Text version
W81C8X80233025
Shoreline Revetment at Lake Shelbyville
The works consists of furnishing all labor, equipment, and materials necessary to reduce the leakage flowing into the center gallery to less than 5 gallons per minute average for 20 minutes at Lake Shelbyville Center Gallery Hatch.
The Magnitude of this project is between $100,000 and $250,000.
This acquisition is Small Business Set-aside.
DEBBIE C WARNER 314 331-8527
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
28-Feb-2018
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance within _______ 10 calendar days and complete it within ________ 365 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________ 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ 1 copies to perform the work required are due at the place specified in Item 8 by ___________ local time ______________ 16 Mar 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______ 180 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
USARMY ENGR DIST ST LOUIS
1222 SPRUCE ST RM 4.207
ST LOUIS MO 63103-2833
W912P9
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
314-331-8746 FAX: TEL: 314-331-8500 TEL: FAX:
W912P918R0014 49
20B. SIGNATURE
(REV. 4-85) STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE 27. PAYMENT WILL BE MADE BY: 26. ADMINISTERED BY
(Include ZIP Code) 14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14) 16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your offer on this solicitation, is hereby accepted as to the items listed. This award con-to furnish and deliver all items or perform all work, requisitions identified summates the contract, which consists of (a) the Government solicitation and on this form and any continuation sheets for the consideration stated in this your offer, and (b) this contract award. No further contractual document is contract. The rights and obligations of the parties to this contract shall be necessary.
governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by refer-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this 28. NEGOTIATED AGREEMENT
(Must be fully completed by offeror) OFFER
W912P918R0014
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
ODS-CENTER GALLERY ACCESS-MOBILIZATION A
FFP
ODS-CENTER GALLERY ACCESS-MOBILIZATION AND DEMO
FOB: Destination
MILSTRIP: W81C8X80233025
PURCHASE REQUEST NUMBER: W81C8X80233025
NET AMT
0002 1 Job
ODS-GALLERY ACCESS HATCH REPAIR-INSTALL
FFP
ODS-GALLERY ACCESS HATCH REPAIR-INSTALL& REMOVAL OF
STOPLOGS
FOB: Destination
0003 1 Job
ODS-CENTER GALLERY ACCESS HATCH RPR-PREC
FFP
ODS-CENTER GALLERY ACCESS HATCH RPR-PRECONSTRUCTION
WORK PLAN
FOB: Destination
0004 1 Job
ODS-CENTER GALLERY ACCESS HATCH RPR-GALL
FFP
ODS-CENTER GALLERY ACCESS HATCH RPR-GALLERY DRAIN
SYSTEM ---
FOB: Destination
0005 1 Job
ODS-CENTER GALLERY ACCESS HATCH RPR-CONS
FFP
ODS-CENTER GALLERY ACCESS HATCH RPR-CONSTRUCTION WORK
PLAN STEEL FRAME
FOB: Destination
0006 1 Job
ODS-CENTER GALLERY ACCESS HATCH REPAIRS-
FFP
ODS-CENTER GALLERY ACCESS HATCH REPAIRS-WORK PLAN
MONOLITH JOINT
FOB: Destination
0007 1 Job
ODS-CENTER GALLERY ACCESS HATCH-RESULTS
FFP
ODS-CENTER GALLERY ACCESS HATCH-RESULTSOF FINAL REPAIRS --
FOB: Destination
0008 1 Job
OPTION ODS-OPT. CENTER GALLERY ACCESS HATCH RPR
FFP
ODS-OPT. CENTER GALLERY ACCESS HATCH RPR-MOBILIZATION AND
DEMOB
FOB: Destination
0009 1 Job
OPTION ODS-OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS-OPT CENTER GALLERY ACCESS HATCH RPR-WORK PLAN FOR
GALLERY DRAINS
FOB: Destination
0010 1 Job
OPTION ODS-OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS-OPT CENTER GALLERY ACCESS HATCH RPR-REMOVE GALLERY
LIGHTS
FOB: Destination
0011 1 Job
OPTION ODS-OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS-OPT CENTER GALLERY ACCESS HATCH RPR-MOBILIZATION AND
DEMOB
FOB: Destination
0012 1 Job
OPTION ODS-OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS-OPT CENTER GALLERY ACCESS HATCH RPR-WORK PLAN FOR
EAST GALLERY DRAINS
FOB: Destination
0013 1 Job
OPTION ODS-OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS-OPT CENTER GALLERY ACCESS HATCH RPR-MOBLIZATION AND
DEMOB
FOB: Destination
0014 1 Job
OPTION ODS-OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS-OPT CENTER GALLERY ACCESS HATCH RPR-WORK PLAN FOR
WEST GALLERY DRAINS
FOB: Destination
0015 1 Job
OPTION ODS-OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS-OPT CENTER GALLERY ACCESS HATCH RPR-MOBLIZATION AND
DEMOB
FOB: Destination
0016 1 Job
OPTION ODS OPT CENTER GALLERY ACCESS HATCH RPR-
FFP
ODS OPT CENTER GALLERY ACCESS HATCH RPR-
FOB: Destination
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
0003 N/A N/A N/A N/A
0004 N/A N/A N/A N/A
0005 N/A N/A N/A N/A
0006 N/A N/A N/A N/A
0007 N/A N/A N/A N/A
0008 N/A N/A N/A N/A
0009 N/A N/A N/A N/A
0010 N/A N/A N/A N/A
0011 N/A N/A N/A N/A
0012 N/A N/A N/A N/A
0013 N/A N/A N/A N/A
0014 N/A N/A N/A N/A
0015 N/A N/A N/A N/A
0016 N/A N/A N/A N/A
BID SCHEDULE
Lake Shelbyville Center Gallery Access Hatch Repairs Bid Schedule
Amount Total
CLIN 0001 – Mobilization and demobilization 1 JB _______ _______
CLIN 0002 – Installation and removal of stoplogs 1 JB ________ ______
CLIN 0003 – Preconstruction work plan 1 JB _______ _______ CLIN 0004 – Measure leakage, clean out and camera inspect gallery drain system 1 JB _______ _______
CLIN 0005 – Construction work plan steel frame
a. First 3 gallons 3 GL _______ _______
b. All over 3 gallons 9 GL _______ _______
CLIN 0006 – Construction work plan monolith joint
a. First 2 gallons 2 GL ________ _______
b. All over 2 gallons 3 GL _______ _______
CLIN 0007 – Results of final repairs 1 JB _______ _______ Option 1:
CLIN 0008 - Mobilization and demobilization 1 JB _______ _______
CLIN 0009 – Work plan for center gallery drains 1 JB _______ _______
CLIN 0010 – Remove center gallery lighting 1 JB _______ _______
Option 2:
CLIN 0011 - Mobilization and demobilization 1 JB _______ _______
CLIN 0012 – Work plan for east gallery drains 1 JB _______ _______
Option 3:
CLIN 0013 - Mobilization and demobilization 1 JB _______ _______
CLIN 0014 – Work plan for west gallery drains 1 JB _______ _______
Option 4:
CLIN 0015 - Mobilization and demobilization 1 JB _______ _______
CLIN 0016 – Work plan for grouting crack
a. First 2 gallons: 2 GL _______ _______
b. All over 2 gallons: 3 GL _______ _______
ABBREVIATIONS
JB Job GL Gallon
Section 00 70 00 - Conditions of the Contract
SOW
Scope of Work
Lake Shelbyville Spillway Center Gallery Access Hatch Repairs
Project Scope:
The area around the center gallery access hatch is leaking water into the center gallery when the middle spillway tainter gate is operated. The leakage appears to be coming around the frame of the access hatch cover and along the monolith joint above the access hatch cover area. The Contractor shall reduce the leakage flowing into the center gallery to less than 5 gallons per minute average for 20 minutes. Pertinent photos of the center gallery access hatch are shown in Appendix A. Drawings applicable to the work areas are shown in Appendix B. Additional drawings and photos may be provided as necessary. Work shall be performed during periods of low releases, typically less than 500 cfs, due to the location of the work.
To aid in determining leakage amounts and verifying reduction, the middle spillway tainter gate shall be operated by USACE personnel for a period of 30 minutes inclusive of opening and closing each time needed. The Contractor shall provide a way to measure the flow of water (leakage) thru the center gallery hatch before and after the repairs are completed. The leakage can be measured via the east and west gallery gutter drains. Potential measuring devices may include weirs or flumes. The measurement shall be to the nearest gallons per minute average for 20 minutes. Before the work of installing a measuring device is started, the device and method shall be reviewed by the Government. The Contractor shall be responsible for placement and removal of the USACE owned stoplogs during repair work to allow for access to the monolith joint upstream of the gate sill and to reduce water leakage from the lake.
Access into the center gallery shall also be the responsibility of the Contractor. USACE personnel shall be allowed use of access means as necessary.
The Contractor shall complete the following:
1. Preconstruction Work – The preconstruction work at a minimum shall include providing a way to measure the water leakage thru the center gallery hatch before and after the repairs are completed. It shall also include cleaning out and camera inspecting the gallery drain system prior to and after repairs to include removal of silt buildup and other potential blockages. An effort to quantify silt amounts prior to removal shall be made for planning purposes. No silt/debris shall be allowed to be flushed through the system without collecting and removing it. The preconstruction work shall be reviewed by the Government before starting the work.
2. Construction Work Steel Frame – The construction work for the steel frame of the access hatch, at a minimum shall include the installation of a high flow epoxy grout to fill the voids around and under the steel frame of the access hatch cover to help prevent water leakage into the center gallery. The construction work steel frame shall be reviewed by the Government before starting the work.
3. Construction Work Monolith Joint – The construction work for the monolith joint repairs, at a minimum shall include the installation of the material selected to fill the voids along the monolith joint above and below the steel frame of the access hatch cover to help prevent water leakage into the center gallery. The construction work monolith joint shall be reviewed by the Government before starting the work.
4. Results of the Final Repair – A detailed report discussing all work activities and results shall be prepared following completion of the work. Photos shall also be included.
The Contractor shall provide a high flow epoxy grout that shall be pumped/injected thru the steel frame of the access hatch cover into the voids between the frame and the existing concrete surface. The epoxy grout shall meet the following requirements:
Working Time: The following working times assume the product has been properly preconditioned for cold or hot weather use:
90 degrees F (32ºC): 45 to 65 minutes 50 degrees F (10ºC): 110 to 150 minutes
Compressive Strength, ASTM C579, Method B:
Standard Consistency, 7-day ambient: 13,000 psi High-Flow Consistency, 7-day ambient: 12,500 psi
Flexural Strength, ASTM C580:
Standard Consistency, 73ºF (23ºC): 4,500 psi High-Flow Consistency, 73ºF (23ºC): 4,100 psi
Tensile Strength, ASTM C307:
Standard Consistency: 1,900 psi High-Flow Consistency: 1,700 psi
Shrinkage, Unrestrained, Linear, ASTM C531:
Standard Consistency: <0.02 percent High-Flow Consistency: <0.04 percent
Slant Shear Bond to Hardened Concrete, ASTM C882 73ºF (23ºC): 3,000 psi
Pumping/injecting the monolith joints shall be completed in the immediate vicinity of the spillway center gallery access hatch as shown in the drawings and photos provided.
The extent of the joint repairs shall be reviewed by the Government. The material shall meet the above requirements for grouting thru the steel frame unless otherwise accepted by the Government.
Optional Bid Items: Upon completion of the original project scope, additional work may be completed in the vicinity of the original work area. Due to the location of the work, Option 1 shall be performed during periods of low releases, typically less than 500 cfs.
Options 2-4 can be performed regardless of dam releases due to the location of the work.
Option 1 – The Contractor shall clean the center gallery foundation drains. Sound, wash, and flush a total of twenty-four (24) 3-inch diameter center gallery foundation drains. Document if each drain is flowing, weeping, or record the depth to water prior to flushing. Sound each drain to determine its pre-washed depth. Wash each drain using a high-pressure water jet with the nozzles angled backwards and flush each drain from the bottom, attempting to restore each drain to its original depth. Care shall be taken as to not damage the existing foundation drain holes with flushing procedures. Close coordination with the USACE project engineer will be necessary. Depths vary depending on the drain and range from 42 to 66 feet. Wash and flush each drain until the return water is running clear of any deposits, but no longer than one (1) hour per drain. Sound and record the depth of each drain after flushing is completed. All material removed from the drains shall be collected and removed from the site. Prepare a report that details the procedures used to complete the work, including before and after depth measurements for each drain, evaluating the effectiveness of the washing and flushing, describing the materials flushed out, and recommending future actions.
Photos shall also be included.
In addition to the foundation drain cleaning, the Contractor shall also remove the center gallery lighting. The lighting does not work and all components shall be removed from the gallery.
Option 2 – Sound, wash, and flush a total of sixty eight (68) 3-inch diameter east gallery foundation drains. Follow the same procedures as outlined in Option 1.
Option 3 – Sound, wash, and flush a total of sixty eight (68) 3-inch diameter west gallery foundation drains. Follow the same procedures as outlined in Option 1.
Option 4 – Grout crack on west side of dam concrete. A large crack exists on the downstream face of the dam. This crack has seeped water during a recent high water event. The crack shall be injected with a polyurethane grout to stop the joint from seeping during another high water event. The injection point shall be on the upstream face of the dam. The work to grout the crack shall be reviewed by the Government before starting the work. Procedures and results shall be documented in a detailed report. Photos shall also be included.
Site Visit: A site visit is scheduled for Monday, March 9th to see the location of the proposed project and help answer any questions related to the scope of work. The visit will commence at 10:00am at the US Army Corps of Engineers Lake Shelbyville
Visitor’s Center (1989 IL-16, Shelbyville, IL 62565). Please contact Angie Grimes (314- 331-8965) to confirm attendance for planning purposes.
SECURITY:
1. Access and General Protection/Security Policy and Procedures – All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
2. For contractors who do not require CAC, but require access to a
Department of Defense (DoD) facility or installation – Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
3. iWATCH and/or CorpsWatch training – The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
4. Will be escorted in areas where they may be exposed to classified and/or sensitive materials – All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
5. Pre-screen candidates using E-Verify Program - The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government 0002 N/A N/A N/A Government 0003 N/A N/A N/A Government 0004 N/A N/A N/A Government 0005 N/A N/A N/A Government 0006 N/A N/A N/A Government 0007 N/A N/A N/A Government 0008 N/A N/A N/A Government 0009 N/A N/A N/A Government 0010 N/A N/A N/A Government 0011 N/A N/A N/A Government 0012 N/A N/A N/A Government 0013 N/A N/A N/A Government 0014 N/A N/A N/A Government 0015 N/A N/A N/A Government 0016 N/A N/A N/A Government
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013 52.203-2 Certificate Of Independent Price Determination APR 1985 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-11 Certification And Disclosure Regarding Payments To
Influence Certain Federal Transactions
SEP 2007
52.203-12 Limitation On Payments To Influence Certain Federal Transactions
OCT 2010
52.204-3 Taxpayer Identification OCT 1998 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
52.204-6 Unique Entity Identifier OCT 2016 52.204-7 System for Award Management OCT 2016 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.211-5 Material Requirements AUG 2000 52.211-13 Time Extensions SEP 2000 52.211-18 Variation in Estimated Quantity APR 1984 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-12 Preparation Of Bids APR 1984 52.214-13 Alt I Telegraphic Bids (Apr 1984) - Alternate I NOV 1988 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-27 Price Reduction for Defective Certified Cost or Pricing Data -
Modifications - Sealed Bidding
AUG 2011
52.214-28 Subcontracting Certified Cost Or Pricing Data-- Modifications--Sealed Bidding
OCT 2010
52.215-19 Notification of Ownership Changes OCT 1997 52.215-20 Requirements for Certified Cost or Pricing Data or
Information Other Than Certified Cost or Pricing Data
OCT 2010
52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data -- Modifications
OCT 2010
52.216-9 Fixed Fee--Construction JUN 2011 52.217-3 Evaluation Exclusive Of Options APR 1984 52.217-4 Evaluation Of Options Exercised At The Time Of Contract
Award
JUN 1988
52.217-5 Evaluation Of Options JUL 1990 52.219-2 Equal Low Bids OCT 1995 52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-16 Liquidated Damages-Subcontracting Plan JAN 1999 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-22 Previous Contracts And Compliance Reports FEB 1999 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-38 Compliance With Veterans' Employment Reporting Requirements
FEB 2016
52.222-50 Combating Trafficking in Persons MAR 2015 52.223-1 Biobased Product Certification MAY 2012 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-2 (Dev) Affirmative Procurement of Biobased Products Under Service and Construction Contracts (Deviation)
SEP 2013
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-11 Ozone-Depleting Substances and High Global Warming
Potential Hydrofluorocarbons.
JUN 2016
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-20 Prohibition on Conducting Restricted Business Operations in
Sudan--Certification
AUG 2009
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
OCT 2015
52.227-1 Authorization and Consent DEC 2007 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-8 Discounts For Prompt Payment FEB 2002 52.232-11 Extras APR 1984 52.232-17 Interest MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-16 Quantity Surveys APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.244-5 Competition In Subcontracting DEC 1996 52.244-6 Subcontracts for Commercial Items NOV 2017 52.246-4 Inspection Of Services--Fixed Price AUG 1996 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
APR 2012
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7005 Representation Relating to Compensation of Former DoD Officials
NOV 2011
252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7006 Billing Instructions OCT 2005 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7031 Secondary Arab Boycott Of Israel JUN 2005 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7002 Obstruction of Navigable Waterways DEC 1991 252.236-7006 Cost Limitation JAN 1997 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.246-7000 Material Inspection And Receiving Report MAR 2008 252.247-7022 Representation Of Extent Of Transportation Of Supplies By
Sea
AUG 1992
252.247-7023 Transportation of Supplies by Sea APR 2014
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within TEN (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than ONE (1) YEAR. * The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $500.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.214-15 PERIOD FOR ACCEPTANCE OF BIDS (APR 1984)
In compliance with the solicitation, the bidder agrees, if this bid is accepted within ONE HUNDRED EIGHTY
(180) calendar days (from the date specified in the solicitation for receipt of bids, to furnish any or all items upon which prices are bid at the price set opposite each item, delivered at the designated point(s), within the time specified in the Schedule.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a FIRM FIXED PRICE (FFP) contract resulting from this solicitation.
(End of provision)
52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (OCT 2014) - ALTERNATE I (SEPT 2015)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.
(2) The small business size standard is $36,000,000.00.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b) Representations. (1) The offeror represents as part of its offer that it ( ___ ) is, ( ___ ) is not a small business concern.
(2) (Complete only if the offeror represented itself as a small business concern in paragraph (b)(1) of this provision.)
The offeror represents, for general statistical purposes, that it ( ___ ) is, ( ___ ) is not a small disadvantaged business concern as defined in 13 CFR 124.1002.
(3) (Complete only if the offeror represented itself as a small business concern in paragraph (b)(1) of this provision.)
The offeror represents as part of its offer that it ( ___ ) is, ( ___ ) is not a women-owned small business concern.
(4) Women-owned small business (WOSB) concern eligible under the WOSB Program. [Complete only if the offeror represented itself as a women-owned small business concern in paragraph (b)(3) of this provision.] The offeror represents as part of its offer that--
(i) It ( ___ ) is, ( ___ ) is not a WOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ___ ] is, [ ___ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (b)(4)(i) of this provision is accurate for each WOSB concern eligible under the WOSB Program participating in the joint venture. [The offeror shall enter the name or names of the WOSB concern eligible under the WOSB Program and other small businesses that are participating in the joint venture: ---- ___ ------.] Each WOSB concern eligible under the WOSB Program participating in the joint venture shall submit a separate signed copy of the WOSB representation.
(5) Economically disadvantaged women-owned small business (EDWOSB) concern. [Complete only if the offeror represented itself as a women-owned small business concern eligible under the WOSB Program in (b)(4) of this provision.] The offeror represents as part of its offer that--
(i) It ( ___ ) is, ( ___ ) is not an EDWOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ___ ] is, [ ___ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (b)(5)(i) of this provision is accurate for each EDWOSB concern participating in the joint venture. [The offeror shall enter the name or names of the EDWOSB concern and other small businesses that are participating in the joint venture: ----- ___ -----.] Each EDWOSB concern participating in the joint venture shall submit a separate signed copy of the EDWOSB representation.
(6) (Complete only if the offeror represented itself as a small business concern in paragraph (b)(1) of this provision.)
The offeror represents as part of its offer that it ( ___ ) is, ( ___ ) is not a veteran-owned small business concern.
(7) (Complete only if the offeror represented itself as a veteran-owned small business concern in paragraph (b)(6) of this provision.) The offeror represents as part of its offer that it ( ___ ) is, ( ___ ) is not a service-disabled veteran-owned small business concern.
(8) [Complete only if the offeror represented itself as a small business concern in paragraph (b)(1) of this provision.] The offeror represents, as part of its offer, that--
(i) It ( ___ ) is, ( ___ ) is not a HUBZone small business concern listed, on the date of this representation, on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration, and no material change in ownership and control, principal office, or HUBZone employee percentage has occurred since it was certified by the Small Business Administration in accordance with 13 CFR part 126; and
(ii) It ( ___ ) is, ( ___ ) is not a joint venture that complies with the requirements of 13 CFR part 126, and the representation in paragraph (b)(8)(i) of this provision is accurate for the HUBZone small business concern or concerns that are participating in the joint venture. (The offeror shall enter the name or names of the HUBZone small business concern or concerns that are participating in the joint venture: ___ .) Each HUBZone small business concern participating in the joint venture shall submit a separate signed copy of the HUBZone representation.
(9) (Complete if offeror represented itself as disadvantaged in paragraph (c)(2) of this provision.) The offeror shall check the category in which its ownership falls:
___ Black American.
___ Hispanic American.
___ Native American (American Indians, Eskimos, Aleuts, or Native Hawaiians).
___ Asian-Pacific American (persons with origins from Burma, Thailand, Malaysia, Indonesia, Singapore, Brunei, Japan, China, Taiwan, Laos, Cambodia (Kampuchea), Vietnam, Korea, The Philippines, Republic of Palau, Republic of the Marshall Islands, Federated States of Micronesia, the Commonwealth of the Northern Mariana Islands, Guam, Samoa, Macao, Hong Kong, Fiji, Tonga, Kiribati, Tuvalu, or Nauru).
___ Subcontinent Asian (Asian-Indian) American (persons with origins from India, Pakistan, Bangladesh, Sri Lanka, Bhutan, the Maldives Islands, or Nepal).
___ Individual/concern, other than one of the preceding.
(c) Definitions. As used in this provision--
Service-disabled veteran-owned small business concern--
(1) Means a small business concern--
(i) Not less than 51 percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled veterans; and
(ii) The management and daily business operations of which are controlled by one or more service-disabled veterans or, in the case of a service-disabled veteran with permanent and severe disability, the spouse or permanent caregiver of such veteran.
(2) Service-disabled veteran means a veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).
"Small business concern," means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR Part 121 and the size standard in paragraph (a) of this provision.
Veteran-owned small business concern means a small business concern--
(1) Not less than 51 percent of which is owned by one or more veterans (as defined at 38 U.S.C. 101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and
(2) The management and daily business operations of which are controlled by one or more veterans.
"Women-owned small business concern," means a small business concern --
(1) That is at least 51 percent owned by one or more women or, in the case of any publicly owned business, at least 51 percent of the stock of which is owned by one or more women; or
(2) Whose management and daily business operations are controlled by one or more women.
(d) Notice.
(1) If this solicitation is for supplies and has been set aside, in whole or in part, for small business concerns, then the clause in this solicitation providing notice of the set-aside contains restrictions on the source of the end items to be furnished.
(2) Under 15 U.S.C. 645(d), any person who misrepresents a firm's status as a small, HUBZone small, small disadvantaged, or women-owned small business concern in order to obtain a contract to be awarded under the preference programs established pursuant to section 8(a), 8(d), 9, or 15 of the Small Business Act or any other provision of Federal law that specifically references section 8(d) for a definition of program eligibility, shall--
(i) Be punished by imposition of fine, imprisonment, or both;
(ii) Be subject to administrative remedies, including suspension and debarment; and
(iii) Be ineligible for participation in programs conducted under the authority of the Act.
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JULY 2013)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts--
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code 237990- assigned to soliciatation number W912P918R0014.
(Contractor to sign and date and insert authorized signer's name and title).
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits will is scheduled for Friday, March 9th to see the location of the proposed project and help answer any questions related to the scope of work. The visit will commence at 10:00am at the US Army Corps of Engineers Lake Shelbyville Visitor’s Center (1989 IL-16, Shelbyville, IL 62565). Please contact Angie Grimes (314-331-
8965) to confirm attendance for planning purposes.
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any FAR SUPPLEMENT (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(c) The use in this solicitation of any FAR SUPPLEMENT (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
UAI 5152.231-9000
UAI 5152.231-9000 Equipment Ownership and Operating Expense Schedule.
As prescribed in 5131.100-70, insert the following clause: EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995) (a) This clause does not apply to terminations. See UAI 5152.249-9000, Basis for Settlement of Proposals, and Federal Acquisition Regulation (FAR) part 49. (b) Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region [insert Roman numeral for the appropriate region of the schedule]. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply. USACE Acquisition Instruction (UAI)Version 4 dated 25 JAN 2017 (c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees. (d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the simplified acquisition threshold (SAT), the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
UAI 5152.249-9000
UAI 5152.249-9000 Basis for Settlement of Proposals
BASIS FOR SETTLEMENT OF PROPOSALS (MAR 2009)
Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under Federal Acquisition Regulation (FAR) 49.206-2(b). In evaluating a termination settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(b) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.
(c) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.
(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation
(FAR) 31.205-11).
(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate
WAGE RATES
General Decision Number: IL20170015
State: Illinois
Construction Types: Heavy and Highway
Counties: Adams, Brown, Cass, Champaign, Christian, Clark, Coles, Cumberland, De Witt, Douglas, Edgar, Logan, Macon, Mason, Menard, Morgan, Moultrie, Piatt, Pike, Sangamon, Schuyler, Scott, Shelby and Vermilion Counties in Illinois.
DE WITT COUNTY:
HEAVY CONSTRUCTION PROJECTS (including Sewer & Water Line Construction & Drainage Projects) & HIGHWAY CONSTRUCTION PROJECTS (excluding tunnels, building structures in rest area projects, and railroad construction; bascule, suspension & spandrel arch…