Specifications W912P823B0022.pdf

PDF 4 MB Posted

Attached to
Grand Isle and Vicinity Project, Post-Ida Clay core/Geotube repairs
Solicitation number
W912P823C0043
Issued by

About this file

This is an award notice for a firm fixed-price construction contract to perform post-Hurricane Ida clay core and geotube repairs for the Grand Isle and Vicinity Project. The contract was awarded by the Department of the Army Corps of Engineers Engineering District New Orleans. Work will include repairing damaged sections of the clay dune and installing new geotube structures, with a period of performance through November 2023. The contractor will mobilize plant and equipment to the project site and perform repairs to restore and strengthen protective barriers along the shoreline.

View the file

Other files

File Type Posted
W912P823C0043 AWARD Package.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01100-a ED 22-054

Section Table of Contents

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER 1

2. DAMAGE TO WORK 2

3. SAFETY PROVISIONS 2

4. INSPECTOR'S FIELD OFFICE 7

5. PROJECT SIGN 8

6. RADIO AND TELEPHONE COMMUNICATIONS 8

7. SEAWORTHINESS CERTIFICATION 9

8. RIGHTS-OF-WAY 9

9. CERTIFICATES OF COMPLIANCE 11

10. ENVIRONMENTAL LITIGATION 11

11. UTILITIES AND IMPROVEMENTS 11

12. PERMISSIBLE HOURS OF WORK 13

13. WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS 13

14. SIGNAL LIGHTS 13

15. CLAY SOURCES 13

16. FORMAT OF SURVEYS 16

17. ACCESS PLAN 17

18. PROJECT BENCHMARKS 18

19. SECURITY REQUIREMENTS 18

20. GOVERNMENT TRANSPORTATION 19

21. DAMAGED ROADWAYS 19

01100-1 ED 22-054

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Clause in Section 00700 CONTRACT CLAUSES, entitled DEFAULT (FIXED PRICE CONSTRUCTION) (FAR 52.249-10). In order, for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(b) The following schedule of monthly anticipated adverse weather delays is based upon data collected by the Louisiana Office of State Climatology for temperature, precipitation and wet ground conditions or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor’s progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities. The adverse weather days apply to rain, fog, high winds, high/low tides, hail, lightning, and high/low temperatures as indicated on the Weather Data Sheet and will be used by the Government to record weather during construction.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS

BASED ON (5) DAY WORK WEEK

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

8 6 3 4 3 3 5 5 4 3 4 4

(c) Upon receipt of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month) and shall be calculated chronologically from the first to the last

01100-2 ED 22-054

day of each month and shall be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Clause in Section 00700 CONTRACT CLAUSES, entitled DEFAULT (FIXED PRICE CONSTRUCTION)

(FAR 52.249-10).

2. DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in the Clause in Section 00700 CONTRACT CLAUSES, entitled PERMITS AND RESPONSIBILITIES (FAR 52.236-7). However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit price or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there is no contract unit or job prices applicable to any part of such work, an equitable adjustment shall be made pursuant to the Clause in Section 00700 CONTRACT CLAUSES, entitled CHANGES (FAR 52.243-4). Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

3. SAFETY PROVISIONS

The safety provisions as specified herein refer to the November 2014 edition of EM 385-1-1. The current document can be found at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM _385-1-1.pdf

(a) Mishap Reporting and Investigation. Refer to EM 385- 1-1, Section 01.D.

Reports shall be submitted on ENG Form 3394. Accidents shall be investigated, and reports completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or his/her representative within one working day after the accident occurs. All data reported must be complete, timely and accurate. A follow-up report shall be submitted when the estimated lost time days differs from the actual lost time days.

(b) Accident Prevention Plan (APP). (See the Contract Clause in Section 00700, entitled ACCIDENT PREVENTION (FAR 52.236-13).) Prior to the preconstruction conference, four copies of the Accident Prevention Plan shall be http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

01100-3 ED 22-054

submitted to the Contracting Officer for review and acceptance. The plan shall be prepared in the following format:

(1) Executed CESO Form A-02, Accident Prevention Plan Checklist (the “fillable form” can be obtained from:

http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1- 1,%202014%20Sections/Checklists/CESO%20Checklist%20A- 02%20Accident%20Prevention%20Plan.pdf). The Contractor shall address each of the elements/sub-elements in the outline contained in Appendix A of EM 385-1-1 in the order that they are provided in the manual. If an item is not applicable because of the nature of the work to be performed, the Contractor shall state this exception and provide a justification.

(2) Activity Hazard Analysis (AHA) Form, Figure 1-2 in Section 1 “Program Management” of EM 385-1-1 (Nov 2014) (Attached at the end of this section).

(3) A copy of company policy statement regarding accident prevention.

(4) When marine plant and equipment are in use under a contract, the method of fuel oil transfer shall be included on MVN Form 385-10 (Latest Edition), Fuel Oil Transfer (attached at the end of this section). (Refer to

33 CFR 156).

(5) EM-385-1-1 01.A.14 (a) requires a hazard analysis for all features of work. For this contract, these hazard analyses shall be submitted with the rest of the APP for review before work begins. Hazard analysis may be refined and resubmitted, at a later date, if the Contractor chooses.

The Contractor shall not commence physical work at the site until the Contracting Officer, or his/her authorized representative has accepted the plan. The Contractor may submit its Activity Hazard Analysis (AHA) only for the first phase of construction provided, that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase. Also refer to Section 1 of EM 385- 1-1.

(c) Comprehensive Hazard Communication Program. The Contractor shall develop, implement, and maintain at the workplace a written, Comprehensive Hazard Communication Program (see Section 06.B.01 of EM 385-1-1) that includes identification of potential hazards as prescribed in 29 CFR Part

1910.1200 and/or 1926.59, effects of exposure and control measures to be used for chemical products and physical agents that may be encountered during the performance of work on this contract, provisions for container labeling, Safety Data Sheets, and employee training program, and other criteria in accordance http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1-1,%202014%20Sections/Checklists/CESO%20Checklist%20A-02%20Accident%20Prevention%20Plan.pdf http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1-1,%202014%20Sections/Checklists/CESO%20Checklist%20A-02%20Accident%20Prevention%20Plan.pdf http://www.usace.army.mil/Portals/2/docs/Safety/EM%20385-1-1,%202014%20Sections/Checklists/CESO%20Checklist%20A-02%20Accident%20Prevention%20Plan.pdf

01100-4 ED 22-054

with 29 CFR Part 1910.1200 and/or 1926.59. Training shall include communication methods and systems to be used (i.e., voice, hand signals, radios, or other means), and training in the use and understanding of safety data sheets and chemical product hazard warning labels. Prior to bringing hazardous substances, as defined in 29 CFR 1910.1200 and/or 1926.59, onto the job site, a copy of the Hazard Communication Program and the Safety Data Sheets of each substance shall be submitted to the Contracting Officer and made available to the Contractor's employees as part of its Accident Prevention Plan. A site map shall be attached to the inventory showing where the inventoried hazardous substances are stored. The inventory list and site map shall be updated monthly to assure accuracy. The Contractor shall note that “Safety Data Sheets (SDS) has replaced Material Safety Data Sheets (MSDS)” referenced in Section 06.B.01 of EM 385-1-1 meeting the criteria of the new OSHA globally harmonized system.

(d) Overhead Electric Lines. In locations where trucks and other equipment will be passing beneath overhead power lines, the Contractor shall install at least 2 signs on either side of the crossings warning drivers of the overhead lines. The signs shall face both directions of travel. The signs shall have arrows pointing upward and state 'Overhead Electric'. The Contractor's proposed sign design shall be submitted to the Contracting Officer for approval.

(e) Daily Inspections. The Contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the jobsite in accordance with Section 01 45

04.00 10, "CONTRACTOR QUALITY CONTROL". The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

(1) Phase(s) of construction underway during the inspection.

(2) Locations of areas where inspections were made.

(3) Results of inspections, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

(f) Safety Sign. The Contractor shall furnish, erect, and maintain a safety sign at the site where indicated by the Contracting Officer. No separate payment will be made for construction and erection of the safety sign and all costs in connection therewith will be considered an incidental obligation of the Contractor. The sign shall conform to the requirements of this paragraph and the drawing included at the end of this section. The lettering shall be black, the safety circle and cross green, and the background white. When placed on a floating plant, the sign may be half size. The sign shall be erected as soon as practicable, but not later than 15 calendar days after the date established for commencement of work. The

01100-5 ED 22-054

data required shall be current. The sign coordinator is Timothy Lacoste, (504) 862-2663.

(g) Ground Fault Protection. Electrical equipment used on this contract shall be equipped with ground fault circuit interrupters in accordance with EM 385-1-1, Section 11.D.05.

(h) Means of Escape for Personnel Quartered or Working on Floating Plant.

Two means of escape shall be provided for assembly, sleeping, and messing areas on floating plants. For areas involving 10 or more persons, both means of egress shall be through standard size doors opening to different exit routes.

Where nine or fewer persons are involved, one of the means of escape may be a window (minimum dimensions 24-inches by 36-inches), which leads to a different exit route. Refer to Section 19 of EM 385-1-1.

(i) Emergency Alarms and Signals.

(1) Alarms. Emergency alarms shall be installed and maintained on all floating plant requiring a crew where it is possible for either a passenger or crewman to be out of sight or hearing from any other person. The alarm system shall be operated from the primary electrical system with standby batteries on trickle charge that will automatically furnish the required energy during an electrical-system failure. A sufficient number of signaling devices shall be placed on each deck so that the sound can be heard distinctly at any point above the usual background noise. All signaling devices shall be so interconnected that actuation can occur from at least one strategic point on each deck.

(2) Signals.

(a) Fire Alarm Signals. The general fire alarm signal shall be in accordance with 46 CFR Ch. I; Subpart E.109.503 of the Coast Guard Rules and Regulations for Cargo and Miscellaneous Vessels, Sub-Chapter I & Ia.

(b) Abandon Ship Signals. The signal for abandon ship shall be in accordance with paragraph 109.503(b) of the reference cited in subparagraph (2)(a) above.

(c) Man-Overboard Signal. Hail and pass the word to the bridge.

All personnel and vessels capable of rendering assistance shall respond.

(j) Hurricane Plan. A detailed plan for protection and evacuation of personnel and the construction site, in the event of an impending hurricane or storm, is required as an enclosure to the Contractor's Accident Prevention Plan. This plan

01100-6 ED 22-054

shall be submitted to the Contracting Officer, or his/her representative, for review and approval prior to the preconstruction conference. Work being performed to satisfy the Hurricane Plan will not be measured for payment. Payment for all work associated with the Hurricane Plan, and providing the equipment required for the duration specified, shall be distributed among the existing bid items. The Hurricane Plan shall include at least the following:

(1) The time each phase of the plan will be put in effect. The time shall be the number of hours remaining for the storm to reach the worksite if it continues at the predicted speed and direction.

(2) The estimated time necessary to secure and evacuate the site including any emergency flood protection.

(3) The safe harbor for personnel and plant specifically identified.

(4) The name of the boat which will be used to move the plant, its type, capacity, speed, and availability.

(5) The estimated time necessary to move the plant to the safe harbor after movement is started.

(k) Hazardous Energy Protection. The Contractor shall develop, implement, and maintain at the workplace, a written Control of Hazardous Energy (Lockout/Tagout) System. Refer to Section 12 of EM 385-1-1.

(l) Site Safety and Health Officer (SSHO). The Contractor shall have a qualified Site Safety and Health Officer (SSHO) on the construction site at all times that work is being performed to manage the Contractor's Accident Prevention Plan.

The SSHO shall be a full-time position with the SSHO having no other duties than Contractor Safety management (See EM 385-1-1, paragraph 01.A.17). The person(s), as a minimum, shall have completed the 30-hour OSHA Construction Industry Safety Class (may be web-based training if the student is able to directly ask questions of the instructor by chat / phone) or an equivalent course (see Appendix A, paragraph 3.d(3)) applicable to the work to be performed and given by a qualified instructor. Such training shall have been completed within the last three (3) years. SSHO's shall maintain competency through taking 8 hours of documented formal, on-line, or self-study safety and health coursework every year. The Contractor shall not commence physical work at the site until the Contracting Officer, or his/her authorized representative, has approved the Contractor's Accident Prevention Plan, and the Contractor's SSHO is ready to begin work. For projects with multiple shifts, an alternate SSHO shall be assigned to assure coverage of the project during all working hours. Alternate SSHO's (as listed in the Contractor's APP) must meet the same requirements as the primary SSHO. Alternate SSHO's may hold other positions when not functioning as an SSHO.

01100-7 ED 22-054

(m) Harsh Working Environment. This solicitation is suitable for Contractors experienced with working in the Gulf of Mexico environment. The environment can be hazardous to floating plant and equipment due to tides, waves, and tropical events. Due to the potential for tropical events the Contractor will need to have the ability to expeditiously move plant/equipment to safe harbor.

4. INSPECTOR'S FIELD OFFICE

(a) The Contractor shall furnish to the Government inspectors on board the floating plant bottled water and a suitable room for an office. The office shall be fully equipped and maintained to the satisfaction of the Government inspectors aboard the floating plant. The office shall be lighted, heated, ventilated, and air conditioned to the satisfaction of the inspectors. Power surge protectors shall be available for the protection of any of the inspector's equipment he/she deems necessary to protect from electrical outlet power surges. The entire cost to the Contractor for furnishing, equipping, and maintaining the accommodations shall be included in the contract job price for “Mobilization and Demobilization”. If the Contractor fails to meet the requirements of this paragraph, the accommodations will be secured by the inspector, and the cost will be deducted from payments due the Contractor.

(b) The office shall be equipped with the following items, which must be supplied in a fully functional condition:

a. A desk with locking drawers and two sets of matching keys;

b. A swivel desk chair with a contoured seat, two arms, and adjustable height and back rest, all of which shall have fully cushioned and upholstered surfaces;

c. A two or more drawer legal sized file cabinet;

d. A three foot by five foot drafting table, with a drafting table fluorescent light that is mechanically adjustable. This equipment shall include appropriate drafting instruments, as requested by the inspector.

e. A legal/letter sized capable copy machine - the Contractor may allow the use of his own in lieu of providing a separate one for the inspector;

f. Double convenience outlets to provide 110 volt power along with surge protectors to protect government equipment.

(c) If the Contractor maintains an establishment at the worksite for the subsistence of his own employees, then he shall furnish to inspectors, and government agents who may visit the work on official business, meals of a quality

01100-8 ED 22-054

satisfactory to the Contracting Officer. All meals shall be available for purchase by the Government's agents and inspectors at the cost of $5.00 per person per meal.

5. PROJECT SIGN

Prior to commencement of work, the Contractor shall construct a project sign at the site of the work at a location directed by the Contracting Officer. The sign, which will identify the work with the Corps of Engineers shall be 4 feet by 6 feet in size and shall conform to the requirements of the PROJECT SIGN drawing and installation instructions attached at the end of this section. The lettering for the 2 feet by 4 feet section of the sign with the Corps logo and Army Star shall be white; all other lettering shall be black. Lettering for the project name shall be Helvetica Bold, all other lettering shall be Helvetica Regular. The sign coordinator is Timothy Lacoste, (504) 862-2663. No separate payment will be made for construction and erection of the project sign and all costs in connection therewith will be considered an incidental obligation of the Contractor. Upon completion of the work, the sign shall become the property of the Contractor and shall be removed from the job site.

6. RADIO AND TELEPHONE COMMUNICATIONS

The Contractor shall furnish and maintain the following radio and telephone equipment throughout the period of the contract. Final approval of the plant will not be made until this equipment is installed and in good working order:

a. Maritime Radio Transceiver. The Contractor shall furnish and maintain throughout the contract, one FM ship's radio transceiver with power not in excess of 25 watts, and at least 15 watts output on the maritime frequencies of 156.800 (Channel 16) and 156.375 (Channel 67) MHz 16F3 emission, with a tolerance of plus or minus 5 kHz deviation at 100 percent modulation for communication concerning navigation in the vicinity of the floating plant. The radio shall be operated in accordance with FCC rules and regulations.

b. Radio Equipment for Additional Floating Plant. In the event that the Contractor should have two (2) plants operating simultaneously under this contract, the above-specified radio equipment shall be furnished and maintained on both floating plants. The radio transceivers provided for hereinabove shall be continuously monitored by qualified Contractor persons operating the floating plants.

c. Satellite Telephone. The Contractor shall provide functioning 24-hour satellite telephone service with voice and facsimile capability within the inspector’s office.

The satellite service shall have, as a minimum, voice capability of 4.8 kb/s (kilobytes per second) voice coding and fax speed of 2.4 kb/s. The satellite telephone shall be made available for official use by Government personnel on a

01100-9 ED 22-054

24-hour per day basis to exclusively conduct Government business and emergency calls.

d. WIFI Capability for RMS Field Reporting. The Contractor shall provide the Inspector's office with a cellular wireless Broadband / WiFi 802.11n capable router that accepts cellular data signals through satellite. The high speed internet service and associated equipment must be capable of providing adequate connection to allow the inspectors to import / export files through RMS (shall provide a minimum download speed of 10 Mbps and a minimum upload speed of 1.5 Mbps for the sole use of the Inspector).

The Contractor shall field verify that the service provider chosen has adequate continuous coverage throughout the site of work. The Contractor shall be responsible for the installation, maintenance of, and the monthly service fees necessary to provide continuous high speed internet service for the duration of the contract. Final approval of the plant will not be made until this equipment is installed and in good working order.

e. No separate measurement or payment will be made for furnishing and maintaining radio and telephone equipment as specified herein. All costs shall be distributed throughout the existing bid items.

7. SEAWORTHINESS CERTIFICATION

EM 385-1-1, Section 19.A.01.b. All floating plants not subject to USCG inspection and certification or not having a current American Bureau of Shipping (ABS) classification shall be inspected in the working mode annually by a marine surveyor accredited by the National Association of Marine Surveyors (NAMS) or Society of Accredited Marine Surveyors (SAMS) and having at least five (5) years’ experience in commercial marine plant and equipment. All other plant shall be inspected annually by a qualified person. The inspection shall be documented, and a copy of the most recent inspection report shall be posted in a public area on board the vessel and a copy shall be furnished to the designated authority upon request. The inspection shall be appropriate for the intended use of the plant and shall, as a minimum, evaluate structural integrity and compliance with NFPA 302, Fire Protection Standard for Pleasure and Commercial Motor Craft.

8. RIGHTS-OF-WAY

a. The rights of entry required for the work to be constructed under this contract, within the rights-of-way limits indicated on the drawings, have been obtained by the Government and are provided without cost to the Contractor. The Contractor shall make its own investigations to determine the conditions, restrictions, and difficulties that may be encountered in the transportation of equipment and material to and from the work site. The Contractor shall stake out the Dune and Beach Right of Way to avoid trespass onto private lands. The proposed work, 01100-10 ED 22-054 including rights-of-way, as defined by these specifications, and as shown on the drawings, is in compliance with all applicable Federal and state environmental laws and regulations. Upon completion of the Contractor’s work, rights-of-way furnished by the Government shall be returned to its original condition prior to construction unless otherwise noted.

b. If the Contractor proposes a deviation from the Government furnished rights-of-way for his convenience, the Contractor shall notify the Contracting Officer or its representative in writing. Contractor shall not provide any permanent rights-of-way for the project. The Contractor is cautioned that any deviation to the Government furnished rights-of-way is subject to all applicable Federal and state environmental laws and regulations. Compliance with these environmental laws and regulations may require additional National Environmental Policy Act (NEPA) documents, cultural resources surveys, coordination with the Louisiana State Historical Preservation Officer, water quality certification, modification of the Federal consistency determination, etc. The Government is ultimately responsible for environmental compliance; therefore, the Government will determine the additional environmental coordination and documentation necessary for a proposed deviation to the Government furnished rights-of-way.

For any environmental investigations the Government is to perform on areas outside of Government furnished rights-of-way, the Contractor shall provide sufficient rights of entry to the Government. The Contracting Officer will advise the Contractor of the additional environmental coordination and documentation that must be completed. The Government shall be responsible for any additional environmental compliance; however, the Contractor may conduct specific tasks identified by the Government. The Government will offer advice and assistance to the Contractor in conducting these tasks. Depending on the environmental impact of the proposed deviation, obtaining the coordination and documentation may not be approved or could take as much as 180 days for approval by the Government. The Government must review, approve, and ensure distribution of all environmental compliance documentation and ensure all comments on the same have been resolved before any utilization of any areas outside of the Government furnished rights-of-way. The Contractor shall reimburse the Government for actual expenses incurred for assistance in completing or attempting to complete additional environmental coordination and documentation, which expenses will not exceed one hundred thousand ($100,000) dollars. There is no guarantee that environmental compliance will be obtained; therefore, the Contractor shall assume all risks and liabilities associated with pursuing a deviation. Any delays resulting from the deviation and/or the environmental coordination and documentation shall not be made the basis of any Contractor claim for increase in the contract cost and/or increase in contract time. Deviations will be at Contractor’s sole risk and liability, including, but not limited to, such liabilities associated with items such as hazardous substances regulated under the Comprehensive Environmental Response, Compensation, and Liability Act (42 U.S.C. 9601 et. seq.), and at no cost to the Government. Government assistance in obtaining additional environmental

01100-11 ED 22-054

clearances does not relieve the Contractor of responsibility for complying with other Federal, state, or local licenses and permits.

9. CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in three (3) copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet specified requirements.

10. ENVIRONMENTAL LITIGATION

(a) The term "environmental litigation", as used herein, means a lawsuit alleging that the work has an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

(b) If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined above, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If the order is not due in any part to acts or omissions of the Contractor (or a Subcontractor at any tier) other than as required by this contract, such suspension, delay, or interruption shall be as if ordered by the Contracting Officer under the Clause in Section 00700 CONTRACT CLAUSES, entitled SUSPENSION OF WORK (FAR 52.242-14). The period of such suspension, delay or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.

11. UTILITIES AND IMPROVEMENTS

(a) There are multiple utilities within the limits of work. Disposition of utilities is Do Not Disturb.

UTILITY # DESCRIPTION OWNER

P1 6” GAS P/L TOWN OF GRAND ISLE

W1 12” WATER LINE TOWN OF GRAND ISLE

01100-12 ED 22-054

E1 7–6” ELECTRICAL CONDUITS ENTERGY LA

P2 ABANDONED 16” NATURAL GAS P/L EXXONMOBIL

P3 12” NATURAL GAS P/L EXXONMOBIL

P4 12” NATURAL GAS P/L ENERGY XXI

P5 12” NATURAL GAS P/L ENERGY XXI

P6 ABANDONED 16” NATURAL GAS P/L VASTAR RESOURCES

INC

P7 ABANDONED 18” OD OUTFALL P/L EXXONMOBIL

P8 12” OIL P/L EXXONMOBIL

P9 ABANDONED 12” PRODUCED

WATERS P/L

EXXONMOBIL

P10 ABANDONED 14” NATURAL GAS P/L FREEPORT

INTERSTATE PIPELINE

CO

P11 6” NATURAL GAS P/L EXXONMOBIL

P12 30” OIL P/L BP LLC

P13 10” CRUDE P/L CONOCO PHILLIPS

(b) Any unidentified pipes or structures which may be found within the limits of the work during the course of construction shall not be disturbed nor shall construction or excavation be performed at these locations unless and until approved by the Contracting Officer. The Contractor shall notify the utility owners by certified mail 45 days, 15 days, and 72 hours prior to construction near the utility. Louisiana One Call must be contacted at least 3 days prior to working in the vicinity of utilities.

(c) Utility Point of Contacts

Ray Santity Town of Grand Isle 985-787-3196 P.O Box 200, Grand Isle, LA

Eric Vickers Entergy

(504) 576-4000 639 Loyola Ave, New Orleans, LA, 70113

Chris Savoie ExxonMobil 985-787-5265 PO Box 301 Grand Isle, LA 70358

01100-13 ED 22-054

Julie Bowen Freeport Interstate Pipeline 504-582-4535 PO Box 61520 New Orleans, LA 70161

12. PERMISSIBLE HOURS OF WORK

When the Contractor elects to work weekends and holidays, notice shall be given to the Contracting Officer, in writing, 36 hours in advance of commencement of such operations to permit suitable arrangements for inspections to be made. Adequate lighting for safe operations and thorough inspection of night operations conducted within the permissible hours of work shall be provided by the Contractor at his/her own expense. However, no pile driving or extracting operations shall be performed between the hours of 9:00 p.m. and 6:00 a.m. If the Contractor elects to haul equipment to Grand Isle, truck hauling operations shall be restricted to the hours of 7 am and sunset.

13. WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS

The Contractor shall coordinate his/her operations with any other Government Contractors who may be working in the vicinity. The Contractor shall coordinate his staging operations, access routes, etc. with any Contractor currently performing work in the general vicinity. No impacts to construction will be allowed for the coordination required between the Contractors working in the area.

14. SIGNAL LIGHTS

The Contractor shall display signal lights and conduct his/her operations in accordance with U. S. Coast Guard regulations governing lights and day signals to be displayed, as set forth in Commandant, U. S. Coast Guard Instruction M16672.2C, Navigation Rules, International - Inland (COMDTINST M16672); 33 CFR 81, Appendix A (International); and 33 CFR 84 through 33 CFR 90 (Inland) as applicable.

15. CLAY SOURCES

(a) On the basis of information and data available to the Contracting Officer, the lands containing the clay sources from the sites designated below have been studied by the Government for environmental concerns and soil suitability. The designated sites, below, may be capable of producing the quality of clay material meeting the requirements set forth in Section 31 24 00.00 12 EMBANKMENT - CLAY, paragraph entitled “MATERIALS” and are subject to the subparagraphs

(b) through (e) below. However, some documentation relating to the below sites may need to be updated prior to their use. The Contractor shall verify that environmental clearances for the below sites have not expired. The Contractor is responsible for submitting a complete Borrow Submittal for Corps review and

01100-14 ED 22-054

approval with all applicable updated documentation. See Section 31 23 00.00 12 EXCAVATION, paragraph entitled "Submittal Package Requirements in Detail".

March 2014

Site Name Point of Contact Contact Information Location

River Birch, Phase 1 Vic Culpepper Office: 504-436-1288 Cell: 504-915-6006 Avondale, LA

River Birch, Phase 2 Vic Culpepper Office: 504-436-1288 Cell: 504-915-6006 Avondale, LA

Pearlington Dirt Johnny Dollar Cell: 318-366-8218 jdollar.chapel.hill@gmail.com Pearlington, MS

Diaz Property (DK Aggregates) Philip Callahan

504-450-6702 philcallahan@cox.net St. Bernard Parish, LA

Eastover Jerry Howell Cell: 504-559-1606 jerryhowell992@hotmail.com New Orleans, LA

St. Gabriel Michael Daigle Office: 225-216-7483 mdaigle@trcsolutions.com Carville, LA

*1025 Florissant Michael Palmer Cell: 504-812-8016 palmertruckin@yahoo.com St. Bernard Parish, LA

Acosta Amanda Phillips Office: 985-626-5204 gsdi@bellsouth.net St. Bernard Parish, LA

3C Riverside Properties H. Ray Coleman Office: 901-309-5844 raycoleman@earthlink.net St. Charles Parish, LA

*Myrtle Grove Kenneth Payne Office: 504-615-1076 Cell: 504-382-5866 gcdr1@hotmail.com Plaquemines Parish, LA

Frierson M. Matt Durand Office: 337-394-6574 Hancock County, MS

Meyer Robert Najor Office: 866-998-6400 Cell: 805-393-9994 bnajor@fortressgroupusa.com Plaquemines Parish, LA

River Birch-Willswood Vic Culpepper Office: 504-436-1288 Cell: 504-915-6006 vculpepper@riverbirchlandfill.com Avondale, LA

Willow Bend Hensley Lee Office: 601-799-1335 Cell: 601-273-0404 hrlee81@hotmail.com

St. John the Baptist Parish, LA

Pearlington Dirt, Phase 2 Johnny Dollar Cell: 318-366-8218 jdollar.chapel.hill@gmail.com Pearlington, MS

*Gathien – Navy Ship Paul Loupe Office: 985-535-0148 Paul.Loupe@loupegroup.com St. Bernard Parish

River Birch-South Kenner Rd. Vic Culpepper

Office: 504-436-1288 Cell: 504-915-6006 vculpepper@riverbirchlandfill.com Avondale, LA

Guillot Paul Loupe Office: 985-535-0148 Paul.Loupe@loupegroup.com St. Bernard Parish

Eastover, Phase 2 Jerry Howell Cell: 504-559-1606 jerryhowell992@hotmail.com New Orleans, LA

Willow Bend, Phase 2 Hensley Lee Office: 601-799-1335 Cell: 601-273-0404 hrlee81@hotmail.com

St. John the Baptist Parish, LA

Tammany Holding Company Robert Torres Office: 985-641-0089 St. Tammany Parish, LA mailto:jdollar.chapel.hill@gmail.com mailto:philcallahan@cox.net mailto:jerryhowell992@hotmail.com mailto:mdaigle@trcsolutions.com mailto:palmertruckin@yahoo.com mailto:gsdi@bellsouth.net mailto:raycoleman@earthlink.net mailto:gcdr1@hotmail.com mailto:bnajor@fortressgroupusa.com mailto:vculpepper@riverbirchlandfill.com mailto:hrlee81@hotmial.com mailto:Paul.Loupe@loupegroup.com mailto:vculpepper@riverbirchlandfill.com mailto:Paul.Loupe@loupegroup.com mailto:jerryhowell992@hotmail.com mailto:hrlee81@hotmial.com

01100-15 ED 22-054

Contact Contact Information Location

Henley Robert Najor Office: 866-998-6400 Cell: 850-393-9994 najorr@bellsouth.net Hancock County, MS

Big Shake Jay Thomas Office: 225-769-8615 laearthcorps@cox.net St. James Parish, LA

Contreras Cells E, F, & Z Philip Callahan Cell: 504-450-6702 philcallahan@cox.net St. Bernard Parish, LA

3C Riverside Properties, Phase 3 H. Ray Coleman Office: 901-309-5844 raycoleman@earthlink.net St. Charles Parish, LA

Bocage Plantation Marion Rundell Cell: 713-253-1700 mrundell@gmail.com Ascension Parish, LA

Idlewild, Stage 1 Jerry Howel. Cell: 504-559-1606 jerryhowell992@hotmail.com Plaquemines Parish, LA

Plaquemines Dirt & Clay Karen Boudrie Office: 504-912-5696 boudriekaren@yahoo.com Plaquemines Parish, LA

Citrus Lands Shirley T. Hall Office: 504-754-6881 Plaquemines Parish, LA

Phillips 66 Emily Campbell Office: 504-656-3103 Cell: 504-415-3568 Plaquemines Parish, LA

Nairn Jerry Howell Cell: 504-559-1606 jerryhowell992@hotmail.com Plaquemines Parish, LA

King Mine Richie Santiago Cell: 228-216-5403 kinglandfill@att.net Hancock County, MS

Idlewild, Stage 2 Jerry Howell Cell: 504-559-1606 jerryhowell992@hotmail.com Plaquemines Parish, LA

Spoil Area Michael Pugh Office: 504-309-4129 Cell: 504-905-6387 mpugh@royalengineering.net St. Bernard Parish, LA

Lilly Bayou Thomas Hymel Office: 985-446-9644, Ext. 117

Cell: 985-665-8344 thymel@phylway.com

East Baton Rouge Parish, LA

Raceland Raw Sugars Dan Duplantis Office: 985-537-3533 rrsdanjr@aol.com Lafourche Parish, LA

Acosta, Phase 2 Amanda Phillips Office: 985-626-5204 Cell: 985-264-2425 gsdi@bellsouth.net

St. Bernard Parish, LA

Scarsdale Michael Pugh Office: 504-309-4129 Cell: 504-905-6387 mpugh@royalengineering.net Plaquemines Parish, LA

River Birch-Landfill Expansion Vic Culpepper

Office: 504-436-1288 Cell: 504-915-6006 vculpepper@riverbirchlandfill.com Avondale, LA

Levis Robert Levis Cell: 985-643-1800 rlevis@levischevycadillac.com St. Tammany Parish, LA

Port Bienville M. Matt Durand Office: 337-394-6574 Hancock County, MS

RBEND II Warren Treme Cell: 504-458-9055 tremebuilders528@bellsouth.net

St. John the Baptist Parish, LA

Robert Brothers Farm Pete Graffagnino Office: 225-473-7778 Cell: 225-715-5525

St. John the Baptist Parish, LA

Assumption Land Company

Richard Robichaux

985-526-6457 985-209-8338 rgr23@bellsouth.net Jefferson Parish, LA

Houma Excavation Renee Sabella 504-739-9551 ext. 1091 Terrebonne Parish, LA mailto:najorr@bellsouth.net mailto:laearthcorps@cox.net mailto:philcallahan@cox.net mailto:raycoleman@earthlink.net mailto:mrundell@gmail.com mailto:jerryhowell992@hotmail.com mailto:boudriekaren@yahoo.com mailto:jerryhowell992@hotmail.com mailto:kinglandfill@att.net mailto:jerryhowell992@hotmail.com mailto:mpugh@royalengineering.net mailto:thymel@phylway.com mailto:rrsdanjr@aol.com mailto:gsdi@bellsouth.net mailto:mpugh@royalengineering.net mailto:vculpepper@riverbirchlandfill.com mailto:rlevis@levischevycadillac.com mailto:tremebuilders528@bellsouth.net mailto:rgr23@bellsouth.net

01100-16 ED 22-054

Contact Contact Information Location renees@orleansshoring.com *No salinity data obtained as Right of Entry not provided

(b) Clay may be furnished from any of the above listed sources, or at the option of the Contractor may be furnished from any other source designated by the Contractor and accepted by the Contracting Officer, subject to the conditions in Section 31 23 00.00 12 EXCAVATION, paragraph entitled CONTRACTOR-

FURNISHED BORROW AREAS.

(c) The Government is not responsible for any agreements or breach of agreements nor the resulting impacts of any breach of agreements between the Contractor and the listed owners and/or agents and or any other persons.

(d) Contact the Point of Contact for the above sources for information regarding the location of the sites and geotechnical boring logs of the material.

(e) Usage of any of the above listed clay sources shall neither relieve the Contractor from its obligation to furnish satisfactory material to the project nor commit the Government to the acceptance of the character, quantity, or availability of material from these sources. Verification of the material should be performed by the Contractor to assure that the material meets the contract specifications for embankment construction material.

16. FORMAT OF SURVEYS

a. The Contractor shall submit compliance surveys upon completion of certain construction activities. The compliance surveys shall be performed, and reports signed, and sealed by a Licensed Surveyor. The survey data shall be collected in accordance with the “USACE New Orleans District Minimum Survey Standards” and delivered in USACE EM Format as described in “Engineering Manual File Format Specifications”. Links to these documents are shown below:

http://www.mvn.usace.army.mil/Missions/Engineering/SurveySection/SurveyingG uidelines.aspx http://www.mvn.usace.army.mil/portals/56/docs/engineering/Geospatial/EM_For mat09.pdf

b. Each surveyed point should be listed on a separate line as a comma-delimited list of the following:

(1) Point ID, northing, easting, elevation, code mailto:renees@orleansshoring.com http://www.mvn.usace.army.mil/Missions/Engineering/SurveySection/SurveyingGuidelines.aspx http://www.mvn.usace.army.mil/Missions/Engineering/SurveySection/SurveyingGuidelines.aspx http://www.mvn.usace.army.mil/portals/56/docs/engineering/Geospatial/EM_Format09.pdf http://www.mvn.usace.army.mil/portals/56/docs/engineering/Geospatial/EM_Format09.pdf

01100-17 ED 22-054

(2) Surveyed points that are part of a profile shall be grouped under the appropriate #P01 record for that profile.

(3) Surveyed points that are part of a cross-section shall be grouped under the appropriate #X01 record for that cross-section.

(4) All other points shall be grouped under the appropriate #M01 record.

c. The code value shall be one of the three letter codes listed in Appendix 2 of “USACE New Orleans District Minimum Survey Standards”. If a surveyed point is not one of the items listed in Appendix 2, the Contractor shall submit a CODES.DAT file containing a semi-colon delimited list of these unique survey codes. Each reference benchmark shall be included as #V/#T records with the surveyed elevation #V/T06, and vertical datum and epoch information. Absolute vertical and horizontal accuracies shall be shown in the #H03 and #H17 records.

Surveys that are referenced to local coordinates, and not true State Plane coordinates, shall use the horizontal epoch “BASELINE” in the #H16 record. The USACE Survey Drivers shall be used to check for proper formatting. The drivers can be downloaded from the following site:

(http://www.mvn.usace.army.mil/Missions/Engineering/GeospatialSection/USACESurvey Drivers.aspx).

d. A survey report shall be delivered which includes a brief synopsis of the survey methodology (traverse run, level loops, GPS). All supporting field books shall be delivered. If static GPS is collected minimally and fully constrained GPS adjustment reports must be delivered. All surveys shall adhere to the requirements of the “USACE New Orleans District Minimum Survey Standards” and be performed and reports signed and sealed by a Licensed Surveyor. The point of contact for survey information is Joshua Hardy at 504-862-1852.

17. ACCESS PLAN

The Contractor shall submit an access plan to be reviewed and approved by the Contracting Officer to include, as a minimum, the following:

(a) Layout drawings showing the location of all equipment, office structures, toilets, and storage areas for materials.

(b) Show mobilization and demobilization routing and locations of large equipment, such as draglines, cranes, etc. while on the jobsite.

(c) Show waterway channels or canals used to mobilize and demobilize equipment and materials and show access routes and docking areas of all marine equipment with respect to the jobsite. Any designated barge onload/offload facilities shall be licensed, permitted facilities approved to accept and stockpile bulk fill material. Any proposed onload/offload sites that are not licensed, permitted facilities approved to accept and stockpile bulk fill material http://www.mvn.usace.army.mil/Missions/Engineering/GeospatialSection/USACESurveyDrivers.aspx http://www.mvn.usace.army.mil/Missions/Engineering/GeospatialSection/USACESurveyDrivers.aspx

01100-18 ED 22-054

may require additional National Environmental Policy Act documentation and/or USACE Regulatory permit issuance.

18. PROJECT BENCHMARKS

a. Benchmark And Project Temporary Benchmarks (TBM). To ensure local/internal consistency, the Contractor shall verify all project benchmarks using differential leveling in accordance with Section D of the “USACE New Orleans District Minimum Survey Standards”. The differential levels must be to Second Order Class II closure standards, as defined in Appendix 4 of the afore mentioned Survey Standards, and as follows: closure error (in feet) must be less than or equal to 0.035 x √(distance in miles). Ties between the “project controls” identified on the drawings and the Contractor utilized temporary benchmarks shall be performed at least every 6 months using differential leveling. Field notes showing all data and the closure error shall be provided to the Government.

Field records of these survey verifications shall be submitted in a survey report, which shall be updated with each periodic verification. A Registered Land Surveyor licensed in any of the 48 contiguous United States shall perform, sign, and seal the benchmark verification survey.

b. Records. Field records of these benchmark verifications shall be submitted to the Contracting Officer’s Representative in electronic format via RMS and emailed to "mvn-cd-q-testresults@usace.army.mil" within 7 days of completion of the benchmark verification. The Contracting Officer's Representative shall be notified immediately if any errors or inconsistencies in the benchmark verifications are found. Field records of the first benchmark verification must be received within 14 days of notice to proceed.

19. SECURITY REQUIREMENTS

a. Suspicious Activity Reporting Training (e.g., iWATCH, CorpsWatch, or See Something, Say Something). The Contractor will not have access to the CORPS network. This is an unclassified contract and the Contractor will not have access to critical information. The Contractor and all associated sub-contractors shall receive locally developed training provided by the New Orleans District Security Office on the Local Suspicious Activity Reporting Program. This training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity relating to the project manager, security representative or law enforcement entity. The Contractor shall provide local background checks to New Orleans District Security Office before performing work. Point of contact is Robin Hebert, 504.862.1656. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The results of this training shall be reported to the COR within 5 calendar days after the completion of the training.

01100-19 ED 22-054

b. Pre-Screen Candidates Using E-Verify Program. The Contractor shall pre-screen Candidates using the E-verify Program (https://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Contractor shall ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates shall be provided to the COR no later than 3 business days after the initial contract award. When contracts are with individuals, the individuals shall complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. The completed Form I-9 shall be provided to the Contracting Officer and shall become part of the official contract file.

20. GOVERNMENT TRANSPORTATION

The Contractor shall furnish, on the request of the Contracting Officer or any Inspector, the use of such boats, boatmen, laborers, and material as may be reasonably necessary in inspecting and supervising the work. The Contractor shall furnish, at no additional cost to the Government, a skiff with an enclosed cabin, overall hull length of at least 18 feet and a combined weight capacity of at least 1200 pounds.