About this file

This is a Standard Form 30 (SF 30) amendment to a construction solicitation for maintenance dredging work along the Houma Navigation Canal in Terrebonne Bay and Cat Island Pass, Louisiana. The amendment is issued by the U.S. Army Corps of Engineers, New Orleans District, and modifies solicitation W912P826BA014, with an effective date of 09 FEB 2026.

The amendment establishes key deadlines and contract modifications: the question due date is Friday, 13 February 2026 at 11:00 AM local time; bid submission receipt closes Monday, 23 February 2026 at 10:00 AM local time; and bid opening occurs Monday, 23 February 2026 at 11:30 AM local time. Contract modifications include reducing the performance period from 160 calendar days to 90 calendar days, increasing daily liquidated damages from $3,345.00 to $5,930.00, and revising the mobilization and demobilization payment structure to 60% upon completion of mobilization and 40% upon completion of demobilization. The bidding schedule specifies base work consisting of dredging from C/L Station 1410+00 to 1660+00 with two bid tiers (first 747,000 cubic yards and all over 747,000 cubic yards), plus three optional work items covering additional dredging segments and additional mobilization/demobilization costs. The document includes comprehensive specifications addressing governmental safety requirements (Section 01 35 26), resident management system contractor mode requirements (Section 01 45 00.15 10), submittal procedures, general provisions, quality control procedures, environmental protection, surveys, and dredging operations with specific technical requirements for channel dimensions, disposal locations, and cross-sectional data across multiple survey stations.

View the file

Other files

File Type Posted
BID ABSTRACT W912P826BA014.pdf PDF
W912P826BA014 Amendment 0002.pdf PDF
W912P824B0005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 - SF 30 CONTINUATION

The required response date/time of 23 February 2026, 10:00 AM has been added.

SPECIFICATIONS:

COVER SHEET

Page 1/277, 2ndSheet. Delete the “Cover Sheet” in its entirety and substitute the attached revised “Cover Sheet”.

SOLICITATION SHEET

Page 3/277, 4thSheet. Delete the “Solicitation Sheet” in its entirety and substitute the attached revised “Solicitation Sheet”.

MAIN TABLE OF CONTENTS

Page 4/277, MTC-I, 5thSheet. Delete the Main Table of Contents in its entirety and substitute the attached revised “Main Table of Contents” with new Section 01 35 26, Governmental Safety Requirements added.

STANDARD FORM 1442

Page 5/277, Block 11. Delete “160 calendar days” and substitute “90 calendar days”.

SECTION 00010

Page 7 and 8/277. Delete the Bidding Schedule in its entirety and substitute the attached revised Bidding Schedule, page 00010-3 thru 7.

SECTION 00100

Page 15/277, 52.236-27 SITE VISIT (CONSTRUCTION)(b). Delete the site visit POC information and substitute the revised POC as follows:

“Name: William Kiddy, P.E., Lafayette Area Office Address: 100 Asma Blvd, Suite 300, Lafayette, LA 70508 Telephone: 907-342-5602”

SECTION 00700 INSERTS

Page 33/277, paragraph 1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK. In the 1st line of paragraph 1c, delete “160 calendar days” and substitute “90 calendar days”.

Page 33/277, paragraph 2 LIQUIDATED DAMAGES – CONSTRUCTION. In the 3rd line of paragraph 2a, delete “$3,345.00” and substitute “$5,930.00”.

Page 38/277, paragraph 9 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION.

Delete paragraph 9 in its entirety and the revised paragraph 9 as follows:

“9. PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DFARS 252.236-7004 -

1991 DEC)

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for “Mobilization and Demobilization” and “Additional Mobilization and Demobilization – OW 2”, if Optional Work is exercised.

(1) Sixty percent (60%) of the lump sum price upon completion of the Contractor's mobilization at the work site.

(2) The remaining forty percent (40%) upon completion of demobilization.

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a)(1) and (a)(2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of:

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization; and

(iii) The remainder of this item in the final payment under this contract.

(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.

NOTE: Payment for additional mobilization and demobilization in accordance with the above clause will be made at the contract job price for "Additional Mobilization and Demobilization – OW 2, if Optional Work is exercised.””

Page 42/277, 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK. In the 3rd line, delete “160 calendar days” and substitute “90 calendar days”.

Page 42/277, 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION. Change “$3,345.00” to “$5,930.00”.

SECTION 01100

Delete Section 01100 GENERAL PROVISIONS in its entirety and substitute the attached revised Section 01100 GENERAL PROVISIONS.

SECTION 01 33 00

Page 113 and 114/277. Delete the Submittal Register at the end of Section 01 33 00 SUBMITTAL PROCEDURES in its entirety and substitute the attached revised “Submittal Register”.

SECTION 01 35 26

Add the new attached “Section 01 35 26, GOVERNMENTAL SAFETY REQUIREMENTS” in its entirety after Section 01 33 00 SUBMITTAL PROCEDURES.

SECTION 01 45 00.15 10

Delete Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) in its entirety and substitute the attached revised Section 01 45 00.15

10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM).

SECTION 01 57 20.01 12

Page 205/277, paragraph 3.6 REPORTING OF POLLUTION SPILLS. Add the new paragraph “3.7 TRAINING OF CONTRACTOR PERSONNEL” after paragraph 3.6 REPORTING OF POLLUTION SPILLS as follows:

“3.7 TRAINING OF CONTRACTOR PERSONNEL

Train the personnel in environmental protection and pollution control. Conduct environmental protection/pollution control meetings for personnel prior to commencing construction activities. Conduct additional meetings for new personnel and when site conditions change. The contractor shall submit to the Contracting Officer proof of environmental protection training for each on-site employee, a copy of each environmental protection meeting's agenda, and a copy of the minutes for each environmental protection meeting held. Include in the training and meeting agenda:

a. methods of detecting and avoiding pollution

b. familiarization with statutory and contractual pollution standards

c. installation and care of devices, and instruments required for monitoring purposes to ensure adequate and continuous environmental protection/pollution control

d. anticipated hazardous or toxic chemicals or wastes, and other regulated contaminants

e. recognition and protection of archaeological sites, artifacts, wetlands, and endangered species”

SECTION 02 21 10.00 12

Page 214/277, paragraph 1.2 MEASUREMENT AND PAYMENT. Delete this paragraph in its entirety and substitute the revised paragraph “1.2 MEASUREMENT AND PAYMENT” as follows:

“1.2 MEASUREMENT AND PAYMENT

No separate measurement or payment will be made for surveys. The cost of the work shall be included in the applicable contract unit price per cubic yard for "Dredging:

Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00", or "Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00", "Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00", or "Optional Dredging 3: Cat Island Pass" C/L Station 1985+00 to C/L Station 2110+00", if Optional Work is exercised.”

Page 218/277, paragraph 3.1.3 Preliminary Field Survey. Delete this paragraph in its entirety and substitute the revised paragraph “3.1.3 Preliminary Field Survey” as follows:

“3.1.3 Preliminary Field Survey

Prior to taking any original cross-sections, the Contractor shall run an electronically controlled preliminary field survey locating the four (4) range lights in Terrebonne Bay, and all towers, buoys, and channel markers within the limits of the work. In addition, controlled cross sections of the channel shall be taken as specified below and in paragraph "Before and After Dredging Cross Sections".

Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00; and Cross sections shall be taken every 2000 feet along the Terrebonne Bay channel centerline and extend 300 feet each side of the channel centerline and, Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00, if exercised

Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00, if exercised or

Optional Dredging 3: Cat Island Pass C/L Station 1985+00 to C/L Station 2110+00, if exercised, and Cross sections shall be taken every 1000 feet along the Cat Island Pass channel centerline and extend 500 feet each side of the channel centerline.

The data from this survey shall be plotted on a layout sheet (Track Plotter Chart) and submitted to the Contracting Officer for determination of the final channel alignment.

All data obtained in this survey shall also be furnished in ASCII format. The cross sections shall also be plotted with the theoretical dredging template superimposed upon the cross sections. The Contractor shall not proceed with any dredging work until the Contracting Officer determines the final channel alignment and furnishes this information to the Contractor.”

SECTION 35 20 23.00 12

Page 223/277, paragraph 1.2.1 Quantity Surveys. Delete this paragraph in its entirety and substitute the revised paragraph “1.2.1 Quantity Surveys” as follows:

“1.2.1 Quantity Surveys

A survey of the sites for dredging shall be made in accordance with the provisions of Section 02 21 10.00 12 SURVEYS and all measurements to determine dredging quantities shall be based on the "before and after dredging" cross sections described therein. The soundings and contours shown on the contract drawings are representative of conditions in Terrebonne Bay and Cat Island Pass that existed in December 2025 and do not necessarily represent existing conditions. Survey data reflecting most recent conditions shall be obtained prior to contract award and provided by amendment prior to bid opening. The elevations shown thereon shall be verified or corrected by the "before dredging" surveys. Determinations of quantities to be paid for in the area specified, after having once been made, will not be reopened.”

Page 225/277, paragraph 1.3.2 Dredging. Delete this paragraph in its entirety and substitute the revised paragraph “1.3.2 Dredging” as follows:

“1.3.2 Dredging

Payment for dredging will be made at the applicable contract unit price per cubic yard for "Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00", or "Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00", "Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00", or "Optional Dredging 3: Cat Island Pass" C/L Station 1985+00 to C/L Station 2110+00", if Optional Work is exercised. Price and payment shall constitute full compensation for furnishing all plant, labor, materials, and performing all work required for surveying, including any additional soundings that may be directed, excavation, disposal of materials, furnishing diesel powered crewboats fully operated, furnishing aluminum skiff fully operated, furnishing survey vessel(s) as required in Section 02 21 10.00 12 SURVEYS, pollution control, furnishing and maintaining radio and telephone communications equipment, clearing and removing crab traps from within the canal, if found, and all operations incidental thereto.”

Page 226/277, paragraph 1.5.2 Report Of Operations. Delete subparagraph (2)(a) in its entirety and substitute the revised subparagraph (2)(a) as follows:

“(a) Area Engineer, Lafayette Area Office ATTN: Mr. William Kiddy, CEMVN-CDL 100 Asma Blvd., Suite 300 Lafayette, LA 70508-3858”

Page 229/277, paragraph 3.1.2 Hydraulic Dredging. Delete this paragraph in its entirety and substitute the revised paragraph “3.1.2 Hydraulic Dredging” as follows:

“3.1.2 Hydraulic Dredging

As depicted on the contract bidding schedule, bidding of dredging of channel limits is required and defined below. Hydraulic cutterhead dredging operations shall be performed within the following limits:

Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00 and, Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00, if exercised

Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00, if exercised or

Optional Dredging 3: Cat Island Pass C/L Station 1985+00 to C/L Station 2110+00, if exercised.

Actual dredging limits shall be verified by the before dredging cross sections. Based on the latest survey available at the time of this contract solicitation, hydraulic cutterhead dredging operations shall be performed within the proposed limits of dredging shown on the contract drawings. The Contracting Officer reserves the right to adjust these dredging limits based on channel conditions at the time of dredging.

All work shall be performed as specified herein and as shown on the contract drawings.”

Page 230/277, paragraph 3.1.5 Slides. Delete the last sentence in its entirety and substitute the revised sentence as follows:

“In the event the slide is not due to the fault of the Contractor, payment for removal shall be included in applicable contract unit price per cubic yard for "Dredging:

Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00", or "Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00", "Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00", or "Optional Dredging 3: Cat Island Pass C/L Station 1985+00 to C/L Station 2110+00", if Optional Work is exercised.”

Page 230/277, paragraph 3.1.6 Character of Materials. At the end of this paragraph in NOTE 1, delete the 5th sentence in its entirety and substitute the revised sentence as follows:

“All debris removal costs shall be included in applicable contract unit price per cubic yard for "Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00", or "Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00", "Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00", or "Optional Dredging 3: Cat Island Pass" C/L Station 1985+00 to C/L Station 2110+00", if Optional Work is exercised.”

Page 232/277, paragraph 3.2.2 Required Dimensions. Delete the 1st paragraph in its entirety and substitute the revised paragraph as follows:

“The Contractor shall provide the following dimensions over all utility crossings by whatever approved method the Contractor elects to use. The dimensions are as follows:

Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00: Depth -

19.0 MLLW, Bottom Width 150-feet; and, Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00, if exercised

Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00, if exercised or

Optional Dredging 3: Cat Island Pass C/L Station 1985+00 to C/L Station 2110+00, if exercised, Depth -23.0 MLLW, Bottom Width 300-feet.”

Page 235/277, paragraph 3.3.1.1 Placement of Dredged Material. Delete this paragraph in its entirety and substitute the revised paragraph “3.3.1.1 Placement of Dredged Material” as follows:

“3.3.1.1 Placement of Dredged Material

Material dredged between Houma Navigation Canal - Terrebonne Bay shall be placed at the single point discharge (SPD) locations, each site being no more than 2550-feet to the west of the channel centerline, as shown on the contract drawings:

Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00 and, Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00, if exercised

Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00, if exercised or

Material dredged between Houma Navigation Canal - Cat Island Pass shall be placed at the single point discharge (SPD) locations, each site being no more than 1610-feet to the west of the channel centerline, as shown on the contract drawings.

Optional Dredging 3: Cat Island Pass C/L Station 1985+00 to C/L Station 2110+00, if exercised.”

SECTION 35 20 23.33

Page 249/277, paragraph 1.2 MEASUREMENT AND PAYMENT. Delete this paragraph in its entirety and substitute the revised paragraph “1.2 MEASUREMENT AND PAYMENT” as follows:

“1.2 MEASUREMENT AND PAYMENT

No separate measurement or payment will be made for the installation, operation, and maintenance of the DQM-certified system as specified herein for the duration of the dredging operations. All costs in connection therewith shall be considered a subsidiary obligation of the Contractor and shall be included in the applicable contract unit price per cubic yard for "Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00", or "Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00", "Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00", or "Optional Dredging 3: Cat Island Pass" C/L Station 1985+00 to C/L Station 2110+00", if Optional Work is exercised.”

DRAWINGS:

SHEET IDENTIFICATION Nos. G-03 and C-01 thru C-12. Delete these drawings in their entirety and substitute the attached revised drawings SHEET IDENTIFICATION Nos. G-03 and C-01 thru C-12.

ED 23-032

IFB NO. W912P826BA014

US Army Corps of Engineers New Orleans District

Houma Navigation Canal

Terrebonne Bay and Cat Island Pass, LA Maintenance Dredging #24-2 Terrebonne Parish, Louisiana

Construction Solicitation And Specifications

February 2026

ALL INQUIRIES REGARDING THIS SOLICITATION

SHOULD BE MADE TO THE FOLLOWING:

TAYLOR BRANDON

CONTRACT SPECIALIST

U.S. ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT

E-MAIL: TAYLOR.H.BRANDON@USACE.ARMY.MIL

PHONE: (504) 862-1009

COLLECT CALLS NOT ACCEPTED

NOTE: FOR THE MOST PROMPT REPSONSE, PLEASE SEND ALL QUESTIONS VIA E-MAIL.

DEPARTMENT OF THE ARMY

U.S. ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT

7400 LEAKE AVENUE

NEW ORLEANS, LA 70118-3651

ED 23-032

SOLICITATION: W912P8-26-B-A014 February 2026

FOR: Houma Navigation Canal, Terrebonne Bay and Cat Island Pass, LA, Maintenance Dredging #24-2, Terrebonne Parish, Louisiana ED 23-032

TO OPEN: 23 February 2026

Prospective contractors must register in the System for Award Management (SAM). See FAR Clause 52.204-7 for required information. The website for SAM is https://www.sam.gov. As of April 4, 2022, the Federal Government has stopped using the DUNS Number as a unique identifier for entities and switched to a Unique Entity ID generated by SAM.gov. In addition, entities with DUNS Numbers but no SAM.gov registration have been able to get Unique Entity IDs without registering in SAM.gov since October 2021. NOTE: The DUNS Number is no longer used in SAM.gov, eSRS, FSRS, FPDS, CPARS, or FAPIIS.

BIDDERS MUST PROVIDE FULL, ACCURATE AND COMPLETE INFORMATION AS REQUIRED BY THIS

SOLICITATION AND ITS ATTACHMENTS. THE PENALTY FOR MAKING FALSE STATEMENTS IN BIDS

IS PRESCRIBED IN 18 U.S.C. 1001. (FAR 52.214-4 APR 1984)

DESCRIPTION AND MAGNITUDE OF WORK: The work consists of satisfactory removal and disposal of shoal material from within the Houma Navigation Canal channel limits as shown on the contract drawings, with disposal of dredged material into single point discharge locations delineated adjacent to the channel. No dike work is included with this project.

CAUTION TO BIDDERS: In delivery of hand-carried bids, bidders are cautioned to allow sufficient time for delays which may be encountered as a result of frequent trains which are subject to block all access roads to place of bid opening for various lengths of time and for visitor background checks by MVN security when entering the installation at place of bid opening. Such delays DO NOT permit acceptance or consideration of late bids.

NOTE: ALL WORK UNDER THESE SPECIFICATIONS SHALL BE PERFORMED IN ACCORDANCE WITH

THE PROVISIONS OF EM 385-1-1 "CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS

MANUAL", DATED 15 MARCH 2024.

ATTENTION: Contractors must complete, and submit with their bid, the provisions located in Section 00600. A bidder may also submit, in lieu of the completed Section 00600, a complete copy of their Online Representations and Certifications from SAM.gov with an expiration date on or after the date of award.

https://www.sam.gov/

Houma Navigation Canal Terrebonne Bay and Cat Island Pass, LA

Maintenance Dredging #24-2 Terrebonne Parish, Louisiana

MTC-1 ED 23-032

MAIN TABLE OF CONTENTS

Division 00 – PROCUREMENT AND CONTRACT REQUIREMENTS

Solicitation, Offer and Award

SF-1442

00010 Bidding Schedule 00100 Instructions to Bidders 00600 Representations and Certifications 00700 Contract Clauses

Division 01 - GENERAL REQUIREMENTS

01100 General Provisions 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 42 00 Sources for Reference Publications 01 45 00.15 10 Resident Management System Contractor Mode (RMS CM) 01 45 04.00 10 Contractor Quality Control 01 57 20.01 12 Environmental Protection – Dredging 01 78 03.00 10 Closeout Submittals – Dredging

Division 02 – EXISTING CONDITIONS

02 21 10.00 12 Surveys

Division 35 – WATERWAY AND MARINE CONSTRUCTION

35 20 23.00 12 Dredging 35 20 23.33 National Dredging Quality Management Program

Pipeline Hydraulic Dredge

SECTION 00010 – BIDDING SCHEDULE

Houma Navigation Canal Terrebonne Bay and Cat Island Pass, LA

Maintenance Dredging #24-2 Terrebonne Parish, LA

* Denote changes from previous Bidding Schedule.

Item Description Estimated Quantity Unit Unit Price Estimated

Amount Base Work

0001 Mobilization and Demobilization 1 Job

*0002 Dredging: Terrebonne Bay C/L Station 1410+00 to C/L Station 1660+00

*0002AA First 747,000 CY 747,000 CY

*0002AB All Over 747,000 CY 130,000 CY

TOTAL BASE WORK: $

OPTIONAL WORK 1 (OW 1)

*0003 Optional Dredging 1: Terrebonne Bay C/L Station 1660+00 to C/L Station 1844+00

*0003AA First 366,000 CY 366,000 CY

*0003AB All Over 366,000 CY 64,000 CY

TOTAL OPTIONAL WORK 1: $

OPTIONAL WORK 2 (OW 2)

*0004 Additional Mobilization and Demobilization - OW 2 1 Job

*0005 Optional Dredging 2: Terrebonne Bay C/L Station 1375+00 to C/L Station 1410+00

*0005AA First 44,000 CY 44,000 CY

*0005AB All Over 44,000 CY 6,000 CY

TOTAL OPTIONAL WORK 2: $

OPTIONAL WORK 3 (OW 3)

*0006 Optional Dredging 3: Cat Island Pass C/L Station 1985+00 to C/L Station 2110+00

*0006AA First 299,000 CY 299,000 CY

*0006AB All Over 299,000 CY 51,000 CY

TOTAL OPTIONAL WORK 3: $

TOTAL BASE WORK + OW 1 + OW 2 + OW 3: $

00010-5 ED 23-032

Award will be made as a whole to one bidder.

NOTE 1: The unit “Job” as used in this Bidding Schedule is synonymous with the term “Lump Sum” used elsewhere within these plans and specifications.

NOTE 2: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE

AND THE EXTENDED TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID

SHALL BE DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR

AWARD.

NOTE 3: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or subline items are materially unbalanced (See FAR 14.404-2, Rejection of Individual Bids).

NOTE 4: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442 after Notice of Award. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within 24 hours after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract have been conducted.

*NOTE 5: OPTIONAL WORK ITEMS. The Government may require the delivery of, in whole or part, the Optional Work Items. The Government may exercise the Optional Work Items by written notice to the Contractor. If the Government activates an Optional Work Item, the activation will occur 30 calendar days prior to completion of the Base Work.

*NOTE 6: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

*NOTE 7: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF OPTIONAL

WORK. In the event that the Optional Work items are exercised under the terms of the contract, the time required for completion of the contract shall be as stipulated below for each Optional Work Item, in addition to the original contract duration of 90 calendar days established for the Base Work Items specified in Section 00700 CONTRACT CLAUSES paragraph entitled "COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK".

00010-6 ED 23-032

OW 1: 30 calendar days OW 2: 15 calendar days OW 3: 30 calendar days

NOTE 8: RAPID VENDOR PAYMENT: Web-based instructions for the submission of invoices may be found at the following website:

http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment

00010-7 ED 23-032

*EVALUATION OF SUBLINE ITEMS (Dec 2019 - AFARS 5152.211-9000).

Item Nos. 0002, 0003, 0005, and 0006 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its subline items.

(End of Clause)

*VARIATIONS IN ESTIMATED QUANTITIES - SUBLINE ITEMS (Dec 2019 - AFARS 5152.211- 9001).

This variation in estimated quantities clause is applicable only to item Nos. 0002, 0003, 0005, and 0006.

(a) Variation from the estimated quantity in the actual work performed under any second or subsequent subline item or elimination of all work under such a second or subsequent subline item will not be the basis for an adjustment in contract unit price.

(b) Where the actual quantity of work performed for item Nos. 0002, 0003, 0005, and 0006 is less than 85% of the quantity of the first subline item listed under such item, the contractor will be paid at the contract unit price for that subline item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause at Federal Acquisition Regulation (FAR) 52.211-18, VARIATION IN ESTIMATED QUANTITY.

(c) If the actual quantity of work performed under item Nos. 0002, 0003, 0005, and 0006 exceeds 115% or is less than 85% of the total estimated quantity of the subline item under that item and/or if the quantity of the work performed under the second subline item or any subsequent subline item under item Nos. 0002, 0003, 0005, and 0006 exceeds 115% or is less than 85% of the estimated quantity of any such subline item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, VARIATION IN ESTIMATED QUANTITY.

(End of Clause)

SOLICITATION NUMBER: W912P826BA014

NOTE: BIDDERS MAY SUBMIT BIDS BY ONLY ONE METHOD: A) ELECTRONIC

COMMERCE (EMAIL) OR BY 2) PHYSICAL SUBMISSION. BIDDERS SHALL LIMIT THE BID

SUBMITTAL TO ONE OPTION OR THE OTHER, NOT BOTH.

Electronic Submission of Bids/Proposals (Email):

The New Orleans District utilizes electronic commerce (Email) for receipt of electronic bids under this IFB solicitation. To submit an electronic commerce (Email) bid please follow these steps:

1. Send an email containing your name, email address and bid/proposal to the following emails associated with the IFB (MUST include all emails):

• TAYLOR.H.BRANDON@USACE.ARMY.MIL

• KAREN.D.HARGRAVE@USACE.ARMY.MIL

2. ALL BIDS SUBMITTED BY EMAIL MUST CONTAIN THE SOLICITATION NUMBER IN

THE SUBJECT LINE.

3. Once the agency receives your bid/proposal at the above email addresses, you will then receive a confirmation email stating your bid/proposal was received. If a bidder does not receive a reply acknowledging receipt electronically from the New Orleans District, it is incumbent upon the bidder to seek confirmation from the issuing Contracting office by phone.

Note: The size limit for incoming emails is 35MB. Any bid/proposal over this size may not be accepted by the server and will constitute the bid not being received timely. Please note that embedded links, URLs, and other html language included may interfere with the USACE server security, which may cause emails to be removed prior to being received by the contracting office. Bidders are advised to refrain from including external links, embedded links, URLs, and other html language not germane to the proposal/bid. Please note it is a bidder’s responsibility, when transmitting its bid electronically, to ensure the receipt of its bid to the proper designee at the proper time. See FAR 14.304(b)(1)(i) regarding untimely electronic bids. Please note, MVN’s computer system firewall may cause a delay in receipt of emails, so be sure to allow ample time for possible delay. If your email would exceed 35MB you can use one of the following methods as a work-around:

• Use .zip files as attachments. Combine multiple files into a .zip file to compress file size prior to adding as an email attachment.

• Send multiple emails. Label each email with same subject line and indicate number of emails. For example: Smith Construction W912P826BAXXX (1 of 2) Smith Construction W912P826BAXXX (2 of 2).

mailto:KAREN.D.HARGRAVE@USACE.ARMY.MIL

Physical Submission of Bids:

Bidders may submit their bids by hand carrying or express mail to the New Orleans District Contracting Office in Room 172. Bidders are advised to allow adequate time to ensure timely submission of its bid. Traffic onto the New Orleans District campus may be delayed by trains blocking the entrance or security either at the gate and/or inside of the building. Express delivery may be utilized but it is incumbent upon the bidder to ensure bid delivery time and date is before the receipt of bid cutoff time. See FAR 14.304(b)(1)(ii) and (c).

Bid Opening:

This bid opening is currently scheduled for Monday, 23 February 2026. And 11:30 AM, local time. The Contracting Officer and Contract Specialist will begin downloading bids at 10:00 AM, local time, with is the bid submission receipt cutoff time. All bids received after 10:00 AM, local time, on Monday, 23 February 2026 will be considered late.

Audio Teleconference Bid Opening Information:

The bid opening will be held electronically and can be accessed via:

Microsoft Teams https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_e638699daece4f6b925a99a9d5b0b554%40thread.v2/0?context=% 7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7- 8f3163d27582%22%2c%22Oid%22%3a%22df68d226-f594-4b15-a055-0aa9ffa0c19c%22%7d

Meeting ID: 993 414 863 659 Passcode: UR9xh9JG

Dial in by phone +1 601-262-2433,,739831023# United States, Vicksburg Find a local number Phone conference ID: 739 831 023#

Following the conclusion of the bid opening, in accordance with FAR 14.403(b), abstracts of offers for unclassified acquisitions shall be available for public inspection via SAM.GOV.

https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_e638699daece4f6b925a99a9d5b0b554%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22df68d226-f594-4b15-a055-0aa9ffa0c19c%22%7d https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_e638699daece4f6b925a99a9d5b0b554%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22df68d226-f594-4b15-a055-0aa9ffa0c19c%22%7d https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_e638699daece4f6b925a99a9d5b0b554%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22df68d226-f594-4b15-a055-0aa9ffa0c19c%22%7d https://dod.teams.microsoft.us/l/meetup-join/19%3adod%3ameeting_e638699daece4f6b925a99a9d5b0b554%40thread.v2/0?context=%7b%22Tid%22%3a%22fc4d76ba-f17c-4c50-b9a7-8f3163d27582%22%2c%22Oid%22%3a%22df68d226-f594-4b15-a055-0aa9ffa0c19c%22%7d tel:+16012622433,,739831023 https://dialin.cpc.dod.teams.microsoft.us/71aa306f-43b1-41da-a46c-76ada22fc845?id=739831023

The following clauses were added:

52.204-8 Annual Representations and Certifications (Mar 2025) (DEVIATION 2025-O0003 and 2025-O0004)

52.217-5 Evaluation of Options (Jul 1990)

52.217-7 Option for Increased Quantity-Separately Priced Line (Mar 1989) Item

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule.

The Contracting Officer may exercise the option by written notice to the Contractor within 30 days prior to completion of the base work. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of clause)

52.244-6 Subcontracts for Commercial Products (Feb 2025) and Commercial Services (Deviation 2025-O0003)

The following clauses were deleted:

52.204-8 Annual Representations and Certifications (Mar 2023)

52.213-4 Terms and Conditions—Simplified Acqusitions (Dec 2023) (Other Than Commercial Products and Commercial Services)

52.222-21 Prohibition of Segregated Facilities. (Apr 2015)

52.222-23 Notice of Requirement for Affirmative Action (Feb 1999) To Ensure Equal Employment Opportunity for Construction

52.222-26 Equal Opportunity (Sep 2016)

52.222-27 Affirmative Action Compliance Requirements (Apr 2015) for Construction.

52.223-19 Compliance with Environmental Management (May 2011) Systems.

52.244-6 Subcontracts for Commercial Products (Dec 2023) and Commercial Services

The following clauses were modified:

52.233-2 SERVICE OF PROTEST (SEP 2006)

hereby reads as follows:

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Karen D. Hargrave, Contracting Officer, U.S. Army Corps of Engineers, ATTN: CEMVN CTW, 7400 Leake Avenue, New Orleans, LA 70118-3651.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

01100-a ED 23-032

Section Table of Contents

SECTION 01100 - GENERAL PROVISIONS

1. ........DAMAGE TO WORK

2. ........SAFETY PROVISIONS

3. ........SIGNAL LIGHTS

4. ........CONTINUITY OF WORK

5. ........INSPECTION

6. ........SHOALING

7 .........ACCOMMODATIONS AND MEALS FOR INSPECTORS

8. ........SEAWORTHINESS CERTIFICATION

9. ........ENVIRONMENTAL LITIGATION

10. ......STATE TAXES

11. ......EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

12. ......FUEL CONSUMPTION REPORTING REQUIREMENTS

13. ......RIGHTS-OF-WAY

14. ......CONTRACT COORDINATION

15. ......CONTRACTOR’S RESPONSIBILITY

16. ......MOBILIZATION OF ATTENDANT PLANT

17. ......ACCESS PLAN

18. ......SUPERVISION

19. ......PRE-BID SITE VISIT

20. ......WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS

21. ......CONTRACTOR PERFORMANCE EVALUTIONS – CONSTRUCTION

22. ......SECURITY REQUIREMENTS

23. ......REGULATORY REQUIREMENTS

24. ......SEAGOING BARGE ACT

25. ......DATUM RELATIONSHIPS

01100-1 ED 23-032

SECTION 01100 - GENERAL PROVISIONS

1. DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in the Clause in Section 00700 CONTRACT CLAUSES, entitled PERMITS AND RESPONSIBILITIES (FAR 52.236-7). However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit price or Job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there is no contract unit or Job prices applicable to any part of such work, an equitable adjustment shall be made pursuant to the Clause in Section 00700 CONTRACT CLAUSES, entitled CHANGES (FAR 52.243-4). Except as herein provided; damage to all work (including temporary construction), utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

2. SAFETY PROVISIONS

The safety provisions as specified herein refer to the USACE Safety and Occupational Health Requirements EM 385-1-1 dated 15 March 2024. The most current edition can be found at:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1- 1%20_EFFECTIVE%2015March2024.pdf

(a) Accident Investigation and Reporting. The reporting and associated investigation of accidents and near misses is considered a leading indicator.

Utilize ENG Form 3394, U.S. Army Corps of Engineers Mishap Notification and Investigation, to report accidents and near misses. Link to ENG Form 3394:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/ Eng_Form_3394_2021Aug.pdf.

Contractors must investigate, analyze, and report all accidents and near misses occurring incidentally to an operation, project, or facility according to EM 385-1-1, Table 2-1 Accident Reporting Required Timeline.

(b) Accident Prevention Plan (APP). (See the Contract Clause in Section 00700, entitled ACCIDENT PREVENTION (FAR 52.236-13).) Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the prework https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf https://www.publications.usace.army.mil/Portals/76/Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf

01100-2 ED 23-032

conference, an electronic copy and one hard copy of the Accident Prevention Plan (APP) Worksheet (ENG FORM 6293) shall be submitted to the Contracting Officer for review and acceptance. Link to ENG form 6293 (APP):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_Aug%2020 24%20-%20FINAL.pdf

(c) The Plan shall be prepared in the following format:

(1) Activity Hazard Analysis (AHA) Requirements. The Contractor shall complete the Activity Hazard Analysis (AHA) Requirements on ENG form 6206 in accordance with EM 385-1-1, Chapter 2-6. Specific AHA requirements are identified in paragraph 6 of each chapter of EM 385-1-1.

Link to fillable ENG form 6206 (AHA form):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_202 3Aug24.pdf

(2) The Contractor shall submit ENG Form 6282 (Site Safety and Health Officer Designation Letter). A Designation Letter is required for all levels of onsite SSHOs. The Contractor shall maintain a copy of the accepted form at the site of work. Link to ENG form 6282:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_202 3Aug28.pdf?ver=_1GgPT1ZS1AFX9P8AKU5og%3d%3d.

(3) Site Safety and Health Officer (SSHO). The Contractor must employ a minimum of one (1) Level 1 Full-time Site Safety and Health Officer to function as the primary Level 1 SSHO responsible for ensuring all site personnel are implementing Safety and Occupational Health requirements according to the contract, EM 385-1-1, applicable federal, state, and local requirements. A designated Level 1 SSHO must be at the site of work whenever work is performed. The SSHO shall meet the training and experience requirements of EM 385-1-1, Chapter 2-3.b. Level 1 SSHOs are not permitted to supervise non-safety personnel at the site of work.

(4) A copy of company policy statement regarding accident prevention.

(5) When marine plant and equipment are in use under a contract, the method of fuel oil transfer shall be included on MVN Form 385-10 (Latest Edition), Fuel Oil Transfer (attached at the end of this section), (Refer to

33 CFR 156).

(d) Commencement of Work. The Contractor shall not commence physical work at the site until the Contracting Officer, or his/her authorized representative has accepted the Accident Prevention Plan. The Contractor may submit its Accident https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_Aug%202024%20-%20FINAL.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_Aug%202024%20-%20FINAL.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf?ver=_1GgPT1ZS1AFX9P8AKU5og%3d%3d https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf?ver=_1GgPT1ZS1AFX9P8AKU5og%3d%3d

01100-3 ED 23-032

Prevention Plan only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase. Also refer to EM 385-1-1, Chapter 2.

(e) Hazard Communication (HazCom) Program. The Contractor shall develop, implement, and maintain at the workplace a written, Hazard Communication Program (see EM 385-1-1, Chapter 6-7) that includes identification of potential hazards as prescribed in 29 CFR Part 1910.1200 and/or 1926.59, effects of exposure and control measures to be used for chemical products and physical agents that may be encountered during the performance of work on this contract, provisions for container labeling, Safety Data Sheets, and employee training program, and other criteria in accordance with 29 CFR Part 1910.1200 and/or

1926.59. Training shall include communication methods and systems to be used (i.e., voice, hand signals, radios, or other means), and training in the use and understanding of safety data sheets and chemical product hazard warning labels.

Prior to bringing hazardous substances, as defined in 29 CFR 1910.1200 and/or 1926.59, onto the job site, a copy of the Hazard Communication Program and the Safety Data Sheets of each substance shall be submitted to the Contracting Officer and made available to the contractor's employees as part of its Accident Prevention Plan. A site map shall be attached to the inventory showing where the inventoried hazardous substances are stored. The inventory list and site map shall be updated monthly to assure accuracy.

(f) Daily Inspections. The Contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the jobsite in accordance with Section 01 45

04.00 10, "CONTRACTOR QUALITY CONTROL". The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

(1) Phase(s) of construction underway during the inspection.

(2) Locations of areas where inspections were made.

(3) Results of inspections, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

(g) Safety Sign. The Contractor shall furnish, erect, and maintain a safety sign at the site where indicated by the Contracting Officer. The sign shall conform to the requirements of this paragraph and the drawing included at the end of these General Provisions. The lettering shall be black, the castle red, green safety circle and cross, and the background white. Upon request, the Government will furnish two (2) decals of the engineer castle. When placed on a floating plant, the sign may be half size. The sign shall be erected as soon as practicable, but

01100-4 ED 23-032

not later than 15 calendar days after the date established for commencement of work. The data required shall be current. . The sign coordinator is Timothy Lacoste@ 504.862.2663. No separate payment will be made for construction and erection of the safety sign and all costs in connection therewith will be considered an incidental obligation of the Contractor.

(h) Ground Fault Protection Equipment. Electrical equipment used on this contract shall be equipped with ground fault circuit interrupters in accordance with EM 385-1-1, Chapter 11-8.

(i) Means of Escape for Personnel Quartered or Working on Floating Plant. Two

(2) means of escape shall be provided for assembly, sleeping, and messing areas on floating plants. For areas involving 10 or more persons, both means of egress shall be through standard size doors opening to different exit routes.

Where nine (9) or fewer persons are involved, one (1) of the means of escape may be a window (minimum dimensions 24 inches by 36 inches) which leads to a different exit route. Refer to EM 385-1-1, Chapter 19-8.h.

(j) Emergency Alarms and Signals.

(1) Alarms. Emergency alarms shall be installed and maintained on all floating plant requiring a crew where it is possible for either a passenger or crewman to be out of sight or hearing from any other person. The alarm system shall be operated from the primary electrical system with standby batteries on trickle charge that will automatically furnish the required energy during an electrical-system failure. A sufficient number of signaling devices shall be placed on each deck so that the sound can be heard distinctly at any point above the usual background noise. All signaling devices shall be so interconnected that actuation can occur from at least one (1) strategic point on each deck.

(2) Signals.

(a) Fire Alarm Signals. The general fire alarm signal shall be in accordance with paragraph 46 CFR Ch. I; Subpart E.109.503 of the Coast Guard Rules and Regulations for Cargo and Miscellaneous Vessels, Sub-Chapter I & Ia.

(b) Abandon Ship Signals. The signal for abandon ship shall be in accordance with paragraph 109.503(b) of the reference cited in subparagraph (2)(a) above.

(c) Man-Overboard Signal. Hail and pass the word to the bridge.

All personnel and vessels capable of rendering assistance shall respond.

01100-5 ED 23-032

(k) Hurricane Plan. A detailed plan for protection and evacuation of personnel and plant in the event of an impending hurricane or storm is required as an enclosure to the Contractor's Accident Prevention Plan. This plan shall be submitted to the Contracting Officer, or his/her representative, for review and approval prior to the preconstruction conference. Work being performed to satisfy the Hurricane Plan will not be measured for payment. Payment for all work associated with the Hurricane Plan, and providing the equipment required for the duration specified, shall be distributed amongst the existing bid items.

The plan shall include at least the following:

(1) The time each phase of the plan will be put in effect. The time shall be the number of hours remaining for the storm to reach the worksite if it continues at the predicted speed and direction.

(2) The estimated time necessary to secure and evacuate the site including any emergency flood protection.

(3) The safe harbor for personnel and plant specifically identified.

(4) The name of the boat(s) which will be used to move the plant, its type, capacity, speed, and availability. If the boat to be used has not yet been identified, the Contractor shall indicate (a) if the vessel will come from his own…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .