ATTACHMENT_1-_STATEMENT_OF_WORK-_REPAIR_HANGAR_ROOF_CAB__1.doc
DOC document 162 KB Posted
- Attached to
- Repair Roof Hangar 1
- Solicitation number
- W912PA-17-R-0005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912PA-17-R-0005-0001_RELEASED_AMENDMENT_1.pdf | ||
| ATTACHMENT_2-TECHNICAL_EXHIBIT_1-_DELIVERABLES.docx | DOCX document | |
| W912PA-17-R-0005_RELEASED.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USAG BENELUX
NATO SHAPE SUPPORT GROUP
ENGINEERING DIVISION
HANGAR # 6 - CHIEVRES AIR BASE
HAINAUT - BELGIUM
SPECIFICATIONS FOR
PROJECT
R-CH-8FD-17172-17
LOCATION
Hangar # 01 - Chièvres Air Base
TITLE
Repair roof.
DATE
August 2017
PERFORMANCE PERIOD
120 calendar days after issuance of Notice to Proceed (NTP)
INDEX
CHAPTER I : GENERAL
CHAPTER II : TECHNICAL PROVISIONS
SECTION 1 : Preparation work
SECTION 2 : Renovation work
SECTION 3 : Finishing work
CHAPTER III : SCHEDULE
CHAPTER I
GENERAL
G-01:
SCOPE OF WORK
A) General work description The purpose of the project described below is to repair the watertightness of the roof.
The site of work is located:
Chievres Air Base Hanger # 01
7950 Chievres
B) Principal features
Principal items to be performed to accomplish the work consist of the following:
1. Site preparation:
· Preparation and protection of the work site
· Dismounting of lightning conductor system
· Complete cleaning of roof
2. Roof renovation
· Vapor barrier
· Insulation
· Sub layer
· Water tightness layer
3. Finish work
· Wall covering
· Zinc work
· Re-installation of lightning system
· Repair metallic roof gutter
· Provide and install rainwater inlets
· Water downspouts pipe PEHD Principal items to be performed to accomplish the work consist of the following:
The Contractor shall perform all work and assume responsibility for planning, programming, administering, managing, and executing all functions necessary to provide the services specified in this Specifications document. The Contractor shall conduct work in accordance with these specifications and all applicable United States (U.S.), Belgium, European, local laws, regulations, standards, provisions, and directives to include applicable publications. The Contractor shall ensure that all work meets the level of service, performance standards, or tolerances specified in the specifications or in applicable referenced documents.
The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawing.
G-02:
DRAWINGS AND STANDARDS
A) Drawings All work under this contract shall be carried out in strict conformity with the following drawing, which forms a part of these specifications. A copy of the drawings may be provided to Contractors who sign a non-disclosure agreement.
DRAWINGS (
TITLE
DATE
R-CH-8FD-17172-17-1/1
Repair roof Hangar # 01 May 17
B) Specific applicable standards All Belgian norms and regulations Bureau de Normalisation (NBN), European Norm (EN) in force concerning the performance of this project shall be applicable.
The following regulations in matter of environmental, safety and health shall be applicable:
- General Regulations for Work Protection (RGPT) and the Act of 4 August 1996 on well-being of workers in the performance of their work.
- General Regulations for Electrical Installations (RGIE)
DIN 52123
Weatherproofing of roofs
DIN 52132
DIN 52133
DIN 1055
Mechanical fixation of weatherproofed layers
DIN 18164
Rigid polyurethane foam
DIN 4108
Insulation coefficient
DIN 4102
Fire resistance
CCT 104
Construction materials
NBN T42
Downspouts and sewage pipes
NBN 306 & STS 33
Downspouts finish
Work performed under this requirement is not limited to those regulations identified above.
G-03:
GUARANTEE, WORKMANSHIP AND MATERIALS
A) Workmanship and materials The contractor shall employ workmen who are skilled in their trades. In particular, all works with potential risk of refrigerants release to the atmosphere should be conducted under the direct supervision or by a person with a category I certificate as specified in the EU regulation (EC 303/2008) and those regulations valid for the Walloon Region area.
For safety purposes, during the execution of the work, the contractor’s workers shall speak French or English. All materials used for the roof repair of Hangar #1 shall be new. The contractor shall not use asbestos containing materials for the performance of his work. All paints shall be lead free, and all hazardous products brought on site by the contractor shall be documented on an inventory list with safety data sheet.
B) Guarantee The contractor shall guarantee his workmanship and materials for a minimum period of 2 years after the date of final acceptance or for the period as specified by pertinent Belgian laws for the workmanship or materials in question, whichever is longer.
G-04:
SCHEDULING OF WORK
Prior to starting any work, the contractor shall provide the contracting officer, for approval, a detailed schedule showing the successive phases of the work. All interruptions or disturbance in normal functioning of US Government organizations shall also be indicated (road closure, water or utility cuts).
G-05:
AS-BUILT DRAWINGS
The contractor shall submit detailed as-built drawings after completion of the project, but before submission of the final invoice. As-built drawings shall be precise and accurate. They shall be drawn on BENTLEY MICROSTATION v8 system or any other 100% compatible system. The CD-Rom of the basic project shall be given to the contractor for correction by request.
G-06:
HOT WORK PERMIT
All security measures as stated in the “Règlement Général sur la Protection du Travail” shall be complied with. Prior to starting the work, the contractor shall request a Hot Work Permit (for welding, cutting work, etc.) from the COR. This permit shall be delivered by the U.S. Army Fire Officer. In addition, no open fires or burning of trash will be allowed within the confines of the USAG Benelux (NSSG) Community.
Contractors, concessionaires or vendors performing work or conducting business on or in facilities under the jurisdiction of the USAG Benelux Military Community Commander Area of Responsibility (AOR) shall conform to the regulation provided below. The COR shall ensure that a copy of the French or Dutch translation of this regulation is handed to contractors at pre-construction conferences and that all requirements therein are adhered to. Specific requirements and limitations are as follows:
1. Smoking is prohibited in the vicinity of hazardous operations and locations.
2. Waste material and rubbish shall not be stored or allowed to accumulate within the building or in the immediate vicinity, but shall be removed from the site at least daily. Rubbish shall not be burned on the site.
3. Contractor materials and equipment shall not be stored in a location or manner which shall create a fire exposure to facilities adjacent to the project site.
4. The contractor shall provide fire extinguishers at all locations where work is carried out.
5. In every building operation where a shed, storage, or other shanty is placed, or room or space is used for storage or workshop, the contractor shall provide at least one approved portable fire extinguisher in an accessible location. Portable fire extinguishers must be verified annually by certified companies following standards NBN S21-050 and technical notice NT117 edited by ANPI, in accordance with tem 358 of General Regulations for Work Protection (RGPT).
6. Flammable liquids and other hazardous materials such as paints, paint thinner, gasoline, asphalt, and tar shall be stored in small detached structure or out in the open and not inside main buildings. Low flash point liquid used within buildings shall be handled only in approved safety cans.
7. Adequate ventilation shall be provided for paint spraying and operations involving the application of materials using adhesives containing flammable solvents. Such operations shall be conducted remote from any potential source of ignition.
8. Asphalt and tar kettles shall be located in a safe place outside of the building. Such kettles shall not be placed on roofs or porches. Continuous supervision shall be maintained while kettles are in operation. Metal covers shall be provided for all kettles to smother flames in case of fire.
9. Electrical wiring and equipment for lighting, heating, and power purposes shall be installed in compliance with current US and Host Nation Electrical Regulation requirements.
10. Cutting and welding shall not be permitted unless:
a. A valid Hot Work Permit (welding permit) is available; AND
b. Combustibles have been safely covered or moved away; AND
c. A fire guard with a serviceable fire extinguisher is posted for the duration of the work and 30 minutes thereafter to assure that sparks or drops of hot material do not start fires.
11. Fire hydrants shall only be used for fire fighting and training of the local fire and Emergency Services. Water can only be taken from hydrants with the permission of the Community Fire and Emergency Services Office. Parking within 2.5 m (8 feet) of a hydrant is not permitted. Vehicles and other equipment with fuel driven motors, with mounted and filled fuel tanks shall be equipped with 2,5 kg or larger carbon dioxide or dry chemical fire extinguishers.
12. Gasoline, oil and grease shall not be disposed into drainage systems or public water systems. Oil contaminated areas shall be covered with an absorbent material and removed in accordance with the Spill Contingency plan. Any POL spillage shall be reported immediately to the DES Fire and Emergency Services Office, DSN 361-5401/5347.
13. Construction offices, huts, construction vehicles, trailers and supplies shall be located at least 10 m from all adjacent buildings.
14. Access for fire fighting vehicles shall be provided to the immediate job site at the start of construction and maintained until all construction is complete. Vehicle parking control measures shall be established.
15. Free access from the street to fire hydrants and to outside connections for standpipes or other firefighting equipment, whether permanent or temporary, shall be provided and maintained at all times. No materials or constructions shall be placed within 10 feet of such hydrants or connections, or between fire hydrants and the center line of the street.
16. Scaffolding materials or equipment shall not block fire escape routes or access routes during performance of projects in occupied buildings.
17. In all buildings over 30 feet in height, at least one stairway shall be provided in a usable condition at all times.
18. Notification and actions to be taken in case of a fire:
a. Persons who discover a fire shall immediately alarm all personnel in the area, and shall report the fire to the Community Military Police using the nearest telephone. Military telephone dial 117.
b. The fire shall be reported using the building number. If the fire is outside of a building, the nearest building number shall be given. Stay on the phone until the operator on duty has completely understood and does not have any further questions. After the notification you should immediately ensure all windows and doors are closed and that all personnel have left the area. The responding fire department must be informed if any special dangers exists; example: If gas and pressurized containers, or paint and other flammable material are within the range of the fire. Not only acute fires, but also fires which have been extinguished and did not cause any damage must be reported.
c. To ensure smooth notification and fire fighting procedures, it is essential to show all employees the location of the nearest telephone, make sure they are familiar with the building number in which they are employed, and inform them of the locations of the fire extinguishers.
Also, for fire safety reasons, hot work permit shall not be issued to perform cutting or welding operations before or after USAG BENELUX AOR regular duty hours (from 8:00 to 16:30).
G-07: ENVIRONMENTAL STEWARDSHIP
All measures shall be taken to prevent occurrence of spills during works. When a leak is detected (i.e. fuel leak on field works vehicles or company vans), the contractor shall coordinate immediate clean-up of the spill. Should clean-up of the spill exceed the contractors response capabilities, the contractor shall immediately contact the following:
1) The COR: TBD
2) The Chievres Air Base Fire Department (068/ 27 54 01).
3) The USAG Benelux Environmental Division (068 27 5704)
4) The Spill Response Coordinator (068 27 5906)
The contractor shall be briefed on the USAG Benelux Environmental Management System (EMS) and its significant aspects prior to commencing work on USAG Benelux. Once the contractor has been briefed, an EMS verification document should be signed and uploaded to the Brussels Regional Contracting Office website.
The USAG Benelux Environmental Management System (EMS):
USAG Benelux implemented EMS IAW EO13693, ISO 14001:2015(E), DoD, and IMCOM requirements. An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. USAG Benelux and EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause a real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities, and authorities while supporting the Garrison’s mission. Contractors and their personnel are required to be aware of, and comply with, the Garrison EMS policy and legal and other requirements when performing work at an installation.
The Garrison EMS is explained during the contractor pre-performance meeting and/or in the EMS manual, which may be requested from the Environmental Division. The USAG Commander’s Environmental Policy may be viewed on line at:
http://www.usagbenelux.eur.army.mil/documents/Policies/BNL_PL17(PWE)EnvironmenalMg t%20System(EMS).pdf
G-08:
SITE MAINTENANCE AND FINAL CLEANING
During performance of the requirement, all measures shall be taken to avoid improper temporary storage of waste generated by performance. Emphasis is placed on Petroleum, Oil and Lubricants (POL) containing equipment or soiled/ hazardous waste (scrap metal, contaminated soil). As soon as the work is finished, the contractor shall remove all equipment, excess materials, debris, etc. generated by his work and shall evacuate them outside US Government installations.
G-09: COORDINATION IN MATTER OF SAFETY AND HEALTH
In accordance with the Royal Decree of 25 January 2001 concerning temporary and mobile worksites, the Safety and Health Plan contains, but is not limited to, the following elements:
- Description of the work to be performed
- Description of the risk analysis results (stage by stage analysis of the risks, analyses which are too vague shall not be acceptable).
- Description of the prevention measures to be taken, to include the following:
1. All the mitigating measures;
2. Specific measures relating to the activities; AND
3. Instructions for the parties involved.
- Expected duration of the work to be performed simultaneously or consecutively.
- A list containing the names and addresses of all project owners and contractors.
- Name and address of the design safety coordinator.
- Name and address of the implementation safety coordinator when he is appointed.
Additionally, and in accordance with the Royal Decree of 25 January 2001, the contractor shall comply with the following:
1. The law of 04 August 1996 related to the welfare of workers during the execution of their work and the royal decree of 25 January 2001 concerning temporary or mobile work sites are applicable for this project.
In accordance with article 71, §3, of above mentioned royal decree, a project-coordination as foreseen in section III, 1st sub section, of this royal decree has been set up during the elaboration of this project. Therefore, there is a safety and health plan related to this project for these specifications.
The contractor shall comply with the recommendations of this safety and health plan (available upon request to the “Engineering Plans and Services Division”, Hangar # 6, Chievres Air Base (David Diricq, EPS Division, tel.068/27.54.46). These recommendations are part of this project.
In application of the same article 71, §3, an execution-coordinator shall be designated by the COR for the coordination in matter of safety and health during the execution of this project.
Within 15 days after contract award, the contractor shall submit at least 3 proposals of execution-coordinator to the COR for approval, along with the necessary documents for the verification of the compliance with the conditions to exercise the coordinator function (art. 56 to 64 of R.D. dated 25.01.2001 completed by the royal decree of 19.12.2001) No proposal may emanate from a coordinator working for the awarding firm or for an office on which the contractor has a supervisory position.
The COR has 10 calendar days to choose the execution-coordinator.
The coordinator’s fee is at the contractor’s charge.
2. The contractor has 15 days from the selection of the coordinator to make up and transmit to the COR. and to the execution-coordinator a document with all the complementary elements to the offer that could be claimed by the coordinator.
3. The execution-coordinator does not act as a substitute for the COR He plays the role of an advisor of the awarding party. His mission is the following:
3.1 General obligations from the law of 04 August 1996 and royal decree of 25 January 2001
1. Coordinate the implementation of the general prevention principles described at article 5 of the law of 04 August 1996, during the technical or planning selections, in order to schedule the various simultaneous or consecutive works or phases of work, as well as during the expectation of the duration of these various works or phases of work;
2. Coordinate the implementation of relevant provisions in order to ensure that the contractors properly implement the general prevention principles and execution principles described at articles 4, 5 and 15 of the law of 04 August 1996;
3. Draw up a coordination logbook comprising the elements described at article 33 of the royal decree of 25 January 2001, except for elements dealing with the design of the project, and to update it;
4. Write down the deficiencies of the various parties in the logbook and to notify the COR;
5. Write down contractors’ remarks in the coordination logbook and leave them for information to the parties concerned;
6. Call and be the chairman of the coordination structure when such a structure has to be set up in accordance with article 37 of the royal decree of 25 January 2001;
7. Draw up an ulterior performance file whose content conforms with article 36 of the royal decree of 25 January 2001;
8. Organize the cooperation and coordination of activities between contractors, including those who follow one another, in order to ensure the protection of workers and the prevention of accidents and professional health hazards, as well as their mutual information;
9. Coordinate the supervision of the proper application of work procedures;
10. Take all necessary precautions so that only authorized people have access to the work site.
11. At the provisional acceptance of the work, to hand over the updated logbook and the ulterior performance file to the COR, and to notify this delivery in a record attached to the ulterior performance file.
3.2 Special obligations within the scope of this project
1. Read and understand these specifications related to the work to be executed, especially the article concerning the safety and health measures to be implemented on the work site in application of the law of 4 August 1996 about the welfare of workers during the execution of their work, and of R.D. of 25 January 2001 about temporary or mobile work sites; the temporary work site will be discussed at the post award conference, and determined in conjunction with the Air Force, contractor, and COR, prior to the issuance of the Notice to Proceed (NTP).
2. The execution coordinator shall offer advice to the COR, document meetings, and make proposals in due time concerning the implementation and adaptations of the document described at item 2 of above mentioned article, during the previous phase described in that item 2 as well as during the execution of the work;
3. Participate in any meeting as requested by the COR or execution-coordinator, and schedule any necessary meetings with the COR or the execution-coordinator in support of the mission;
4. Control the application of the hazards prevention measures described at item 3 of the above mentioned additional article;
5. Monitor and track contractor’s obligation deficiencies as foreseen in above mentioned item 3 in the logbook; contractor deficiencies will be documented by the COR via Non-conformance reports (NCR).
6. Provide a copy of the health and safety plan for this worksite which mentions the results of the risk analysis.
7. The contractor applies the hazards prevention measures foreseen in the document described at item 2, adapted if necessary. All sections of this document will also be applied to sub-contractors.
8. During the execution of the work, the contractor updates the document described at paragraph 3.1.2, either independently, when the progress of the work justifies it, the identification of unforeseen or insufficiently known hazards justifies it, at the onset of employee turnover, for any modification to the project, or at the COR’s discretion. If some update occurs as a result of contractor action, the contractor must inform the COR and the execution-coordinator. The contractor shall take into account any possible remark expressed by the COR.
In particular, the contractor shall also provide the following information to the COR, as well as the execution-coordinator:
· Name of the subcontractor(s), with their certificate, the nature and cost of the work they are responsible for, the expected starting date and duration;
· Traffic rules and road signs for the work site, for the public traffic area (automobiles, bicycles, handicapped people…) and for the area reserved for the work and workers, and the access rules;
· Storage procedures and evacuation of materials and debris; AND
· Work planning.
9. The contractor shall give to the execution-coordinator, spontaneously or by request, any information that is indispensable for the execution of the mission. The contractor shall invite the execution-coordinator to any meeting where the execution-coordinator’s presence is necessary for the accomplishment of the subject task. The obligations of paragraph 8 shall also be applied to all possible subcontractors, enforced by the contractor.
10. The compliance with the obligations described in items 2, 5 and 6 above is an integral part of this project. The application of hazards prevention measures described at item 4 is also an integral part of the project, provided that these measures do not exceed the general obligations that the law of 4 August 1996 and the R.D. of 25 January 2001 impose to contractors, in particular articles 7 and 15 of the law, and section VI, sub section IV of the decree.
11. The full text related to the coordination in matter of safety and health concerning this project can be requested to the “Engineering Division”, Hangar # 6, Chievres Air Base (POTTIEZ Christophe, tel.068/27.56.83).
G-10: ACCESS TO THE MILITARY INSTALLATION
Access control/Photography. The contractor and all associated subcontractor employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor shall also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.” Contractor must receive written approval from PAO prior to taking any photos or making any sketches, and may not discuss layout of any infrastructure with anyone outside the USAG Benelux or not associated with the contract. Contractor must receive written approval from PAO prior to taking any photos or sketches. All photos, sketches, and designs must be returned to DPW upon completion of the contract.
AT Level I Training. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas shall complete AT Level I awareness training within [insert number of calendar days] calendar days after the contract start-date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within [insert number of calendar days] calendar days after training is completed by all employees and subcontractor personnel. AT Level I awareness training is available online at https://atlevel1.dtic.mil/at.
Access and General Protection/Security Policy and Procedures. The contractor and all associated subcontractor employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor shall also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
OPSEC Training.
According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training, and submit required training certificates to the COR.
G-11:
SPECIALS CONSIDERATIONS (UFC 3-260-01 on 17 NOVEMBER 2008)
UFC 3-260-01: 17 NOVEMBER 2008
SECTION 14 CONSTRUCTION PHASING PLAN AND OPERATIONAL SAFETY
ON AIRFIELDS DURING CONSTRUCTION
Link: https://www.wbdg.org/ccb/DOD/UFC/ufc_3_260_01.pdf
G-12: FINAL INSPECTION
The COR shall conduct the final inspection of the work in the presence of the contractor.
G-13: QUALITY CONTROL PLAN
The contractor shall develop and maintain a Quality Control Plan (QCP) to ensure services are performed in accordance with this Statement of Work (SOW). The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor's QCP is the means by which it assures that the work provided complies with the requirements of the contract.
CHAPTER II
TECHNICAL PROVISIONS
SECTION 1
PRELIMINARY WORK AND DISMOUNTING
TP-1-01:
Preparation and protection of the work site According to the ENs, to comply with in matters of safety and health, the contractor shall fence the work site, install scaffolding, and shall take all precautions to protect his personnel, and the personnel and users of the building. The work site area shall be completely protected by a rigid fence (to be submitted to the COR’s approval) to prohibit access to unauthorized people.
Moreover, to prevent dust from spreading in the building during the work, the contractor shall install a double plastic protection over the air handling units.
TP-1-02:
Dismounting of lightning system Lightning rods and cables (grounding) shall be carefully dismounted and stored during performance, and shall be reinstalled after the roof repair is completed.
TP-1-03:
Full cleaning of the roof The existing roof shall be entirely cleaned, all fittings included (weather fillets, wall covering, gutters, etc.). All waste materials shall be evacuated to an authorized public dump.
For the repair of the roof itself, the work shall be executed in phases so that the roof does not remain partly uncovered at the end of one day’s work. Once the cleaning of one area is complete, the vapor barrier insulation and sub layer shall be directly installed in order to limit maximum risks of water infiltration. At the end of the day, the sub layer shall be glued to the existing roof. A detailed planning showing the successive phases of the work must be submitted with the contractor’s proposal for evaluation purposes. A finalized plan shall be submitted to the COR for approval three (3) weeks before commencement of work.
General remark The contractor is responsible for the prevention of all water entering the building, and keeping all Government equipment/property from being damaged. Additionally, the contractor shall insure the safety of all individuals with access to the site, staging areas, and work area foot print.
Contractor must provide technical data of materials, shop drawings, work schedule and safety plan prior to beginning work. The above must be approved prior to ordering material and processing with work. Three (3) copies of submittals and shop drawings must be provided to COR 3 weeks prior to contractor ordering materials.
SECTION 2
ROOF RENOVATION
TP-2-01:
Existing roof deck
The existing roof deck is made of 2 crosswise installed roof panels with inserted wool insulation.
Type: MP 90.500/1 Under and MP 42.333/3 Upper brand Metal PROFIL. The bottom panel (bearing panel) is laid on the metallic beams.
TP-2-02:
Vapor barrier Rolls shall be aligned and unfolded on the support with an overlap of 10cm, and then folded back again. Pour a hot bitumen layer with a sprinkler before the roll (overlapping included). The roll shall be immediately unfolded and pressed in the bitumen. The consumption of bitumen depends on the flatness of the support, with a minimum of 1kg/m2.
Bitumen membrane reinforced with a 3mm thick glass membrane.
Bitumen Technical characteristics
- Bitumen content: min. 2100g/m2
- Filler content: 30% max.
- Surface mass: min 3000g/m2
- Creep temperature: min 70oC
- Folding test: no cracks 20oC
- Folding test: no break 3oC
The vapor barriers shall be glued on the steel deck and welded with 10cm overlap. In order to properly install this layer, a thin water resistant wooden panel Multiplex shall be inserted between the metal and the vapor barrier with 4mm thickness.
TP-2-03:
Insulating material
Flat roof insulation panels on steel deck partially bonded bituminous waterproofing with hot bitumen. The thermal insulation shall be executed with a board of rigid Polyisocyanurate foam with a core volume weight of ± 30 kg/m3 and a Euroclass E fire resistance according to EN 13501-1.
Boards shall be coated on both sides with a mineral and perforated glass membrane.
The production of the insulation boards is certified according to:
- ISO 9001: 2008 standards and ISO 14001:20004
- ATG 1575.
- ATG/H750
- CTG-077
- NBN EN 13165
The declared thermal conductivity coefficient is λD = 0.027 W/mK. The minimum thickness shall be 120mm, with pressure resistance with 10% distortion ≥ 120 kPa (1.2 kg/cm2).The dimensions of the boards are 1200 mm x 1000 mm x 120 mm.
The minimum thickness of insulation panels shall be 1/3 of the corrugation width of the steel plate. When the corrugation width is larger than 100 mm care should be taken so that the insulation board edges are fully supported. The boards are installed staggered and with closed joints. The waterproofing is applied directly after the installation of the insulation. The boards are mechanically fixed to the steel deck. The amount of fastenings shall be defined according to their quality, the wind load and the thickness of the steel board, with a minimum of 6 fastenings per board in the central roof area and a minimum of 8 per board in the edge zone and in the corners of the roof. Fixation on the roof edge shall be provided. The mechanical fixations to be used shall meet the requirements in compliance with the UEAtc-class II and shall have a minimum diameter of 4.8mm. On the insulation boards, a perforated bituminous layer (15% perforations) suitable for using hot bitumen is applied. The insulation boards are fully bonded to the waterproofing membrane with hot bitumen.
The necessity of a vapor control layer shall be determined by a calculation or by the Technical Information Notice 215 “Flat Roof” from the CSTC (Centre Scientifique et Technique de la Construction). The specific guidelines in this note are applicable.
TP-2-04:
Sub layer (vapor spread) Rolls shall be aligned and unfolded on the support with an overlapping of 10cm, and then folded back again. Pour a hot bitumen layer with a sprinkler before the roll (overlapping included). The roll shall be immediately unfolded and pressed in the bitumen. The consumption of bitumen depends on the flatness of the support, with a minimum of 1kg/m2.
Bitumen membrane reinforced with a 3mm thick glass membrane.
Bitumen Technical characteristics
- Bitumen content: min. 2100g/m2
- Filler content: 30% max.
- Surface mass: min 3000g/m2
- Creep temperature: min 70oC
- Folding test: no cracks 20oC
- Folding test: no break 3oC
TP-2-05:
Water tightness layer The membrane shall be composed of a blend made of specific bitumen modified by noble polymers (high-grade APP also called TPO) & two distinct reinforcements, fiberglass & non-woven polyester.
A 4mm membrane, obtained by coating and surfacing of non woven polyester (150g/m2) and glass membrane (55g/m2) by means of a mixture of specific bitumen, noble thermoplastic atactic polyolefines (TPO) and a “halogen free”, nature friendly, fireproof system.
Inside the membrane, reinforcements shall be off centered towards the upper part with regard to the middle plan. The glass membrane shall be separated from the non woven polyester, and is visible at the upper side of the membrane.
The membrane shall conform to the fire resistance norm pr EN 1187-1, -2 and -3. The finished product shall be totally recyclable. The management system of the production and control of the membrane shall be certified ISO 9002 and ISO 14001.
Technical characteristics
- Thickness: 4mm
- Glass membrane reinforcements: 55 ± 10g/m2
- Non woven polyester
- Heat resistance: 150oC
- Cold flexibility: -20oC
- Resistance to longitudinal traction: 675N/5cm; to transversal traction: 625N/5cm
- Breaking longitudinal elongation: 50%; breaking transversal elongation: 50%
- Dimensional stability: ≤ 0.1% (*)
(*) 15cm shrinking on transversal overlapping and executed according to prescriptions = 0mm.
Welding of membrane Rolls are aligned on the support with an overlapping of 10cm between each other, and folded back. Unroll the watertightness membrane, heating up its lower side to flux it; have the membrane adhere to the support. The overlapping must always be welded with a flame over their entire width of 10cm; edges are then pressed with a ±15kg roller. Transversal overlappings are 15cm. A small quantity of bitumen must flow off the overlapping joint. The bitumen cord may be beveled with the tip of the heated trowel.
Raised parts Raised parts totally shall be adhered by flame welding. Raised water tightness coverings shall be distinct from those applied horizontally, with which they connect at the basis of the 10cm min. overlappings welded with a flame. The angle of the raised part must always have two thicknesses. The edges shall be laid in max. width corresponding to the width of the rolls with an overlapping of 10cm.
Type of membrane: same as described in the “water tightness” item.
Remark Raised parts must at least be 150mm higher than the finished level of the roof, which is determined by the water tightness. Along the acroter, the raised part must be put under the wall cover.
Important remark
By decision of the Fire Chief of the U.S. Army, it is strictly forbidden to install heating devices (i.e. cauldrons) directly on the roof. The solution proposed by the contractor must be approved by the COR and the Fire Chief three (3) weeks before starting the work.
SECTION 3
FINISH WORK
TP-3-01:
Wall cover The contractor shall be responsible for the supply and installation of new wall covers. The dismounting of old wall covers must be included in this item. The model of wall cover proposed by the contractor shall be submitted to the COR’s approval three (3) weeks before installation.
TP-3-02:
Zinc work The contractor shall be responsible for the supply and installation of zinc pieces for the protection and watertightness of all related building roof components along the gutter. The model of zinc work proposed by the contractor shall be submitted to the COR.’s approval before installation.
TP-3-03:
Reinstallation of lightning system The lightning rods and associated cables shall be reinstalled according to Norm IEC 62305. If necessary, additional length of cables shall be foreseen to adapt the system to the new roof. After reinstallation, the installation must be approved by BELAC certified firm (http://economie.fgov.be/en/entreprises/life_enterprise/quality_policy/Accreditation/).
TP-3-04:
Repair metallic roof gutter
The Contractor shall be responsible for the following work:
- Clean and evacuate debris.
- Cut the roof overlapping in the gutter in order to widen the gutter
- Carefully brush the gutter to remove rust particles
- Paint metallic gutter with Steoline ferro paint with zinc and iron phosphate basis
- Lay primer bond coat
- Provide and install polyester finish profile
- Provide and install finish water tight membrane, with accessories and joints
- Provide and install watertight membrane between the gutter and the roof slope
TP-3-05:
Provide and install rainwater inlets The Contractor shall be responsible for the following work:
- Provide and install 24 rainwater inlets with a diameter of 100mm, with connections and opening in the existing roof gutter.
TP-3-06:
Water downspouts The water downspouts and accessories (funnels, elbows, Tees, etc.) shall be made of black Polyethylene High Density (PEHD), of mirror welded type, with Ethylene Propylene Diene Monomer (EPDM) connection joints (for aesthetic reasons, electrically welded sleeves are prohibited).Downspouts and accessories shall be BENOR certificated according to norm NBN EN1519.
Water downspouts shall be fitted with appropriated hinged collars every meter. The installation of expansion sleeves and fixed point shall be done according to the manufacturer’s recommendations.
Characteristics
- Color: black
- Shape: rounded
- UV proof
- Thickness: 6.2mm
- Diameter: 160mm
- BENOR certified according to NBN EN 1519
CHAPTER III
SCHEDULE
The contractor shall submit proposals according to the following schedule:
| Item |
| Description |
| QTY |
| U |
| U.P. |
| T.P. |
| TP-1-01 |
| Preparation and protection of work site |
| 1 |
| LS |
| TP-1-02 |
| Dismounting of lightning system |
| 1 |
| LS |
| TP-1-03 |
| Full cleaning of roof |
| 2400 |
| M2 |
| TP-2-02 |
| Vapor barrier |
| 2440 |
| M2 |
| TP-2-03 |
| Insulation |
| 2440 |
| M2 |
| TP-2-04 |
| Sub layer |
| 2440 |
| M2 |
| TP-2-05 |
| Watertightness layer |
| 2440 |
| M2 |
| TP-3-01 |
| Wall cover |
| 122 |
| LM |
| TP-3-02 |
| Zinc work along the gutter |
| 80 |
| LM |
| TP-3-03 |
| Reinstallation of lightning system |
| 1 |
| LS |
| TP-3-04 |
| Repair gutter |
| 80 |
| LM |
| TP-3-05 |
| Provide and install rainwater inlets diam.100mm |
| 24 |
| EA |
| TP-3-06 |
| Water downspouts PEHD pipe diam. 160mm |
| 218 |
| LM |
| G-10 |
| Coordination in matter of safety and health |
| 1 |
| LS |
TOTAL:
Units:
LS – Lump sum
EA – Each
LM – Linear meter
M2 – Square meter