Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

W912P8

The above numbered solicitation for Calcasieu River and Pass, LA, Dredge Material Management Plan (DMMP), Confined Disposal Facility (CDF) 1 Dike Remediation, Including CDF-2 Option Work, Calcasieu Parish, Louisiana is amended as follows:

1. Quantity Surveys (FAR 52.236-16) Apr 1984, insert the following note at the end of clause:

Note: In Para. 7(c), the word "Promptly" is defined as "within three (3) calendar days".

2. Questions and answers are included.

3. Bid Opening Date remains the same Tuesday, 19 September 2017 at 2:00 P.M. CDT.

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT-W, ROOM 326

7400 LEAKE AVENUE

NEW ORLEANS, LA 70118-3651

SEE ITEM 6

J

W912P8-17-B-0039

1 2

08/30/2017

08/07/2017

Questions and Answers

Solicitation Number W912P8-17-B-0039 29 August 2017

QUESTION: Is there an estimated acreage for clearing and grubbing?

RESPONSE: The estimated acres of clearing and grubbing for CDF-1 are approximately 51 acres, and approximately 10 acres for CDF-2, as indicated/defined on the contract drawings

QUESTION: I didn't see an approved access road. Will there be access by land?

RESPONSE: This is addressed in the General Provision (Section 01100) clause entitled ACCESS PLAN which states:

"Access to the project site, CDF-1 and CDF-2, shall be via the Calcasieu River Ship Channel into each site.

The Contractor shall submit an Access Plan to be reviewed and approved by the Contracting Officer".

So access to CDF-1 and CDF-2 shall be along the bank line adjacent to the ship channel by barge and water vessels.

No access via public roads will be provided by the Government. Also, staging areas for CDFs 1 and 2 are defined on the contract drawings and within the furnished ROW.