This solicitation package seeks proposals for the construction of two pump stations and two relief wells for the Wood River Levee District. Key requirements include installation of Pump Stations No. 2 and No. 3, drilling of two relief wells, removal of debris from the construction limits, and coordination with local authorities and utility owners. Proposals are due to the specified Corps of Engineers recipients by the stated deadline. The selected contractor will be responsible for traffic control, obtaining utilities, complying with safety standards, and conducting surveys. Insurance coverage must be provided, and the contractor will be evaluated on performance. The stone sources listed are pre-approved for use on the project.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 SURVEYS
1.2 PAY REQUESTS
1.3 RIGHT-OF-WAY
1.4 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
1.5 DAMAGE TO WORK
1.6 QUANTITY SURVEYS
1.7 PARTIAL PAYMENT
1.8 CERTIFICATES OF COMPLIANCE
1.9 PURCHASE ORDERS
1.10 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
1.11 ACCIDENT INVESTIGATIONS AND REPORTING
1.12 ACCIDENT PREVENTION PROGRAM
1.13 DAILY INSPECTIONS
1.14 ENVIRONMENTAL LITIGATION
1.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.16 SUBCONTRACTS
1.17 REQUIRED INSURANCE - WORK ON A NON-GOVERNMENT INSTALLATION.
1.18 PROTECTION OF MATERIAL AND WORK
1.19 CONTAMINATION OF WATER
1.20 COMMERCIAL WARRANTY
1.21 ORDER AND COORDINATION OF WORK
1.22 SUBMITTALS
1.23 STONE SOURCES
1.24 CONTRACTOR PERFORMANCE EVALUATIONS
1.25 SECURITY REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 08 00 Page 1
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 SURVEYS
The work indicated on the drawings is determined from the latest available survey data. If any of the Contractor's pre-work field measurements indicate any substantial changes in the site condition which, in the opinion of the Contracting Officer, may require a revision in any design feature, drawings and supplementary specifications will be issued.
1.2 PAY REQUESTS
Pay requests authorized in the Contract Clause entitled "Payments Under Fixed-Price Construction Contracts", will be paid pursuant to the clause entitled "Prompt Payment for Construction Contracts". Pay requests shall be submitted on ENG Form 93 and 93a, "Payment Estimate-Contract Performance" and "Continuation", respectively. All information and substantiation required by the identified contract clauses shall be submitted with the ENG Form 93, and the required certification shall be included on the last page of the ENG Form 93a, signed by an authorized official of the Contractor and dated when signed. The designated billing office is the Office of the Area Engineer.
1.3 RIGHT-OF-WAY
Right-of-way for construction purposes will be furnished by the Government without cost to the Contractor. Where right-of-way for access to a work site is not available over existing public roads, access through private lands as shown on the contract drawings will be furnished by the Government without cost to the Contractor. The Contractor will be required at its own expense to do all work necessary to make such right-of-way suitable for traveling to and from the work site without interrupting the existing drainage. Upon completion of the contract work, any such access roadway and right-of-way furnished by the Government shall be left in a condition satisfactory to the Contracting Officer.
1.4 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not move or disturb any public utilities or private improvements. Such removals, alterations, and/or relocations, where necessary, will be made by others. The locations shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.
b. The attention of the Contractor is directed to the possibility that public utilities or private improvements may be encountered within the construction limits, some of which may be buried, and the existence of which is presently not known. Should any such utilities or improvements be encountered, the Contractor shall immediately notify the Contracting Officer so that a determination may be made as to whether they shall be removed, relocated, or altered. After such
DOCUMENT 00 08 00 Page 2 determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required and an equitable adjustment will be made. In the event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latters' removal, alteration, or relocation operations.
1.5 DAMAGE TO WORK
a. The responsibility for damage to any part of the work to be performed under this contract shall be as set forth in the clause of the contract entitled "Permits and Responsibilities". However, if the cofferdam(s) is constructed in accordance with plans and progress schedules approved by the Contracting Officer, but is overtopped by flood and such flood causes damage to the cofferdam or if any part of the permanent work is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precaution or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such damaged work, an equitable adjustment pursuant to the Contract Clause entitled, "Changes", will be made as full compensation therefore.
b. The Contractor may, subject to approval of the Contracting Officer, or the Contracting Officer may order the Contractor to, flood or breach the cofferdam during a rise prior to, and in anticipation of, natural flooding due to overtopping. Such flooding or breach will be considered the same as though the cofferdam, if constructed in accordance with plans and progress schedules approved by the Contracting Officer, had been overtopped, in which event an equitable adjustment will be made for damages to the cofferdam and/or any part of the permanent work, as provided in (a) above.
1.6 QUANTITY SURVEYS
The Contractor shall have a Professional Land Surveyor registered in the state the work is being accomplished conduct original and final earthwork surveys. Surveys shall be performed in the presence of the Contracting Officer and all field survey notes be initialed by the Government Representative and furnished to the Government within 24 hours unless directed otherwise by the Contracting Officer.
1.7 PARTIAL PAYMENT
At the discretion of the Contracting Officer, partial payment will be made for equipment delivered and stored on site or off site providing such storage is in accordance with the provisions of these specifications and the Contractor furnishes satisfactory evidence that title to such equipment has been acquired and that it will be utilized on the work covered by these specifications. Partial payment is defined as the invoice amount plus shipping costs. If the equipment is stored off site, the Government shall have the right to inspect the equipment.
DOCUMENT 00 08 00 Page 3
1.8 CERTIFICATES OF COMPLIANCE
Any certificates required for demonstrating proof of compliance of materials with specification requirements shall include the signature and title of an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from responsibility for furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
1.9 PURCHASE ORDERS
Two copies of all purchase orders for other than stock materials showing the firm names and addresses and list of material shall be furnished to the Contracting Officer or an authorized representative as soon as issued.
1.10 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
The Safety and Health Requirements Manual EM 385-1-1 forms a part of these specifications. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/USACEPublications/Engineer-Manuals/ .
Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.11 ACCIDENT INVESTIGATIONS AND REPORTING
Refer to EM 385-1-1, Paragraph 01.D. Accidents, involving contractor and/or subcontractor employees performing any work or related work on a USACE project, shall be investigated and reported immediately to the Contracting Officer or authorized Contracting Officer's representative.
This reporting requirement applies to on-site or off-site accidents. Upon receipt of the initial accident report notification, the Contracting Officer shall issue additional guidance concerning continuing project operations which may include a "cease work" directive. If a cease work directive is issued, the Contractor will not be allowed to resume work related to the accident until all conditions of the "cease work" directive are met. After the initial notification, the Contractor shall ensure a formal investigation is conducted and reports are completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or an authorized representative within one working day after the accident occurs. The accident Investigation report shall be made on ENG Form 3394.
1.12 ACCIDENT PREVENTION PROGRAM
Refer to Contract Clause FAR 52.236-13 entitled, "Accident Prevention".
Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the prework conference, the original and one copy of the Accident Prevention Program shall be submitted to the Contracting Officer for review. See EM 385-1-1 Appendix A (2014 Edition) and checklist included at the end of this section for guidance in creating the Accident Prevention Plan.
DOCUMENT 00 08 00 Page 4
The program shall also include a copy of company policy statement of accident prevention and any other guidance statements normally provided new employees. Each company employee shall be required to sign the company policy statement of accident prevention to verify that all employees have been informed of the safety program, and such signed statements shall be maintained at the project site.
When marine plant and equipment are in use under this contract, the requirements of EM 385-1-1, Section 19 shall be met.
The Contractor shall not commence physical work at the site until the program has been reviewed and found acceptable by the Contracting Officer, or an authorized representative. The Contractor shall submit for approval the Activity Hazard Analysis for each phase of construction prior to the beginning of work in each phase. Also refer to Section 1 of EM 385-1-1.
1.13 DAILY INSPECTIONS
The Contractor shall perform daily safety inspections and record them in RMS. Reports of daily inspections shall be maintained at the job site.
The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:
a. Phase(s) of construction underway during the inspection.
b. Locations of areas inspections were made.
c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.
1.14 ENVIRONMENTAL LITIGATION
a. If the performance of all or any part of the work is ordered by a court of competent jurisdiction to be suspended, delayed, or interrupted as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a Subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the Contract Clause entitled "Suspension of Work".
b. The term "environmental litigation", as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
1.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled, "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this
DOCUMENT 00 08 00 Page 5 clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
b. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The delay must be beyond the control and without the fault or negligence of the Contractor. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous day), be calculated chronologically from the first to the last day of each month, and be recorded as full days. The Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a time extension modification in accordance with the FAR Clause 52.249-10 entitled "Default (Fixed Price Construction)".
1.16 SUBCONTRACTS
In accordance with the Contract Clause entitled "Subcontracts", the Contractor shall, within seven days after the award of any subcontract by the Contractor or a Subcontractor, deliver to the Contracting Officer an electronic copy of a completed Standard Form 1413 with the original signatures of both parties.
1.17 REQUIRED INSURANCE - WORK ON A NON-GOVERNMENT INSTALLATION.
a. The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract at least the kinds and minimum amounts of insurance required in the following schedule:
(1) Workmen's Compensation . Amounts required by applicable jurisdictional statutes.
(2) Employer's Liability Insurance . $100,000
(3) Comprehensive General Liability Insurance .
Bodily Injury - $500,000 per occurrence
(4) Comprehensive Automobile Insurance .
Bodily Injury - $200,000 each person $500,000 each accident Property Damage - $ 20,000 each accident
b. Within 15 days after receipt of Notice of Award and before commencing work under this contract, the Contractor shall notify the
DOCUMENT 00 08 00 Page 6
Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective
(1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
c. The Contractor shall insert the substance of this clause, including this paragraph c, in subcontracts under this contract and shall require subcontractors to provide and maintain the insurance required in paragraph a above. The Contractor shall maintain a copy of all subcontractor's proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
d. Statements of required insurance should be submitted to the following address:
Department of the Army St. Louis District, Corps of Engineers Central Area Office; CEMVS-EC-CA 1222 Spruce Street St. Louis, Missouri 63103
1.18 PROTECTION OF MATERIAL AND WORK
The Contractor shall at all times protect and preserve all materials, supplies, and equipment of every description (including property which may be Government-furnished or owned) and all work performed. All reasonable requests of the Contracting Officer to enclose or specially protect such property shall be complied with. If, as determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payments due to the Contractor.
1.19 CONTAMINATION OF WATER
In addition to the requirements set forth in SECTION 01 11 30, paragraph Protection of Water Resources, the Contractor shall take positive protective measures to prevent spillage of potential pollutant materials such as fuel, emulsion materials, chemicals etc., from storage containers or equipment, into lakes or tributary waters. Such positive protective measures may include, but are not limited to, the following:
(1) A berm enclosure of sufficient capacity to contain such materials.
(2) Security measures to prevent acts of vandalism which could result in spillage of such materials (fences, guards, etc.).
(3) Storage of such materials in an area where the terrain would preclude leakage into lake or tributary waters.
(4) Utilization of secure Government storage areas if the Contracting Officer indicates such space is available. No storage past immediate needs (2 days) without the consent of the Contracting Officer.
The Contractor shall submit its proposals for implementing the above
DOCUMENT 00 08 00 Page 7 provisions in accordance with SECTION 01 11 30, paragraph Environmental Protection Plan.
1.20 COMMERCIAL WARRANTY
The Contractor agrees that the standard commercial equipment furnished under this contract shall be covered by the most favorable commercial warranties the manufacturer gives to any customer for such equipment, and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the Government by any other clause of this contract. The Contractor shall furnish 2 hard copies or an electronic copy of the warranties to the Contracting Officer.
1.21 ORDER AND COORDINATION OF WORK
a. Speed Limit. The Contractor shall be required to strictly adhere to all posted speed limits for all vehicles traveling over local, county and State of Illinois roads.
b. Coordination. The Contractor shall coordinate all activities with the local authorities and utility companies involved. Points of contact are as follows:
Wood River Drainage & Levee District (WRD&LD) Kevin Williams 543 W. Madison Ave.
Wood River, IL 62095 618/401-7226 kwilliams@wrleveedist.org
Ameren (New service, shielding, de-energizing) Brad Long C: 618-610-2896 O: 618-463-4030 blong@ameren.com
Roxana Water Department O: (618)-254-5513
Mayor of Hartford - Bill Robertson billrobertson@hartfordillinois.net
Mayor of Roxana - Marty Reynolds mreynolds@roxana-il.org
Village of Hartford Department of Public Woks Road Closure Coordination O: (618)-251-2694
c. Utilities. The Contractor shall provide potable water, electricity, and sanitary facilities required in the performance of this contract. The Contractor may obtain and utilize these utilities from sources approved by the Contracting Officer. The absence of Government utilities will not relieve the Contractor of his obligation to provide these services.
The Contractor shall field verify all utilities and ensure construction
DOCUMENT 00 08 00 Page 8 activities do not cause any disturbance or damage to the existing utilities. The Contractor is not authorized to undertake any additional work that would be at an additional cost at the direction of one of the POCs listed above. If coordination yields a requirement for additional work at an additional cost outside the scope of this contract, the Contractor shall communicate with the Contracting Officer. Necessary additional work will then be handled in accordance with Section 00700, Contract Clause entitled, "Changes".
Any overhead utility lines shall be protected during construction operations in the vicinity of the existing lines, and the Contractor shall coordinate construction activities with the Electric Utility and any other affected utilities. Installation of any temporary utility items or de-energizing of lines required shall be coordinated with the respective utilities involved. Any disturbance or damage to existing utilities caused by the Contractor shall require immediate notification to the utility owner, and such disturbance or damage shall be repaired by the Contractor or such repair paid for by the Contractor (should the utility require self-performance of such work) at no expense to the Government.
The Contractor will be required to furnish all required electrical construction power required for all construction activities including temporary electrical distribution equipment. The Contractor has the option of negotiating with the local power utility company to bring in temporary power lines, or using gasoline powered engine-generator sets, or both. The Contractor shall include with its bid all up-front and monthly costs for this service. Construction site power lines shall in no way interfere with site work or operations by the Wood River Levee District. All temporary power equipment shall be removed by the Contractor before completion of the contract.
The contractor shall notify the Roxanna Water Department prior to starting construction. The contractor shall always protect the integrity of the existing waterline by bracing, shoring, or some other acceptable means
d. Traffic Control. All traffic shall be handled by means of existing pavement, new temporary and permanent construction, and road closures.
The Contractor shall provide a minimum 30-day public notice to the WRD&LD and the Villages of Hartford and Roxana prior to implementing any road closures or detours. At the end of construction, the Contractor shall be responsible for obliterating any and all temporary roads and connections, and restore them to their pre-construction condition, unless specifically required otherwise. The Contractor shall additionally return existing roads impacted by construction to their pre-construction condition, unless specifically noted otherwise. The contractor shall maintain traffic control for the repairs to Canal Road at all times according to Illinois DOT Standard Specification, Section 701.
e. Sequence Restrictions.
(1) The Contractor shall coordinate with the WRD&LD for the location and restrictions of the Contractor's staging area provided by the local sponsors.
(2) The Contractor shall close Canal Road at the landside of the levee for no more than 7 days in order to install the Pump Station force main discharge pipes under the road. The Road closure shall be coordinated with the WRD&LD and the Villages of Hartford and Roxana.
DOCUMENT 00 08 00 Page 9
f. Sequence Restrictions.
(1) The Contractor shall drill Pilot Hole (PH-272-22) within 45-days after notice to proceed has been initiated. The pilot hole requirements are outlined within specification 33 26 00.00 10 - RELIEF WELLs.
g. Contractor Requirements. The Contractor is advised that the following requirement must be followed:
(1) The Contractor shall remove any and all debris and trash within the construction limits as shown on the drawings. The Contractor shall dispose of all debris and trash off site.
(2) The Contractor shall coordinate any and all dewatering/unwatering operations of the construction site with the WRD&LD. The Contractor's operations shall in no way inhibit or restrict the District's ability to operate the existing gatewell.
(3) The Contractor shall not install or allow the relief wells at PS No. 2 to become operational until PS No. 2 is in operation, or the contractor has another means to control the discharge flow from the relief wells so that it doesn't impact the work site or adjoining properties.
(4) A local storm in the Cahokia Creek watershed can cause the Cahokia Diversion Channel to rise quickly, but any adverse effect on construction operations on the riverside of the levee would be rare. On the interior of the levee, the ditch leading to the gravity drain begins to pond when the gravity drain is closed. Gate closing is heavily dictated by interior rain events at the gravity drains. The closure of the gate based on the flood event will be closed by the levee district between stages of 25 to 32 on The Mel Price gage. Accumulation of local runoff during a closed gravity situation may prevent construction operations if ponding exceeds the natural ground elevation at the construction site. The Contracting Officer will determine the extent of the delay to the work due to high exterior or interior water levels, and the time fixed for completion of the contract will be extended for the period of the time delay, in accordance with Section 00700, Contract Clause entitled, "Default".
1.22 SUBMITTALS
Additional submittals for this contract that are not listed within individual technical provisions are listed below. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 - SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Program; G Statements of Required Insurance; G
SD-06 Test Reports
Ledge Testing; G
DOCUMENT 00 08 00 Page 10
1.23 STONE SOURCES
a. On the basis of information and data available to the Contracting Officer, stone meeting the quality requirements of these specifications has been produced from the sources listed at the end of these Special Clauses.
b. Stone may be furnished from any of the currently listed sources or, at the option of the Contractor, may be furnished from any other source designated by the Contractor and accepted by the Contracting Officer, subject to the conditions hereinafter stated.
c. It is the Contractor's responsibility to determine that the stone source or combination of sources selected are capable of supplying the quantities and gradation needed and at the rate needed to maintain the scheduled progress of the work.
d. After the award of the contract, the Contractor shall designate in writing only one source or one combination of sources from which stone will be furnished. If the Contractor proposes to furnish stone from a source not currently listed, only a single additional source for stone may be designated. Samples for acceptance testing shall be provided as required by SECTION 35 31 19. If a source for stone so designated by the Contractor is not accepted for use by the Contracting Officer, the Contractor may not propose other sources but shall furnish the stone from a source listed at no additional cost to the Government.
e. Acceptance of a source of stone is not to be construed as acceptance of all material from that source. The right is reserved to reject materials from certain localized areas, zones, strata, or channels when such materials are unsuitable for stone as determined by the Contracting Officer. Materials produced from a listed or unlisted source shall meet all the requirements of SECTION 35 31 19, of the Technical Provisions of these specifications.
f. If the Contractor proposes to furnish stone from a source or sources listed, he shall submit Department of transportation ledge testing information from within the past 12 months. Selected ledge or ledges for producing crushed stone shall meet the following MINIMUM requirements: Stone shall weigh more than 155 lbs/cubic foot. The stone shall also have an absorption less than 2 percent. The Contractor shall also schedule a site visit to the quarry to inspect the proposed ledge(s) that stone will be produced. The Government shall be included in the scheduling of the site visit and a minimum 72-hour notice shall be given.
1.24 CONTRACTOR PERFORMANCE EVALUATIONS
In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $100,000.00, the USACE will evaluate contractor's performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period
DOCUMENT 00 08 00 Page 11 of 30 days. Accessing and using CPARS requires specific software, called PKI certification, which is installed on the user's computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor.
Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.navy.mil/. If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.
1.25 SECURITY REQUIREMENTS
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --