A21_W912P818R0070_Am_0005.pdf
PDF 237 KB Posted
- Solicitation number
- W912P818R0070
About this file
A21_W912P818R0070_Am_0005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A21_W912P918R0070_Am_0006.pdf | ||
| A21_W912P818R0070_Am_0004.pdf | ||
| A21_W912P818R0070_Am_0003.pdf | ||
| A21_W912P818R0070_Am_0002.pdf | ||
| A21_W912P818R0070_Am_0001.pdf | ||
| A21_W912P818R0070.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W42HEM82156346
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The above numbered solicitation for Mitigation Banking Credits, Comite River Diversion Project Mitigation Project for Bottomland Hardw ood Impacts, U.S. Army Corps of Engineers, New Orleans District, is hereby amended as follow s:
1. Answ er Contractor's questions w ith CEMVN responses.
NOTE: The date for receipt of proposals remains Wednesday, April 17, 2019 at 10:00 am
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Apr-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P818R0070
X 9B. DATED (SEE ITEM 11)
12-Sep-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Apr-2019
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P818R0070
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following items are applicable to this modification:
QUESTIONS AND RESPONSES
CONTRACTOR QUESTIONS/CEMVN RESPONSES
Question 1: May we bid mitigation credits/acres which are pending release?
CEMVN Response: A mitigation bank may only offer to sell credits/acres that have been released to the bank by CEMVN Regulatory Branch at the time of submission of its proposal.
Question 2: I am trying to determine who was responsible for calculating the Wetland Value Assessment Mitigation Potential for the banks listed in the RFP so I may be able to get a copy of the calculations. Any help would be much appreciated.
CEMVN Response: CEMVN is responsible for the WVA information. CEMVN works with USFWS under the Fish and Wildlife Coordination Act to complete the WVA analysis. WVA information will only be released to the owner/Sponsor of the bank or its representative.
Question 3: Our question is, a mitigation purchase agreement was also included in your latest amendment #4, do we need to complete this if we’ve already submitted it to you last month with all our other documents? It appears to be the same, with no changes.
CEMVN Response: Yes, you need to resubmit all required information by the new proposal due date and acknowledge having seen all amendments in order to be considered for award.
(End of Summary of Changes)
File details come from the government source that posted it.