W912PA-16-R-0002-0001.pdf
PDF 28 KB Posted
- Attached to
- Finishing Works throughout Belgium
- Solicitation number
- W912PA16R0002
About this file
Questions and Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ELIN_Schedule_E.pdf | ||
| Past_Performance_Questionnaire.pdf | ||
| W912PA-16-R-0002.pdf | ||
| Specifications_E_revised.pdf | ||
| Specifications_F_revised.pdf | ||
| ELIN_Schedule_F.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US MILITARY FORCE - RCO BENELUX
GENEVIEVE PEIFFER
32-2-7179613
LEUVENSESTEENWEG 13
1932 SINT-STEVENS-WOLUWE
BELGIUM
0010774406 R-CH-O2D-15045-15
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
a. The purpose of this Amendment is to address questions submitted by offerors. Questions and answ ers are attached.
b. The closing date and time is extended to 25 April 2016 - 14.00 hrs
c. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Apr-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PA-16-R-0002
X 9B. DATED (SEE ITEM 11)
14-Mar-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Apr-2016
CODE
US MILITARY FORCE - RCO BENELUX
LEUVENSESTEENWEG 13
1932 SINT-STEVENS-WOLUWE
BELGIUM
W912PA 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W912PA
FACILITY CODECODE
EMAIL:TEL:
W912PA-16-R-0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 18-Apr-2016 02:00 PM to 25-Apr-2016 02:00 PM.
The Issued By organization below has been added:
US MILITARY FORCE - RCO BENELUX
GENEVIEVE PEIFFER
32-2-7179613
LEUVENSESTEENWEG 13
1932 SINT-STEVENS-WOLUWE
BELGIUM
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been added by full text:
QUESTIONS AND ANSWERS
1) Sub-factor a can we demonstrate possession of these certificates through a subcontractor?
Response: No. Prime must have the certifications.
- Class 4 (up to € 900,000.00), D13 (painting)
- Class 3 (up to € 500,000.00), D25 (wall and floor covering work other than marble, wooden flooring and floor tiles)
2) Sub-factor c can we demonstrate the possession of the VCA certificate through a subcontractors?
Response: No. Prime must have certifications.
3) Is this a full and open competition?
Response: Yes.
4) Questions posed by contractors during a site visit, and information related to each building are provided below, and broken down by location:
a. Thrift Store:
i. How many layers of flooring are under the exposed flooring, and how many layers will need to be removed?
Response: Unknown at this time.
ii. New electrical work will be provided for under a different contract.
b. Barracks:
i. All walls currently have walls with tile extending approximately ¾ up with the wall. This is the same on every floor.
ii. The finishing works in the barracks will consist of painting the walls and replacing carpet tiles only. The ceilings and sprinkler system will remain untouched.
c. Hangar 6:
i. Exterior walls of the building may be painted.
ii. Removal of vinyl flooring may be requested.
iii. Painting of interior walls may be requested.
iv. Painting of large hangar sliding door may be requested.
W912PA-16-R-0002
v. Removal of ceiling tiles may be requested.
d. Off Base Housing:
i. Painting will be required after a change of occupancy.
e. Additional questions:
i. Will the work be accomplished step by step, or office by office?
Response: This is an IDIQ; therefore, the amount of work to be completed will be identified by each delivery order at the time of issue. The Government cannot anticipate the size of each delivery order at this time, as this will depend on availability of funds or other information at the time of the order.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .