 12978

EN 12445

and USA military standards & regulations

Withholding of payment until performance is completed and in compliance

Repair

1..6 1.7.5 1.7.6.

Performance to contract standard Repairs are completed within (4) four hours unless otherwise approved by Contracting Officer Representative

(COR).

100% Inspections

100% IAW CEI;

ISPESL; 46/90

100% IAW CEI;

ISPESL; 46/90

Machinery Directive

98/37/CE

European

EN 13241-1

EN 12453

EN 12978

EN 12445

and USA military standards & regulations

Withholding of payment until performance is

Reports

1.7.3

The report shall be provide to the COR and included in the log book within a working day unless otherwise approved by Contracting Officer Representative

(COR).

Verification

Every certifications Automatic gates systems shall be performed in accordance with

100% PWS

15% Withholding of payment until

Quality Control

4.3

Performance to

Verification

100% PWS

Withholding of 15% from each semi

Plan contract standard annual payment until

SECTION III

GOVERNMENT FURNISHED PROPERTY AND SERVICES

3.1. GENERAL INFORMATION. Reserved.

3.2. Reserved.

3.3. CONTRACTOR FURNISHED PROPERTY (CFP). The Contractor shall provide her/his own transportation and all necessary equipment includes portable toilets, electrical generator, portable lights sufficient to fulfill this contract. Supplies not available through Government channels can be purchased by the Contractor at its expenses. The Contractor shall The Government will not be responsible in any way for damages to the Contractor’s supplies, materials, equipment, or to personal property as a result of fire, theft, accident, natural disaster, or other events.

3.4. GOVERNMENT-FURNISHED SERVICES. The contractor will not be required to reimburse the Government for the cost of the following services. Notwithstanding the services listed below, the contractor shall perform all tasks identified in this contract.

3.4.1. Government-Furnished Utilities: RESERVED.

3.5. GOVERNMENT PROVIDED TRAINING: RESERVED.

SECTION IV

GENERAL INFORMATION

4.1. CONTRACTOR QUALIFICATIONS. The contractor shall provide qualified personnel who meet the minimum qualifying criteria at the beginning of their employment. If a changeover of personnel occurs, the contractor must ensure a replacement is hired and in place prior to the departure of the incumbent.

4.1.1. The Contractor must possess the following.

a. The Contractor must have at least Five years of working experience in the electrical mechanical and gate automatism systems.

The contractor shall be qualified to build and certify in house steel structural works.

4.2. CONTRACTOR PERSONNEL.

4.2.1. The contractor shall not employ any person for work under this contract if such person is identified to the contractor by the Contracting Officer as a potential threat to the health, safety, security, general well being or operational mission of the installation and its population. The contractor shall not transfer or rehire any American National employee whose employment is terminated for cause under this contract to any other job or position under any contract held by the contractor within the jurisdiction of the Department of Defense. The contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest. In the event it becomes necessary to replace any contract personnel for any of the above reasons, the contractor shall not be reimbursed for costs associated with such removal including the costs for replacement of any personnel so removed. The contractor shall inform immediately the COR in writing of any incidents of misconduct by their employees that violate laws of the USA or the Host Nation.

4.2.2. The contractor shall be responsible for obtaining any necessary licenses and permits to comply with any applicable U.S. and host nation laws, codes, and regulations. The contractor shall ensure that employees have current and valid professional certifications before starting work as required in this PWS. The contractor shall ensure all employees driving on base are required to have a valid driver’s license. The contractor shall ensure that employees maintain proper professional appearance while in the performance of their duties. The contractor’s employees shall be recognizable by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges, which contain the company name and employee name.

4.3. QUALITY CONTROL.

4.3.1. The contractor shall provide a Quality Control Plan. This plan shall describe in detail the contractor’s Quality Control Program and shall be submitted no later than 20 calendar days after contract award. The plan shall become a compliance document after review and acceptance by the Contracting Officer. Reference CDRL 0003 under Exhibit 5.3 of this PWS for further direction on submission.

Reference CDRL 0003 under exhibit 5.3 of this PWS for further direction on submission.

4.3.2. The quality control plan will include the following as a minimum.

4.3.2.1. A method of obtaining and maintain the safety condition of the gates in accordance with European and US normative.

4.3.2.2. A method to control the maintenance and repair work performed by their technician.

4.3.2.3. A method to maintain the automatic gates always in operative condition and to implement procedures to identify and prevent defective services from recurring.

4.4. QUALITY ASSURANCE.

4.4.1. The Government will evaluate the contractor’s performance under this contract according to contract clause “52.212-4 -- Contract Terms and Conditions -- Commercial Items”, the Quality Assurance Surveillance Plan and the contractors’ Quality Control Plan.

4.4.2. Inspections/Evaluations/Reviews By Other Than COR. The contractor shall permit Department of Defense inspection visits, COR team visits, host base visits, other required functional reviews, evaluations or inspections as required by the Government, to include Army Head Quarters Europe, Defense Information Systems

Agency, General Accounting Office or other Government agencies. The inspection teams may make unannounced visits and shall be provided unescorted access to facilities and equipment. The contractor will be given the purpose of the visit and copies of any reports created. The contractor shall take necessary actions and coordinate with the Government to resolve any discrepancies found as part of these inspections.

4.4.3. MAINTENANCE- The Government will perform an inspection on each Gate after maintenance.

4.4.3 REPAIRS- The Government will perform 100% inspection on every repair.

4.5. PHYSICAL SECURITY. The contractor shall be responsible for safeguarding and protecting all Government property provided for contractor use.

4.6. HOURS OF OPERATIONS

4.6.1. Normal Hours. The contractor shall perform the services required under this contract during the following hours: Monday through Saturday, 0800 – 1800 hours.

4.6.2. Extended Service Hours. RESERVED

4.6.3. Recognized Holidays. Reference contract clause CCE 204-4000, “U.S. AND HOST NATION

HOLIDAYS”

4.7. CONSERVATION OF UTILITIES.: RESERVED

4.8. RECORDS.

4.8.1. The contractor shall be responsible for creating, maintaining, and disposing of only those Government required records that are specifically cited in this PWS or those required by the provisions of a mandatory directive listed in Technical Exhibit 5.2. Publications & Forms. If requested by the Government, the contractor shall provide the original record, or a reproducible copy of any such record within 5 working days of receipt of the request.

4.8.2. Records Management Documentation created or received by the contractor in performance of this contract are considered Government records, and the contractor shall be responsible for their maintenance.

4.8.3. Maintaining Records. RESERVED

SECTION V

TECHNICAL EXHIBITS

5.1. WORKLOAD ESTIMATES

ITEM

NAME

ESTIMATED QUANTITY

1 Inspect, test, and maintain automatic electrical gates & barriers systems

14_ Unit

2 Number of Recurring Maintenance per year 2_ Ea

3 Number of emergency repair calls (BASED ON LAST

YEAR'S EMERGENCY CALLS)

_16_ Ea

LIST OF THE AUTOMATIC GATES

GATE# 9 AMMO AREA - This gate consists of:

d. One gate with engine “FAAC 844T”

e. Pedestrian Rotating Gate, ARITEC Mfg.

f. Automatic barrier DELTA Scientific Mfg.

GATE # 4 CAMP DARBY - This gate consists of:

b. Double gates “ entrance” with engine FAAC 884 and “ exit” with engine FAAC Mfg.

AUTO CRAFT # CAMP DARBY - This gates consists of:

c. Double gates “ entrance” and “ exit” with engines FAAC Mfg 220volt.

d. One entrance gates with engines FAAC Mfg 220volt.

GATE # 27 DEPOT - This gate consists of:

b. Double gates “entrance” and “exit” with engines FAAC Mfg.

GATE # 28 DEPOT - This gate consists of :

b. Double gates with engine FAAC Mfg.

GATE# 29 DEPOT - This gate consists of:

b. One gate with engine FAAC Mfg.

GATE# for 5150 - This gate consists of:

f. One gate north side FAAC 740

g. One gate west side FAAC 740

h. One gate south side “engine arms FAAC

GATE# for 5881 - This gate consists of:

i. Gates “entrance/ exit” with engine Elbox Mfg.

j. Turnstile GUNNEBO ENTRANCE CONTROL

CARABINIERI This gate consist of:

b. Barrier FAAC Mfg.

Variation in Workload. RESERVED

5.2. PUBLICATIONS AND FORMS

5.2.1. GENERAL. RESERVED

5.2.2. PUBLICATIONS : Machinery Directive 98/37/CE

European EN 13241-1

EN 12453

EN 12978

EN 12445

And applicable USA military standards & regulations

5.2.3. FORMS: RESERVED

5.3. REQUIRED REPORTS

CONTRACT DATA REQUIREMENTS LIST

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA

ITEM NO.

2. TITLE OF DATA ITEM

LOG BOOK UPDATE REPORTS AND CERTIFICATIONS

3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.)

5. CONTRACT REFERENCE

1.7.2

6. REQUIRING OFFICE

DPW UTILITIES DIVISION - COR

7. DD 250

REQ

NO

9. DIST

STATEMENT

REQUIRED

A

10. FREQUENCY

SEE BLK 16

12. DATE OF FIRST

SUBMISSION

SEE BLK 16

14. DISTRIBUTION

8. APP

CODE

N/A

11. AS OF DATE

N/A

13. DATE OF

SUBSEQUENT

N/A

a. ADDRESSEE

b. COPIES

Draf t

Final

Reg Repr o

16. REMARKS

Contractor has to provide the written applied Report and certifications to the COR at the end of each semi-annual visit and after each repair works, updating and signing the log book .

COR

15. TOTAL 0 2 0

DD FORM 1423, AUG 96

OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

CMR Report Notification

4. AUTHORITY (Data Acquisition

1.11

REQ

NO

9. DIST

ONCE A YEAR

8. APP

CODE

N/A

11. AS OF DATE

N/A

13. DATE OF

SUBSEQUENT

o

16. REMARKS

BLKS 12 & 13. Last business day in the awarding month for the base year and each option year

15. TOTAL 0 2 0

OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

Quality Control Plan

4. AUTHORITY (Data Acquisition Document No.)

5. CONTRACT REFERENCE

4.3

6. REQUIRING OFFICE

DPW UTILITIES DIVISION - COR

7. DD 250

REQ

NO

9. DIST

SEE BLK 16

8. APP

CODE

N/A

11. AS OF DATE

A

13. DATE OF

SUBSEQUENT

o

Submit Draft QCP 20 days after Contract Award. Submit Chances as required.

15. TOTAL 1 2 0

OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

PLANNED WORK SCHEDUL

4. AUTHORITY (Data Acquisition

1.7.2

REQ

NO

9. DIST

SEE BLK 16

10 working date after contract start date

14. DISTRIBUTION

8. APP

CODE

N/A

11. AS OF DATE

N/A

13. DATE OF

SUBSEQUENT

10 working date after contract start date

Repro

Contractor has to provide one written planned work schedule to the COR to the COR for approval 10 working date after contract start date

15. TOTAL 1 2 0