04 Attachment I, Specification 15Nov19.pdf

PDF 665 KB Posted

Attached to
Maintenance of Government Quarters, USAG Bavaria, Hohenfels
Solicitation number
W912PB20B8001
Issued by

View the file

Other files

File Type Posted
02 Bid Label.docx DOCX document
03 Solicitation W912PB20B8001.pdf PDF
01 Cover letter.pdf PDF
06 Attachment III, Totals.xlsx XLSX spreadsheet
05 Attachment II, Price Schedule 28Aug19.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT # I

DEPARTMENT OF THE ARMY

UNITED STATES ARMY GARRISON BAVARIA

DIRECTORATE OF PUBLIC WORKS

UNIT 28130

APO AE 09114-8130

15 November 2019

S P E C I F I C A T I O N

Maintenance of Government Quarters, USAG Bavaria, Hohenfels Military Community

L E I S T U N G S B E S C H R E I B U N G

Instandhaltung von Armee - Unterkünften, USAG Bavaria, Hohenfels Military Community

In the event of a disagreement between the English text and the courtesy translation of this specification the English text shall govern.

Im Falle einer Unstimmigkeit zwischen dem englischen Text der Leistungsbeschreibung und der Gefälligkeitsübersetzung ist der englische Text maßgebend.

Page 2 of 120 Pages Seite 2 von 120 Seiten

GENERAL DESCRIPTION

This project specifies the following work:

Perform the following work in Government Quarters of US Housing Areas, Bachelor Officers Quarters (BOQ), Senior Enlisted Bachelor Quarters (SEBQ) within Hohenfels as well as Leased Quarters within a radius of 40 kilometers.

Items A/B/C/D/E 001: Cleaning work Items A/B/C/D/E 002: Repair and Interior Painting Work Items A/B/C/D/E 003: Repair and Replace Floors Items A/B/C/D/E 004: Mold removal and other Repair Work

ALLGEMEINE BESCHREIBUNG

Dieses Projekt umfaßt folgende Arbeiten:

Ausführen folgender Arbeiten in den Unterkünften der US Wohnsiedlungen, „Bachelor Officers Quarters (BOQ)“, „Senior Enlisted Bachelor Quarters“ (SEBQ) im Lager Hohenfels sowie angemieteten Wohnungen in einem Umkreis von 40 Kilometern.

Positionen A/B/C/D/E 001: Reinigungsarbeiten Positionen A/B/C/D/E 002: Reparatur und Innenanstricharbeiten Positionen A/B/C/D/E 003: Reparatur und Ersetzen von Bodenbelägen Positionen A/B/C/D/E 004: Entfernen von Schimmel und andere Reparaturarbeiten

Page 3 of 120 Pages Seite 3 von 120 Seiten

General Preamble Allgemeine Vorbemerkungen

1. Regulations

The work to be accomplished and material to be furnished shall be in accordance with following standards and regulations:

a. DIN standards (German Industry Standards) of German Construction Contract Procedures (VOB), Part C, identified below are governing:

DIN 4 108 Thermal Insulation in Building Construction DIN 4 109 Sound Insulation in Building Construction DIN 4 420 Scaffolding Work DIN 18 202 Variation in Dimensions for the Evenness of Floor Coverings, Ceilings, Floor Finishing.

DIN 18 334 Carpentry and Constructional Timber Work DIN 18 350 Plaster and Stucco Work DIN 18 353 Floor Finish Work DIN 18 354 Asphalt Work DIN 18 356 Parquetry Work DIN 18 363 Painting Work DIN 18 365 Floor Covering Work

b. Other regulations:

TT-E-489 H Type I Enamel, alkyd, gloss for interior and exterior surfaces TT-E-505 B Enamel, alkyd, odorless, interior, high gloss TT-E-509 C Enamel, alkyd, semigloss, interior odorless, heat resistant up to 120°C = 248°F TT-E-545 C Enamel, alkyd, odorless, undercoat, interior TT-P-19-D Paint Latex, acrylic emulsion, exterior TT-P-29 J (2) Type I Paint, latex based, interior painting.

TT-P-25 E (2) Enamel, undercoat, exterior TT-S-179 B Sealer, surface, pigmented oil, plaster and wallboard TT-V-121 H Varnish, spar, water resistant TT-P-664 A Primer paint

1. Vorschriften

Die auszuführenden Arbeiten und zu liefernden Materialien müssen den folgenden Vorschriften entsprechen:

a. DIN Bestimmungen der VOB, Teil C, wie nachfolgend aufgeführt, sind gültig:

DIN 4 108 Wärmeschutz im Hochbau DIN 4 109 Schallschutz im Hochbau DIN 4 420 Gerüstordnung DIN 18 202 Maßtoleranzen für die Ebenheit der Oberflächen von Rohdecken, Estrichen und Bodenbelägen.

DIN 18 334 Zimmer- und Holzbauarbeiten DIN 18 350 Putz- und Stuckarbeiten DIN 18 353 Estricharbeiten DIN 18 354 Asphaltarbeiten DIN 18 356 Parkettarbeiten

Page 4 of 120 Pages Seite 4 von 120 Seiten

DIN 18 363 Anstricharbeiten DIN 18 365 Bodenbelagsarbeiten fläche

b. Sonstige Bestimmungen:

TT-E-489 H Type I Lackfarbe, Alkyd, glänzend für innen und außen TT-E-505 B Lackfarbe, Alkyd, geruchslos, innen, hoch glänzend TT-E-509 C Lackfarbe, Alkyd mattglänzend, geruchslos, innen, hitzebeständig bis zu 120°C = 248°F TT-E-545 C Lackfarbe, Alkyd, geruchslos,Grundierung innen, TT-P-19-D Farbe Latex, acrylic emulsion, exterior TT-P-29 J (2) Type I Farbe, Latex basierend, für innen TT-P-25 E (2) Lackfarbe, Grundierung außen TT-S-179 B Grundierung für fläche Oberflächen, pigmentiert, Putz und Sperrholz TT-V-121 H Klarlack, wasserabweisend TT-P-664 A Grundierfarbe

2. Special requirements for mold removal (Items A/B/C/D/E 004)

Cleaning agent and disinfection material as well as impregnation shall be bio-degradable, free of chlorine and formaldehyde, non-toxic and suitable for the cleaning of sub bases which are molded, covered with algae or moss.

During application and work performance all regulations concerning hygiene and safety shall be followed, such as the wearing of protective clothing and dust masks.

The following shall be considered:

- Principles of biological-material order

- The technical rules for biologic material TRBA 460

- The technical rules for hazardous material TRGS 440, TRGS 440, TRGS 524, TRGS 540, TRGS 900 and

TRGS 907.

Mold clean up shall only be performed by a certified firm for mold removal.

Dismantled material shall be disposed of by the contractor in accordance with German law.

Submit the disposal certificate to the COR.

2. Gesonderte Anforderungen für Schimmelbeseitigung (Positionen A/B/C/D/E 004)

Das Reinigungs- und Desinfektionsmaterial sowie die Imprägnierung müssen biologisch abbaubar, chlor-und formaldehydfrei, nicht toxisch und geeignet für das Reinigen von verschimmelten, veralgten und vermoosten Untergründen sein.

Bei der Anwendung und Ausführung der Arbeiten sind sämtliche Hygiene- und Sicherheitsvorschriften unbedingt zu beachten, wie zum Beispiel das Tragen von Schutzkleidung und Atemschutz-Masken.

Zu berücksichtigen sind ferner:

- Richtlinien der Biostoff-Verordnung

- Die technischen Regeln für Biologische Arbeitsstoffe TRBA 460

- Die technischen Regeln für Gefahrstoffe TRGS 440, TRGS 440, TRGS 524, TRGS 540, TRGS 900 und

TRGS 907.

Die Schimmelsanierung darf nur von einem befähigten Schimmelpilz-Sanierungs-Fachbetrieb ausgeführt werden.

Ausgebautes Material ist vom Unternehmer nach deutschem Gesetz zu entsorgen.

Der Entsorgungsnachweis ist dem COR zu übergeben.

Page 5 of 120 Pages Seite 5 von 120 Seiten

3. Authorization to Perform Work in Germany

a. Contractors performing work in the Federal Republic of Germany (FRG) shall comply with German law. The contractor shall determine whether performance requires registration with German authorities or authorization to do business in Germany and, if so, shall comply with all requirements. Whether or not registration or authorization to do business is required, the contractor also shall determine what documents or authorization its employees and any subcontractor employees must possess to work in Germany. The contractor shall ensure affirmatively that its employees and subcontractor employees possess such documents or authorizations.

b. Contractor employees who:

(1) are not nationals of Germany or other European Union countries, and

(2) are not members of the force, the civilian component or their dependents, and

(3) do not have assimilated status under Articles 71, 72, or 73 of the

Supplementary Agreement to the NATO SOFA shall possess work and residence permits.

c. The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable laws, codes, and regulations applicable to the performance of the work.

d. By acceptance of and performance under this contract and any task orders or delivery orders issued hereunder, the contractor affirms that it has complied with the requirements above. Compliance with this clause and German law is a material contract requirement. Noncompliance by the contractor or subcontractor at any tier shall be grounds for issuing a negative performance evaluation and terminating this contract, task order, or delivery order for default.

3. Befugnis in Deutschland zu arbeiten

a. Auftragnehmer, die in der Bundesrepublik Deutschland (BRD) Arbeitsleistungen erbringen, müssen deutsches Recht befolgen. Der Auftragnehmer muss ermitteln, ob die Ausführung der Arbeiten die Registrierung bei deutschen Behörden erfordert oder ob eine Genehmigung, Geschäfte zu tätigen, eingeholt werden muss, und - wenn dies der Fall ist - allen Anforderungen entsprechen. Gleichgültig, ob eine Registrierung oder die Genehmigung, Geschäfte zu tätigen, erforderlich ist, oder nicht, muss der Auftragnehmer ermitteln, welche Dokumente oder Autorisierungen seine eigenen Arbeitnehmer sowie sämtliche Arbeitnehmer von Subunternehmern besitzen müssen, um in Deutschland arbeiten zu dürfen.

Der Auftragnehmer muss unbedingt sicherstellen, dass seine eigenen Arbeitnehmer und die Arbeitnehmer der Subunternehmer derartige Dokumente oder Autorisierungen besitzen.

b. Arbeitnehmer von Auftragnehmer, die:

(1) keine deutschen Staatsbürger oder keine Staatsbürger anderer Staaten der Europäischen Union sind, und

(2) keine Mitglieder der Streitkräfte, Zivilisten oder deren Familienangehörige sind, und

(3) über keinen gleichgestellten Rechtsstatus gemäß Artikel 71, 72, oder 73 der Zusatzvereinbarung zum NATO Truppenstatut verfügen (SOFA = Status of Forces Agreement), müssen Arbeits- und Aufenthaltsgenehmigungen besitzen.

c. Der Auftragnehmer ist, ohne dass zusätzliche Kosten für den Auftraggeber entstehen, dafür verantwortlich, jegliche Erlaubnis einzuholen und sämtliche notwendige Genehmigungen zu besorgen, und sich an sämtliche, für die Arbeitsdurchführung maßgeblichen Gesetze, Vorschriften und Bestimmungen zu halten.

Page 6 of 120 Pages Seite 6 von 120 Seiten

d. Mit der Zustimmung zu diesem Vertrag und der Ausführung von Leistungen im Rahmen dieses Vertrages und sämtlicher hierunter erteilten Arbeits- oder Lieferaufträge, versichert der Auftragnehmer die Erfüllung der obigen Anforderungen. Die Einhaltung dieser Klausel und des deutschen Rechts ist eine wesentliche Vertragsbedingung. Eine Zuwiderhandlung seitens des Auftragnehmers oder Subunternehmers, gleich auf welcher Ebene, hat die Erteilung einer negativen Arbeitsbeurteilung und die Beendigung dieses Vertrages, Arbeitsauftrages oder Lieferauftrages wegen Nichterfüllung zur Folge.

4. German Accident Prevention Laws and Regulations

The contractor shall comply with FAR 52.236-13, Accident Prevention, the references contained therein (e.g. EM 385-1-1), and applicable Host Nation Safety Laws and Regulations. The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:

a. Before initiation of work at the job site, an accident prevention plan, written by the contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385- 1-1, will be approved by designated Government personnel. Specific requirements for development of the accident prevention plan are found in 01.A and Appendix A of EM 385-1-1. EM 385-1-1 is available online at www.usace.army.mil.

b. Before beginning any work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, an activity hazard analysis (AHA) shall be prepared by the contractor (see paragraph 01.a.09 of EM 385-1-1).

c. The contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work.

d. The contractor shall discuss the plans in conferences convened by the contracting officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas. The plan for accomplishing the initial work phase shall be submitted within 15 calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted no later than 15 calendar days prior to initiation of work on each major phase.

e. In all areas where construction, demolition, alteration, building, or similar related activities take place, the contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:

(1) Short sleeve shirt.

(2) Long trousers.

(3) Steel-toed safety boots.

(4) Hard hat.

f. In addition to other requirements for accident prevention specified in this contract, the contractor is responsible for compliance with all Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes. In particular, within the requirements of the German Safety and Health Protection Regulation for Construction Sites, Baustellenverordnung (BaustellV), dated 10 June 1998, the contractor is responsible for coordination of all work at the site, including development of plans and providing advance notices. The contractor shall indicate its plan for compliance considering conditions of the work described by the design, technical proposal, operational activities of the Government or others in the area of the work, identification of the coordinator, and implementation of all other accident prevention provisions of this contract. For the compliance with host nation laws and regulations, the contractor will assure that it complies with the non-exclusive list of duties described in this clause. If the contractor determines that additional activities are required to fully comply, the contractor shall assure that compliance with the laws is complete. The duties include:

Page 7 of 120 Pages Seite 7 von 120 Seiten

(1) Conditions of construction and operational activities to be considered include but are not limited construction activities meeting the following criteria:

(a) The work is scheduled to last longer than 30 working days and on which more than 20 workers are occupied simultaneously, or

(b) The volume of work is scheduled to exceed 500 person days, or the work presents particularly hazardous tasks (e.g. excavations deeper than 5 meters, falls from a height of greater than 7 meters, exposures to hazardous chemical or biological substances, work at less than 5 meters from high voltage lines, underground earth works or tunnels, danger of drowning, diving, use of compressed air, work with ionizing radiation, explosives, or work involving assembly or dismantling of heavy prefabricated components (10 tons or greater)).

(2) If the contractor determines that the BaustellV, dated 10 June 1998, applies, the contractor shall prepare a Safety and Health Protection Plan (SIGE) as required under that regulation. The SIGE shall be submitted two weeks prior to mobilization. In addition, the contractor shall appoint a qualified Safety Coordinator who will ensure that safety measures are implemented during construction. The Safety Coordinator must meet minimum training and experience requirements required under Host Nation laws.

(a) The SIGE will be written in a comprehensive form and explained in language the workers understand and shall contain the following minimum information:

(i) Maintenance of tools and equipment.

(ii) Provisions for the storage and disposal of materials and waste, particular hazardous materials and substances.

(iii) Modifying performance periods for such work, taking into consideration the site conditions.

(iv) Organizing cooperation between different employers and contractors without employees.

(v) Interaction between work at the site and other operational activities in the area, on which or near which the first identified work will be performed, and taking into consideration the instructions and advice of the coordinator as well as safety and health plans.

(b) The contractor is responsible for completing and providing any safety notifications required by host nation authorities and will provide proof to the contracting officer that such notifications were made.

4. Deutsche Unfallverhütungsgesetze und -vorschriften

Der Auftragnehmer muss die FAR 52.236-13, Federal Acquisition Regulation, (Beschaffungsverordnung der US-Bundesbehörden) zur Unfallverhütung befolgen, sowie die darin enthaltene Dienstvorschriften (zum Beispiel EM 385-1-1, Engineers Manual = Ingenieursdienstvorschrift) und die maßgeblichen Sicherheitsgesetze und Vorschriften des Gastgeberstaates. FAR 52.236-13 und besonders die Dienstvorschrift EM 385-1-1 umfassen unter anderem die nachfolgenden Anforderungen:

a. Noch vor Arbeitsbeginn auf der Baustelle, wird ein vom Auftragnehmer verfasster

Unfallverhütungsplan für die spezielle Arbeit und die Gefahren des Vertrages, unter genauer Einhaltung der einschlägigen Anforderungen der Dienstvorschrift EM 385-1-1, von designiertem Regierungspersonal genehmigt. Die genauen Anforderungen für die Entwicklung des Unfallverhütungsplanes sind im Abschnitt 01.A und Anhang A der Dienstvorschrift EM 385-1-1 zu finden. Die Dienstvorschrift EM 385-1- 1 ist online unter dem Link: www.usace.army.mil. verfügbar.

Page 8 of 120 Pages Seite 8 von 120 Seiten

b. Noch vor Beginn jeglicher Arbeiten, die Gefahren darstellen, welche in vorherigen Projektabläufen noch nicht vorkamen oder bei der ein neues Team oder Subunternehmer Arbeiten durchführen müssen, hat der mit der Tätigkeit betraute Auftragnehmer eine Tätigkeits-Gefahrenanalyse (AHA - activity hazard analysis) zu erstellen. (Siehe Paragraph 01.a.09 der EM 385-1-1)

c. Der Auftragnehmer hat seine Subunternehmer zu verpflichten, eine Arbeitsablaufsplanung vorzulegen, die die beabsichtigten Maßnahmen für die Durchführung wichtiger Arbeitsphasen aufzeigt.

d. Noch bevor mit den Arbeiten für jede größere Arbeitsphase begonnen wird, muss der Auftragnehmer in vom Contracting Officer einberufenen Konferenzen seine Pläne besprechen. Die Pläne müssen alle relevanten Informationen enthalten, wie zum Beispiel Lagepläne für Transportstraßen, Zugangsstraßen, Ablagerungsflächen, elektrische Verteilungsleitungen, die Maßnahmen, die eine Gefährdung durch Überkopf-Lasten auf ein Minimum beschränken und die Art und Weise, wie die Arbeitsstätten erreicht werden können. Der Plan zur Verwirklichung der Arbeiten in der Anfangsphase muss innerhalb von 15 Kalendertagen nach Auftragsvergabe vorliegen. Pläne für größere, darauffolgende Arbeitsphasen müssen spätestens 15 Kalendertage vor dem Arbeitsbeginn jeder größeren Phase vorliegen.

e. In allen Bereichen, in denen Bau-, Abbruch- und Änderungsarbeiten durchgeführt, Bauwerke erstellt oder ähnliche, damit in Verbindung stehende Aktivitäten stattfinden, muss der Auftragnehmer als Mindesterfordernis für jeden Arbeiter oder Besucher die im Folgenden beschriebene, persönliche Schutzkleidung und Ausrüstungsteile zur Verfügung stellen:

(1) Kurzärmeliges Hemd

(2) Lange Hose

(3) Sicherheitsschuhe mit Stahlkappen

(4) Schutzhelm

f. Zusätzlich zu weiteren Anforderungen an die in diesem Vertrag aufgeführten

Unfallverhütungsmaßnahmen, ist der Auftragnehmer für die Einhaltung aller Bundes- und Staatsvorgaben, die für den Sicherheits- und Gesundheitsschutz auf Baustellen maßgeblich sind, sowie anderer zutreffender berufsbezogener Sicherheitsvorschriften, verantwortlich. Im Besonderen innerhalb der Anforderungen der deutschen Verordnung über Sicherheit und Gesundheitsschutz auf Baustellen (Baustellenverordnung - BaustellV), vom 10 Juni 1998, ist der Auftragnehmer für die Koordination aller Arbeiten auf der Baustelle, sowie für die Planentwicklung und die Erbringung von Vorabmitteilungen verantwortlich. Der Auftragnehmer muss seinen Plan zur Einhaltung anzeigen unter Berücksichtigung der Arbeiten, welche im Design und im technischen Angebot beschrieben sind, der operativen Aufgaben der Regierung oder anderer im Arbeitsbereich, die Bestimmung des Koordinators und die Anwendung aller Unfallverhütungsmaßnahmen dieses Vertrages. Zur Einhaltung der Gesetze und Vorschriften des Gastgeberstaates stellt der Auftragnehmer sicher, dass er die nicht-exklusive Liste der in dieser Klausel beschriebenen Verpflichtungen befolgt. Wenn der Auftragnehmer feststellt, dass zusätzliche Maßnahmen zur vollständigen Einhaltung notwendig sind, muss er sicherstellen, dass die Gesetze eingehalten werden.

Die Verpflichtungen beinhalten:

(1) Die einzuhaltenden Konditionen für bauliche und betriebliche Tätigkeiten beinhalten - unter anderem - Baumaßnahmen, die folgende Kriterien erfüllen:

(a) Die voraussichtliche Dauer der Arbeiten beträgt mehr als 30 Arbeitstage und es werden mehr als 20 Arbeiter gleichzeitig beschäftigt, oder

(b) Der Umfang der Arbeiten übersteigt 500 Personentage, oder die Arbeit beinhaltet besonders gefährliche Tätigkeiten (z.B. Erdaushub in einer Tiefe von mehr als 5 Metern, Arbeiten in einer Höhe von über 7 Meter, Umgang mit gefährlichen chemischen oder biologischen Substanzen, Arbeiten in einem Abstand von weniger als 5 Meter von Hochspannungsleitungen, Tiefbau- oder Tunnelarbeiten, Gefahr zu ertrinken, Arbeiten mit Tauchgeräten, Arbeiten mit Druckluft, Arbeiten mit ionisierender Strahlung, Sprengstoff oder Arbeiten die den Aufbau bzw. Abbau von schweren Fertigbauteilen beinhalten (10 Tonnen oder mehr)).

Page 9 of 120 Pages Seite 9 von 120 Seiten

(2) Stellt der Auftragnehmer fest, dass die BaustellV vom 10 June 1998, zutreffend ist, muss er gemäß dieser Verordnung einen Sicherheits- und Gesundheitsschutzplan (SIGE) erstellen. Der „SIGE“ muss zwei Wochen vor der Baustelleneinrichtung eingereicht werden. Außerdem muss der Auftragnehmer einen qualifizierten Sicherheitsbeauftragten bestimmen, der sicherstellt, dass alle Sicherheitsmaßnahmen während der Baumaßnahme umgesetzt werden. In Übereinstimmung mit der Rechtsordnung des Gastgeberstaates muss der Sicherheitsbeauftragte ein Mindestmaß an Training und die notwendigen Erfahrungen aufweisen.

(a) SIGE wird in umfassender Form geschrieben und in einer von den Arbeitern verständlichen Sprache erklärt und soll mindestens folgende Informationen enthalten:

(i) Instandhaltung der Arbeitsmittel.

(ii) Vorkehrungen zur Lagerung und Entsorgung der Arbeitsstoffe und Abfälle, insbesondere umweltgefährdende Materialien und Gefahrstoffe.

(iii)Anpassen der Ausführungszeiten für die Arbeiten unter Berücksichtigung der Gegebenheiten auf der Baustelle.

(iv) Zusammenarbeit zwischen verschiedenen Arbeitgebern und Auftragnehmern ohne Beschäftigte.

(v) Wechselwirkungen zwischen den Arbeiten auf der Baustelle und anderen betrieblichen Tätigkeiten auf dem Gelände, auf dem oder in dessen Umgebung die erstgenannten Arbeiten ausgeführt werden. Dabei sind die Anweisungen und Empfehlungen des Koordinators sowie der Sicherheits- und Gesundheitsschutzplan zu berücksichtigen.

(b) Der Auftragnehmer ist verantwortlich für die Erstellung und Bereitstellung jeglicher, von der zuständigen Behörde des Gastgeberlandes geforderten, Sicherheitsbekanntmachungen und muss dem Contracting Officer einen Nachweis darüber liefern.

5. Instructions for Contractor's Quality Control Plan

a. The contractor will coordinate with the COR (or receiving activity, if no COR has been appointed) to establish a contractor's Quality Control Plan (CQCP).

b. The contractor will provide a copy of the CQCP annotated with the contract number to the COR at least one week after contract start date. The COR will submit an approved copy to the contracting officer at the below listed address not later than three weeks after contract start date:

Regional Contracting Office Bavaria Building 542, Lager 92655 Grafenwöhr

c. In addition to any requirements in the specification or statement of work, the contractor's quality control plan must have as a minimum:

(1) Identification and clearly defined authority of key personnel under the contractor's organization.

(2) A quality inspection system covering all general and specific tasks included in the contract scope of work. It should specify tasks or areas to be inspected on either a scheduled or unscheduled basis, and the manner in which inspections are to be conducted.

(3) The names of firms or individuals tasked to perform inspections and the extent of their authority. This may be in the form of an organization chart or other form approved by the contracting officer's representative (COR).

(4) Proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable. Tests must be specified.

Page 10 of 120 Pages Seite 10 von 120 Seiten

(5) A method of identifying deficiencies in the quality of services or construction performed before the level of performance becomes unacceptable.

(6) A method of documenting and enforcing quality control operations of both prime and subcontractor work, including inspection and testing.

(7) Key control, internal control or security procedures, if applicable.

(8) Any winterization plans and procedures for outdoor and exposed contractor and Government furnished equipment, if applicable.

(9) A method of identifying deficiencies in the quality of manufacturing, services, or construction performed before the level of performance becomes unacceptable.

(10) Detailed information specifying the types of action the contractor will take to correct deficiencies and prevent their recurrence.

(11) Detailed information on the inspection methods used and proposed test methods, including names of technicians or qualified testing laboratories to be used, if applicable. Tests shall be specified.

5. Qualitätskontrollplan des Auftragnehmers

a. Der Auftragnehmer muss in Abstimmung mit dem COR (oder, falls kein COR ernannt wurde, mit dem Leistungsempfänger) einen annehmbaren Fertigungs-/Gütekontrollplan (CQCP) erstellen.

b. Eine Kopie des genehmigten Fertigungs-/Gütekontrollplans, unter Angabe der Vertragsnummer, muss spätestens eine Woche nach Vertragsbeginn beim Vertreter des Contracting Officers(COR) vorliegen.

Der Vertreter des Contracting Officers hat den genehmigten Fertigungs-/Gütekontrollplans dem Contracting Officer spätestens drei Wochen nach Vertragsbeginn unter folgender Adresse einzureichen.

Regional Contracting Office Bavaria Building 542, Lager 92655 Hohenfels

c. Außer den Anforderungen des Leistungsverzeichnisses bzw. der Arbeitsbeschreibung, muss der Fertigungs-/Gütekontrollplan mindestens folgendes beinhalten:

(1) Benennung des verantwortlichen Schlüsselpersonals (Bauleiter etc.) und dessen Befugnisse innerhalb der Organisation des Vertragsnehmers.

(2) Alle speziellen Erfordernisse, die den Umfang der Arbeit ausmachen, müssen durch das Fertigungs-/Gütekontrollsystem abgedeckt sein. Die Art der Kontrolle/Inspektion, planmäßig oder außerplanmäßig, sowie die Arbeit/Arbeitsbereiche selber müssen genau dargelegt werden.

(3) Die Namen der Firmen oder Einzelpersonen, die damit beauftragt wurden, die Fertigungs- /Gütekontrollen durchzuführen und deren klare Befugnisse. Dies kann in der Form einer Organisationsübersicht oder eines anderen, vom Vertreter des Contracting Officers (COR) genehmigten Vorschlages erfolgen.

(4) Die beabsichtigten Prüfungsmethoden, unter Angabe der Namen der Techniker bzw. der Testlaboratorien, die dafür vorgesehen sind (falls zutreffend). Die Tests müssen ausführlich beschrieben werden.

(5) Eine Methode zur Feststellung von Mängeln im Arbeits-/ Leistungsablauf, die eine Nichtabnahme/-annahme seitens des Auftraggebers vorbeugend verhindert.

(6) Ein Nachweis- bzw. Ausführungsverfahren der Fertigungs-/ Gütekontrollmethoden von Leistungen des Hauptunternehmers als auch aller Subunternehmer, einschließlich der vorgesehenen Inspektionen und Tests.

(7) Alle wesentlichen und innerbetrieblichen Kontrollen sowie alle Sicherheitsmaßnahmen (falls zutreffend).

(8) Alle Pläne und Verfahren zur Winterfestmachung von ungeschützten Ausrüstungsgegenständen des Vertragsnehmers oder -gebers.

(9) Eine Methode zur Feststellung von Qualitätsmängeln in der Produktion, im Dienstleistungsbetrieb oder bei den Bauarbeiten, die eine Nichtabnahme/-annahme seitens des Auftraggebers vorbeugend verhindert.

(10) Ausführliche Informationen welche Maßnahmen der Auftragnehmer ergreifen wird um Mängel zu korrigieren und ihre Wiederholung zu verhindern.

Page 11 of 120 Pages Seite 11 von 120 Seiten

(11) Ausführliche Informationen über die angewandten Inspektionsmethoden und die beabsichtigten Testmethoden, unter Angabe der Namen der Techniker bzw. der Testlaboratorien, die dafür vorgesehen sind (falls zutreffend). Die Tests müssen ausführlich beschrieben werden.

6. Disposal of Debris

a. The Sanitary Landfill Hohenfels will not accept material, such as asphalt, concrete, wood, construction debris, metal, branches, rootstocks, cardboard, hazardous waste (cleaning agents, paints etc.), dismantled material (cables, pipes, installation material etc.) or soil excavation. This material becomes property of the contractor and shall be disposed of in accordance with German laws and regulations (for example Closed Cycle and Waste Management Act, Ordinance of Waste Wood Management, Guideline 3.4/1 of the Bavarian Water Board for tar debris, etc.). If applicable, the contractor must commission a certified laboratory to analyze representative samples for classification. Sampling and chemical analysis of the excavated soil shall be executed according to LAGA PN 98 (German Interstate Working Party on Waste Processing - Ordinance for the procedure for physical, chemical and biological analyses in connection with recycling/removal of waste). If the sample analysis shows contamination classifications not included in any of the specification items, an appropriate contract modification will be issued.

b. Waste wood resulting from demolition work shall be disassembled individually and stored separate from other debris. The disposal shall be in compliance with the German Ordinance on the Management of Waste wood ("Altholzverordnung"). Waste wood shall be categorized and disposed of based on the Ordinance on the Management of Waste wood.

c. A copy of the waste consignment document shall be provided to the COR.

d. The dismantled material shall be stored in water-tight covered containers until removal and shall be disposed of at least once a week.

e. Within USAG Bavaria, Hohenfels Military Community there is a separate sewer system for rain water and waste water. Therefore, accumulated waste water shall be disposed of via waste water duct in coordination with the COR.

6. Bauschuttabfuhr

a. Material, wie Teeraufbruch, Beton, Holz, Bauschutt, Metall, Äste, Wurzelstöcke, Kartonagen, Sondermüll (Reiniger, Farben, etc.), ausgebaute Materialien (Kabel, Rohre, Installationsmaterialien, etc.)

oder Erdaushub werden nicht an der Mülldeponie im Lager Hohenfels angenommen. Diese Materialien werden Eigentum des Auftragnehmers und sind gemäß deutschen Gesetzen und Vorschriften (zum Beispiel Kreislaufwirtschaftsgesetz, Altholzverordnung, Merkblatt 3.4/1 des Bayerischen Landesamt für Wasserwirtschaft für Teeraufbruch, etc.) zu entsorgen. Gegebenenfalls muss der Auftragnehmer ein zertifiziertes Labor beauftragen, repräsentative Proben zu untersuchen und entsprechend einzustufen. Die Probenahme und Analytik des Bodenaushubs muss nach der Richtlinie LAGA PN 98 (Länderarbeitsgemeinschaft Abfall - Richtlinie für das Vorgehen bei physikalischen, chemischen und biologischen Untersuchungen im Zusammenhang mit der Verwertung / Beseitigung von Abfällen) erfolgen. Falls die Probeuntersuchung eine Einstufung_der Kontamination aufweist, die nicht in irgendeiner Position der Leistungsbeschreibung beinhaltet ist, wird eine entsprechende Vertragsmodifikation erstellt.

b. Fallen im Zuge der Abbrucharbeiten Holzabfälle an, sind diese separat zurückzubauen und von den übrigen Abfällen getrennt zur Entsorgung bereitzustellen. Die Entsorgung ist in der Altholzverordnung geregelt. Der anfallende Holzabfall ist gemäß den Kategorien der Altholzverordung einzuteilen und zu entsorgen.

c. Eine Kopie des jeweiligen Entsorgungsnachweises muss dem COR ausgehändigt werden.

Page 12 of 120 Pages Seite 12 von 120 Seiten

d. Bauabfälle sind bis zur Abfuhr in wasserdicht abgedeckten Containern zu lagern und mindestens einmal pro Woche abzufahren.

e. Im Bereich der USAG Bavaria, Hohenfels Military Community besteht ein Trennsystem für Regenwasser und Schmutzwasser. Anfallendes Schmutzwasser muss deshalb nach Angabe des COR über den Schmutzwasserkanal entsorgt werden.

7. Paints

All paints, oil, lubricating products and containers of chemical products and materials shall be disposed of at an appropriate waste disposal site according to German laws and regulations. They must not be dumped on U. S. Army controlled property.

7. Farben

Alle Farben, Öle, Schmierprodukte und Behälter von chemischen Produkten und Materialien müssen auf einem geeigneten Entsorgungsplatz nach deutschen Gesetzen und Vorschriften deponiert werden. Sie dürfen nicht auf Eigentum der U. S. Armee deponiert werden.

8. German Paint Products

German paint products may be used. However, these products must be in accordance with American specifications.

8. Deutsche Farbprodukte

Es können auch deutsche Farbprodukte verwendet werden. Diese müssen jedoch den amerikanischen Spezifikationen entsprechen.

9. Colors and Colorshade Samples

Unless otherwise specified herein, the color of the paint material required for use shall be determined by the COR. Color shade samples shall be submitted on color cards from the paint manufacturer, or on wooden strips size 5 x 15 cm, or where feasible displayed on surfaces which are intended for painting.

9. Farben und Farbtonmuster

Wenn in dieser Leistungsbeschreibung nicht anders angegeben, werden die Farben (Farbtöne) des zur Anwendung kommenden Farbmaterials vom COR bestimmt. Farbtonmuster sind entweder auf Farbtonregister des Farbenherstellers oder auf Holzstreifen ca 5 x 15 cm vorzulegen, oder wenn möglich, durch Musteranstrich auf den zum Streichen vorgesehenen Flächen vorzuführen.

10. Preparation work for painting

Prepare surfaces to guarantee proper adhesion of paint. Remove loose and cracked plaster. Apply new plaster on the surfaces. For this purpose, use only suitable plaster material wich guarantees proper adhesion and matches the surface appearance of the adjacent plaster. Fill failing spots, such as holes, scratches and cracks on surfaces to be painted with suitable filler material and plaster. This also applies to all newly plastered and repaired plaster surfaces. Clean all surfaces prior to painting. Remove oil, grease, dirt, chalk, rust, dust, scale, efflorescence, old cracked and loose paint coats and other foreign material. All primer and sealer compounds used shall be compatible with the subsequent paint coats. Lightly sand all

Page 13 of 120 Pages Seite 13 von 120 Seiten existing paint coats to guarantee proper bond of the new paint. Notify the COR after preparing the surfaces. Do not apply paint coat without COR’s approval.

10. Vorbereitende Arbeiten für Farbanstrich

Vorbereiten der Flächen, um eine ausreichende Farbhaftung zu gewährleisten. Entfernen von losem und brüchigem Putz. Neu verputzen der Flächen. Für diesen Zweck müssen geeignete Verputzmaterialien, die eine gute Haftung gewährleisten und gleiche Oberflächenstruktur wie die angrenzenden Putzflächen aufweisen, benutzt werden. Schadstellen wie Löcher, Verkratzungen und Risse in den zu streichenden Oberflächen sind mit geeignetem Füllmaterial zu verspachteln und zu verputzen. Dieses ist auch auf allen neu verputzten und reparierten Putzstellen auszuführen. Vor dem Anstrich sind die zu streichenden Flächen zu reinigen. Öl, Fett, Schmutz, Kalk, Rost, Staub, Zunder, Ausblühungen, alte gerissene und abblätternde Farbe und andere Fremdstoffe sind zu entfernen. Die zur Verwendung kommenden Versiegler und Grundiermittel müssen so beschaffen sein, dass sie mit den nachfolgenden Anstrichen verträglich sind. Alle alten Farbanstriche sind vor dem Anstreichen leicht anzurauhen, um eine gute Haftung des Neuanstrichs zu gewährleisten. Nach Abschluss der Vorbereitungsarbeiten muss der COR benachrichtigt werden. Der Farbanstrich darf ohne vorherige Genehmigung des COR nicht aufgetragen werden.

11. Application of paint

Unless otherwise directed, apply paint coats under dry and dust-free conditions in accordance with manufacturer's instructions. Do not apply paint if the temperature of the surfaces to be painted and the ambient temperature are below 50 degrees Fahrenheit (10 degrees C). Do not apply water-diluted paint coatings when there is a risk that temperatures will drop to freezing point before the coat is dry. Perform spray painting only when specified.

The coat thickness at edges, corners, crevices, welds and rivets shall be equivalent to the adjacent surfaces.

Each paint coat shall have a slight variation in color shade to distinguish it from the previous paint coat.

Properly stir paint and keep it in a uniform consistency during application. Do not dilute paint exceeding the manufacturer's instructions. All finished surfaces shall be free of smears, drips, ridges, waves, laps, brush marks, other imperfections and variations in color, structure and finish. Perform spray painting for wall and ceiling surfaces of stairwells which cannot be painted.

11. Aufbringen der Farbe

Wenn nicht anders angegeben, sind die Farbmaterialien unter trockenen und staubfreien Verhältnissen und gemäß den Anweisungen des Herstellers aufzutragen. Die Farben dürfen nicht aufgetragen werden, wenn die Temperatur der zu streichenden Flächen und die Umgebungstemperatur unter 50 Grad F (+10 Grad C) sind. Wasserverdünnte Farben dürfen nicht aufgetragen werden, wenn die Gefahr besteht, dass die Temperatur auf den Gefrierpunkt absinkt, bevor die Farbe trocken ist. Wenn nicht anders angegeben, darf kein Anstrich mit Spritzverfahren ausgeführt werden.

Besondere Aufmerksamkeit muss darauf verwendet werden, dass der Farbfilm an Kanten, Ecken, Ritzen, Nähten, Nieten, genauso stark ist, wie der auf den angrenzenden Flächen. Der Farbton einer jeden Farbschicht muss leicht voneinander abweichen, so dass er von dem vorausgegangenen Anstrich zu unterscheiden ist. Die Farbe soll sorgfältig aufgerührt und während des Auftragens in gleichmäßiger Konsistenz gehalten werden. Die Farbe darf nicht über die Anweisungen des Herstellers hinaus verdünnt werden. Die fertig gestrichenen Flächen dürfen keine Schlieren, Tropfen, Buckel, Wellen, verschmierte Kanten, Pinselstriche, andere Mängel sowie Abweichungen in Farbe, Struktur und Oberflächenbeschaffenheit aufweisen. Wand- und Deckenflächen in den Treppenhäusern, die nicht gestrichen werden können, sind zu spritzen.

Page 14 of 120 Pages Seite 14 von 120 Seiten

12. Traffic Control

The contractor shall ensure that traffic flow interruptions, due to construction work, will be kept to a minimum. No construction work shall impede traffic between 0630 and 0730 hours and between 1530 and 1630 hours. The contractor is responsible for traffic control; if necessary, traffic lights shall be used.

12. Verkehrsregelung

Der Auftragnehmer hat dafür Sorge zu tragen, dass die Bauarbeiten den fließenden Verkehr nicht übermäßig behindern. Deshalb sind zwischen 06.30 und 07.30 Uhr und zwischen 15.30 und 16.30 Uhr Bauarbeiten, die den Verkehr behindern, zu unterbrechen. Für die Verkehrsregelung ist Sorge zu tragen, notfalls mit einer Ampelanlage.

13. Spill reporting procedures for contractors working within the USAG Bavaria, Hohenfels Military Community

a. Applicability: In accordance with USAG Bavaria’s Environmental Management System (EMS) the following procedures shall be followed in the event of a spill of hazardous substances caused by vehicles or equipment of contractors working within the USAG Bavaria, Hohenfels Military Community

b. Hazards for humans and environment:

- Release of hazardous substances during accidents (mainly Petroleum, Oil and Lubricant

(POL)products);

- Release of hazardous substances caused by equipment failure (mainly POL products)

- Release of hazardous substances during transportation of hazardous materials/waste (excluding Class 1, explosives).

c. Protective Measures and Procedures: The following requirements must be met when operating a vehicle within the USAG Bavaria, Hohenfels Military Community.

- Valid driving license appropriate for the vehicle;

- Valid hazardous cargo driver’s license for the transportation of hazardous material/hazardous waste;

- Follow the Road Traffic Regulation:

- Road Traffic Law (Straßenverkehrsgesetz - StVG);

- Road Traffic Regulation (Straßenverkehrsordnung - StVO)Federal Motor Vehicle Safety Standards

(Straßenverkehrs-Zulassungs-Ordnung - StVZO);

- European Agreement concerning the international carriage of dangerous goods by road (Accord europeen relatif au transport international des marchandises Dangereuses par Route - ADR);

- Load safety according to VDI 2700 and ADR

- Spill equipment shall be kept on hand (e.g. absorbent, absorbent pads etc.).

d. The following procedures shall be followed should hazardous situations arise:

- Immediately notify the COR and the local US Fire Department under the following number: 09472 – 83

112 if hazardous substances (diesel, hydraulic fluid etc.), including hazardous waste, are released due to failure of vehicles or construction equipment;

- The contractor shall take immediate protective measures to prevent spilled material from spreading;

- The necessary spill clean-up shall be performed by the contractor or their subcontractors.

Page 15 of 120 Pages Seite 15 von 120 Seiten

e. Emergency Procedures – First Aid:

- Secure scene of the accident;

- Inform the COR and the local U.S. Fire Department at 09472 – 83 112;

- Provide first aid to injured individuals

f. Refueling, Maintenance, Disposal:

- To avoid impacting the environment, appropriate precautionary measures shall be taken during refueling of construction vehicles / equipment;

- Maintenance of vehicles and equipment shall only be conducted on paved surfaces connected to an oil/water separator (such as maintenance hardstands/refueling pads);

- The contractor is responsible for the disposal of hazardous substances and contaminated soil caused by accidents or failure of vehicles/equipment. Proof of proper disposal shall be provided to the COR (Entsorgungsnachweis).

13. Verhaltensregeln für Auftragnehmer bei Freisetzung von Gefahrstoffen in USAG Bavaria, Hohenfels Military Community

a. Geltungsbereich: Gemäß dem Umweltmanagementsystem (Environmental Management System – EMS) von USAG Bavaria, wird im Folgenden das Verhalten bei Freisetzung von Gefahrstoffen während des Betriebs von Baufahrzeugen von in USAG Bavaria, Hohenfels Military Community tätigen Auftragnehmern beschrieben.

b. Gefahren für Mensch und Umwelt:

- Freisetzen von Gefahrstoffen bei Unfällen(in der Regel Mineralöle).

- Freisetzen von Gefahrstoffen durch defekte Maschinen (in der Regel Mineralöle).

- Freisetzen von Gefahrstoffen bei Gefahrstofftransporten/Sondermülltransporten (ausgenommen Klasse

1, Sprengstoffe)

c. Schutzmaßnahmen und Verhaltensregeln: Voraussetzung für das Führen eines Fahrzeuges in USAG Bavaria, Hohenfels Military Community:

- Gültige Fahrerlaubnis für das entsprechende Fahrzeug.

- Gültiger Gefahrgutführerschein beim Transport von Gefahrgut/Sondermüll.

- Einhalten der Vorschriften des Straßenverkehrsrechts:

- Straßenverkehrsgesetz (StVG)

- Straßenverkehrsverordnung (StVO)

- Straßenverkehrs-Zulassungs-Ordnung (StVZO)

- Europäisches Abkommen zum internationalen Transport von Gefahrgütern auf Straßen (Accord europeen relatif au transport international des marchandises Dangereuses par Route - ADR).

- Ladungssicherung entsprechend VDI 2700 und ADR

- Ausrüstung zur Bekämpfung von Ölunfällen ist für den Notfall bereitzuhalten (z.B. Bindemittel, Ölbindematten etc.).

d. Verhalten bei Störungen und im Gefahrfall:

- Bei Freisetzen von Gefahrstoffen (auch Sondermüll) oder Betriebsmitteln (Hydrauliköl, Diesel usw.)

durch Defekte an Fahrzeugen bzw. Baumaschinen sind sofort der COR und die Standortfeuerwehr unter der Telefonnummer 09472 – 83 112 zu verständigen.

- Der Auftragnehmer hat dafür zu sorgen, dass geeignete Sofortmaßnahmen getroffen werden um ein Ausbreiten zu verhindern.

- Die anfallenden Reinigungsarbeiten sind vom Auftragnehmer bzw. Subunternehmer durchzuführen.

Page 16 of 120 Pages Seite 16 von 120 Seiten

e. Verhalten bei Unfällen - Erste Hilfe:

- Unfallstelle sichern.

- COR und Standortfeuerwehr unter 09472 – 83 112 verständigen.

- Verletzte versorgen.

f. Betanken, Instandhaltung, Entsorgung:

- Beim Betanken von Baustellenfahrzeugen / Baumaschinen sind geeignete Vorsichtsmaßnahmen zu treffen, um Umweltschäden zu vermeiden.

- Instandhaltungsarbeiten an Fahrzeugen und Baumaschinen sind grundsätzlich nur auf befestigtem

Untergrund mit Anschluss an einen Ölabscheider durchzuführen (z.B. Wartungs- und Betankungsflächen).

- Die Entsorgung von ausgelaufenen Substanzen oder von verunreinigtem Boden als Folge von Unfällen oder durch defekte Fahrzeuge/Baumaschinen ist vom Auftragnehmer selbst durchzuführen. Dem COR ist ein Entsorgungsnachweis vorzulegen.

14. Security Checks

The contractor must consider delays caused by checks when entering and leaving the construction sites on US installations, as this will not be separately reimbursed.

14. Sicherheitskontrollen

Verzögerungen bedingt durch Zugangskontrollen beim Betreten und Verlassen der Baustellen innerhalb von Liegenschaften der US-Armee sind vom Auftragnehmer zu berücksichtigen, da diese nicht extra bezahlt werden.

15. Anti-Terrorism/Operations Security (AT/OPSEC) Requirements

Contractors and subcontractors shall comply with the following marked AT/OPSEC requirements:

X a. Access and General Protection/Security Policy and Procedures. The contractor and all associated subcontractor employees will comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor will also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

X b. iWATCH/iSALUTE Training. The contractor and all associated subcontractors will brief all employees on the local iWATCH/iSALUTE program (training standards provided by the requiring activity AT officer). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training will be completed within 30 calendar days after the contract is awarded and within 5 calendar days after new employees commence contract performance, with the results reported to the COR within 30 calendar days after the contract is awarded.

Page 17 of 120 Pages Seite 17 von 120 Seiten

X c. Antiterrorism Level 1 Training. The contractor and all associated subcontractors will brief all employees on the local AT Level 1 program (training standards provided by the requiring activity AT officer). This locally developed training may change based on local threat at which time the AT officer will provide updated materials for the briefing. This training will be completed within 30 calendar days after the contract is awarded and within 5 calendar days after new employees commence contract performance, with the results reported to the COR within 30 calendar days after the contract is awarded.

X d. OPSEC Training. The contractor and all associated subcontractors will brief all employees on the local OPSEC program (training standards provided by the requiring activity AT officer). This locally developed training may change based on local threat at which time the AT officer will provide updated materials for the briefing. This training will be completed within 30 calendar days after the contract is awarded and within 5 calendar days after new employees commence contract performance, with the results reported to the COR within 30 calendar days after the contract is awarded.

15. Vorschriften zur Sicherheit und Anti-Terrormaßnahmen (AT/OPSEC)

Auftragnehmer und Subunternehmer sollen die folgenden markierten AT/OPSEC Vorschriften erfüllen:

X a. Vorschriften und Regelungen für den Zutritt zum Gelände und allgemeine Schutzmaßnahmen. Der Auftragnehmer und alle Subunternehmer müssen die gültigen Vorschriften und Anweisungen für den Zutritt zum Gelände und allgemeine Sicherheitsregeln befolgen (werden von einem Vertreter der US Armee ausgehändigt). Der Auftragnehmer muss alle Unterlagen zur Durchführung einer Sicherheitsüberprüfung vorlegen, damit die Zutrittsvoraussetzungen der örtlichen Militärpolizei, der Abteilung für Katastrophenschutz sowie des Büros für Sicherheit erfüllt werden. Die Mitarbeiter der Vertragsfirma sind ausweispflichtig gemäß den Bestimmungen des U.S. Verteidigungsministeriums, des Hauptquartiers der U.S. Armee, und den Bestimmungen vor Ort. Zusätzlich zu Änderungen aufgrund der Änderungsklausel zu diesem Vertrag, kann die Regierung die Sicherheitsmaßnahmen oder -vorschriften ändern, wenn sich die Sicherheitseinstufung (FPCON) eines Gebäudes oder Standorts ändert.

X b. iWatch/iSalute Training. Der Auftragnehmer und alle Subunternehmer müssen ihre Mitarbeiter über das örtliche iWATCH/iSALUTE Programm in Kenntnis setzen. Die erforderlichen Schulungsunterlagen werden vom Anti-Terrorismus-Bevollmächtigten der auftraggebenden Dienststelle zur Verfügung gestellt. Inhalt der Schulung ist es, die Mitarbeiter aufzuklären, gegenüber welchen ungewöhnlichen Umständen sie wachsam sein sollen, und welche sie an den COR melden sollen.

This is the start of the file's text. The full file is on GovTribe.