A22_W912P918B0001.pdf
PDF 875 KB Posted
- Attached to
- Carlyle Lake Environmental Dredging Contact Federal contract opportunity
- Solicitation number
- W912P918B0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B01BIDSummary.Sheet.pdf | ||
| B05_W912P918B0001offer_Bid_Summary_Sheet.pdf | ||
| A02_Appendices.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Requirement consists of furnishing all equipment, labor, and materials, necessary for the excavation and disposal of dredge materials. The projects will take place at Carlyle Lake, Carlyle, Illinois, at the Kaskaskia Navigation Channel from Fayetteville, Illinois (River Mile 36.0) to the mouth of the Kaskaskia River (River Mile 0.0), at Lake Shelbyville, Shelbyville, IL and at the Mississippi River between L&D 24-27. This requirement will consist of a base and four additional one year option periods.
The estimated cost range of this project is between $1,000,000 and $5,000,000
The Guaranteed Minimum is $20,000 (Base Year) and $10,000 (Each Option Year)
The Cumulative Maximum is $1,000,000 each year
All responses to the invitation for Bid are due No Later Than 19 January 2018 0900. A public opening will be held in the St. Francis River Conference Room in Room 4.207 at the Robert A Young Federal Building at 1222 Spruce Street, St. Louis, MO 63103-2833.
X
ANGIE L GRIMES 314 331-8965
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
05-Jan-2018
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance within _______ 10 calendar days and complete it within ________ 365 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ 1 copies to perform the work required are due at the place specified in Item 8 by ___________ local time ______________ 05 Feb 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______ 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
US ARMY ENGR DIST ST LOUIS
1222 SPRUCE STREET, RM 9.104A
ST LOUIS MO 63103-2833
W912P9
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
09:00 AM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
314 331-8746 FAX: TEL: TEL: FAX:
W912P918B0001 91
20B. SIGNATURE
(REV. 4-85) STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE 27. PAYMENT WILL BE MADE BY: 26. ADMINISTERED BY
(Include ZIP Code) 14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14) 16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your offer on this solicitation, is hereby accepted as to the items listed. This award con-to furnish and deliver all items or perform all work, requisitions identified summates the contract, which consists of (a) the Government solicitation and on this form and any continuation sheets for the consideration stated in this your offer, and (b) this contract award. No further contractual document is contract. The rights and obligations of the parties to this contract shall be necessary.
governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by refer-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this 28. NEGOTIATED AGREEMENT
(Must be fully completed by offeror) OFFER
W912P918B0001
Section 00 10 00 - Solicitation
BID NOTES
SECTION B
SUPPLIES OR SERVICES AND PRICES/COSTS
Furnish all labor, equipment and materials necessary for dredging at Carlyle Lake, Carlyle, Illinois, at the Kaskaskia Navigation Channel from Fayetteville, Illinois (River Mile 36.0) to the mouth of the Kaskaskia River (River Mile 0.0), at Lake Shelbyville, Shelbyville, Illinois and the Mississippi River between L&D 24-27 in accordance with the solicitation specifications, clauses and provisions.
Note 1: Estimated quantities are to be used for bid evaluation only.
Note 2. Bidders must bid on all items. Failure to bid on any item will be cause for the Government to determine the bid non-responsive.
Note 3. All prices must be on a firm basis.
Note 4. Legend for unit of measure abbreviations:
HR = Hour EA = Each AC = Acre FT = Feet DY = Day MN = Month
Note 5. AMOUNT.
Cumulative Guaranteed Minimum - $20,000.00, Base Year, $10,000.00 each option year with a Maximum $1,000,000 per year with the ability in Option Year Four to utilize unused dollar amount capabilities from the previous four years of the contract.
Minimum and Maximum delivery order amounts are referenced in Section I, Contract Clauses.
Note 6. Information concerning indefinite quantity contracts, as well as the issuance and limitations of delivery orders may be found in Section I, contract Clauses. Each Delivery Order timeframe for completion will be negotiated with the Contractor prior to issuance.
BID SCHEDULE
BASE YEAR
AREA 1- CARLYLE LAKE
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
0001 Small Dredge 40 HR 0001A Mobilization & De-Mobilization of Small Dredge 1 EA 0002 Discharge tubing(12”) 500 Ft Increments 3 EA 0003 Medium Dredge 40 HR 0003A Mobilization & De-Mobilization of Medium Dredge 1 EA 0004 Discharge tubing(14”) 500 Ft Increments 3 EA 0005 Booster Pump(12”) (1-80 HRS) 40 HR 0006 Booster Pump(12”) (80+ HRS) 80 HR 0006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 0007 Booster Pump(14”) (1-80 HRS) 40 HR 0008 Booster Pump(14”) (80+ HRS) 80 HR 0008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 0009 Containment Barge XX XX XX XX 0009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 0010 Spud Barge with Crane XX XX XX XX 0010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
0011 Sectional Barge 40 DY 0012 Sectional Barge 1 MN 0012A Mobilization & De-Mobilization of Sectional Barge 1 EA 0013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 0014 Trackhoe Excavator-60' (80+ HRS) 80 HR 0014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
0015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 0016 Trackhoe Excavator-20' (80+ HRS) 80 HR 0016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
0017 Backhoe Loader 40 HR 0017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 0018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 0019 Track Type Dozer-80 hp (80+ HRS) 80 HR 0019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
0020 Track Type Dozer-150 hp 20 HR 0020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
0021 Skid Steer Loader 20 HR 0021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA 0022 Dump Truck 20 HR 0023 Work Boat 1 DY
0024 Seeding (5 ac) 2 EA 0024A Seeding Additional (1ac) 10 EA 0025 Geotextile Tube 200 FT 0026 Forestry Mower 40 HR 0027 Tow Boat XX XX XX XX 0028 Riprap Boat 40 HR 0028A Mobilization & De-Mobilization of Riprap Boat 1 EA 0029 Relocation of Dredge (10 mile) 1 EA
GRAND TOTAL BASE YEAR
AREA 2- KASKASKIA RIVER
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
0001 Small Dredge 40 HR 0001A Mobilization & De-Mobilization of Small Dredge 1 EA 0002 Discharge tubing(12”) 500 Ft Increments 3 EA 0003 Medium Dredge 40 HR 0003A Mobilization & De-Mobilization of Medium Dredge 1 EA 0004 Discharge tubing(14”) 500 Ft Increments 3 EA 0005 Booster Pump(12”) (1-80 HRS) 40 HR 0006 Booster Pump(12”) (80+ HRS) 80 HR 0006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 0007 Booster Pump(14”) (1-80 HRS) 40 HR 0008 Booster Pump(14”) (80+ HRS) 80 HR 0008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 0009 Containment Barge 5 DY 0009A Mobilization & De-Mobilization of Containment Barge 1 EA 0010 Spud Barge with Crane 40 DY 0010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
0011 Sectional Barge 40 DY 0012 Sectional Barge 1 MN 0012A Mobilization & De-Mobilization of Sectional Barge 1 EA 0013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 0014 Trackhoe Excavator-60' (80+ HRS) 80 HR 0014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
0015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 0016 Trackhoe Excavator-20' (80+ HRS) 80 HR 0016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
0017 Backhoe Loader 40 HR 0017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 0018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 0019 Track Type Dozer-80 hp (80+ HRS) 80 HR 0019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
0020 Track Type Dozer-150 hp 20 HR 0020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
0021 Skid Steer Loader 20 HR 0021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
0025 Geotextile Tube 200 FT 0026 Forestry Mower 40 HR 0027 Tow Boat 1 DY 0028 Riprap Boat 40 HR 0028A Mobilization & De-Mobilization of Riprap Boat 1 EA
AREA 3- MISSISSIPPI RIVER-L&D 24, 25, 26, 27
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
0001 Small Dredge 40 HR 0001A Mobilization & De-Mobilization of Small Dredge 1 EA 0002 Discharge tubing(12”) 500 Ft Increments 3 EA 0003 Medium Dredge 40 HR 0003A Mobilization & De-Mobilization of Medium Dredge 1 EA 0004 Discharge tubing(14”) 500 Ft Increments 3 EA 0005 Booster Pump(12”) (1-80 HRS) 40 HR 0006 Booster Pump(12”) (80+ HRS) 80 HR 0006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 0007 Booster Pump(14”) (1-80 HRS) 40 HR 0008 Booster Pump(14”) (80+ HRS) 80 HR 0008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 0009 Containment Barge 5 DY 0009A Mobilization & De-Mobilization of Containment Barge 1 EA 0010 Spud Barge with Crane 40 DY 0010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
0011 Sectional Barge 40 DY 0012 Sectional Barge 1 MN 0012A Mobilization & De-Mobilization of Sectional Barge 1 EA 0013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 0014 Trackhoe Excavator-60' (80+ HRS) 80 HR 0014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
0015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 0016 Trackhoe Excavator-20' (80+ HRS) 80 HR 0016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
0017 Backhoe Loader 40 HR 0017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 0018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 0019 Track Type Dozer-80 hp (80+ HRS) 80 HR 0019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
0020 Track Type Dozer-150 hp 20 HR 0020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
0021 Skid Steer Loader 20 HR 0021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
0025 Geotextile Tube 200 FT 0026 Forestry Mower 40 HR 0027 Tow Boat 1 DY 0028 Riprap Boat 40 HR 0028A Mobilization & De-Mobilization of Riprap Boat 1 EA
AREA 4- LAKE SHELBYVILLE
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
0001 Small Dredge 40 HR 0001A Mobilization & De-Mobilization of Small Dredge 1 EA 0002 Discharge tubing(12”) 500 Ft Increments 3 EA 0003 Medium Dredge 40 HR 0003A Mobilization & De-Mobilization of Medium Dredge 1 EA 0004 Discharge tubing(14”) 500 Ft Increments 3 EA 0005 Booster Pump(12”) (1-80 HRS) 40 HR 0006 Booster Pump(12”) (80+ HRS) 80 HR 0006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 0007 Booster Pump(14”) (1-80 HRS) 40 HR 0008 Booster Pump(14”) (80+ HRS) 80 HR 0008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 0009 Containment Barge XX XX XX 0009A Mobilization & De-Mobilization of Containment Barge XX XX XX 0010 Spud Barge with Crane XX XX XX 0010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX
0011 Sectional Barge 40 DY 0012 Sectional Barge 1 MN 0012A Mobilization & De-Mobilization of Sectional Barge 1 EA 0013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 0014 Trackhoe Excavator-60' (80+ HRS) 80 HR 0014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
0015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 0016 Trackhoe Excavator-20' (80+ HRS) 80 HR 0016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
0017 Backhoe Loader 40 HR 0017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 0018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 0019 Track Type Dozer-80 hp (80+ HRS) 80 HR 0019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
0020 Track Type Dozer-150 hp 20 HR 0020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
0021 Skid Steer Loader 20 HR 0021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
0025 Geotextile Tube 200 FT 0026 Forestry Mower 40 HR 0027 Tow Boat XX XX XX XX 0028 Riprap Boat 40 HR 0028A Mobilization & De-Mobilization of Riprap Boat 1 EA
OPTION YEAR 1
AREA 1- CARLYLE LAKE
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
1001 Small Dredge 40 HR 1001A Mobilization & De-Mobilization of Small Dredge 1 EA 1002 Discharge tubing(12”) 500 Ft Increments 3 EA 1003 Medium Dredge 40 HR 1003A Mobilization & De-Mobilization of Medium Dredge 1 EA 1004 Discharge tubing(14”) 500 Ft Increments 3 EA 1005 Booster Pump(12”) (1-80 HRS) 40 HR 1006 Booster Pump(12”) (80+ HRS) 80 HR 1006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 1007 Booster Pump(14”) (1-80 HRS) 40 HR 1008 Booster Pump(14”) (80+ HRS) 80 HR 1008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 1009 Containment Barge XX XX XX XX 1009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 1010 Spud Barge with Crane XX XX XX XX 1010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
1011 Sectional Barge 40 DY 1012 Sectional Barge 1 MN 1012A Mobilization & De-Mobilization of Sectional Barge 1 EA 1013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 1014 Trackhoe Excavator-60' (80+ HRS) 80 HR 1014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
1015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 1016 Trackhoe Excavator-20' (80+ HRS) 80 HR 1016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
1017 Backhoe Loader 40 HR 1017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 1018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 1019 Track Type Dozer-80 hp (80+ HRS) 80 HR 1019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
1020 Track Type Dozer-150 hp 20 HR 1020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
1021 Skid Steer Loader 20 HR 1021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA 1022 Dump Truck 20 HR 1023 Work Boat 1 DY
1024 Seeding (5 ac) 2 EA 1024A Seeding Additional (1ac) 10 EA 1025 Geotextile Tube 200 FT 1026 Forestry Mower 40 HR 1027 Tow Boat XX XX XX XX 1028 Riprap Boat 40 HR 1028A Mobilization & De-Mobilization of Riprap Boat 1 EA 1029 Relocation of Dredge (10 mile) 1 EA
GRAND TOTAL OPTION YEAR 1
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
1001 Small Dredge 40 HR 1001A Mobilization & De-Mobilization of Small Dredge 1 EA 1002 Discharge tubing(12”) 500 Ft Increments 3 EA 1003 Medium Dredge 40 HR 1003A Mobilization & De-Mobilization of Medium Dredge 1 EA 1004 Discharge tubing(14”) 500 Ft Increments 3 EA 1005 Booster Pump(12”) (1-80 HRS) 40 HR 1006 Booster Pump(12”) (80+ HRS) 80 HR 1006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 1007 Booster Pump(14”) (1-80 HRS) 40 HR 1008 Booster Pump(14”) (80+ HRS) 80 HR 1008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 1009 Containment Barge 5 DY 1009A Mobilization & De-Mobilization of Containment Barge 1 EA 1010 Spud Barge with Crane 40 DY 1010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
1011 Sectional Barge 40 DY 1012 Sectional Barge 1 MN 1012A Mobilization & De-Mobilization of Sectional Barge 1 EA 1013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 1014 Trackhoe Excavator-60' (80+ HRS) 80 HR 1014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
1015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 1016 Trackhoe Excavator-20' (80+ HRS) 80 HR 1016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
1017 Backhoe Loader 40 HR 1017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 1018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 1019 Track Type Dozer-80 hp (80+ HRS) 80 HR 1019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
1020 Track Type Dozer-150 hp 20 HR 1020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
1021 Skid Steer Loader 20 HR 1021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
1025 Geotextile Tube 200 FT 1026 Forestry Mower 40 HR 1027 Tow Boat 1 DY 1028 Riprap Boat 40 HR 1028A Mobilization & De-Mobilization of Riprap Boat 1 EA
AREA 3- MISSISSIPPI RIVER -L&D 24, 25, 26, 27
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
1001 Small Dredge 40 HR 1001A Mobilization & De-Mobilization of Small Dredge 1 EA 1002 Discharge tubing(12”) 500 Ft Increments 3 EA 1003 Medium Dredge 40 HR 1003A Mobilization & De-Mobilization of Medium Dredge 1 EA 1004 Discharge tubing(14”) 500 Ft Increments 3 EA 1005 Booster Pump(12”) (1-80 HRS) 40 HR 1006 Booster Pump(12”) (80+ HRS) 80 HR 1006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 1007 Booster Pump(14”) (1-80 HRS) 40 HR 1008 Booster Pump(14”) (80+ HRS) 80 HR 1008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 1009 Containment Barge 5 DY 1009A Mobilization & De-Mobilization of Containment Barge 1 EA 1010 Spud Barge with Crane 40 DY 1010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
1011 Sectional Barge 40 DY 1012 Sectional Barge 1 MN 1012A Mobilization & De-Mobilization of Sectional Barge 1 EA 1013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 1014 Trackhoe Excavator-60' (80+ HRS) 80 HR 1014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
1015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 1016 Trackhoe Excavator-20' (80+ HRS) 80 HR 1016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
1017 Backhoe Loader 40 HR 1017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 1018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 1019 Track Type Dozer-80 hp (80+ HRS) 80 HR 1019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
1020 Track Type Dozer-150 hp 20 HR 1020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
1021 Skid Steer Loader 20 HR 1021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
1025 Geotextile Tube 200 FT 1026 Forestry Mower 40 HR 1027 Tow Boat 1 DY 1028 Riprap Boat 40 HR 1028A Mobilization & De-Mobilization of Riprap Boat 1 EA
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
1001 Small Dredge 40 HR 1001A Mobilization & De-Mobilization of Small Dredge 1 EA 1002 Discharge tubing(12”) 500 Ft Increments 3 EA 1003 Medium Dredge 40 HR 1003A Mobilization & De-Mobilization of Medium Dredge 1 EA 1004 Discharge tubing(14”) 500 Ft Increments 3 EA 1005 Booster Pump(12”) (1-80 HRS) 40 HR 1006 Booster Pump(12”) (80+ HRS) 80 HR 1006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 1007 Booster Pump(14”) (1-80 HRS) 40 HR 1008 Booster Pump(14”) (80+ HRS) 80 HR 1008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 1009 Containment Barge XX XX XX XX 1009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 1010 Spud Barge with Crane XX XX XX XX 1010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
1011 Sectional Barge 40 DY 1012 Sectional Barge 1 MN 1012A Mobilization & De-Mobilization of Sectional Barge 1 EA 1013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 1014 Trackhoe Excavator-60' (80+ HRS) 80 HR 1014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
1015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 1016 Trackhoe Excavator-20' (80+ HRS) 80 HR 1016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
1017 Backhoe Loader 40 HR 1017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 1018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 1019 Track Type Dozer-80 hp (80+ HRS) 80 HR 1019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
1020 Track Type Dozer-150 hp 20 HR 1020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
1021 Skid Steer Loader 20 HR 1021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
1025 Geotextile Tube 200 FT 1026 Forestry Mower 40 HR 1027 Tow Boat XX XX XX XX 1028 Riprap Boat 40 HR 1028A Mobilization & De-Mobilization of Riprap Boat 1 EA
OPTION YEAR 2
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
2001 Small Dredge 40 HR 2001A Mobilization & De-Mobilization of Small Dredge 1 EA 2002 Discharge tubing(12”) 500 Ft Increments 3 EA 2003 Medium Dredge 40 HR 2003A Mobilization & De-Mobilization of Medium Dredge 1 EA 2004 Discharge tubing(14”) 500 Ft Increments 3 EA 2005 Booster Pump(12”) (1-80 HRS) 40 HR 2006 Booster Pump(12”) (80+ HRS) 80 HR 2006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 2007 Booster Pump(14”) (1-80 HRS) 40 HR 2008 Booster Pump(14”) (80+ HRS) 80 HR 2008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 2009 Containment Barge XX XX XX XX 2009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 2010 Spud Barge with Crane XX XX XX XX 2010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
2011 Sectional Barge 40 DY 2012 Sectional Barge 1 MN 2012A Mobilization & De-Mobilization of Sectional Barge 1 EA 2013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 2014 Trackhoe Excavator-60' (80+ HRS) 80 HR 2014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
2015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 2016 Trackhoe Excavator-20' (80+ HRS) 80 HR 2016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
2017 Backhoe Loader 40 HR 2017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 2018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 2019 Track Type Dozer-80 hp (80+ HRS) 80 HR 2019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
2020 Track Type Dozer-150 hp 20 HR 2020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
2021 Skid Steer Loader 20 HR 2021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA 2022 Dump Truck 20 HR 2023 Work Boat 1 DY
2024 Seeding (5 ac) 2 EA 2024A Seeding Additional (1ac) 10 EA 2025 Geotextile Tube 200 FT 2026 Forestry Mower 40 HR 2027 Tow Boat XX XX XX XX 2028 Riprap Boat 40 HR 2028A Mobilization & De-Mobilization of Riprap Boat 1 EA 2029 Relocation of Dredge (10 mile) 1 EA
GRAND TOTAL OPTION YEAR 2
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
2001 Small Dredge 40 HR 2001A Mobilization & De-Mobilization of Small Dredge 1 EA 2002 Discharge tubing(12”) 500 Ft Increments 3 EA 2003 Medium Dredge 40 HR 2003A Mobilization & De-Mobilization of Medium Dredge 1 EA 2004 Discharge tubing(14”) 500 Ft Increments 3 EA 2005 Booster Pump(12”) (1-80 HRS) 40 HR 2006 Booster Pump(12”) (80+ HRS) 80 HR 2006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 2007 Booster Pump(14”) (1-80 HRS) 40 HR 2008 Booster Pump(14”) (80+ HRS) 80 HR 2008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 2009 Containment Barge 5 DY 2009A Mobilization & De-Mobilization of Containment Barge 1 EA 2010 Spud Barge with Crane 40 DY 2010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
2011 Sectional Barge 40 DY 2012 Sectional Barge 1 MN 2012A Mobilization & De-Mobilization of Sectional Barge 1 EA 2013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 2014 Trackhoe Excavator-60' (80+ HRS) 80 HR 2014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
2015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 2016 Trackhoe Excavator-20' (80+ HRS) 80 HR 2016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
2017 Backhoe Loader 40 HR 2017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 2018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 2019 Track Type Dozer-80 hp (80+ HRS) 80 HR 2019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
2020 Track Type Dozer-150 hp 20 HR 2020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
2021 Skid Steer Loader 20 HR 2021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
2025 Geotextile Tube 200 FT 2026 Forestry Mower 40 HR 2027 Tow Boat 1 DY 2028 Riprap Boat 40 HR 2028A Mobilization & De-Mobilization of Riprap Boat 1 EA
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
2001 Small Dredge 40 HR 2001A Mobilization & De-Mobilization of Small Dredge 1 EA 2002 Discharge tubing(12”) 500 Ft Increments 3 EA 2003 Medium Dredge 40 HR 2003A Mobilization & De-Mobilization of Medium Dredge 1 EA 2004 Discharge tubing(14”) 500 Ft Increments 3 EA 2005 Booster Pump(12”) (1-80 HRS) 40 HR 2006 Booster Pump(12”) (80+ HRS) 80 HR 2006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 2007 Booster Pump(14”) (1-80 HRS) 40 HR 2008 Booster Pump(14”) (80+ HRS) 80 HR 2008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 2009 Containment Barge 5 DY 2009A Mobilization & De-Mobilization of Containment Barge 1 EA 2010 Spud Barge with Crane 40 DY 2010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
2011 Sectional Barge 40 DY 2012 Sectional Barge 1 MN 2012A Mobilization & De-Mobilization of Sectional Barge 1 EA 2013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 2014 Trackhoe Excavator-60' (80+ HRS) 80 HR 2014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
2015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 2016 Trackhoe Excavator-20' (80+ HRS) 80 HR 2016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
2017 Backhoe Loader 40 HR 2017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 2018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 2019 Track Type Dozer-80 hp (80+ HRS) 80 HR 2019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
2020 Track Type Dozer-150 hp 20 HR 2020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
2021 Skid Steer Loader 20 HR 2021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
2025 Geotextile Tube 200 FT 2026 Forestry Mower 40 HR 2027 Tow Boat 1 DY 2028 Riprap Boat 40 HR 2028A Mobilization & De-Mobilization of Riprap Boat 1 EA
AREA 4 - LAKE SHELBYVILLE
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
2001 Small Dredge 40 HR 2001A Mobilization & De-Mobilization of Small Dredge 1 EA 2002 Discharge tubing(12”) 500 Ft Increments 3 EA 2003 Medium Dredge 40 HR 2003A Mobilization & De-Mobilization of Medium Dredge 1 EA 2004 Discharge tubing(14”) 500 Ft Increments 3 EA 2005 Booster Pump(12”) (1-80 HRS) 40 HR 2006 Booster Pump(12”) (80+ HRS) 80 HR 2006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 2007 Booster Pump(14”) (1-80 HRS) 40 HR 2008 Booster Pump(14”) (80+ HRS) 80 HR 2008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 2009 Containment Barge XX XX XX XX 2009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 2010 Spud Barge with Crane XX XX XX XX 2010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
2011 Sectional Barge 40 DY 2012 Sectional Barge 1 MN 2012A Mobilization & De-Mobilization of Sectional Barge 1 EA 2013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 2014 Trackhoe Excavator-60' (80+ HRS) 80 HR 2014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
2015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 2016 Trackhoe Excavator-20' (80+ HRS) 80 HR 2016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
2017 Backhoe Loader 40 HR 2017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 2018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 2019 Track Type Dozer-80 hp (80+ HRS) 80 HR 2019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
2020 Track Type Dozer-150 hp 20 HR 2020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
2021 Skid Steer Loader 20 HR 2021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
2024A Seeding Additional (1ac) 10 EA 2025 Geotextile Tube 200 FT 2026 Forestry Mower 40 HR 2027 Tow Boat XX XX XX XX 2028 Riprap Boat 40 HR 2028A Mobilization & De-Mobilization of Riprap Boat 1 EA
OPTION YEAR 3
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
3001 Small Dredge 40 HR 3001A Mobilization & De-Mobilization of Small Dredge 1 EA 3002 Discharge tubing(12”) 500 Ft Increments 3 EA 3003 Medium Dredge 40 HR 3003A Mobilization & De-Mobilization of Medium Dredge 1 EA 3004 Discharge tubing(14”) 500 Ft Increments 3 EA 3005 Booster Pump(12”) (1-80 HRS) 40 HR 3006 Booster Pump(12”) (80+ HRS) 80 HR 3006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 3007 Booster Pump(14”) (1-80 HRS) 40 HR 3008 Booster Pump(14”) (80+ HRS) 80 HR 3008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 3009 Containment Barge XX XX XX XX 3009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 3010 Spud Barge with Crane XX XX XX XX 3010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
3011 Sectional Barge 40 DY 3012 Sectional Barge 1 MN 3012A Mobilization & De-Mobilization of Sectional Barge 1 EA 3013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 3014 Trackhoe Excavator-60' (80+ HRS) 80 HR 3014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
3015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 3016 Trackhoe Excavator-20' (80+ HRS) 80 HR 3016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
3017 Backhoe Loader 40 HR 3017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 3018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 3019 Track Type Dozer-80 hp (80+ HRS) 80 HR 3019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
3020 Track Type Dozer-150 hp 20 HR 3020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
3021 Skid Steer Loader 20 HR 3021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA 3022 Dump Truck 20 HR
3023 Work Boat 1 DY 3024 Seeding (5 ac) 2 EA 3024A Seeding Additional (1ac) 10 EA 3025 Geotextile Tube 200 FT 3026 Forestry Mower 40 HR 3027 Tow Boat XX XX XX XX 3028 Riprap Boat 40 HR 3028A Mobilization & De-Mobilization of Riprap Boat 1 EA 3029 Relocation of Dredge (10 mile) 1 EA
GRAND TOTAL OPTION YEAR 3
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
3001 Small Dredge 40 HR 3001A Mobilization & De-Mobilization of Small Dredge 1 EA 3002 Discharge tubing(12”) 500 Ft Increments 3 EA 3003 Medium Dredge 40 HR 3003A Mobilization & De-Mobilization of Medium Dredge 1 EA 3004 Discharge tubing(14”) 500 Ft Increments 3 EA 3005 Booster Pump(12”) (1-80 HRS) 40 HR 3006 Booster Pump(12”) (80+ HRS) 80 HR 3006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 3007 Booster Pump(14”) (1-80 HRS) 40 HR 3008 Booster Pump(14”) (80+ HRS) 80 HR 3008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 3009 Containment Barge 5 DY 3009A Mobilization & De-Mobilization of Containment Barge 1 EA 3010 Spud Barge with Crane 40 DY 3010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
3011 Sectional Barge 40 DY 3012 Sectional Barge 1 MN 3012A Mobilization & De-Mobilization of Sectional Barge 1 EA 3013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 3014 Trackhoe Excavator-60' (80+ HRS) 80 HR 3014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
3015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 3016 Trackhoe Excavator-20' (80+ HRS) 80 HR 3016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
3017 Backhoe Loader 40 HR 3017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 3018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 3019 Track Type Dozer-80 hp (80+ HRS) 80 HR 3019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
3020 Track Type Dozer-150 hp 20 HR 3020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
3021 Skid Steer Loader 20 HR 3021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
3024A Seeding Additional (1ac) 10 EA 3025 Geotextile Tube 200 FT 3026 Forestry Mower 40 HR 3027 Tow Boat 1 DY 3028 Riprap Boat 40 HR 3028A Mobilization & De-Mobilization of Riprap Boat 1 EA
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
3001 Small Dredge 40 HR 3001A Mobilization & De-Mobilization of Small Dredge 1 EA 3002 Discharge tubing(12”) 500 Ft Increments 3 EA 3003 Medium Dredge 40 HR 3003A Mobilization & De-Mobilization of Medium Dredge 1 EA 3004 Discharge tubing(14”) 500 Ft Increments 3 EA 3005 Booster Pump(12”) (1-80 HRS) 40 HR 3006 Booster Pump(12”) (80+ HRS) 80 HR 3006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 3007 Booster Pump(14”) (1-80 HRS) 40 HR 3008 Booster Pump(14”) (80+ HRS) 80 HR 3008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 3009 Containment Barge 5 DY 3009A Mobilization & De-Mobilization of Containment Barge 1 EA 3010 Spud Barge with Crane 40 DY 3010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
3011 Sectional Barge 40 DY 3012 Sectional Barge 1 MN 3012A Mobilization & De-Mobilization of Sectional Barge 1 EA 3013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 3014 Trackhoe Excavator-60' (80+ HRS) 80 HR 3014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
3015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 3016 Trackhoe Excavator-20' (80+ HRS) 80 HR 3016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
3017 Backhoe Loader 40 HR 3017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 3018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 3019 Track Type Dozer-80 hp (80+ HRS) 80 HR 3019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
3020 Track Type Dozer-150 hp 20 HR 3020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
3021 Skid Steer Loader 20 HR 3021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
3024A Seeding Additional (1ac) 10 EA 3025 Geotextile Tube 200 FT 3026 Forestry Mower 40 HR 3027 Tow Boat 1 DY 3028 Riprap Boat 40 HR 3028A Mobilization & De-Mobilization of Riprap Boat 1 EA
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
3001 Small Dredge 40 HR 3001A Mobilization & De-Mobilization of Small Dredge 1 EA 3002 Discharge tubing(12”) 500 Ft Increments 3 EA 3003 Medium Dredge 40 HR 3003A Mobilization & De-Mobilization of Medium Dredge 1 EA 3004 Discharge tubing(14”) 500 Ft Increments 3 EA 3005 Booster Pump(12”) (1-80 HRS) 40 HR 3006 Booster Pump(12”) (80+ HRS) 80 HR 3006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 3007 Booster Pump(14”) (1-80 HRS) 40 HR 3008 Booster Pump(14”) (80+ HRS) 80 HR 3008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 3009 Containment Barge XX XX XX XX 3009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 3010 Spud Barge with Crane XX XX XX XX 3010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
3011 Sectional Barge 40 DY 3012 Sectional Barge 1 MN 3012A Mobilization & De-Mobilization of Sectional Barge 1 EA 3013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 3014 Trackhoe Excavator-60' (80+ HRS) 80 HR 3014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
3015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 3016 Trackhoe Excavator-20' (80+ HRS) 80 HR 3016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
3017 Backhoe Loader 40 HR 3017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 3018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 3019 Track Type Dozer-80 hp (80+ HRS) 80 HR 3019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
3020 Track Type Dozer-150 hp 20 HR 3020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
3021 Skid Steer Loader 20 HR 3021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
3024A Seeding Additional (1ac) 10 EA 3025 Geotextile Tube 200 FT 3026 Forestry Mower 40 HR 3027 Tow Boat XX DY 3028 Riprap Boat XX XX XX XX 3028A Mobilization & De-Mobilization of Riprap Boat 1 EA
OPTION YEAR 4
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
4001 Small Dredge 40 HR 4001A Mobilization & De-Mobilization of Small Dredge 1 EA 4002 Discharge tubing(12”) 500 Ft Increments 3 EA 4003 Medium Dredge 40 HR 4003A Mobilization & De-Mobilization of Medium Dredge 1 EA 4004 Discharge tubing(14”) 500 Ft Increments 3 EA 4005 Booster Pump(12”) (1-80 HRS) 40 HR 4006 Booster Pump(12”) (80+ HRS) 80 HR 4006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 4007 Booster Pump(14”) (1-80 HRS) 40 HR 4008 Booster Pump(14”) (80+ HRS) 80 HR 4008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 4009 Containment Barge XX XX XX XX 4009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 4010 Spud Barge with Crane XX XX XX XX 4010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
4011 Sectional Barge 40 DY 4012 Sectional Barge 1 MN 4012A Mobilization & De-Mobilization of Sectional Barge 1 EA 4013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 4014 Trackhoe Excavator-60' (80+ HRS) 80 HR 4014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
4015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 4016 Trackhoe Excavator-20' (80+ HRS) 80 HR 4016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
4017 Backhoe Loader 40 HR 4017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 4018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 4019 Track Type Dozer-80 hp (80+ HRS) 80 HR 4019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
4020 Track Type Dozer-150 hp 20 HR 4020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
4021 Skid Steer Loader 20 HR 4021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
4022 Dump Truck 20 HR 4023 Work Boat 1 DY 4024 Seeding (5 ac) 2 EA 4024A Seeding Additional (1ac) 10 EA 4025 Geotextile Tube 200 FT 4026 Forestry Mower 40 HR 4027 Tow Boat XX XX XX XX 4028 Riprap Boat 40 HR 4028A Mobilization & De-Mobilization of Riprap Boat 1 EA 4029 Relocation of Dredge (10 mile) 1 EA
GRAND TOTAL OPTION YEAR 4
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
4001 Small Dredge 40 HR 4001A Mobilization & De-Mobilization of Small Dredge 1 EA 4002 Discharge tubing(12”) 500 Ft Increments 3 EA 4003 Medium Dredge 40 HR 4003A Mobilization & De-Mobilization of Medium Dredge 1 EA 4004 Discharge tubing(14”) 500 Ft Increments 3 EA 4005 Booster Pump(12”) (1-80 HRS) 40 HR 4006 Booster Pump(12”) (80+ HRS) 80 HR 4006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 4007 Booster Pump(14”) (1-80 HRS) 40 HR 4008 Booster Pump(14”) (80+ HRS) 80 HR 4008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 4009 Containment Barge 5 DY 4009A Mobilization & De-Mobilization of Containment Barge 1 EA 4010 Spud Barge with Crane 40 DY 4010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
4011 Sectional Barge 40 DY 4012 Sectional Barge 1 MN 4012A Mobilization & De-Mobilization of Sectional Barge 1 EA 4013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 4014 Trackhoe Excavator-60' (80+ HRS) 80 HR 4014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
4015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 4016 Trackhoe Excavator-20' (80+ HRS) 80 HR 4016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
4017 Backhoe Loader 40 HR 4017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 4018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 4019 Track Type Dozer-80 hp (80+ HRS) 80 HR 4019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
4020 Track Type Dozer-150 hp 20 HR 4020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
4021 Skid Steer Loader 20 HR 4021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
4024 Seeding (5 ac) 2 EA 4024A Seeding Additional (1ac) 10 EA 4025 Geotextile Tube 200 FT 4026 Forestry Mower 40 HR 4027 Tow Boat 1 DY 4028 Riprap Boat 40 HR 4028A Mobilization & De-Mobilization of Riprap Boat 1 EA
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
4001 Small Dredge 40 HR 4001A Mobilization & De-Mobilization of Small Dredge 1 EA 4002 Discharge tubing(12”) 500 Ft Increments 3 EA 4003 Medium Dredge 40 HR 4003A Mobilization & De-Mobilization of Medium Dredge 1 EA 4004 Discharge tubing(14”) 500 Ft Increments 3 EA 4005 Booster Pump(12”) (1-80 HRS) 40 HR 4006 Booster Pump(12”) (80+ HRS) 80 HR 4006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 4007 Booster Pump(14”) (1-80 HRS) 40 HR 4008 Booster Pump(14”) (80+ HRS) 80 HR 4008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 4009 Containment Barge 5 DY 4009A Mobilization & De-Mobilization of Containment Barge 1 EA 4010 Spud Barge with Crane 40 DY 4010A Mobilization & De-Mobilization of Spud Barge with
Crane
1 EA
4011 Sectional Barge 40 DY 4012 Sectional Barge 1 MN 4012A Mobilization & De-Mobilization of Sectional Barge 1 EA 4013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 4014 Trackhoe Excavator-60' (80+ HRS) 80 HR 4014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
4015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 4016 Trackhoe Excavator-20' (80+ HRS) 80 HR 4016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
4017 Backhoe Loader 40 HR 4017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 4018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 4019 Track Type Dozer-80 hp (80+ HRS) 80 HR 4019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
4020 Track Type Dozer-150 hp 20 HR 4020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
4021 Skid Steer Loader 20 HR 4021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
4025 Geotextile Tube 200 FT 4026 Forestry Mower 40 HR 4027 Tow Boat 1 DY 4028 Riprap Boat 40 HR 4028A Mobilization & De-Mobilization of Riprap Boat 1 EA
ITEM DESCRIPTION QTY U/I PRICE AMOUNT
4001 Small Dredge 40 HR 4001A Mobilization & De-Mobilization of Small Dredge 1 EA 4002 Discharge tubing(12”) 500 Ft Increments 3 EA 4003 Medium Dredge 40 HR 4003A Mobilization & De-Mobilization of Medium Dredge 1 EA 4004 Discharge tubing(14”) 500 Ft Increments 3 EA 4005 Booster Pump(12”) (1-80 HRS) 40 HR 4006 Booster Pump(12”) (80+ HRS) 80 HR 4006A Mobilization & De-Mobilization of Booster Pump (12”) 1 EA 4007 Booster Pump(14”) (1-80 HRS) 40 HR 4008 Booster Pump(14”) (80+ HRS) 80 HR 4008A Mobilization & De-Mobilization of Booster Pump (14”) 1 EA 4009 Containment Barge XX XX XX XX 4009A Mobilization & De-Mobilization of Containment Barge XX XX XX XX 4010 Spud Barge with Crane XX XX XX XX 4010A Mobilization & De-Mobilization of Spud Barge with
Crane
XX XX XX XX
4011 Sectional Barge 40 DY 4012 Sectional Barge 1 MN 4012A Mobilization & De-Mobilization of Sectional Barge 1 EA 4013 Trackhoe Excavator-60' (1-80 HRS) 40 HR 4014 Trackhoe Excavator-60' (80+ HRS) 80 HR 4014A Mobilization & De-Mobilization of Trackhoe
Excavator-60'
1 EA
4015 Trackhoe Excavator-20' (1-80 HRS) 40 HR 4016 Trackhoe Excavator-20' (80+ HRS) 80 HR 4016A Mobilization & De-Mobilization of Trackhoe
Excavator-20'
1 EA
4017 Backhoe Loader 40 HR 4017A Mobilization & De-Mobilization of Backhoe Loader 1 EA 4018 Track Type Dozer-80 hp (1-80 HRS) 20 HR 4019 Track Type Dozer-80 hp (80+ HRS) 80 HR 4019A Mobilization & De-Mobilization of Track Type Dozer-
80 hp
1 EA
4020 Track Type Dozer-150 hp 20 HR 4020A Mobilization & De-Mobilization of Track Type Dozer-
150 hp
1 EA
4021 Skid Steer Loader 20 HR 4021A Mobilization & De-Mobilization of Skid Steer Loader 1 EA
4025 Geotextile Tube 200 FT 4026 Forestry Mower 40 HR 4027 Tow Boat XX XX 4028 Riprap Boat 40 HR XX XX 4028A Mobilization & De-Mobilization of Riprap Boat 1 EA
SOW
SECTION C
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
1. GENERAL
1.1 Scope. The work to be accomplished under this contract shall consist of furnishing all equipment, labor, and materials, necessary for the excavation and disposal of dredge materials. The projects will take place at Carlyle Lake, Carlyle, Illinois, at the Kaskaskia Navigation Channel from Fayetteville, Illinois (River Mile 36.0) to the mouth of the Kaskaskia River (River Mile 0.0), at Lake Shelbyville, Shelbyville, IL and at the Mississippi River between L&D 24-27. (See Location maps Appendix A).
1.2 Definitions. As used throughout this description/specification, the following terms have the meaning set forth below:
a. Contractor. The term "contractor" refers to the prime contractor and all contract employees and personnel. The prime contractor shall be responsible for ensuring all sub-contractor comply with the provisions of the contract.
b. Contractor Representative. The term "contractor representative" refers to a foremen or superintendent assigned to represent the interests of the contractor with regards to all matter involving the contract.
c. Contracting Officer.(CO) The term "Contracting Officer" means the person executing this contract on behalf of the Government, and any other officer or civilian employee who is properly designated Contracting Officer; and the term includes, except as otherwise provided in this contract, the authorized representative of an Officer acting within the limits of their authority.
d. Contracting Officers Representative.(COR) An individual designated in writing by the Contracting Officer to be responsible for administration of the contract.
e. Ordering Officer. An individual designated in writing by the Contracting Officer to be responsible for issuing delivery orders against the contract within the limits of their authority.
f. Delivery Orders.(DO) The services to be furnished under this contract shall be ordered on a document referred to as a delivery order. These orders shall be issued by the Ordering Officer or Contracting Officer acting within the limits of their authority. Each Delivery Order timeframe for completion will be negotiated with the Contractor prior to issuance.
g. Suspension of Operations. Should weather conditions or high river stages develop after a delivery order is issued, which will, in the opinion of the Contracting Officer, make further work impracticable or undesirable, the Contractor will be ordered to suspend operations until such time as the working conditions improve and become suitable for further work to proceed. The Contractor shall be required to recommence work within 48 hours after notification by the Contracting Officer.
2. EQUIPMENT
2.1 General. The hourly prices bid for equipment shall include equipment, equipment operators, and such other personnel for equipment as necessary for operation of the equipment at the worksite, fuel, and lubricants. The equipment furnished shall be of standard make and the capacities indicated herein. Personnel furnished as operators for this equipment shall be thoroughly qualified in the use of equipment in order that maximum capacity may be obtained. The contractor will only be paid for actual hours of operation of the equipment. All equipment and labor furnished by the Contractor shall be subject to the approval of the Contracting Officer.
2.2 Permits and Licenses. The contractor shall comply with all Federal, State, and Local permits and licenses pursuant to this contract.
2.3 Mobilization and Demobilization. The price bid shall include delivery of the necessary equipment with operators to the worksite as directed by the Contracting Officer or his authorized representative and removal of each piece of equipment from the worksite upon completion of the delivery order. The contractor will be issued a delivery order; a minimum of five days prior to date equipment is needed by the Contracting Officer. The equipment shall be available seven days a week for a minimum of eight hours a day.
2.4 Relocation of Equipment. The price bid shall include all equipment and personnel necessary for take down and setup of the dredge at the next site as specified in the delivery order.
2.5 Maintenance of Equipment. Repairs and maintenance of equipment shall be made by the contractor, and all equipment shall be in safe and good working condition when furnished and shall be kept in safe and good working condition when in use. Contractor shall furnish all fuel, grease, and other operating supplies as required for the proper operation of the equipment. Costs for the foregoing shall be included in the contract unit prices and no separate payment therefore will be made.
2.6 Replacement of Equipment. Any equipment which, in the opinion of the Contracting Officer, proves to be deficient in quality shall be promptly replaced by the contractor to the satisfaction of the Contracting Officer. If such deficient equipment is not promptly made good by the contractor, the Contracting Officer reserves the right to terminate the use of such equipment.
2.7 Specific Equipment. All contractor supplied equipment shall conform to the following specifications.
a. Small Dredge. The contractor shall provide a dredge boat with operators and all necessary support equipment.
This is the start of the file's text. The full file is on GovTribe.