W912P8-16-B-0050

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Reference Solicitation W912P8-16-B-0050 for New Orleans to Venice, Hurricane Protection System, West Bank Non-Federal Levee, Floodw all, NOV-NF-W-04a.1, Plaquemines Parish, Louisiana. This solicitation is modified as follow s:

See continuation page for changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Oct-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P8-16-B-0050

X 9B. DATED (SEE ITEM 11)

14-Sep-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Oct-2016

CODE

VICKSBURG DISTRICT CONTRACTING OFFICE

4155 CLAY ST.

VICKSBURG MS 39183-3435

W912EE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

00010-2 Ed xx-xxx

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

SPECIFICATIONS: Bidding Schedule, Section 01100, Section 31 05 19.05 12 and Section 31 41 16.00 12 are revised and replaced.

DRAWINGS: Drawings G-002, C-003, C-102, C-105, C-302, S-002, and S-101 are revised and replaced.

Specifications revised by this amendment have the notation "Revised by Amendment 0001" at the bottom of the page. Text added by this amendment is shown as underlined. Text deleted by this amendment is shown as overstruck.

Drawings revised by this amendment have the notation “Revised by Amendment 0001” in the title block. Drawings added by this amendment have the notation “Added by Amendment 0001” in the title block.

(End of Summary of Changes)

00010-3 Ed xx-xxx

SECTION 00010 – BIDDING SCHEDULE

Hurricane Protection System West Bank Non-Federal Levee NOV-NF-W-04a.1, Floodwall

Plaquemines Parish, Louisiana

Item DESCRIPTION Estimated Quantity Unit Unit Price Estimated Amount

BASE WORK

0001 Mobilization and Demobilization 1 JOB

0002 Temporary Flood Protection 1 JOB

0003 Temporary Retaining Structures 1 JOB

0004 Silt Fences 2,210 LF

0005 Truck Wash-Down Rack 1 JOB

0006 Clearing and Grubbing 1 JOB

0007 Project Access Improvements 1 JOB

0008 Structural Excavation 4,250 CY

0009 Non-Select Backfill 3,725 CY

0010 Construction Dewatering 1 JOB

0011 Embankment, Compacted Fill 4,825 CY

Supply and Drive Steel Sheet Piling, Type PZ-22, including Painting

8,120 SF

Steel Sheet Piling, Type

PZC-13

2,040 SF

0014 Dynamic Pile Load Tests - - - - - - - -

0014AA First Test 1 EA

0014AB All Over Test 1 EA

Furnish, Deliver, and Drive Steel H-Pile, HP 14x89, including Painting

19,043 LF

0016 Concrete Slope Pavement 180 SQ

0017 Demolition 1 JOB

0018 Reinforced Concrete Floodwall 1 JOB

*Revised by Amendment 0001

00010-4 Ed xx-xxx

0019 Excavation 1 JOB

0020 Seeding and Mulching 2.14 AC

0021 Fertilizer 95 LB

0022 Lime Soil Amendment 2.14 TON

0023 Sulfur Soil Amendment 1.07 TON

0024 Reinforcement Geotextile 715 SY

0025 Surfacing 135 CY

TOTAL BASE WORK: $

**The unit "JOB" as used in this Bidding Schedule is synonymous with the term "Lump Sum" used elsewhere within these plans and specifications.

Award will be made as a whole to one bidder.

NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED

TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL BE

DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR

AWARD.

NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2).

NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

NOTE 4: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;

http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPaym ent.aspx

*Revised by Amendment 0001 http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx

SECTION 00010 – BIDDING SCHEDULE

Hurricane Protection System West Bank Non-Federal Levee NOV-NF-W-04a.1, Floodwall Plaquemines Parish, Louisiana

Item DESCRIPTION Estimated Quantity Unit Unit Price Estimated Amount

BASE WORK

0001 Mobilization and Demobilization 1 JOB

0002 Temporary Flood Protection 1 JOB

0003 Temporary Retaining Structures 1 JOB

0004 Silt Fences 2,210 LF

0005 Truck Wash-Down Rack 1 JOB

0006 Clearing and Grubbing 1 JOB

0007 Project Access Improvements 1 JOB

0008 Structural Excavation 4,250 CY

0009 Non-Select Backfill 3,725 CY

0010 Construction Dewatering 1 JOB

0011 Embankment, Compacted Fill 4,125 CY

Supply and Drive Steel Sheet Piling, Type PZ-22, including Painting

8,120 SF

Steel Sheet Piling, Type

PZC-13

2,040 SF

0014 Dynamic Pile Load Tests - - - - - - - -

0014AA First Test 1 EA

0014AB All Over Test 1 EA

Furnish, Deliver, and Drive Steel H-Pile, HP 14x89, including Painting

19,043 LF

0016 Concrete Slope Pavement 180 SQ

4,825

Revised By Amendment 0001

B4EDGDML

Line

01100-a

Section Table of Contents

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER 1

2. DAMAGE TO WORK 2

3. SAFETY PROVISIONS 2

4. INSPECTOR'S FIELD OFFICE 7

5. PROJECT SIGN 8

6. RIGHTS-OF-WAY 9

7. CERTIFICATES OF COMPLIANCE 10

8. ENVIRONMENTAL LITIGATION 10

9. UTILITIES AND IMPROVEMENTS 10

10. PERMISSIBLE HOURS OF WORK 13

11. U.S. ARMY CORPS OF ENGINEERS CRD-C STANDARDS 13

12. AGGREGATE SOURCES 14

13. CLAY SOURCES 15

14. STATE TAXES 19

15. FORMAT OF SURVEYS 20

16. PROJECT BENCHMARKS 21

17. FLOODWALL ELEVATION VERIFICATION SURVEYS 21

18. BASELINE RE-ESTABLISHMENT AND FLOODWALL ALIGNMENT LAYOUT 22

19. COMMERCIAL WARRANTY 23

20. ACCESS PLAN 23

21. SPECIAL WORK REQUIREMENTS 24

22. SPECIAL HANDLING OF FOUNDATION PILES, SHEET PILE AND EQUIPMENT WITHIN THE

FACILITY OWNERS’ RIGHTS-OF WAY CONTAINING ACTIVE PIPELINES 24

23. VIBRATION MONITORING (Revised May 2006) 25

24. EMERGENCY GAP CLOSURE PLAN 27

25. FIELD VERIFICATION OF UTILITY LOCATIONS 28

26. COORDINATION WITH LOCAL INTERESTS 28

27. PROJECT ACCESS 29

28. RECOMMENDED CONSTRUCTION SEQUENCE 30

29. SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS 31

Revised By Amendment 0001

01100-1

SECTION 01100 - GENERAL PROVISIONS

1. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause in Section 00700, entitled Default (Fixed Price Construction) (FAR 52.249-10). In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(b) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) for temperature, precipitation and wet ground conditions or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities. Also considered in the chart below was wind, fog, high or low tides, etc.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS

BASED ON (5) DAY WORK WEEK

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Monthly adverse weather days will be supplied by Construction Division during local review.

(c) Upon receipt of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

01100-2

(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), and shall be calculated chronologically from the first to the last day of each month, and shall be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause in Section 00700, entitled Default (Fixed Price Construction) (FAR 52.249-10).

2. DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause in Section 00700, entitled Permits and Responsibilities (FAR 52.236-7). However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit price or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there is no contract unit or job prices applicable to any part of such work, an equitable adjustment shall be made pursuant to the Contract Clause in Section 00700, entitled Changes (FAR 52.243-4). Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

3. SAFETY PROVISIONS

The safety provisions as specified herein refer to the November 2014 edition of EM 385-1-1. The current document can be found at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM _385-1-1.pdf

(a) Accident Reporting and Recordkeeping. Refer to EM 385- 1-1, Section 01.D.

Reports shall be submitted on ENG Form 3394. Accidents shall be investigated and reports completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or his/her representative within one working day after the accident occurs. All data reported must be complete, timely and accurate. A follow-up report shall be submitted when the estimated lost time days differs from the actual lost time days.

(b) Accident Prevention Program (APP). (See the Contract Clause in Section 00700, entitled Accident Prevention (FAR 52.236-13).) Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the prework

Revised By Amendment 0001 http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

01100-3 conference, four copies of the Accident Prevention Program shall be submitted to the Contracting Officer for review and acceptance. The program shall be prepared in the following format:

(1) Executed MVN Form 385-43 (Latest Edition), Accident Prevention Program Administrative Plan (available upon request), see Appendix A of

EM 385-1-1.

(2) Executed MVN 385-43/1 (Latest Edition), Accident Prevention Plan Checklist and MVN Form 385-43/2 (Latest Edition), Activity Hazard Analysis (available upon request), see Figure 1-2 of EM 385-1-1.

(3) A copy of company policy statement regarding accident prevention.

The Contractor shall have on the construction site during working hours a trained Site Safety and Health Officer (SSHO) in accordance with paragraph 01.A.17 of EM 385-1-1. The Contractor shall not commence physical work at the site until the Contracting Officer, or his/her authorized representative has accepted the program. The Contractor may submit its Activity Hazard Accident Prevention Program only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase. Also refer to Section 1 of EM 385-1-1.

(c) Comprehensive Hazard Communication Program. The Contractor shall develop, implement, and maintain at the workplace a written, Comprehensive Hazard Communication Program (see Section 06.B.01 of EM 385-1-1) that includes identification of potential hazards as prescribed in 29 CFR Part

1910.1200 and/or 1926.59, effects of exposure and control measures to be used for chemical products and physical agents that may be encountered during the performance of work on this contract, provisions for container labeling, Safety Data Sheets, and employee training program, and other criteria in accordance with 29 CFR Part 1910.1200 and/or 1926.59. Training shall include communication methods and systems to be used (i.e., voice, hand signals, radios or other means), and training in the use and understanding of safety data sheets and chemical product hazard warning labels. Prior to bringing hazardous substances, as defined in 29 CFR 1910.1200 and/or 1926.59, onto the job site, a copy of the Hazard Communication Program and the Safety Data Sheets of each substance shall be submitted to the Contracting Officer and made available to the Contractor's employees as part of its Accident Prevention Program. A site map shall be attached to the inventory showing where the inventoried hazardous substances are stored. The inventory list and site map shall be updated monthly to assure accuracy. The Contractor shall note that “Safety Data Sheets (SDS) has replaced Material Safety Data Sheets (MSDS)” referenced in Section 06.B.01 of EM 385-1-1 meeting the criteria of the new OSHA globally harmonized system.

01100-4

(d) Daily Inspections. The Contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the jobsite in accordance with Section 01 45

04.00 10, "CONTRACTOR QUALITY CONTROL". The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

(1) Phase(s) of construction underway during the inspection.

(2) Locations of areas where inspections were made.

(3) Results of inspections, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

(e) Safety Sign. The Contractor shall furnish, erect, and maintain a safety sign at the site where indicated by the Contracting Officer. The sign shall conform to the requirements of this paragraph and the drawing included at the end of this section. The lettering shall be black, the safety circle and cross green, and the background white. When placed on a floating plant, the sign may be half size.

The sign shall be erected as soon as practicable, but not later than 15 calendar days after the date established for commencement of work. The data required shall be current. The sign coordinator is Mary H. Ferry@ 504.862.2000.

(f) Ground Fault Protection. Electrical equipment used on this contract shall be equipped with ground fault circuit interrupters in accordance with EM 385-1-1, Section 11.D.05.

(g) Haul Roads. Whenever practical, one-way haul roads shall be used on this contract. Haul roads built and maintained for this work shall comply with the following:

(1) One-way haul roads for off-the-road equipment; e.g., belly dumps, scrapers, and off-the-road trucks shall have a minimum usable width of 25-feet. One-way haul roads for over-the- road haulage equipment only (e.g., dump trucks, etc.) may be reduced to a usable width of 15-feet.

When the Contracting Officer determines that it is impractical to obtain the required width for one-way haul roads (e.g., a road on top of a levee), a usable width of not less than 10-feet may be approved by the Contracting Officer, provided a positive means of traffic control is implemented. Such positive means shall be signs, signals, and/or signalmen and an effective means of speed control.

01100-5

(2) Two-way haul roads for off-the-road haulage equipment shall have a usable width of 60-feet. Two-way haul roads for over-the-road haulage equipment only may be reduced to a usable width of 30-feet.

(3) Haul roads shall be graded and otherwise maintained to keep the surface free from potholes, ruts, and similar conditions that could result in unsafe operation.

(4) Grades and curves shall allow a minimum sight distance of 200-feet for one-way roads and 300-feet for two-way roads. Sight distance is defined as the centerline distance an equipment operator (4.5-feet above the road surface) can see an object 4.5-feet above the road surface.

When conditions make it impractical to obtain the required sight distance (e.g., ramps over levees), a positive means of traffic control shall be implemented.

(5) Dust abatement shall permit observation of objects on the roadway at a minimum distance of 300-feet.

(6) Haul roads shall have the edges of the usable portion marked with posts at intervals of 50-feet on curves and 200-feet maximum elsewhere.

Such markers shall extend 6-feet above the road surface and, for nighttime haulage, be provided with reflectors in both directions.

(h) Safety Fence. The Contractor shall provide, erect, and maintain a temporary safety fence around the limits of work. The fabric for the safety fence shall be zinc coated hog wire mesh at least 48 inches high. Posts shall be 3½ inch diameter wood posts (treated or untreated) or steel-T posts that are at least 6½ feet long. Posts shall extend at least 48 inches above ground and shall be spaced at 10 feet on center. Swing gates shall be at least 12 feet wide by 48 inches high. The swing gate frame shall be fabricated of either 1-3/8-inch O.D.

tubular steel, or 1/4-inch angle iron brace with an adjustable brace wire to prevent sagging. Gates shall be fitted with hinges and shall be supported by 1- 3/8- inch O.D. tubular steel posts embedded in 3-feet of concrete. The fabric from the gates shall be the same as that for the fence. All gates shall be closed and padlocked at the end of each work day. When necessary, an owner of a facility located within the limits of work will obtain keys from the levee district. The Contractor shall provide and maintain on the fence "NO TRESPASSING" signs every 100 feet facing out from the work. Details of the safety fencing and location shall be submitted to the Contracting Officer for approval. No separate measurement or payment will be made for this work. Payment for all work associated with the safety fence shall be distributed amongst the existing bid items.

(i) Hurricane Plan. A detailed plan for protection and evacuation of personnel and the construction site, in the event of an impending hurricane or storm, is

01100-6 required as an enclosure to the Contractor's Accident Prevention Program. This plan shall be submitted to the Contracting Officer, or his/her representative, for review and approval prior to the preconstruction conference. The Hurricane Plan shall include at least the following:

(1) The time each phase of the plan will be put in effect. The time shall be the number of hours remaining for the storm to reach the worksite if it continues at the predicted speed and direction.

(2) The estimated time necessary to secure and evacuate the site including any emergency flood protection.

Work being performed to satisfy the Hurricane Plan will not be measured for payment. Payment for all work associated with the Hurricane Plan, and providing the equipment required for the duration specified, shall be distributed amongst the existing bid items.

(j) Handling Sheet Piling: The Contractor’s personnel shall not sit or place themselves on top of the sheet piling during the handling, installation, and removal of the piling.

(k) Cranes. The Contractor (including subcontractors) shall have cage boom guards, insulating links, or proximity warning devices on cranes that will be working adjacent to power lines. These devices shall not alter the requirements of any other regulation of this part - even if such device is required by law or other regulation. Insulating links shall be capable of withstanding a 1-minute dry low frequency dielectric test of 50,000 volts, alternating current (EM 385-1-1, Section 11.F.08). Calibration records or stamped date of required manufacturer inspection of proximity warning devices shall be kept on the crane. Additionally, prior to any work commencing an Activity Hazard Analysis (EM 385-1-1, Fig. 1-1) identifying and satisfying EM 385-1-1, Section 11.A.02, 11.F.03, 11.F.04, 11.F.05, and Table 11-1 requirements shall be submitted and accepted by the Contracting Officer.

(l) Contractor shall employ a competent person at each project to function as the Site Safety and Health Office (SSHO). The SSHO will manage the Contractor’s APP. (This may be a collateral duty responsibility unless specified differently in the contract.) See EM 385-1-1 Appendix A. The person(s), as a minimum, must have completed the 30-hour OSHA Construction Industry safety class (may be web-based training if the student is able to directly ask questions of the instructor by chat/phone), or an equivalent course (See Appendix A, paragraph 3.d.(3)) applicable to the work to be performed and given by qualified instructors. Such training shall have been within the last four (4) years. An SSHO shall be on-duty at all times when work is being performed and shall be responsible for enforcing and implementing the Contractor’s Safety and Health Program in accordance with the accepted APP.

01100-7

(m) In locations where trucks and other equipment will be passing beneath overhead power lines, the contractor shall install at least 2 signs on either side of the crossings warning drivers of the overhead lines. The signs shall face both directions of travel. The signs shall have arrows pointing upward and state 'Overhead Electric'. The contractor shall submit his proposed sign design to the Contracting Officer for approval.

4. INSPECTOR'S FIELD OFFICE

(a) The Contractor shall furnish, throughout the contract period, for the exclusive use of the Government employees, a temporary waterproof building, or trailer, to be utilized as a field office. It shall be conveniently located at the site of construction and shall be independent of any building, or trailer, used by the Contractor. Toilet facilities and potable water, including bottled water with water cooler, shall be provided within the Inspector's office. It shall be equipped with a telephone answering machine, at least three ceiling lamp receptacles, at least three double convenience outlets, and a fax / copier / printer machine. It shall be equipped with the required switches and fuses to provide 110-volt power for lighting and operating a laptop computer and printer. It shall be equipped with an air conditioning unit to provide cooling in warm or hot weather, and a heater, properly installed and vented in accordance with the National Fire Protection Association Code, for heating in cold weather, as required. The Contractor shall make the necessary arrangements to obtain or to generate the power required to operate the air conditioning unit, lights, and laptop computer and printer, and the power or fuel required for the heater, and shall bear the cost thereof. A drafting table providing a working surface having dimensions of at least 4-feet by 6-feet (which may consist of a piece of plywood, at least 3/4-inch thick, hinged to a wall of the building with hinged legs) shall be installed in the building. The building shall have a built-in locker, extending from the floor to the ceiling, having dimensions of at least 2- feet by 5-feet, with a shelf 12-inch from the top, and one door equipped with two hinges, a hasp and a padlock. All exterior doors and window frames of the building shall be equipped with iron security guards. The door shall also be equipped with butt hinges and a cylinder lock. One draftsman's stool, two strong chairs and two desks shall be provided. The building or trailer shall conform to the following minimum requirements:

Ceiling height, not less than 6-feet 9-inches

Floor space, no less than 480 square feet

Windows, not less than 4

Doors, outside 2

Rooms 3

01100-8

Screens over windows; walls and ceilings shall be insulated; and interior walls finished.

(b) The building, or trailer, shall be removed by the Contractor after completion of all work under this contract and before final acceptance thereof. No separate payment will be made for furnishing, maintaining, providing the prescribed utilities, and removing the inspector's field office, but the cost of the same shall be distributed throughout the existing bid items. In the event the Contractor fails to furnish the required facilities, the Government may elect to procure the required facilities and deduct all costs from amounts due or to become due under this contract.

(c) The Contractor shall provide daily janitorial services for this and other buildings at the site throughout the life of the contract. The cost of this service shall be distributed throughout the existing bid items and there shall be no separate payment.

(d) The Contractor shall provide the inspector’s field office with a hard line broadband high speed internet service and associated equipment for the exclusive use of the Government. If this service is not practical at the jobsite, the Contractor may instead provide the inspector’s field office with a cellular wireless Broadband / WiFi 802.11n capable router that accepts cellular data signals through Express Card / Air Card or USB modems. This service must be capable of providing adequate connection to allow the inspectors to import/export files through RMS. The Contractor must field verify that the service provider chosen has adequate continuous coverage at the construction site. This service shall provide a minimum download speed of 10 Mbps and a minimum upload speed of

1.5 Mbps. The Contractor shall be responsible for the installation, the maintenance of, and the monthly service fees necessary to provide continuous high speed internet service for the duration of the contract.

5. PROJECT SIGN

Prior to commencement of work, the Contractor shall construct a project sign at the site of the work at a location directed by the Contracting Officer. The sign, which will identify the work with the Corps of Engineers shall be 4 feet by 6 feet in size and shall conform to the requirements of the PROJECT SIGN drawing and installation instructions attached at the end of this section. The lettering for the 2 feet by 4 feet section of the sign with the Corps logo shall be white; all other lettering shall be black.

Lettering for the project name shall be Helvetica Bold, all other lettering shall be Helvetica Regular. The sign coordinator is Mary H. Ferry @ 504.862.2000. No separate payment will be made for construction and erection of the project sign and all costs in connection therewith will be considered an incidental obligation of the Contractor. Upon completion of the work, the sign shall become the property of the Contractor and shall be removed from the job site.

01100-9

6. RIGHTS-OF-WAY

(a) The rights of entry required for the work to be constructed under this contract, within the rights-of-way limits indicated on the drawings, have been obtained by the Government and are provided without cost to the Contractor.

The Contractor shall make its own investigations to determine the conditions, restrictions, and difficulties that may be encountered in the transportation of equipment and material to and from the work site. The proposed work, including rights-of-way, as defined by these specifications and as shown on the drawings, is in compliance with all applicable Federal and state environmental laws and regulations. Upon completion of the Contractor’s work, rights-of-way furnished by the Government shall be returned to its original condition prior to construction unless otherwise noted.

(b) If the Contractor proposes a deviation from the Government furnished rights-of-way for his convenience, the Contractor shall notify the Contracting Officer or its representative in writing. Contractor shall not provide any permanent rights-of-way for the project. The Contractor is cautioned that any deviation to the Government furnished rights-of-way is subject to all applicable Federal and state environmental laws and regulations. Compliance with these environmental laws and regulations may require additional National Environmental Policy Act (NEPA) documents, cultural resources surveys, coordination with the Louisiana State Historical Preservation Officer, water quality certification, modification of the Federal consistency determination, etc. The Government is ultimately responsible for environmental compliance; therefore, the Government will determine the additional environmental coordination and documentation necessary for a proposed deviation to the Government furnished rights-of-way.

For any environmental investigations the Government is to perform on areas outside of Government furnished rights-of-way, the Contractor shall provide sufficient rights of entry to the Government. The Contracting Officer will advise the Contractor of the additional environmental coordination and documentation that must be completed. The Government shall be responsible for any additional environmental compliance; however, the Contractor may conduct specific tasks identified by the Government. The Government will offer advice and assistance to the Contractor in conducting these tasks. Depending on the environmental impact of the proposed deviation, obtaining the coordination and documentation may not be approved or could take as much as 180 days for approval by the Government. The Government must review, approve and ensure distribution of all environmental compliance documentation and ensure all comments on the same have been resolved before any utilization of any areas outside of the Government furnished rights-of-way. The Contractor shall reimburse the Government for actual expenses incurred for assistance in completing or attempting to complete additional environmental coordination and documentation, which expenses will not exceed one hundred thousand ($100,000.) dollars. There is no guarantee that environmental compliance will be obtained; therefore, the Contractor shall assume all risks and liabilities

01100-10 associated with pursuing a deviation. Any delays resulting from the deviation and/or the environmental coordination and documentation shall not be made the basis of any Contractor claim for increase in the contract cost and/or increase in contract time. Deviations will be at Contractor’s sole risk and liability, including, but not limited to, such liabilities associated with items such as hazardous substances regulated under the Comprehensive Environmental Response, Compensation, and Liability Act (42 U.S.C. 9601 et. seq.), and at no cost to the Government. Government assistance in obtaining additional environmental clearances does not relieve the Contractor of responsibility for complying with other Federal, state or local licenses and permits.

7. CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in three (3) copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet specified requirements.

8. ENVIRONMENTAL LITIGATION

(a) The term "environmental litigation", as used herein, means a lawsuit alleging that the work has an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

(b) If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If the order is not due in any part to acts or omissions of the Contractor (or a Subcontractor at any tier) other than as required by this contract, such suspension, delay, or interruption shall be as if ordered by the Contracting Officer under the Contract Clause in Section 00700, entitled Suspension of Work (FAR 52.242-14). The period of such suspension, delay or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.

9. UTILITIES AND IMPROVEMENTS

01100-11

(a) All known utilities within the limits of the work, such as pipes, communication lines, power lines, etc., that would interfere with construction work will be removed, modified or relocated by local interests or utility companies at no cost to the Contractor unless otherwise noted in the plans and/or specifications. The Contractor, however, shall cooperate with the authorities or company representatives and shall conduct his/her operations in such manner as to result in a minimum of inconveniences to the owners of said utilities. The Contractor shall notify each utility owner by certified mail 45 days, 15 days, and again 72 hours prior to the date utilities must be moved and provide a copy of these notifications to the Contracting Officer.

(b) The below disposition table (Table 2) is provided for Contractor information and is supplemented by the POC list (Table 1), including the facility owner’s commodity and pipeline nominal size and a disposition summary. Detailed coordination of work for each facility owner, identifying the responsibility of the owner and the Contractor is provided in paragraph entitled SPECIAL WORK REQUIREMENTS of this section.

TABLE 1

OWNERS POINT OF CONTACTS

FACILITY OWNER/

MAILING ADDRESS

COMMODITY

(AND PIPE SIZE)

POC

TELEPHONE

NUMBERS

American Midstream (Louisiana Intrastate), L.L.C.

170 New Camellia Blvd Suite 100 Covington, LA 70433

Two (2) 12-inch Steel Natural Gas Pipelines

Dan Fayard 504-849-2217 (O) dan.fayard@jacobs.com 985-807-8272 (C)

Chalmette Liquids Sulphur River 5949 Sherry Ln Suite 755 Dallas, TX 75225

16-inch Steel Propylene Pipeline

Greg Vujovich 214-373-1091 (O) Ext. 208 gvujovich@sulphurriver.com 214-505-4849 (C)

TABLE 2

FACILITY OWNER DISPOSITION TABLE

OWNER/COMMODITY LOCATION DISPOSITION (SUMMARY)

American Midstream 12" Natural Gas Lines

South of Hwy

Relocation is concurrent with construction. The pipeline remains active and will pass through the floodwall’s sheetpile wall. See paragraphs entitled “VIBRATION

MONITORING”, “SPECIAL WORK REQUIREMENTS”

and “SPECIAL HANDLING OF FOUNDATION PILES, SHEET PILE AND EQUIPMENT WITHIN THE FACILITY

OWNERS’ RIGHTSOF WAY CONTAINING ACTIVE

01100-12

PIPELINES” and drawing entitled “JACKING SHEET

PILE UNDER UTILITIES”.

Chalmette Liquids 16" Propylene Line

South of Hwy 23 Relocation is concurrent with construction. The pipeline remains active and will pass through the floodwall’s sheetpile wall. See paragraphs entitled “VIBRATION

MONITORING”, “SPECIAL WORK REQUIREMENTS”

and “SPECIAL HANDLING OF FOUNDATION PILES, SHEET PILE AND EQUIPMENT WITHIN THE FACILITY

OWNERS’ RIGHTSOF WAY CONTAINING ACTIVE

PIPELINES” and drawing entitled “JACKING SHEET

PILE UNDER UTILITIES”.

(c) Special Requirements regarding vibrations and pile driving for handling of foundation piles are addressed in this section (see paragraphs entitled “VIBRATION MONITORING” and “SPECIAL HANDLING OF FOUNDATION

PILES, SHEET PILE AND EQUIPMENT WITHIN THE FACILITY OWNERS’

RIGHTS-OF WAY CONTAINING ACTIVE PIPELINES”).

(d) Any unidentified pipes or structures which may be found within the limits of the work during the course of construction shall not be disturbed nor shall construction or excavation be performed at these locations unless and until approved by the Contracting Officer.

(e) The Contractor shall verify the location of all facilities with the facility owners and the COR. All known facilities and their POCs are identified above. Facility owners have marked their facilities in the field. However, the Contractor may ask the COR to request from the owners additional field markings for their pipelines.

(f) The Contractor shall provide the COR with a specific work schedule for the floodwall work which shall identify the order of work for facility owners at least 60 days in advance of commencing work in the area of pipelines. Thereby, allowing the facility owners ample time to mobilize their forces to perform the relocation work.

(I) American Midstream.

This facilities are impacted at three separate locations south of Hwy 23, i.e., at the floodwall and at the reconnection locations in the protected and flood sides, as shown on the drawings. The pipeline generally runs perpendicular to Hwy 23 throughout the project area, from the Pipeline Canal, perpendicularly underneath the existing levee, and continues beyond our project limits to the northeast. The owner has agreed to coordinate with the contractor for the pipe sleeve installation at the

01100-13 floodwall sheetpile as shown in the drawings. See paragraphs entitled “VIBRATION MONITORING”, “SPECIAL WORK REQUIREMENTS” and

“SPECIAL HANDLING OF FOUNDATION PILES, SHEET PILE AND

EQUIPMENT WITHIN THE FACILITY OWNERS’ RIGHTS-OF WAY

CONTAINING ACTIVE PIPELINES” and drawing entitled “JACKING

SHEET PILE UNDER UTILITIES”.

(2) Chalmette Liquids.

This facilities are impacted at three separate locations south of Hwy 23, i.e., at the floodwall and at the reconnection locations in the protected and flood sides, as shown on the drawings. The pipeline generally runs perpendicular to Hwy 23 throughout the project area, from the Pipeline Canal, perpendicularly up and over the existing levee, and continues beyond our project limits to the northeast. The owner has agreed to coordinate with the contractor for the pipe sleeve installation at the floodwall sheetpile as shown in the drawings. See paragraphs entitled “VIBRATION MONITORING”, “SPECIAL WORK REQUIREMENTS” and

“SPECIAL HANDLING OF FOUNDATION PILES, SHEET PILE AND

EQUIPMENT WITHIN THE FACILITY OWNERS’ RIGHTS-OF WAY

CONTAINING ACTIVE PIPELINES” and drawing entitled “JACKING

SHEET PILE UNDER UTILITIES”.

10. PERMISSIBLE HOURS OF WORK

When the Contractor elects to work weekends, holidays, and nights, notice shall be given to the Contracting Officer, in writing, 36 hours in advance of commencement of such operations to permit suitable arrangements for inspections to be made.

Adequate lighting for safe operation and thorough inspection of night operations shall be provided by the Contractor at his/her own expense. However, no pile driving or extracting operations shall be performed between the hours of 9:00 p.m. and 6:00 a.m.

11. U.S. ARMY CORPS OF ENGINEERS CRD-C STANDARDS

CRD-C standards can be found at the following case sensitive address:

www.wes.army.mil/SL/MTC/handbook/handbook.htm

01100-14

12. AGGREGATE SOURCES

(a) Concrete aggregates meeting the quality requirements of these specifications have been produced from the sources listed below:

3 December 2012

PRODUCER NEAREST TOWN TO PIT* TYPE PIT DESIGNATION

B. & M. B., Inc. Jackson, LA S, G Dudley Pit

B. & M. B., Inc. Wakefield, LA S, G Island Pit

B. & M. B., Inc. Jackson, LA S, G Thompson Pit

Barriere’s Construction Co., LLC Arcola, LA S, G Ponder Pit

Bayou Sand and Gravel, LLC Amite, LA S, G Bayou Sand and Gravel

Blain Sand & Gravel, Inc. Georgetown, MS S, G Bailey Pit

Bunch Gravel Co. Clinton, LA G Bunch Gravel Plant #1

Bunch Gravel Co. Darlington, LA S, G Bunch Gravel Plant #2

DK Aggregates, LLC Nicholson, MS S, G DK Aggregates Pit

Fleniken Sand & Gravel Co. Grangeville, LA S, G Flen-Rock Pit (Spears Lease)

Irv Daniel Wakefield, LA S, G Island Pit

Lafarge North America Pearl River, LA S, G Honey Island Operation

Lafarge North America Sun, LA S, G Isabel Plant

Martin Marietta Aggregates Smithland, KY LS Three Rivers Quarry

Mears Sand & Gravel Co. Watson, LA S, G Penny & Easterly Lease

Norris Springs Gravel Sicily Island, LA S, G Norris Springs Gravel Pit

Pine Bluff Sand & Gravel Co. Delaware, AR SS River Mountain Quarry

Southern Aggregates, LLC Watson, LA S, G Glaciel Lease

Southern Aggregates, LLC Watson, LA S, G Mullins Lease

Southern Aggregates, LLC Watson, LA S, G Weyerhauser Lease

Southern Aggregates Watson, LA S, G Clemons Plant

Standard Gravel Co., Inc. Hattiesburg, MS S Plant 63

Standard Gravel Co., Inc. Hattiesburg, MS S Plant 80

Standard Gravel Co. Enon, LA S, G Enon Pit (C-10 & CZ-30 leases)

Standard Gravel Co. Franklinton, LA G Green Lakes Plant

Standard Gravel Co. Pearl River, LA S, G Mitchell - 11 Plant

Standard Gravel Co. Pearl River, LA S, G Nicholson Plant (Nic-9)

Texas Industries, Inc. Perryville, LA S, G Perryville Plant

Texas Industries, Inc. Woodworth, LA S, G Woodworth Plant

Tower Rock Stone Co. Scott City, MO LS Grays Point Quarry

Trinity Materials, Inc DeRidder, LA S, G Anacoco Creek Plant

Vulcan Materials Co. Lake City, KY LS Grand Rivers Quarry

Warren Paving Co. Salem, KY LS Slats Lucas Quarry

01100-15

Type:

G = Gravel LS = Limestone S = Sand SS = Sandstone

*“Nearest Town to Pit” according to LDOTD Official State Highway Map and Rand McNally Road Atlas copyrighted 2010.

(b) Concrete aggregates may be furnished from any of the above listed sources or at the option of the Contractor may be furnished from any other source designated by the Contractor and approved by the Contracting Officer, subject to the conditions hereinafter stated and as specified in Section 03 31 00.00 12.

(c) After the award of the contract, the Contractor shall designate in writing only one source or one combination of sources from which he/she proposes to furnish aggregates. If the Contractor proposes to furnish aggregates from a source or from sources not listed above, he/she may designate only a single source or single combination of sources of aggregates. If a source for coarse and/or fine aggregate so designated by the Contractor is not approved for use by the Contracting Officer, the Contractor may not submit for approval other sources but shall furnish the coarse and/or fine aggregate, as the case may be, from a source listed above at no additional cost to the Government.

(d) The listings of the names of the aggregate suppliers do not constitute an endorsement of such companies. Approval of a source of concrete aggregate is not to be construed as approval of all material from that source. The right is reserved to reject materials from certain localized areas, zones, strata, or channels, when such materials do not conform to the quality requirements of ASTM C 33-2011, Concrete Aggregates. Aggregate gradations shall be in accordance with the specified requirements of Section 03 31 00.00 12. Materials produced from any source, including those listed above, shall also meet all the requirements of Section 03 31 00.00 12 of the Technical Specifications.

(e) It is the Contractor's responsibility to determine that the aggregate source or combination of sources selected is capable of supplying the quantities and gradations needed and at the rates needed to maintain the scheduled progress of the work. The inability of a source or combination of sources to maintain the necessary volume shall not be the basis for any claim for a time extension.

13. CLAY SOURCES

(a) On the basis of information and data available to the Contracting Officer, the lands containing the clay sources from the sites designated below have been studied by the Government for environmental concerns and soil suitability. The designated sites, below, may be capable of producing the quality of clay material meeting the requirements set forth in Section 31 24 00.00 12, paragraph entitled “MATERIALS”, including the salinity requirements set forth in Section 31 23

00.00 12, paragraph entitled “Borrow Area Agronomy Report”, and are subject to

01100-16 the subparagraphs (b) through (e) below. However, some documentation relating to the below sites may need to be updated prior to their use. The Contractor is responsible for submitting a complete Borrow Submittal for Corps review and approval with all applicable updated documentation. See Section 31 23 00.00 12, paragraph entitled "Submittal Package Requirements in Detail".

March 2014

Site Name Point of Contact

Contact Information Location

River Birch, Phase 1 Vic Culpepper Office: 504-436-1288 Avondale, LA

Cell: 504-915-6006

River Birch, Phase 2 Vic Culpepper Office: 504-436-1288 Avondale, LA

Pearlington Dirt Johnny Dollar Cell: 318-366-8218 Pearlington, MS jdollar.chapel.hill@gmail.com

Diaz Property (DK Aggregates)

Philip Callahan 504-450-6702 St. Bernard Parish, LA philcallahan@cox.net

Eastover Jerry Howell Cell: 504-559-1606 New Orleans, LA jerryhowell992@hotmail.com

St. Gabriel Michael Daigle Office: 225-216-7483 Carville, LA mdaigle@trcsolutions.com

*1025 Florissant Michael Palmer Cell: 504-812-8016 St. Bernard Parish, LA palmertruckin@yahoo.com

Acosta Amanda Phillips Office: 985-626-5204 St. Bernard Parish, LA gsdi@bellsouth.net