Bid Abstract W912P824B0051_revised 16SEP24.pdf
PDF 684 KB Posted
- Solicitation number
- W912P824B0051
About this file
This document is a Bid Abstract for a federal contract opportunity related to maintenance dredging of the Calcasieu River and Pass in Louisiana. The solicitation number is W912P824B0051, and the project is for dredging from Mile 5.0 to Mile 17.0 in Calcasieu and Cameron Parishes.
The government estimate for the work is $37,591,545.00. Five bidders submitted offers, with the lowest responsive bid being $16,496,280.00 from Inland Dredging Company, LLC. The work includes mobilization/demobilization, aerial photography, dredging, and construction of several confined disposal facilities (CDFs). Optional work items include additional dredging at Devil's Elbow and ditching/draining of several CDFs. The solicitation was issued as an Invitation for Bid (IFB) on an unrestricted basis with a NAICS code of 237990 and an estimated magnitude between $25-100 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract W912P824B0051.pdf | ||
| W912P824B0051 Amd 0005.pdf | ||
| W912P824B0051 Amd 0004.pdf | ||
| W912P824B0051 Amd 0003.pdf | ||
| W912P824B0051 Amd 0002.pdf | ||
| W912P824B0051 Amd 0001.pdf | ||
| W912P824B0051 Pkg.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Mike Hooks, LLC $19,645,854.00 409 Mike Hooks Road Westlake, LA 70669
2. Inland Dredging Company, LLC 16,496,280.00$ 103 King Avenue Dyerburg, TN 38024
3. Orion Marine Consruction, Inc. 31,934,303.00$ 1715 N West Shore Blvd, Suite 875 Tampa, FL 33607
4. Crosby Dredging, LLC 39,609,584.00$ 17771 Highway 3235 Galliano, LA
5. Weeks Marine, Inc. 45,215,005.00$ 304 Gille Drive Covington, LA 70433
IGE Amount: 37,591,545.00$
Calcasieu River and Pass, LA, Maintenance Dredging FY24, Mile 5.0 to Mile 17.0, Calcasieu and Cameron Parishes, LA
Solicitation Number: W912P8-24-B-0051
2. DATE ISSUED 3. DATE OPENED
15-Jul-24 06-Sep-24
SAM: Active Small: No SAM: Active Small: No SAM: Active Small: No
7A. ITEM 7C. EST. D. UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
Column1 Column2 Column3 Column4 Column5 Column6 Column7 Column8 Column9 Column10 Column131000 Column141001 0001 Mobilization and Demobilization 1 JOB $ 2,606,000.00 $ 2,606,000.00 $ 2,310,000.00 $ 2,310,000.00 3,100,000.00$ $ 3,100,000.00 2,770,000.00$ $ 2,770,000.00 0002 Aerial Photographic Documentation 1 JOB $ 5,245.00 $ 5,245.00 $ 1,000.00 $ 1,000.00 60,000.00$ $ 60,000.00 35,000.00$ $ 35,000.00 0003 Dredging - Mile 9.0 to Mile 17.0
*0003AA First 1,125,000 CY 1,125,000 CY $ 9.09 $ 10,226,250.00 $ 5.50 $ 6,187,500.00 4.00$ $ 4,500,000.00 10.00$ $ 11,250,000.00 *0003AB All Over 1,125,000 CY 375,000 CY $ 6.75 $ 2,531,250.00 $ 5.50 $ 2,062,500.00 1.50$ $ 562,500.00 6.00$ $ 2,250,000.00
0004 Dike Construction - CDF 13 1 JOB $ - $ - $ 460,000.00 $ 460,000.00 1.00$ $ 1.00 740,000.00$ $ 740,000.00 0005 Dike Construction - CDF 15 1 JOB $ - $ - $ 1.00 $ 1.00 1.00$ $ 1.00 1.00$ $ 1.00 0006 Dike Construction - CDF 17 1 JOB $ 722,000.00 $ 722,000.00 $ 325,000.00 $ 325,000.00 1.00$ $ 1.00 550,000.00$ $ 550,000.00 0007 Dike Construction – CDF 22 1 JOB $ 720,000.00 $ 720,000.00 $ 370,000.00 $ 370,000.00 841,818.00$ $ 841,818.00 550,000.00$ $ 550,000.00 0008 Dike Construction - CDF E 1 JOB $ 1,177,500.00 $ 1,177,500.00 $ 560,000.00 $ 560,000.00 1,077,035.00$ $ 1,077,035.00 600,000.00$ $ 600,000.00 0009 Dike Construction - CDF H 1 JOB $ 1,072,000.00 $ 1,072,000.00 $ 250,000.00 $ 250,000.00 736,221.00$ $ 736,221.00 350,000.00$ $ 350,000.00 0010 Dike Construction - CDF M 1 JOB $ - $ - $ 1.00 $ 1.00 1.00$ $ 1.00 600,000.00$ $ 600,000.00
TOTAL BASE WORK: $ 19,060,245.00 $ 12,526,002.00 $ 10,877,578.00 $ 19,695,001.00
OPTIONAL WORK (OW) 1
0011 Dredging - Devil's Elbow – OW 1 *0011AA First 200,000 CY 200,000 CY $ 15.68 $ 3,136,000.00 $ 5.60 $ 1,120,000.00 5.10$ $ 1,020,000.00 9.00$ $ 1,800,000.00 *0011AB All Over 200,000 CY 150,000 CY $ 7.19 $ 1,078,500.00 $ 5.60 $ 840,000.00 3.50$ $ 525,000.00 4.50$ $ 675,000.00
0012 Dike Construction Devil’s Elbow - OW 1 1 JOB $ 1,419,000.00 $ 1,419,000.00 $ 1.00 $ 1.00 470,435.00$ $ 470,435.00 1.00$ $ 1.00 *Total OW 1 $ 5,633,500.00 $ 1,960,001.00 $ 2,015,435.00 $ 2,475,001.00
OPTIONAL WORK (OW) 2
0013 Dredging – Mile 5.0 to Mile 9.0 – OW 2 400,000 CY $ 11.27 $ 4,508,000.00 $ 6.00 $ 2,400,000.00 4.00$ $ 1,600,000.00 12.50$ $ 5,000,000.00 0014 Additional Dike Construction – OW 2 1 JOB $ 1,081,000.00 $ 1,081,000.00 $ 1.00 $ 1.00 1.00$ $ 1.00 1.00$ $ 1.00
*Total OW 2 $ 5,589,000.00 $ 2,400,001.00 $ 1,600,001.00 $ 5,000,001.00
OPTIONAL WORK (OW) 3
0015 Additional Mobilization and Demobilization – OW 3 1 JOB $ 77,000.00 $ 77,000.00 $ 75,000.00 $ 75,000.00 36,000.00$ $ 36,000.00 250,000.00$ $ 250,000.00 0016 Ditching/Draining CDF 1 – OW 3 1 JOB $ 272,000.00 $ 272,000.00 $ 134,140.00 $ 134,140.00 154,179.00$ $ 154,179.00 162,380.00$ $ 162,380.00 0017 Ditching/Draining CDF 3 – OW 3 1 JOB $ 478,000.00 $ 478,000.00 $ 235,600.00 $ 235,600.00 120,141.00$ $ 120,141.00 310,000.00$ $ 310,000.00 0018 Ditching/Draining CDF 8 – OW 3 1 JOB $ 1,044,000.00 $ 1,044,000.00 $ 389,500.00 $ 389,500.00 242,110.00$ $ 242,110.00 656,000.00$ $ 656,000.00 0019 Ditching/Draining CDF 11 – OW 3 1 JOB $ 427,000.00 $ 427,000.00 $ 278,160.00 $ 278,160.00 230,164.00$ $ 230,164.00 292,800.00$ $ 292,800.00 0020 Ditching/Draining CDF 12B – OW 3 1 JOB $ 1,583,000.00 $ 1,583,000.00 $ 463,980.00 $ 463,980.00 249,931.00$ $ 249,931.00 976,800.00$ $ 976,800.00 0021 Ditching/Draining CDF 13 – OW 3 1 JOB $ 1,468,000.00 $ 1,468,000.00 $ 547,580.00 $ 547,580.00 277,517.00$ $ 277,517.00 922,240.00$ $ 922,240.00 0022 Ditching/Draining CDF 17 – OW 3 1 JOB $ 521,000.00 $ 521,000.00 $ 339,530.00 $ 339,530.00 280,446.00$ $ 280,446.00 357,400.00$ $ 357,400.00 0023 Ditching/Draining CDF 22 – OW 3 1 JOB $ 1,078,000.00 $ 1,078,000.00 $ 255,360.00 $ 255,360.00 310,278.00$ $ 310,278.00 631,680.00$ $ 631,680.00
*Total OW 3 $ 6,948,000.00 $ 2,718,850.00 $ 1,900,766.00 $ 4,559,300.00
OPTIONAL WORK (OW) 4
*0024 Bird Nesting Prevention and Avoidance Measures – OW 4 205 DAY $ 1,760.00 $ 360,800.00 $ 200.00 $ 41,000.00 500.00$ $ 102,500.00 1,000.00$ $ 205,000.00 *Total OW 4 $ 360,800.00 $ 41,000.00 $ 102,500.00 $ 205,000.00
$37,591,545.00 $19,645,854.00 $16,496,280.00 $31,934,303.00
Note: Only the top 3 bidders meeting the requirements of the solicitation are shown on the abstract.
NO. 05
Orion Marine Construction, Inc.
Ack. Amendments: Yes
B. BID SECURITY: 20% or $3M
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE
B. BID SECURITY: 20% B. BID SECURITY: 20% or $3M
Mike Hooks, LLC
Ack. Amendments: Yes
Inland Dredging Company, LLC
Ack. Amendments: Yes
9. OFFERS
(Without Profit)
TOTAL:
Calcasieu River and Pass, LA, Maintenance Dredging FY24, Mile 5.0 to Mile 17.0, Calcasieu and Cameron Parishes, LA
7B. DESCRIPTION OF OFFERED ITEM
6. NUMBER OF AMENDMENTS ISSUED
(Check A, B or C and complete D, E, and F)
US ARMY ENGINEER DISTRICT, NOD
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
7400 Leake Avenue New Orleans, LA 70118
A. HIRED LABOR
NO. 01 NO. 02
ABSTRACT OF OFFERS 1. SOLICITATION NUMBER W912P824B0051
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
C. REASONABLE CONTRACT
(Including Profit)
B. REASONABLE CONTRACT
4. ISSUING OFFICE
Taylor Brandon, Contract Specialist
Christopher Nuccio, Contracting Officer
| abstract cover page |
| abstract |
| 2024-09-16T09:59:06-0500 | |
| NUCCIO.CHRISTOPHER.1296631457 |