W912P822B0019 Amendment 0002.pdf
PDF 374 KB Posted
- Solicitation number
- W912P822B0019
About this file
This document provides an amendment to a solicitation for construction services as well as responses to questions from potential offerors. The solicitation is for a stone spur construction project on the west jetty at Grand Isle, Louisiana, with an estimated value between $1,000,000 and $5,000,000. The amendment changes the unit of measure for armor stone from metric tons to tons of 2,000 pounds. It also provides responses to six questions from offerors related to benchmark verification, measurement and payment units, anticipated piling removal, dimensions, contract duration and issuance of notice to proceed. The resulting firm-fixed-price contract will be awarded by the U.S. Army Corps of Engineers, New Orleans District, with a submission deadline of February 24, 2022.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ED-22-018
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Grand Isle and Vicinity, LA, West Jetty Spur Dike and Extension, Jefferson Parish, LA (ED-22-018) has been amended to:
1. Change the Unit of Measure for Item No. 0004 from Metric Ton to Actual Ton
2. Respond to Questions
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Feb-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P822B0019
X 9B. DATED (SEE ITEM 11)
10-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Feb-2022
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P822B0019
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00100 - INSTRUCTIONS TO BIDDERS
The following have been added by full text:
RESPONSE TO QUESTIONS
Grand Isle and Vicinity, LA, West Jetty Spur Dike, Jefferson Parish, LA (ED-22-018) W912P822B0019 Questions Specification Section 01100- General Provisions Part 18 Project Benchmarks
Question #1: a. Benchmark And Project Temporary Benchmarks (TBM). To ensure local/internal consistency, the Contractor shall verify all project benchmarks using differential leveling in accordance with Section D of the “USACE New Orleans District Guide for Minimum Survey Standards”. The differential levels must be to Second Order Class II closure standards, as defined in Appendix 4 of the afore mentioned Survey Standards, and as follows: closure error (in feet) must be less than or equal to 0.035 x √(distance in miles). Ties between the “project controls” identified on the drawings and the Contractor utilized temporary benchmarks shall be performed at least every 6 months using differential leveling. Field notes showing all data and the closure error shall be provided to the Government. Field records of these survey verifications shall be submitted in a survey report, which shall be updated with each periodic verification. A Registered Land Surveyor licensed in any of the 48 contiguous United States shall perform, sign, and seal the benchmark verification survey.
Would the USACE consider allowing us to use RTK GNSS methods to verify the benchmarks?
Response #1: In order to be certain that there is minimal disturbance of the benchmarks, we do require the Contractor to do the benchmark verification with differential leveling as stated in the project specs. If it is not possible to do differential leveling, the contractor shall contact the USACE Survey Section.
Question #2: The bid form shows the armor stone & bedding & core material to be measured & paid in metric tons. The specs, page 246 of the pdf says measurement & payment is by the ton & defines tons to be 2000 pounds. Please clarify.
Response #2: The measurement and payment of armor stone and bedding and core material is by the ton. 1 Ton = 2,000 pounds.
Question #3: The specs, section 35 31 29.03 12 Page 7, paragraph 3.1 says, among other things, to remove any piling. Are there any piling to be removed? If so, are you able to say how many, how long & what material?
Response #3: There is no anticipation of piling to be removed.
W912P822B0019
Question #4: The Theoretical Spur Cross Section on C-02 is NTS & the width of the top of the core material is not dimensioned. Please clarify the width of the flat top portion of the core material.
Response #4: The width of the flat top of the core material is 2.875’.
Question #5: the contract time at 80 days is very short considering that we cannot place an order for the rock until a contract is in place, and then we must submit on the rock & acquire approval, have the rock produced, & then shipped to the jobsite & installed.
We request that, if at all possible, at least 60 days be added to the contract duration.
Response #5: USACE concurs with the additional days needed for stone retrieval. The total contract duration shall be changed to 140 calendar days.
Question #6: Section 00010-3 Note 3 NTP. The note says that the NTP will be issued immediately after acceptance of the P&P bonds. Please consider allowing a minimum of 30 days after acceptance of P&P bonds to issue the NTP to allow the contractor to get the upfront paperwork submitted and approved. We are seeing that it is taking longer to get the plans in and approved due to Covid and personnel shortages.
Response #6: See Response #5
(End of Summary of Changes)