Solicitation Amendment W912P826BA0160002 SF 30.pdf

PDF 40 MB Posted

Attached to
Freshwater Bayou - Lock to The Gulf, Freshwater Bayou Maintenance Dredging #26-1, ED 25-018
Solicitation number
W912P826BA016
Issued by

About this file

This is a Solicitation Amendment (SF 30) for U.S. Army Corps of Engineers contract W912P826BA016 extending the bid opening date and incorporating specification and drawing revisions for a dredging project.

The project involves maintenance dredging of the Freshwater Bayou Channel from Station 70+00 (Mile 1.3) to Station -210+00 (Mile -4.0) in Vermilion Parish, Louisiana. The base work requires removal of material above elevation -16.0 Mean Low Gulf (MLG) from a 125-foot bottom width channel and disposal of all dredged material on the Gulf shoreline west of the channel. The contract includes optional work (OW) to extend dredging from Station 5+50 to 0+00 with a 250-foot bottom width. The base work contract duration is 120 calendar days; if optional work is exercised, an additional 30 calendar days will be added. The bid schedule includes mobilization/demobilization (lump sum), base dredging with tiered pricing (first 700,000 cubic yards at one rate, all material over 700,000 cubic yards at a lower rate), and optional work with similar tiered pricing (first 400,000 cubic yards, then all over). Amendment 0002, effective 20 July 2026, extends the bid opening to Thursday, 23 July 2026, at 1:00 p.m. local time, with bid submission cutoff at 10:00 a.m. The amendment incorporates revisions to the table of contents, bid schedule, specifications (Sections 00010, 00073, 01100, 01330, 01450, 01572, 02210, and 352023), and contract drawings (Sheets C-01 through C-04). Key specification revisions include completion time of 120 calendar days, Contractor Quality Control Plan requirements with pre-work meetings, Dredging Quality Management (DQM)-certified system requirements, survey procedures, hazardous waste handling, environmental protection protocols, and safety requirements per USACE EM 385-1-1. The procurement is unrestricted with NAICS code 237990 and estimated contract value between $10 million and $25 million. The Contracting Officer is Evan Woitha (504-862-1214, evan.g.woitha@usace.army.mil) at the New Orleans District Contracting Division.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

Project Table of Contents

Page 4/485. Delete this page in its entirety and substitute with the attached revised Table of Contents, therefore.

STANDARD FORM 1442

Page 5/485, Block 11b. Change "137” to "120”.

Section 00010

Pages 00010-3, 4, and 5. Delete these pages in their entirety and substitute the attached pages 00 00 10-3, 4, and 5, therefore.

Section 00 73 00

Page 271/485. Paragraph 1, subparagraph (c). Delete this subparagraph in its entirety and substitute the following, therefore:

“(c). Complete the entire work ready for use not later than 120 calendar days after the date of receipt by him of notice to proceed. The time stated for completion shall include final cleanup of the premises.”

Section 01100

Pages 01100a through 01100-17. Delete this section in its entirety and substitute with the attached Section 01 10 00, therefore.

Section 01 33 00

1. Page 4, paragraph 1.4.1. Delete this paragraph in its entirety and substitute the following revised paragraph, therefore:

“1.4.1 Government Approved

Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract provision in Section 00 72 00 GENERAL CONDITIONS entitled SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FAR 52.236-21), they are considered to be "shop drawings." Any reference to Government approval by the Contracting Officer (CO) includes the approving authority of the CO, the Administrative Contracting Officer (ACO), or the Contracting Officer's Representative

(COR).”

2. Page 4, paragraph 1.6. Delete this paragraph in its entirety and substitute the following revised

“1.6. DISAPPROVED SUBMITTALS

The Contractor must respond to all concerns expressed by the Contracting Officer and promptly make any corrections necessary to address those concerns. The Contractor must promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal.

If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract provision in Section 00 72 00 GENERAL CONDITIONS entitled CHANGES (FAR 52.243-4), must be given promptly to the Contracting Officer.”

Section 01 45 04.00 10

1. Page 2, paragraph 3.1. Delete this paragraph in its entirety and substitute the following revised

“3.1 GENERAL REQUIREMENTS

The Contractor is responsible for quality control and must establish and maintain an effective quality control system in compliance with the Contract provision in Section 00 72 00 GENERAL CONDITIONS entitled INSPECTION OF CONSTRUCTION (FAR 52.246-12). The quality control system must consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The system must cover all construction operations, both onsite and offsite, and must be keyed to the proposed construction sequence. The site project superintendent and Quality Control Manager will be held responsible for the quality of work on the job and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. The site project superintendent in this context must be the highest level manager responsible for the overall construction activities at the site, including quality and production. The site project superintendent must maintain a physical presence at the site at all times, except as otherwise acceptable to the Contracting Officer, and must be responsible for all construction and construction related activities at the site.”

2. Page 3, paragraph 3.2. Delete this paragraph in its entirety and substitute the following revised

“3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN

The Contractor must furnish for review by the Government, not later than 15 days after receipt of notice of award, the Contractor Quality Control Plan proposed to implement the requirements of the Contract provision in Section 00 72 00 GENERAL CONDITIONS entitled INSPECTION OF CONSTRUCTION (FAR 52.246-12). The plan must identify personnel, procedures, control, instructions, tests, records, and forms to be used. The Government will consider an interim plan for the first 30 days of operation. Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional features of work to be started. A sample CQC Plan is attached at the end of the section.”

3. Page 4, paragraph 3.3. Delete this paragraph in its entirety and substitute the following revised

“3.3 Pre-Work Meeting

Prior to the start of construction, the contractor shall meet with the Contracting Officer or his/her authorized representative in a Pre-Construction Conference and a Pre-Work Coordination Meeting. At least 14 calendar days prior to the Preconstruction Conference, the contractor shall submit to the government for review and approval his/her Contractor Accident Prevention Plan and Contractor Quality Control Plan.”

4. Page 5, add the following new subparagraph after paragraph 3.3, therefore:

“3.3.1 Pre-Work Coordination Meeting

After the Pre-Construction Conference, and before the start of construction, the contractor shall meet with the Contracting Officer, or his/her authorized representative, in a Pre-Work Coordination Meeting to discuss the contractor’s Quality Control Plan. During the Coordination Meeting, a mutual understanding of the system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting shall be prepared by the Government and signed by both the Contractor and the Contracting Officer. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor.”

5. Page 8, paragraph 3.7.1. Delete this paragraph in its entirety and substitute the following revised

“3.7.1 Punch-Out Inspection

Near the end of the work, or any increment of the work established by a time stated in the Contract provision in Section 00 73 00 SUPPLEMENTARY CONDITIONS entitled COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) or stated elsewhere in the specifications, the CQC Manager must conduct an inspection of the work. A punch list of items which do not conform to the approved drawings and specifications must be prepared and included in the CQC documentation, as required by paragraph DOCUMENTATION. The list of deficiencies must include the estimated date by which the deficiencies will be corrected. The CQC System Manager or staff must make a second inspection to ascertain that all deficiencies have been corrected. Once this is accomplished, the Contractor must notify the Government that the facility is ready for the Government Pre-Final inspection.”

6. Page 9, paragraph 3.7.3. Delete this paragraph in its entirety and substitute the following revised

“3.7.3 Final Acceptance Inspection

The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative must be in attendance at this inspection. Additional Government personnel including, but not limited to, those from the New Orleans District, Mississippi Valley Division, and local interest may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notice must be given to the Contracting Officer at least 14 days prior to the final acceptance inspection and must include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the Contract provision in Section 00 72 00 GENERAL CONDITIONS entitled INSPECTION OF

CONSTRUCTION (FAR 52.246-12).”

Section 01 57 20.01 12

1. Page 3, paragraph 1.3.3. Delete this paragraph in its entirety and substitute the following revised

“1.3.3 Hazardous/Regulated Waste

If the Contractor uncovers an existing hazardous/regulated waste not Contractor generated, not shown on the drawings, and not specified herein, the Contractor shall notify the Contracting Officer's Representative immediately. Payment for handling, removal, transportation and disposal of hazardous and/or regulated solid wastes not Contractor generated, not shown on the drawings, and not specified herein will be made as an equitable adjustment in contract price under the Contract provision in Section 00 72 00 GENERAL CONDITIONS entitled CHANGES

(FAR 52.243-4).

2. Page 6, paragraph 3.1.1. Delete this paragraph in its entirety and substitute the following revised

“3.1.1 General

The land resources within the project boundaries and outside the limits of permanent work performed under this contract must be preserved in their present condition or be restored to a condition after completion of construction that will appear to be natural and not detract from the appearance of the project. The Contractor must confine his/her construction activities to areas defined by the plans and/or specifications. The following additional requirements are intended to supplement and clarify the requirements of the Contract provisions in Section 00 72 00 GENERAL CONDITIONS entitled PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (FAR 52.236-9); OPERATIONS AND

STORAGE AREAS (FAR 52.236-10); and CLEANING UP (FAR 52.236-12)”

Section 02 21 10.00 12

1. Page 3, paragraph 1.2. Delete this paragraph in its entirety and substitute the following revised

“1.2 MEASUREMENT AND PAYMENT

No separate measurement or payment will be made for surveys. The cost of the work covered under this section shall be included in the applicable contract unit price per cubic yard for “Dredging C/L Station 70+00 to C/L Station -210+00” and “Dredging – C/L STA. 5+50 – C/L STA (-) 210+00 (OW), if OW is exercised.”

2. Page 3, paragraph 1.4, SD-02, submittal “Before and After Dredging Cross sections”. Delete this submittal in its entirety and substitute the following revised submittal, therefore:

“Before and After Dredging Cross Sections

Before and after dredging cross sections of Freshwater Bayou – Lock to Gulf Bar Channel shall be taken and submitted. (See Paragraph “Before and After Dredging Cross Sections”)”

3. Page 3, paragraph 1.5. Delete this paragraph in its entirety and substitute the following revised

“1.5 QUALITY CONTROL

The Contractor must establish and maintain quality control for the work specified in this section to assure compliance with the contract requirements and maintain records of his quality control for all surveying including but not limited to the following:

(1) Layouts and Surveys. Daily log of layout and surveys consisting of type and location using Contractor furnished control system as stated in the Contract provision in Section 00 72 00 GENERAL CONDITIONS entitled LAYOUT OF WORK (FAR 52.236-17).

(2) Reporting. The original and two (2) copies of these reports and tests as well as the records of corrective action taken must be furnished to the Government daily. The report must include a record of times and dates surveys were run, the horizontal control stations used and their coordinates, the vertical control points used and their elevations, and weather conditions.

Format of report must be as prescribed in Section 01 45 04.00 10 CONTRACTOR QUALITY

CONTROL..”

Section 35 20 23.00

1. Page 4, paragraph 1.2.1. Delete this paragraph in its entirety and substitute the following revised

“1.2.1 Quantity Surveys

A survey of the sites for dredging shall be made in accordance with the provisions of Section 02 21 10.00 12 SURVEYS and all measurements to determine dredging quantities will be based on the "before and after dredging" cross sections described therein. The soundings and contours shown on the contract drawings are representative of conditions in the Freshwater Bayou – Lock to Gulf Bar Channel that existed June 2026 and do not necessarily represent existing conditions. Survey data reflecting most recent conditions shall be obtained prior to contract award and provided by amendment prior to bid opening.” The elevations shown thereon shall be verified or corrected by the "before dredging" surveys. Determinations of quantities to be paid for in the area specified, after having once been made, will not be reopened.”

2. Page 4, paragraph 1.2.6. Delete this paragraph in its entirety and substitute the following revised

“1.2.6 Progress Payments

Monthly progress payments will be made based on quantities determined using "before dredging" surveys taken in accordance with Contract provision in Section 00 70 00 CONDITIONS OF THE CONTRACT entitled QUANTITY SURVEYS - ALTERNATE I (FAR 52.236-16) and Section 02 21 10.00 12 SURVEYS; provided the after dredging surveys and any additional soundings that may be directed indicate that the Contractor has met the required dimensions and acceptance reach length.”

3. Page 4, paragraph 1.3.1. Delete this paragraph in its entirety and substitute the following revised

“1.3.1 Mobilization and Demobilization

An item to cover the cost of initial mobilization and final demobilization of the Contractor's plant and equipment under this contract is included and will be paid for as stipulated in the Contract provision in Section 00 72 00 CONDITIONS OF THE CONTRACT entitled PAYMENT FOR

MOBILIZATION AND DEMOBILIZATION.”

4. Page 5, paragraph 1.3.2. Delete this paragraph in its entirety and substitute the following revised

“1.3.2 Dredging

Payment for dredging will be made at the applicable contract unit price per cubic yard for “Dredging: C/L Station 70+00 to C/L Station -210+00” and “Dredging – C/L STA. 5+50 – C/L STA (-) 210+00(OW)”, if OW is exercised. Price and payment shall constitute full compensation for furnishing all plant, labor and materials and performing all work for surveying, including any additional soundings that may be directed, excavation, disposal of materials, furnishing diesel powered crewboats fully operated, aluminum skiff fully operated, furnishing survey vessel(s) as required in Section 02 21 10.00 12 SURVEYS, pollution control, furnishing and maintaining radio and telephone communications equipment, the installation, operation, and maintenance of the Dredging Quality Management DQM-certified system; and all operations incidental thereto.”

5. Page 6, Paragraph 1.4. Delete this paragraph in its entirety and substitute the following revised

“1.4 Submittals

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Dredge Plant Data

Plant Data Sheets. The Contractor shall complete the plant data sheets attached at the end of this section for the dredge and attendant plant the contractor intends to use to perform the work under this contract. Dredge physical data is required for submittal in the data sheets.

Plan of Operation; G, EDC

Submit a Plan of Operation at each pipeline and utility crossing. (See Paragraph

WORKING IN THE VICINITY OF STRUCTURES AND UTILITY CROSSINGS)

Disposal of Dredged Material; G, EDC

Submit a disposal of dredging material plan in Government furnished disposal areas no later than seven (7) days prior to commencement of the work. (See Paragraph DISPOSAL OF DREDGE MATERIAL)

Access Plan; G, EDC

See paragraph "Access Plan", and Section 01 10 00 GENERAL PROVISIONS entitled ACCESS PLAN.

Construction Schedule; G, CD

See paragraph "Construction Schedule" and Section 00 72 00 GENERAL CONDITIONS entitled SCHEDULES FOR CONSTRUCTION CONTRACTS.

SD-07 Certificates

Certified Letter; G, EDC

Submit a copy of Certified Letters to Pipelines and Utilities Owners

SD-11 Closeout Submittals

Report of Operations; G, EDC

See paragraph QUALITY CONTROL, subparagraph "Report Of Operations"

6. Page 6, paragraph 1.5.2, item 4. Delete the contact information in its entirety and substitute the following revised contact information, therefore:

“(4) All required reports shall be made available in electronic format. The Contractor shall distribute one (1) copy of each report to each of the following:

(a) Area Engineer, Lafayette Area Office ATTN: Mr. William W. Kiddy, P.E.

100 Asma Blvd., Suite 301 Lafayette, LA 70508-3858

(b) Government Inspector”

7. Page 7, paragraph 1.5.3. Delete this paragraph in its entirety and substitute the following revised

“1.5.3 Access Plan

The Contractor shall submit an Access Plan to be reviewed and approved by the Contracting Officer. The requirement is specified and further detailed in the Section 01 10 00 GENERAL PROVISIONS, paragraph entitled ACCESS PLAN.”

8. Page 7, paragraph 1.5.4. Delete this paragraph in its entirety and substitute the following revised

“1.5.4 Construction Schedule

The Contractor shall submit a practicable construction schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work. The requirement is specified and further detailed in the Contract provision found in Section 00 72 00 CONDITIONS OF THE CONTRACT entitled SCHEDULES FOR CONSTRUCTION CONTRACTS.”

9. Page 10, paragraph 3.1.2. Delete this paragraph in its entirety and substitute the following revised

“3.1.2 Hydraulic Cutterhead Dredging

As depicted on the contract bidding schedule, bidding of dredging of channel limits is required and defined below. Hydraulic cutterhead dredging operations shall be performed within the following limits: “Dredging: C/L Station 70+00 to C/L Station -210+00” and “Dredging – C/L STA.

5+50 –C/L STA (-) 210+00 (OW)”, if OW is exercised. All work shall be performed as specified herein and as shown on the contract drawings.”

10. Page 10, paragraph 3.1.3. Delete this paragraph in its entirety and substitute the following revised

“3.1.3 Channel Dimensions

The channel shall be dredged to the required dimensions shown on the contract drawings and indicated below. A box cut will be permitted. The extent of required dredging and control of the box cut is illustrated in the Box Cut detail attached at the end of this section.

C/L Stations 70+ 00 to (-)210+00: Depth (-)16.0 feet MLG with a Bottom Width of 125 feet.”

Option Work (OW), if exercised, will include the following: C/L Stations 5+50 to 0+00:

Depth (-)16.0 feet MLG with a uniform transition from 125 feet to 250 feet in Bottom Width.

Option Work (OW) if exercised, will include the following: C/L Stations 0+00 to (- )210+00: Depth (-) 16.0 feet MLG at a Bottom Width of 250 feet.”

11. Page 10, paragraph 3.1.4. Delete this paragraph in its entirety and substitute the following revised

“3.1.4 Excessive Dredging

Excessive dredging is defined to be any dredging which is in excess of the required dimensions, as shown on the contract drawings. Any material removed in excess of the required dimensions will not be measured for payment. The Contractor shall be responsible for damages caused by excessive dredging. Nothing herein shall be construed to prevent payment for removal of shoals performed in accordance with the applicable provisions of the Section 01 10 00 GENERAL PROVISIONS paragraph entitled SHOALING.”

12. Page 10, paragraph 3.1.5. Delete this paragraph in its entirety and substitute the following revised

“3.1.5 Slides

In the event sliding occurs in any part of any excavation after its completion but prior to its acceptance, the Contractor shall remove such portions of the slide as the Contracting Officer may direct. In the event, the slide is caused through the fault of the Contractor as determined by the Contracting Officer, the slide shall be removed by the Contractor at no additional expense to the Government. In the event the slide is not due to the fault of the Contractor, payment for removal will be made at the applicable contract unit price for dredging to which it is incidental.”

13. Page 10, paragraph 3.1.6. Delete this paragraph in its entirety and substitute the following revised

“3.1.6 Character of Materials

The material to be removed within the required dimensions specified consists of shoaling that has occurred since the channel was last dredged and insitu material. Sand, silt, clay, shell, logs, stumps, snags, debris, and other obstructions may be encountered. Bidders are expected to examine the site of the work and, after investigation, decide for themselves the character of the materials. The Contractor shall note the following dredging jobs previously performed.

Limits Date Dredged Design Elevation Depth(ft-MLG) Width Dimensions

C/L Station 70+00 to Mar 2007 -16.0 125 C/L Station 5+50

C/L Station 0+00 to Mar 2007 -16.0 250 C/L Station -210+00

C/L Station 70+00 to Apr 2009 -16.0 125 C/L Station 5+50

C/L Station 0+00 to Apr 2009 -16.0 250 C/L Station -210+00

C/L Station 70+00 to Apr 2019 -16.0 125 C/L Station 5+50

C/L Station 0+00 to Apr 2019 -16.0 250 C/L Station -210+00

C/L Station 70+00 to Oct 2023 -16.0 125 C/L Station 5+50

C/L Station 0+00 to Nov 2023 -16.0 250 C/L Station -210+00

Note: Channel transitions from 125 feet to 250 feet in width between C/L Stations 5+50 and 0+00 only if Option Work (OW) is exercised. All debris removal costs shall be included in the applicable contract unit price per cubic yard for dredging.

Virgin material may be encountered below the channel dimensions listed above. The table above indicates the last maintenance dredging event performed. Dredging history of Freshwater Bayou is available on request.”

Section 35 20 23.33

Page 10, paragraph 1.3. Delete this paragraph in its entirety and substitute the following revised paragraph, therefore:

“1.3 MEASUREMENT AND PAYMENT

Separate payment for installation, operation, and maintenance of the DQM-certified system as specified herein for the duration of the dredging operations is not allowed; All costs in connection therewith shall be considered a subsidiary obligation of the Contractor and shall be included in the applicable contract unit price per cubic yard for “Dredging - C/L Station 70+00 to C/L Station -210+00” and “Dredging – C/L STA. 5+50 – C/L STA (-) 210+00(OW)" if OW is exercised.”

DRAWINGS

SHEET IDENTIFICATION Nos. C-01, C-02, C-03, and C-04. Delete these drawings in their entirety and substitute with the attached revised drawings SHEET IDENTIFICATION Nos. C-01, C-02, C-03, and C-04.

PTC-i Ed 25-018

PROJECT TABLE OF CONTENTS

Division 00 – PROCUREMENT AND CONTRACTING

Solicitation, Offer and Award Sf-1442 00 10 00 Bidding Schedule 00 21 00 Instructions to Bidders 00 22 00 Supplementary Instructions 00 45 00 Representations and Certifications 00 70 00 Conditions of The Contract 00 72 00 General Conditions 00 73 00 Supplementary Conditions

Division 01 - GENERAL REQUIREMENTS

01 10 00 General Provisions 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 42 00 Sources for Reference Publications 01 45 00.15 10 Resident Management System Contractor Mode (RMS CM) 01 45 04.00 10 Contractor Quality Control 01 57 20.01 12 Environmental Protection - Dredging 01 78 02.00 10 Closeout Submittals

Division 02 – EXISTING CONDITIONS

02 21 10.00 12 Surveys

Division 35 – WATERWAY AND MARINE CONSTRUCTION

35 20 23.00 12 Dredging 35 20 23.33 National Dredging Quality Management Program Pipeline

Hydraulic Dredge

SECTION 00 00 10 – BIDDING SCHEDULE

Freshwater Bayou to Gulf Freshwater Bayou

Maintenance Dredging #26-1 Vermilion Parish, Louisiana

00 00 10-3 ED 25-018

Item DESCRIPTION Estimated Quantity Unit Unit Price Estimated Amount

BASE WORK

0001 Mobilization and Demobilization 1 JOB

0002 Dredging – C/L STA 70+00 –

C/L STA (-)210+00

0002AA First 700,000 700,000 CY

0002AB All Over 700,000 150,000 CY

TOTAL BASE WORK: $

OPTION WORK – OW

*0003 Dredging - C/L STA. 5+50 –

C/L STA (-)210+00 (OW)

*0003AA First 400,000 400,000 CY

*0003AB All Over 400,000 100,000 CY

TOTAL OPTION WORK: $

TOTAL BASE WORK + OPTION WORK: $

Award will be made as a whole to one bidder.

NOTE 1: The unit “JOB” as used in this Bidding Schedule is synonymous with the term “Lump Sum” used elsewhere within these plans and specifications.

NOTE 2: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE

UNIT PRICE AND THE EXTENDED TOTAL OR ESTIMATED AMOUNT FOR ANY

ITEM, ITS BID SHALL BE DECLARED NON-RESPONSIVE AND THEREFORE

INELIGIBLE FOR AWARD.

*NOTE 3: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or subline items are materially unbalanced (See RFO 14.306-3, Rejection of Individual Bids).

00 00 10-4 ED 25-018

*NOTE 4: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442 after Notice of Award. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

*NOTE 5: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s). **If an option is to be exercised at the time of contract award FAR 17.208 shall be used in place of FAR 52.217-5.

*NOTE 6: OPTION WORK ITEM: This provision pertains to Bid Item 0003. The Government may require the delivery of, in whole or part, the numbered line item identified in the schedule as an OPTIONAL WORK item, in the quantity and price stated in the schedule. The Contracting Officer may exercise the OPTIONAL WORK by written notice to the Contractor. If the Government activates the Optional Work Item, the activation will occur within fourteen (14) calendar days of the NTP. No additional mobilization/demobilization will be paid to the Contractor for the Optional Work. Bidders shall bid on all items including optional items (see “Evaluation of Options” FAR 52.217- 5). Failure to bid on all items will result in a non-responsive bid.

*Note 7: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF OPTIONAL

WORK.

In the event that OPTIONAL WORK item 0003 is exercised under the terms of the contract, the time required for completion of the contract will be adjusted by 30 calendar days, in addition to the original contract duration of 120 calendar days established for the BASE WORK items specified in the contract provision in Section 00 73 00 SUPPLEMENTARY CONDITIONS entitled COMMENCEMENT, PROSECUTION, AND

COMPLETION OF WORK.

*NOTE 8: RAPID VENDOR PAYMENT. Web-based instructions for the submission of invoices may be found at the following website:

http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx

00 00 10-5 ED 25-018

EVALUATION OF SUBLINE ITEMS (Dec 2019 - AFARS 5152.211-9000).

Item Nos. 0002 & 0003 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its subline items.

(End of Clause)

VARIATIONS IN ESTIMATED QUANTITIES - SUBLINE ITEMS (Dec 2019) - AFARS 5152.211-9001).

This variation in estimated quantities clause is applicable only to item Nos. 0002 & 0003.

(a) Variation from the estimated quantity in the actual work performed under any second or subsequent subline item or elimination of all work under such a second or subsequent subline item will not be the basis for an adjustment in contract unit price.

(b) Where the actual quantity of work performed for item Nos. 0002 and 0003 is less than 85% of the quantity of the first subline item listed under such item, the contractor will be paid at the contract unit price for that subline item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the contract clause at VARIATION IN ESTIMATED

QUANTITY.

(c) If the actual quantity of work performed under item No. 0002 and 0003 exceeds 115% or is less than 85% of the total estimated quantity of the subline item under that item and/or if the quantity of the work performed under the second subline item or any subsequent subline item under item Nos. NONE exceeds 115% or is less than 85% of the estimated quantity of any such subline item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the contract clause VARIATION IN ESTIMATED QUANTITY.

(End of Clause)

01 10 00-a ED 25-018

Section Table of Contents

SECTION 01 10 00 - GENERAL PROVISIONS

1. ........ DAMAGE TO WORK

2. ........ SAFETY PROVISIONS

3. ........ SIGNAL LIGHTS

4. ........ CONTINUITY OF WORK

5. ........ INSPECTION

6. ........ SHOALING

7 ......... ACCOMMODATIONS AND MEALS FOR INSPECTORS

8. ........ SEAWORTHINESS CERTIFICATION

9. ........ ENVIRONMENTAL LITIGATION

10. ...... STATE TAXES

11. ...... FUEL CONSUMPTION REPORTING REQUIREMENTS

12. ...... RIGHTS-OF-WAY

13. ...... CONTRACT COORDINATION

14. ...... CONTRACTOR’S RESPONSIBILITY

15. ...... MOBILIZATION OF ATTENDANT PLANT

16. ...... ACCESS PLAN

17. ...... SUPERVISION

18. ...... PRE-BID SITE VISIT

19. ...... WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS

20. ...... CONTRACTOR PERFORMANCE EVALUATIONS – CONSTRUCTION

21. ...... SECURITY REQUIREMENTS

22. ...... REGULATORY REQUIREMENTS

23. ...... DATUM RELATIONSHIPS

24. ...... EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

01 10 00-1 ED 25-018

SECTION 01 10 00 - GENERAL PROVISIONS

1. DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in the provision in Section 00 72 00 GENERAL CONDITIONS entitled PERMITS AND RESPONSIBILITIES (FAR 52.236-7). However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit price or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there is no contract unit or job prices applicable to any part of such work, an equitable adjustment shall be made pursuant to the provision in Section 00 72 00 GENERAL CONDITIONS entitled CHANGES (FAR 52.243-4). Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

2. SAFETY PROVISIONS

The safety provisions as specified herein refer to the USACE Safety and Occupational Health Requirements EM 385-1-1 dated 15 March 2024. The most current edition can be found at:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf

(a) Accident Investigation and Reporting. The reporting and associated investigation of accidents and near misses is considered a leading indicator. Utilize ENG Form 3394, U.S. Army Corps of Engineers Mishap Notification and Investigation, to report accidents and near misses. Link to ENG Form 3394:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerFor ms/Eng_Form_3394_2021Aug.pdf.

Contractors must investigate, analyze, and report all accidents and near misses occurring incidentally to an operation, project, or facility according to EM 385-1-1, Table 2-1 Accident Reporting Required Timeline.

(b) Accident Prevention Plan (APP). (See the provision in Section 00 72 00 -

GENERAL CONDITIONS entitled ACCIDENT PREVENTION (FAR 52.236-https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf

01 10 00-2 ED 25-018

13).) Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the prework conference, an electronic copy and one hard copy of the Accident Prevention Plan (APP) Worksheet (ENG FORM 6293) shall be submitted to the Contracting Officer for review and acceptance. Link to ENG form 6293 (APP):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_Aug%20 2024%20-%20FINAL.pdf

(c) The Plan shall be prepared in the following format:

(1) Activity Hazard Analysis (AHA) Requirements. The contractor shall complete the Activity Hazard Analysis (AHA) Requirements on ENG form 6206 in accordance with EM 385-1-1, Chapter 2-6. Specific AHA requirements are identified in paragraph 6 of each chapter of EM 385- 1-1. Link to fillable ENG form 6206 (AHA form):

(2) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2 023Aug24.pdf

(3) The contractor shall submit ENG Form 6282 (Site Safety and Health

Officer Designation Letter). A Designation Letter is required for all levels of onsite SSHOs. The contractor shall maintain a copy of the accepted form at the site of work. Link to ENG form 6282:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2 023Aug28.pdf?ver=_1GgPT1ZS1AFX9P8AKU5og%3d%3d.

(4) Site Safety and Health Officer (SSHO). The contractor must employ a minimum of one (1) Level 1 Full-time Site Safety and Health Officer to function as the primary Level 1 SSHO responsible for ensuring all site personnel are implementing Safety and Occupational Health requirements according to the contract, EM 385-1-1, applicable federal, state, and local requirements. A designated Level 1 SSHO must be at the site of work whenever work is performed. The SSHO shall meet the training and experience requirements of EM 385-1-1, Chapter 2-3.b. Level 1 SSHOs are not permitted to supervise non-safety personnel at the site of work.

(5) A copy of company policy statement regarding accident prevention.

(6) When marine plant and equipment are in use under a contract, the method of fuel oil transfer shall be included on MVN Form 385-10 (Latest Edition), Fuel Oil Transfer (attached at the end of this section), (Refer to 33 CFR 156).

(d) Commencement of Work. The contractor shall not commence physical work at the site until the Contracting Officer, or his/her authorized representative https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_Aug%202024%20-%20FINAL.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_Aug%202024%20-%20FINAL.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf?ver=_1GgPT1ZS1AFX9P8AKU5og%3d%3d https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf?ver=_1GgPT1ZS1AFX9P8AKU5og%3d%3d

01 10 00-3 ED 25-018

has accepted the Accident Prevention Plan. The contractor may submit its Accident Prevention Plan only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase. Also refer to EM 385-1-1, Chapter 2.

(e) Hazard Communication (HazCom) Program. The contractor shall develop, implement, and maintain at the workplace a written, Hazard Communication Program (see EM 385-1-1, Chapter 6-7) that includes identification of potential hazards as prescribed in 29 CFR Part 1910.1200 and/or 1926.59, effects of exposure and control measures to be used for chemical products and physical agents that may be encountered during the performance of work on this contract, provisions for container labeling, Safety Data Sheets, and employee training program, and other criteria in accordance with 29 CFR Part

1910.1200 and/or 1926.59. Training shall include communication methods and systems to be used (i.e., voice, hand signals, radios or other means), and training in the use and understanding of safety data sheets and chemical product hazard warning labels. Prior to bringing hazardous substances, as defined in 29 CFR 1910.1200 and/or 1926.59, onto the job site, a copy of the Hazard Communication Program and the Safety Data Sheets of each substance shall be submitted to the Contracting Officer and made available to the contractor's employees as part of its Accident Prevention Plan. A site map shall be attached to the inventory showing where the inventoried hazardous substances are stored. The inventory list and site map shall be updated monthly to assure accuracy.

(f) Daily Inspections. The contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the jobsite in accordance with Section 01 45 04.00 10, CONTRACTOR QUALITY CONTROL. The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

(1) Phase(s) of construction underway during the inspection.

(2) Locations of areas where inspections were made.

(3) Results of inspections, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

(g) Safety Sign. The contractor shall furnish, erect, and maintain a safety sign at the site where indicated by the Contracting Officer. The sign shall conform to the requirements of this paragraph and the drawing included at the end of this section. The lettering shall be black, the safety circle and cross green, and the background white. When placed on a floating plant, the sign may be half

01 10 00-4 ED 25-018

size. The sign shall be erected as soon as practicable, but not later than 15 calendar days after the date established for commencement of work. The data required shall be current. The sign coordinator is Timothy Lacoste@ 504.862.2663.

(h) Ground Fault Protection Equipment. Electrical equipment used on this contract shall be equipped with ground fault circuit interrupters in accordance with EM 385-1-1, Chapter 11-8.

(i) Means of Escape for Personnel Quartered, or Working on Floating

Plant. Two means of escape shall be provided for assembly, sleeping, and messing areas on floating plants. For areas involving 10 or more persons, both means of egress shall be through standard size doors opening to different exit routes. Where nine or fewer persons are involved, one of the means of escape may be a window (minimum dimensions 24-inches by 36-inches), which leads to a different exit route. Refer to EM 385-1-1, Chapter 19-8.h.

(j) Emergency Alarms and Signals.

(1) Alarms. Emergency alarms shall be installed and maintained on all floating plant requiring a crew where it is possible for either a passenger or crewman to be out of sight or hearing from any other person. The alarm system shall be operated from the primary electrical system with standby batteries on trickle charge that will automatically furnish the required energy during an electrical-system failure. A sufficient number of signaling devices shall be placed on each deck so that the sound can be heard distinctly at any point above the usual background noise. All signaling devices shall be so interconnected that actuation can occur from at least one strategic point on each deck.

(2) Signals.

(a) Fire Alarm Signals. The general fire alarm signal shall be in accordance with 46 CFR Ch. I; Subpart E.109.503 of the Coast Guard Rules and Regulations for Cargo and Miscellaneous Vessels, Sub-Chapter I & Ia.

(b) Abandon Ship Signals. The signal for abandon ship shall be in accordance with paragraph 109.503(b) of the reference cited in subparagraph (2)(a) above.

(c) Man-Overboard Signal. Hail and pass the word to the bridge. All personnel and vessels capable of rendering assistance shall respond.

01 10 00-5 ED 25-018

(k) Hurricane Plan. A detailed plan for protection and evacuation of personnel and the construction site, in the event of an impending hurricane or storm, is required as an enclosure to the contractor's Accident Prevention Plan. This plan shall be submitted to the Contracting Officer, or his/her representative, for review and approval prior to the preconstruction conference. Work being performed to satisfy the Hurricane Plan will not be measured for payment.

Payment for all work associated with the Hurricane Plan, and providing the equipment required for the duration specified, shall be distributed amongst the existing bid items. The Hurricane Plan shall include at least the following:

(1) The time each phase of the plan will be put in effect. The time shall be the number of hours remaining for the storm to reach the worksite if it continues at the predicted speed and direction.

(2) The estimated time necessary to secure and evacuate the site including any emergency flood protection.

(3) The safe harbor for personnel and plant specifically identified.

(4) The name of the boat which will be used to move the plant, its type, capacity, speed, and availability.

(5) The estimated time necessary to move the plant to the safe harbor after movement is started.

NOTE: Floating plant, boat, or other marine activities must submit an Emergency Plan for Marine Activities which includes a Severe Weather Plan for Marine Activities per EM 385-1-1, Chapters 19-7.a and 19-7.b.

(l) Hazardous Energy Control Program. The contractor shall develop, implement, and maintain at the workplace, a written Hazardous Energy Control Program (HECP). Refer to EM 385-1-1, Chapter 12-7.

(m) Access/Haul Road Plan. A written Access/Haul Road Plan is required when access or haul roads are to be used. Work on the haul road must not commence until USACE supervisor/KO or COR has accepted the plan, refer to EM 385-1-1, Chapter 4-7.b.

(n) Cranes. The contractor (including subcontractors) shall have cage boom guards, insulating links, or proximity warning devices on cranes that will be working adjacent to power lines. These devices shall not alter the requirements of any other regulation of this part - even if such device is required by law or other regulation. Insulating links shall be rated for the energized lines they are working near (EM 385-1-1, Chapter 11- 8.t.6.d). Calibration records or stamped date of required manufacturer inspection of proximity warning devices shall be kept on the crane. Additionally, prior to any work commencing an Activity Hazard

01 10 00-6 ED 25-018

Analysis) identifying and satisfying EM 385-1-1, Chapter 2-6, requirements shall be submitted and accepted by the Contracting Officer.

(o) Crane/Derrick and Dragline Certification. The contractor shall submit a copy of the certification and performance test in accordance with EM-385-1-1, Chapter 16-5.

(p) Emergency Drills. The Contractor shall conduct its drills in accordance with

EM 385-1-1, Chapter 19-8.b.

(q) Equipment Operator Authorization. The contractor shall submit a list of designated personnel qualified and authorized to operate machinery and mechanized equipment in accordance with EM 385-1-1, Chapter 16-3.

(r) Dive Plan. The contractor shall submit a Dive Plan in accordance with EM

385-1-1, Chapter 30-7.

(s) Radiation. If a production meter that uses nuclear materials is being used aboard the dredge, the contractor shall perform following requirements. The production meter nuclear device system designer and installer shall be qualified in these fields of expertise by the Nuclear Regulatory Commission (NRC). The contractor shall obtain licensing and training as required by the NRC for their personnel aboard the dredge for the use of those components of the production meter containing or are affected by the nuclear source. The contractor shall implement A Nuclear Device Awareness Program as required by the NRC for all personnel aboard the dredge not directly involved in the activities of the nuclear device. The contractor shall submit a Nuclear Device Safety Plan to the Government within 24 hours after receipt of Notice to Proceed by the contractor. While a nuclear device is present aboard the dredge, the contractor shall strictly adhere to all applicable NRC rules and regulations.

(t) Overhead Power Lines. In locations where trucks and other equipment will be passing beneath overhead power lines, the contractor shall install at least 2 signs on either side of the crossings warning drivers of the overhead lines.

The signs shall face both directions…