This solicitation is for repair and rehabilitation work at Lock and Dam No. 24 on the Mississippi River. The work consists of painting and repairing 15 Tainter gates and bridge spans, including installation of new chain guides on gates, repairing cracks and replacing damaged components, and painting interior and exterior surfaces. The bridge repairs include replacing bearing shoe bolts, removing and replacing gusset plates, replacing crane rail clips and walkway grating, and painting the service bridge. All work will be performed from a floating plant, with bulkheads installed by the government. The solicitation is designated for small businesses, with a response date of December 20, 2019 and award anticipated by February 1, 2020.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 19R0032-0001.pdf | ||
| Amendment 19R0032-0002.pdf | ||
| 19R0032-0001-Sign-In Sheet.pdf | ||
| A22-19R0032-Solicitation.pdf | ||
| H01-19R0032-Ref-Drawings_Part3.pdf | ||
| A02-19R0032-AdvSpecs.pdf | ||
| H01-19R0032-Ref-Drawings_Part9.pdf | ||
| H01-19R0032-Ref-Drawings_Part4.pdf | ||
| H01-19R0032-Ref-Drawings_Part11.pdf | ||
| H01-19R0032-Plans.pdf | ||
| H01-19R0032-Ref-Drawings_Part14.pdf | ||
| H01-19R0032-Ref-Drawings_Part8.pdf | ||
| H01-19R0032-Ref-Drawings_Part5.pdf | ||
| H01-19R0032-Ref-Drawings_Part7.pdf | ||
| H01-19R0032-Ref-Drawings_Part10.pdf | ||
| H01-19R0032-Ref-Drawings_Part13.pdf | ||
| H01-19R0032-Ref-Drawings_Part16.pdf | ||
| H01-19R0032-Ref-Drawings_Part1.pdf | ||
| H01-19R0032-Ref-Drawings_Part2.pdf | ||
| H01-19R0032-Ref-Drawings_Part12.pdf | ||
| H01-19R0032-Ref-Drawings_Part6.pdf | ||
| H01-19R0032-Ref-Drawings_Part15.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lock 24 Gate and Bridge Rehab 19-R-0032
1. What is the estimated number of gates and/or spans to be included in the initial task order?
RESPONSE: At this time, the FY 20 Budget has not been signed and we are under a Continuing Resolution Authority thru 20 Dec 2019. The initial task order will be based on available funding for this project based on the approved FY 20 Budget appropriation.
2. What is the estimated funding for this work in fiscal year 2020.
RESPONSE: This contract is an Indefinite Quantity and Indefinite Delivery Contract which guarantees the Contractor $33,000 whether the government issues any task orders or not. The initial task order will be based on available funding for this project based on the approved FY 20 Budget appropriation and future budget appropriations.
3. Will subsequent individual task orders include the entire scope for repair of at least one gate and/or one span?
RESPONSE: Individual task orders may include partial items on a gate or bridge span, entire scope of gate and/or bridge spans, or multiple gates and/or bridge spans. Ideally at a minimum, an individual task order would include the entire scope for an entire gate and associated bridge span (excluding Storage Yard Bridge Span 16); however, the work to be included in an individual task order will be determined based on available funding.
4. FAR 52.211-10 states the CO will assign task order completion dates. Will the $2,909 per day liquidated damages stated in FAR 52.211-12 apply to any individual task orders? If not, please clarify the value of LD’s for individual task orders if any.
RESPONSE: LD’s apply to each task order.
5. Please refer to 00 08 00 Article 1.22(d). Does the mandated no-work period of Dec 1 to February 23 count as calendar days of contract completion time?
RESPONSE: Yes, the number of days in the no-work period are included in the contract completion time.
6. Please provide photographs of the GFE. If not available, can the GFE be viewed in person?
RESPONSE: Photos of Tainter Gate Pocket Chain Machinery have been included in amendment 0001
7. Refer to Bidding Schedule, Item 0004BA. 0004BA(a) Description is 1st 75 CY, but quantity is 150 CY. Please clarify.
RESPONSE: Bid item 0004BA a. should read “First 150 cubic yards”. Bid item 0004BA b. should read “All over 150 cubic yards”.
8. Refer to Bidding Schedule Notes, Article 11,Variations in Est. Quantities. Please clarify Item 0004BA(b). How does this Article relate to 0004BA(b)?
RESPONSE: 0004BA(b) is considered the second subitem of 0004BA. Subitem (b) will be increased or decreased dependent on actual quantities and is not subject to an equitable adjustment.
9. Due to the Thanksgiving holiday, the complexity of the work and extensive Proposal requirements, we request the bid submittal date be extended an additional 4 business days to December 20, 2019.
RESPONSE: Date extended per amendment 0001.
10) Please state the correct name for the Solicitation. Reads different in various solicitation documents.
RESPONSE: Official title is stated on the Plans and Specifications covers.
11) Refer to Solicitation Proposal Requirements- Tab 3: Subfactor 3 Small Business SBPCD The SB requirement is 25% of TCV. Clarify if 5% minimum of TCV (part of the 25% minimum TCV total), should be indicated in one or any the following categories: VOSB; SDVOSB; Hubzone; WOSB.
RESPONSE: SBD: Must have a Minimum of 5%
12) it’s our understanding this solicitation is a Indefinite Quantity as stated in Bidding Schedule Notes #8, see below for a quick reference. In this note it states that information concerning Indefinite Quantity can be found in section 00700 “Contract Clauses”, however we could not find this section in either “A22- 19R0032 – Solicitation” or “A02 – 19R0032-AdvSpecs”.
Information concerning indefinite quantity contracts, as well as the issuance and limitations of delivery orders may be found in Section 00700, Contract Clauses.
RESPONSE: Please refer to the following Contract Clauses located in SECTION 00 07 00 - Conditions of the Contract:
52.216-18 Ordering Page 45 of the Solicitation 52.216-19 Order Limitations Page 45 of the Solicitation 52.216-22 Indefinite Quantity Page 46 of the Solicitation
13) Spec Sec 00 08 00-1.22-I first states that all work shall be done from the downstream side of the dam, but then later in the same paragraph talks about being able to be upstream of bulkheads. Please clarify the USACE intent of this statement.
RESPONSE: Section revised per amendment 0001. Specification Section 00 08 00 -1.22 (i.) now states, “All work by the Contractor shall be performed from a floating plant, either on the upstream side or downstream side of the dam, or from a fixed platform. The minimum distance between the edge of the floating plant and the bulkheads shall be 3’. The contractor shall not tie off to the bulkheads in any way.
Spuds shall not be lowered onto the apron and/or stilling basing when the floating plant is on the downstream side of the dam; extents of the apron and/or stilling basin are provided in drawings and reference drawings. The Government will determine what flows the Contractor is able to safely operate the floating plant upstream of the dam; floating plant use upstream of the dam is restricted during high flow stages. The floating plant shall be powered by a vessel with no less than 1100 horsepower in order to safely maneuver the floating plant upstream of the dam.”
14) General Note 2 on page SB-401 calls for the entire structure above elevation 471.0 to be painted.
The Tainter Gate Repair Schedule on page SG-535 depicts the repair items and the cleaning & painting scope required for the elevation bellow elevation 471.0 There are some ladders and rails (RS-105,106 & RS-107/ interior and exterior) located in the area below the 471.0 elevation. Do those get painted?
RESPONSE: The handrails and stair treads shown on RS-106 for Pier No. 1, do not get painted. The ladder rungs below Elevation 471.0 for Piers No. 2 through No. 16, shown on RS-107 do not get painted.
The handrails and stair treads shown on RS-113 for Pier No 17, do not get painted.
15) Does the entire interstitial space of each tainter gate receive abrasive blasting and coating?
RESPONSE: The interior and exterior of the Tainter Gates are to be coated with System No. 5-E-Z, as described in Specification Section 09 97 02 Paragraph 3.5 “Painting Schedules”. All the rivets and gusset plates in the interior of the Tainter gates require abrasive blasting for Government inspection to determine which rivets and gussets require replacement, as described in Specification 09 97 02 Paragraph 3.1.5.
16) Are there any records or is it known what the existing coating system is on the interstitial space of each tainter gate?
RESPONSE: The repairs performed as shown in reference drawings RS-251 through RS-257 were coated with System No. 5-E-Z. The coating system applied to the other areas on the interior of the Tainter gate is not known. Test results from paint on the interior of Tainter Gate #1 from 2004 indicate lead, cadmium and chromium. Test results of the sediment on the interior of Tainter Gate #1 from 2004 indicate lead and other heavy metals. Test results from paint and sediment on interior of Tainter Gate #1 from 2004, along with a limited lead based paint risk assessment from 2013 for the project have been provided in Amendment 0001.
17) Given the amount of effort necessary by the contractor for this proposal and in full disclosure, we wanted to know if the USACE St. Louis District would accept a proposal with a schedule showing that we start in 2021 rather than 2020?
RESPONSE: Award of Contract is anticipated NLT 1 February 2020. The submittal process is expected to take approximately 6 months (approximately August 2020) after NTP which will be a partial NTP to complete submittals. As per Specifications, river based operations will only be permitted between 24 February and 30 November. It is likely the best interest of the Government to start construction at the beginning of the construction season in February 2021 after all the submittals have been approved. The issuance of task orders is based on available funding. The contract Length is based on 16 spans with 4 spans completed per year. 4 years for construction and 1 year for submittals. POP of each task order will be awarded as funding becomes available which may span numerous construction seasons over the course of the contract duration.
18) Lastly, what would be the response time required by the contractor once an order is received?
RESPONSE: The Contractor shall be required to commence work under this contract within 10 calendar days after the date the Contractor receives notice to proceed. See FAR 52.211-10 clause in this solicitation. NTP will be given individually for each task order, and typically within 30 days of task order award.
Amendment 0001
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCE DRAWINGS
1.2 PAY REQUESTS
1.3 PHYSICAL DATA (APR 1984) FAR 52.236-4
1.4 WORK AREAS
1.5 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
1.6 DAMAGE TO WORK.
1.7 QUANTITY SURVEYS
1.8 PARTIAL PAYMENT
1.9 CERTIFICATES OF COMPLIANCE
1.10 PURCHASE ORDERS
1.11 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
1.12 ACCIDENT INVESTIGATIONS AND REPORTING
1.13 ACCIDENT PREVENTION PROGRAM
1.14 DAILY INSPECTIONS
1.15 ENVIRONMENTAL LITIGATION
1.16 SUBCONTRACTS
1.17 REQUIRED INSURANCE
1.18 PROTECTION OF MATERIAL AND WORK
1.19 CONTAMINATION OF WATER
1.20 COMMERCIAL WARRANTY
1.21 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.22 ORDER AND COORDINATION OF WORK
1.23 SUBMITTALS
1.24 AS-BUILT DRAWINGS
1.25 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING
PLANT
1.26 EMERGENCY ALARMS AND SIGNALS
1.27 USE OF MECHANIZED EQUIPMENT ON FLOATING PLANT
1.28 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002
1.29 SIGNAL LIGHTS
1.30 INSPECTION FACILITIES
1.31 IDENTIFICATION OF GOVERNMENT-FURNISHED PROPERTY.
1.32 CONTRACTOR PERFORMANCE EVALUATIONS
1.33 SECURITY REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 08 00 Page 1
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCE DRAWINGS
a. One set of the reference drawings which cover details of the existing structure, will be included in each set of the contract drawings furnished the Contractor without charge, in accordance with Contract Clause DFARS 252.236-7001. Drawings showing additional details are available for examination at the Dept. of the Army, St.
Louis District, Corps of Engineers, St. Louis, Missouri. Additional prints of reference drawings will be furnished to the Contractor on request at the cost of reproduction.
b. The stationing and dimensions shown on the contract and reference drawings for the existing structure have been taken from the original contract drawings and the shop drawings for the original construction. The Contractor shall verify all the above stationing and dimensions and shall be responsible for making the new material and work fit the existing conditions.
1.2 PAY REQUESTS
Pay requests authorized in the Contract Clause entitled "Payments Under Fixed-Price Construction Contracts", will be paid pursuant to the clause entitled "Prompt Payment for Construction Contracts". Pay requests shall be submitted on ENG Form 93 and 93a, "Payment Estimate-Contract Performance" and "Continuation", respectively. All information and substantiation required by the identified contract clauses shall be submitted with the ENG Form 93, and the required certification shall be included on the last page of the ENG Form 93a, signed by an authorized official of the Contractor and dated when signed. The designated billing office is the Office of the Area Engineer.
1.3 PHYSICAL DATA (APR 1984) FAR 52.236-4
Data and information furnished or referred to below is furnished for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
a. Physical Conditions. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys.
b. Weather Conditions. Information with respect to temperatures and precipitation may be obtained from the National Weather Service.
c. Transportation Facilities. Railroads and highways serve the general area of the work. Water transportation is available to the site of the work.
d. Condition of River Channel. Data relating to river stages, soundings and flow may be obtained by calling the St. Louis District Corps of Engineers Water Control Management Office at either
DOCUMENT 00 08 00 Page 2
314-331-8342 or 800-432-1208, or by visiting the St. Louis District Corps of Engineers Water Control website at http://mvs-wc.mvs.usace.army.mil.
e. Channel Traffic. There is moderate commercial and pleasure traffic operating in the Mississippi River adjacent to the site. The passage of large craft may delay operations in the channel.
f. Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon completion of the work under this contract, all plant including ranges, buoys, piles, and other marks placed in navigable waters or on shore by the Contractor, shall be promptly removed.
g. Datum and Gages. Coordinate systems are indicated on the plans.
h. Delivery of Government-Furnished Property. The Government-furnished property described herein will be made available to the Contractor upon request as described in the technical specifications and as shown on the drawings. The Contractor shall give the Contracting Officer 5 days notice prior to taking delivery of the Government-furnished property.
1.4 WORK AREAS
In accordance with the Contract Clause entitled, "Operations and Storage Areas", and subject to the approval of the Contracting Officer and the restrictions imposed by SECTION 01 11 30 - ENVIRONMENTAL PROTECTION, of the Technical Provisions, the Contractor will be allowed use of Government-controlled land within the construction limits shown on the drawings or as specified herein.
1.5 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not move or disturb any public utilities or private improvements. Such removals, alterations, and/or relocations, where necessary, will be made by others. The locations shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.
b. The attention of the Contractor is directed to the possibility that public utilities or private improvements may be encountered within the construction limits, some of which may be buried, and the existence of which is presently not known. Should any such utilities or improvements be encountered, the Contractor shall immediately notify the Contracting Officer so that a determination may be made as to whether they shall be removed, relocated, or altered. After such determination is made, the Contractor shall, if so directed by the
DOCUMENT 00 08 00 Page 3
Contracting Officer, remove, relocate, or alter them as required and an equitable adjustment will be made. In the event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latters' removal, alteration, or relocation operations.
1.6 DAMAGE TO WORK.
The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause entitled "Permits and Responsibilities." However, if in the judgment of the Contracting Officer any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or job prices as fixed and established in the contract. If in the opinion of the Contracting Officer there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to the Contract Clause entitled, "Changes," of the contract will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
1.7 QUANTITY SURVEYS
The Contractor shall have a Professional Land Surveyor registered in the state the work is being accomplished conduct original and final earthwork surveys. Surveys shall be performed in the presence of the Contracting Officer and all field survey notes be initialed by the Government Representative and furnished to the Government within 24 hours unless directed otherwise by the Contracting Officer.
1.8 PARTIAL PAYMENT
At the discretion of the Contracting Officer, partial payment will be made for equipment delivered and stored on site or off site providing such storage is in accordance with the provisions of these specifications and the Contractor furnishes satisfactory evidence that title to such equipment has been acquired and that it will be utilized on the work covered by these specifications. Partial payment is defined as the invoice amount plus shipping costs. If the equipment is stored off site, the Government shall have the right to inspect the equipment.
1.9 CERTIFICATES OF COMPLIANCE
Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in 3 copies.
Each certificate shall include the signature and title of an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report
DOCUMENT 00 08 00 Page 4 applies. Certification shall not be construed as relieving the Contractor from responsibility for furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
1.10 PURCHASE ORDERS
Two copies of all purchase orders for other than stock materials showing the firm names and addresses and list of material shall be furnished to the Contracting Officer or an authorized representative as soon as issued.
1.11 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
The Safety and Health Requirements Manual EM 385-1-1 forms a part of these specifications. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/USACEPublications/Engineer-Manuals/.
Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.12 ACCIDENT INVESTIGATIONS AND REPORTING
Refer to EM 385-1-1, Paragraph 01.D. Accidents, involving contractor and/or subcontractor employees performing any work or related work on a USACE project, shall be investigated and reported immediately to the Contracting Officer or authorized Contracting Officer's representative.
This reporting requirement applies to on-site or off-site accidents. Upon receipt of the initial accident report notification, the Contracting Officer shall issue additional guidance concerning continuing project operations which may include a "cease work" directive. If a cease work directive is issued, the Contractor will not be allowed to resume work related to the accident until all conditions of the "cease work" directive are met. After the initial notification, the Contractor shall ensure a formal investigation is conducted and reports are completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or an authorized representative within one working day after the accident occurs. The accident Investigation report shall be made on ENG Form 3394.
1.13 ACCIDENT PREVENTION PROGRAM
Refer to Contract Clause FAR 52.236-13 entitled, "Accident Prevention".
Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the prework conference, the original and one copy of the Accident Prevention Program shall be submitted to the Contracting Officer for review. See EM 385-1-1 Appendix A (2014 Edition) and checklist included at the end of this section for guidance in creating the Accident Prevention Plan.
The program shall also include a copy of company policy statement of accident prevention and any other guidance statements normally provided new employees. Each company employee shall be required to sign the company policy statement of accident prevention to verify that all employees have been informed of the safety program, and such signed statements shall be maintained at the project site.
When marine plant and equipment are in use under this contract, the requirements of EM 385-1-1, Section 19 shall be met.
DOCUMENT 00 08 00 Page 5
The Contractor shall not commence physical work at the site until the program has been reviewed and found acceptable by the Contracting Officer, or an authorized representative. The Contractor shall submit for approval the Activity Hazard Analysis for each phase of construction prior to the beginning of work in each phase. Also refer to Section 1 of EM 385-1-1.
1.14 DAILY INSPECTIONS
The Contractor shall perform daily safety inspections and record them in RMS. Reports of daily inspections shall be maintained at the job site.
The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:
a. Phase(s) of construction underway during the inspection.
b. Locations of areas inspections were made.
c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.
1.15 ENVIRONMENTAL LITIGATION
a. If the performance of all or any part of the work is ordered by a court of competent jurisdiction to be suspended, delayed, or interrupted as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a Subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the Contract Clause entitled "Suspension of Work".
b. The term "environmental litigation", as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
1.16 SUBCONTRACTS
In accordance with the Contract Clause entitled "Subcontracts", the Contractor shall, within seven days after the award of any subcontract by the Contractor or a Subcontractor, deliver to the Contracting Officer two copies of a completed Standard Form 1413. Both copies must contain the original signatures of both parties.
1.17 REQUIRED INSURANCE
a. As required by the Contract Clause entitled "Insurance-Work on a Government Installation", the Contractor shall within 15 days after receipt of Notice of Award and prior to the commencement of work, furnish to the Contracting Officer, a written statement of required insurance as evidence of the following minimum insurance:
DOCUMENT 00 08 00 Page 6
(1) Workmen's Compensation. Amounts required by applicable jurisdictional statutes.
(2) Employer's Liability Insurance. $100,000
(3) Comprehensive General Liability Insurance.
Bodily Injury - $500,000 per occurrence
(4) Comprehensive Automobile Insurance.
Bodily Injury - $200,000 each person $500,000 each accident Property Damage - $ 20,000 each accident
b. Statements of required insurance shall be submitted to the following address:
Department of the Army St. Louis District, Corps of Engineers Northern Resident Office, CEMVS-EC-CN 3307 N HIGHWAY 79, Suite 1 Elsberry, MO 63343-3230
1.18 PROTECTION OF MATERIAL AND WORK
The Contractor shall at all times protect and preserve all materials, supplies, and equipment of every description (including property which may be Government-furnished or owned) and all work performed. All reasonable requests of the Contracting Officer to enclose or specially protect such property shall be complied with. If, as determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payments due to the Contractor.
1.19 CONTAMINATION OF WATER
In addition to the requirements set forth in SECTION 01 11 30, paragraph Protection of Water Resources, the Contractor shall take positive protective measures to prevent spillage of potential pollutant materials such as fuel, emulsion materials, chemicals etc., from storage containers or equipment, into lakes or tributary waters. Such positive protective measures may include, but are not limited to, the following:
(1) A berm enclosure of sufficient capacity to contain such materials.
(2) Security measures to prevent acts of vandalism which could result in spillage of such materials (fences, guards, etc.).
(3) Storage of such materials in an area where the terrain would preclude leakage into lake or tributary waters.
(4) Utilization of secure Government storage areas if the Contracting Officer indicates such space is available. No storage past immediate needs (2 days) without the consent of the Contracting Officer.
The Contractor shall submit its proposals for implementing the above provisions in accordance with SECTION 01 11 30, paragraph Environmental
DOCUMENT 00 08 00 Page 7
Protection Plan.
1.20 COMMERCIAL WARRANTY
The Contractor agrees that the standard commercial equipment furnished under this contract shall be covered by the most favorable commercial warranties the manufacturer gives to any customer for such equipment, and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the Government by any other clause of this contract. The Contractor shall furnish two copies of the warranties to the Contracting Officer.
1.21 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled, "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(5) (6) (7) (7) (7) (8) (8) (9) (6) (6) (7) (7)
c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause entitled "Default (Fixed Price Construction)".
DOCUMENT 00 08 00 Page 8
1.22 ORDER AND COORDINATION OF WORK
The Contractor may start and complete the work in such order and sequence as desired subject to compliance with the following paragraphs:
a. The Contractor shall develop a detailed written work plan in addition to the project schedule required in SECTION 01 13 20 to sequence all work in compliance with the requirements of the plans and specifications and with the following paragraphs. The Contractor shall submit this detailed work plan with the project schedule submittal to the Government for approval before commencement of any work. The work plan shall be in written narrative format and include, but not be limited to, description and sketches/drawings to adequately communicate anticipated construction methods for all work items and sequencing requirements of all activities.
b. The Lock and Dam shall remain in operation during the construction period except as noted on the construction drawings or in the specifications, or as directed by the Contracting Officer's Representative. Lock and Dam operation takes precedence over construction Contractor operations. The Contractor shall coordinate all work with the Contracting Officer's Representative and the Lockmaster, including the setting and removal of Tainter gate bulkheads by the Government. The Contractor shall conduct its operations to not interfere with the functions of the Government personnel and the use of the lock by river traffic.
c. The Contractor will not be given priority over other waterway users for lockages. The Contractor shall adhere to normal queuing procedures as required unless otherwise permitted by the Lockmaster.
d. The Contractor shall be advised that no river based operations and/or gate work will be permitted under this contract during the time period of 1 December to 23 February due to cold temperatures and ice on the river. The Contractor shall remove floating plant from the immediate work site during this period (1 Dec to 23 Feb). The Government will remove bulkheads during this period. Any work started on any gate(s) prior to these dates shall be complete by 30 November such that all gates are fully operational during the period of 1 December to 23 February. Work on the service bridge during the aforementioned timeframe, that is not dependent on the use of a floating plant, will be considered by special request to the Contracting Officer for permission. Due to scheduled lock closures for LD24 and LD25 from 15 December 2019 to 31 March 2020, the floating plant access to the downstream side of dam is restricted.
e. Not more than two Tainter gates shall be out of service for rehabilitation at any one time. When two Tainter gates are out of service, the two gates shall be adjacent to each other. The amount of concurrent structural demolition/rehabilitation on two gates shall be limited as shown on the drawings. Gates on either side of the bulkheaded gate(s) will be adjusted by the Government to the extent permissible for the flow conditions at the time in an attempt to minimize turbulence below the gate being rehabilitated. The Contractor shall be responsible for monitoring water currents within work areas to maintain worker and equipment safety and coordinate all requirements for possible adjacent gate closures with the Government.
All requests by the Contractor, with respect to gate settings, will be coordinated with the Lockmaster. The Lockmaster is responsible for
DOCUMENT 00 08 00 Page 9 maintaining safety and operability of the lock and dam and will only concur and direct gate change settings as determined safe by the Lockmaster.
f. All work required in this contract, including proper containment and disposal of debris, shall be accomplished in place at Contractor's expense.
g. In order to perform required work on Tainter gates as specified in this contract, it will be necessary to close off flow to the gate bay. Emergency bulkheads for closing off the flow to the gates are stored in the storage yard at the east end of the dam. The Government will be responsible for transporting bulkheads from the storage yard, placement and movement of bulkheads. The Contractor shall schedule work within the following parameters:
1) The Government bridge crane shall not be available to the Contractor for any type of use. The Government will utilize the bridge crane for placing bulkheads.
2) The Contractor shall coordinate all requirements related to movement and placement of bulkheads with the Contracting Officer's Representative and the Lockmaster. The Contractor shall notify the Contracting Officer's Representative and Lock master a minimum of five
(5) days prior to the need for movement of any bulkheads. The Government will not be available on weekends and Federal Holidays for bulkhead operations.
3) Prior to the removal of a Tainter gate from service by placement of bulkheads, all materials and equipment needed to complete the required contract work on that gate shall be available on-site and ready for installation.
h. All Tainter gate movements and machinery equipment operations will be conducted by the Government for the Contractor. The Contractor shall schedule any required gate movement within the following parameters:
1) Gate operations will only be performed during the day shift, 0800 to 1600 hours, Monday thru Friday, excluding Government holidays.
2) The Contractor shall provide a minimum 24 hour advance notice to the Contracting Officer's Representative for all gate operations.
Notice shall be provided on a working day (working day = Monday thru Friday, excluding holidays).
3) Flow conditions permitting, prior to the Government placing bulkheads, the Government will flush water under the gate for a minimum of 4 hours.
4) The Contractor shall allow four hours for the Government to complete requested gate position changes.
5) The Government will operate for any purpose, including testing, only one gate at a time.
i. All work by the Contractor shall be performed from a floating plant, either on the upstream side or downstream side of the dam, or from a fixed platform. The minimum distance between the edge of the
DOCUMENT 00 08 00 Page 10 floating plant and the bulkheads shall be 3'. The contractor shall not tie off to the bulkheads in any way. Spuds shall not be lowered onto the apron and/or stilling basing when the floating plant is on the downstream side of the dam; extents of the apron and/or stilling basin are provided in drawings and reference drawings. The Government will determine what flows the Contractor is able to safely operate the floating plant upstream of the dam; floating plant use upstream of the dam is restricted during high flow stages. The floating plant shall be powered by a vessel with no less than 1100 horsepower in order to safely maneuver the floating plant upstream of the dam.
j. The Contractor shall monitor fluctuations of tailwater elevation and make tie off adjustments such that the floating plant shall not damage the piers. Adequate protection between the barge and pier shall be provided by the Contractor at all times to prevent damage to the pier concrete surfaces. The Contractor shall be required to have a safety boat in accordance with Corps of Engineers safety requirements. At all times when work is not in progress, the Contractor shall be required to have a 24 hour telephone number where the Government may reach a representative of the Contractor to notify of any problems with the floating plant. The representative must be available to be on site to attend to work barge(s) within 60 minutes of a phone call from the Government 24 hours a day, 7 days a week.
The Contractor shall post and keep current telephone numbers for emergency action. The Contractor shall submit the contingency plans for addressing headwater and/or tailwater fluctuations to the Contracting Officer for approval at least 7 days before mobilization.
k. The Contractor shall keep the top of the dam clear of debris and equipment at all times and the Contractor shall not restrict the movement of the traveling bridge crane along the length of the entire dam and shall maintain dam walkway access (walkway which is downstream of the downstream crane rail) along the entire length of the dam for daily dam gate setting operations, unless noted otherwise. During Contractor work on the bridge deck, all equipment placement and operations on the deck should be minimized and shall be coordinated with the Lockmaster. The Contractor shall keep all hatches on top of the service bridge closed except for access or egress by personnel, at which time the openings will be barricaded as per EM 385-1-1. This access shall be for the bay in which the bulkheads are being removed/installed and the two adjacent bays.
l. The Contractor shall protect the existing piezometers on the dam piers from damage. Repair to any damage to existing piezometers shall be responsibility of the Contractor.
m. The Contractor will not be allowed access to the lock and dam control station other than for coordination purposes.
n. The Contractor shall furnish all electrical power or other required utilities required for construction activities. No temporary hookups to existing lock facilities will be allowed unless stated otherwise in this specification. The Contractor will be responsible to provide a source of emergency backup power for the Contractor's operations to ensure critical operations can continue in the event of an electrical power disruption.
o. At least 30 days prior to mobilization, the Contractor shall submit the plan for storage of materials and equipment at the site to
DOCUMENT 00 08 00 Page 11 the Contracting Officer for approval.
p. Construction limits will extend as shown on the drawings.
Contractor personnel may cross the main lock upper and/or lower miter gate when the gates are closed, and may cross the auxiliary lock miter gate and dam using the service bridge to gain access to the construction limits. Only hand carried equipment shall be brought across the miter gates and the dam by Contractor personnel. The Contractor shall be provided one keycard to open the front gate, to be used by the QC Superintendent during working hours. The keycard can be checked out from Lock personnel at the start of construction season and shall be checked in after each subsequent construction season.
The QC Superintendent shall be the sole person allowed the keycard and shall be responsible for contractor personnel access through the gate during working hours. If the Contractor works multiple shifts, the Government will allow a different, similar method for keeping the keycard.
q. The Contractor's employees will be required to park personal vehicles as designated on drawings.
r. Potable water and portable toilet facilities for Contractor use shall be provided by the Contractor.
s. No floating plant will be allowed behind the lower guide wall.
Size restriction of floating plant moored at Contractor staging area shall be a maximum combined width of seventy (70) feet.
t. If river levels are such that bulkheads may be overtopped during allowable work periods, the Contractor shall remove all floating plant from dam piers and moor plant off site or to the back side of the Intermediate Wall for the duration of the high water event. The dam bulkheads are overtopped at approximately Stage 27.5' on the Mississippi River at Clarksville Lock and Dam 24 gage.
u. Utilities not shown or identified in the plans or specifications may be encountered by the Contractor during construction activities.
The Contractor shall submit the plan to relocate and restore utilities as required for approval by the Contracting Officer's Representative.
v. Security fencing and hand railing may be removed in work areas during construction as long as safety and security is maintained and replacement made to its original location and condition, including an approved method and type of touch up painting as necessary.
Contractor proposals for modifying fencing and handrails shall meet requirements in EM 385-1-1 and be submitted for approval.
w. Floating plant and personnel shall comply with the applicable U.S. Coast Guard regulations and licensing requirements. Floating plant equipment shall meet the applicable requirements of 46 CFR Chapter 1 Subchapter E and 46 CFR 44.05-10. Floating vessels operating on the Mississippi River and its tributaries must be operated in accordance with 33 CFR 207.3, "Ohio River, Mississippi River above Cairo, Ill., and their tributaries; use, administration, and navigation." The Contractor's methods for disposal of sanitary sewage, and bilge water accumulated aboard floating plant, shall meet applicable local, state, and federal requirements.
x. All elevations and dimensions shall be verified in the field
DOCUMENT 00 08 00 Page 12 before work begins. The Contractor is responsible for confirming all dimensions prior to shop drawing preparation and material fabrication.
y. Various structures identified for work activities contain lead based paint. For structures that are to be painted, all spent abrasive blast material and removed paint shall be contained and disposed of properly. See specification sections for lead based paint removal, containment, and disposal requirements.
z. Diving operations are prohibited for this contract.
aa. Materials which are not salvaged by the Government shall be disposed of in accordance with contract specifications.
bb. The Contractor is advised that the upstream bulkheads may not completely seal while holding back pool, which may affect construction activities. The leakage is variable with water height and seal condition. Due to potential leakage from the bulkheads, the Contractor may find it necessary to install measures in order to facilitate work behind the bulkheads in the gate bays. Leakage prevention measures shall be performed at no expense to the Government and shall be submitted for approval.
cc. The Contractor shall provide measures to protect all new and existing operating machinery and electrical components adjacent to the work areas from contamination by surface preparation, abrasive blast debris, powerspraying, weld splatter, concrete splatter, paint overspray, dust or other related debris during performance of the work. Items to be protected include, but are not limited to, Tainter gate hoists and appurtenant equipment including electrical panels.
The Contractor shall be responsible for any repairs resulting from damage to all new and existing operating machinery and electrical components. If contamination occurs, the Contractor shall adjust the protection to eliminate contamination at other areas as work progresses.
dd. Gate settings on limit switches shall be recorded on each gate immediately prior to commencement of work on that gate. After work is complete on a gate, the limit switches on that gate shall be reset by the Contractor. The limit switch settings shall be verified by the Contracting Officer's Representative and the Lockmaster prior to initially removing the gate from service and prior to bulkhead removal for that gate.
ee. Any metallic surfaces of the dam which receive overspray from the painting operations shall be repainted with the appropriate paint system as directed by the Contracting Officer at no additional cost to the Government. The Contractor shall protect the concrete surfaces on the dam piers from overspray. If any overspray reaches concrete surfaces, the Contractor shall remove it with a method as approved by the Contracting Officer's Representative. All costs associated with overspray removal shall be at the Contractor's expense.
ff. Lengths of Tainter gate chain may be stiff or seized. The Contractor shall be required to free up or cut the links prior to lifting the chain out of the operating machinery below service bridge deck.
gg. The Government will verify, for every gate that has been
DOCUMENT 00 08 00 Page 13 rehabilitated in any manner that the gate can operate through the entire service range while the bulkheads are still in place for that gate. This will be verified to the satisfaction of both the Contracting Officer's Representative and the Lockmaster prior to returning the gate to service. If the gate does not operate to the satisfaction of the Government, the Contractor will correct the problem at his expense.
hh. There are two sets of Tainter gate bulkheads and a single pick-up beam available. Handling and placement of bulkheads will be by the Government.
ii. At Lock and Dam 24, access to the dam across the overflow spillway shall be limited to rubber-tired passenger vehicles or pickup trucks. At pool Elevation 449.10 there is restricted land access with overtopping of the overflow spillway imminent. If the spillway is overtopped the Contractor will not have access from the Illinois side. Due to current security threat levels the Contractor shall be required to keep the storage yard gate and Pier 16 access door locked at all times, when not actually entering or exiting the storage yard or accessing the dam. If the Illinois gate is to be used for Contractor access, the Contractor shall provide a security guard, stationed at the gate, to control such access.
jj. The staging area for the contract shall be the area downstream of the entrance road where it crosses the railroad tracks as shown on contract drawings. No loading or unloading of materials and supplies shall be permitted from the lock walls or guide walls.
kk. The Contractor will be allowed to use the riverside of the I-wall for mooring floating plant. Size restriction of floating plant moored to riverside I-wall is shown on the drawings.
ll. The Contractor shall provide the Contracting Officer and the Lockmaster or the designated representatives a minimum of a two (2) week initial notification and a final 48 hour advance notice prior to commencement of any work. The Contractor shall also coordinate access to the construction area with the Contracting Officer and Lockmaster or designated representatives at the contact information provided below:
Ryan Lee, Lockmaster 350 North 1st Street Clarksville, MO 63336 573-242-3524
1.23 SUBMITTALS
Additional submittals for this contract that are not listed within individual technical provisions are listed below. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 - SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Program; G
DOCUMENT 00 08 00 Page 14
Statements of Required Insurance; G Work Plan; G Contingency Plans; G Storage Of Materials And Equipment; G Relocate And Restore Utilities; G Modifying Fencing And Handrails; G Leakage Prevention Measures; G
SD-08 Manufacturer's Instructions
Touch Up Painting; G Overspray Removal Method; G
1.24 AS-BUILT DRAWINGS
a. "As-Built" Contract Drawings. The Contractor shall maintain a separate set of full-size contract drawings, marked up in red, to indicate as-built conditions. Each as-built contract drawing shall include the Contract Number (W912P9-XX-C-XXXX) associated with the contract. These drawings shall be maintained in a current condition at all times until completion of the work and shall be available for review by Government personnel at all times. All variations from the contract drawings, for whatever reason, including those occasioned by modifications, optional materials, and the required coordination between trades, shall be indicated. These variations shall be shown in the same general detail utilized in the contract drawings.