Amendment 0002_W912P824B0047_(SAM).pdf
PDF 803 KB Posted
- Attached to
- Morganza to the Gulf of Mexico, Louisiana Reach A Phase 1 Levee Construction (ED 22-042)
- Solicitation number
- W912P824B0047
About this file
This document is an amendment to a solicitation for the Morganza to the Gulf of Mexico, Louisiana Reach A Phase 1 Levee Construction (ED 22-042) contract. The amendment provides responses to bidder questions submitted prior to the established deadline, limited to the government responses provided in the previous amendment. No further questions will be addressed at this time. The bid submission deadline of June 24, 2024 at 11:00 AM local time, as well as the virtual bid opening date and time of June 24, 2024 at 1:00 PM local time, remain unchanged. Bidders are required to acknowledge receipt of this amendment and submit it with their bid.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The subject solicitation for Mississippi River and Tributaries, Morganza to the Gulf of Mexico, Louisiana, Reach A, Phase 1 Levee Construction, Terrebonne Parish, Louisiana (ED 22-042) is hereby amended as follow s:
1) Provide responses to bidder(s) questions submitted prior to the established deadline and limited to the Government responses provided in Amendment 0001 only.
It is anticipated that this w ill be the last amendment for this requirement. No further questions w ill be addressed at this time. The bid submission deadline of 24 Jun 2024, 11:00AM, local time, as w ell as the virtual bid opening date and time of 24 Jun 2024, 1:00PM, local time, remains unchanged.
***PLEASE ACKNOWLEDGE THIS AMENDMENT AND SUBMIT WITH YOUR BID***
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Jun-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P824B0047
X 9B. DATED (SEE ITEM 11)
24-May-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Jun-2024
CODE
CONTRACTING DIV- CHIEF
7400 LEAKE AVENUE, ROOM 172
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P824B0047
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AM 0002
Bidders Questions and Government Responses
Question: Section 31 24 00.00 12, Paragraph 3.1.2, Drainage, states that “The foundation receiving fill and all partially completed fill shall be kept thoroughly drained by constructing and maintaining necessary retaining dikes; dewatering operations necessary for foundation preparation as accomplished by ditching, sump pumping, or other approved methods.”
Paragraph 3.2.1, Compacted Fill, states that “Embankment material may be placed in water until it is 1-foot above water surface, at which point, compacted method begins.”
Note that this compacted fill requirement was further iterated in Amendment 0001 Questions and Responses. The requirements of these two (2) paragraphs are in conflict. Please clarify that Paragraph 3.1.2, Drainage, is not applicable to the placement of levee embankment, compacted fill.
Response: Clarifying that in reference to Paragraph 3.1.2, Drainage, is not applicable to the placement of levee embankment, compacted fill.
(End of Summary of Changes)