Casting Articulated Concrete Mattress, St. Fracisville Casting Field, Louisiana
Solicitation number
W912P8-16-B-0028
Issued by

About this file

W912P8-16-B-0028 Amendment 0001

View the file

Other files

File Type Posted
B01_-_16B0028BIDABSTRACT.pdf PDF
16B0028BIDABSTRACT.pdf PDF
A22_-_W912P8-16-B-0028.pdf PDF
H01_-_drawings _signed.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The above numbered solicitation for casting articulated concrete mattress, St. Francisville Casting Field, Louisiana, is amended to answ er questions, how ever, no changes to the specifications are made.

Bid opening date of Wednesday, 4 May 2016, 2pm CST, remains unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 13-Apr-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P8-16-B-0028

X 9B. DATED (SEE ITEM 11)

04-Apr-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Apr-2016

CODE

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT, ROOM 172

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

Casting Articulated Concrete Mattress, St. Francisville Casting Field, Louisiana Solicitation Number: W912P8-16-B-0028 Agency: Department of the Army Office: U.S. Army Corps of Engineers Location: USACE District, New Orleans

Questions:

Page C1-9, Paragraph 7.5.4 Coarse Aggregates and Paragraph 7.5.4.1 Storage of Coarse Aggregates the contract states the following- “Material from different aggregate sources shall be stockpiled separately.”

Q: Will the contractor have to stockpile aggregate from similar sources separately, the sources we utilize are delivering coarse aggregate that is similar in specific gravity and water absorption, is it the intent to separate stockpiles based on different types of coarse aggregate (i.e. crushed stone, washed gravel, sandstone) or is it based on different suppliers?

In accordance with Page C1-9, Paragraph 7.5.4, coarse aggregate (i.e. crushed stone, washed gravel, sandstone) shall be stockpiled separately from different aggregate sources. Coarse aggregate that is similar in specific gravity and water absorption maybe stockpiled together.

NOTE: The Contractor is responsible for providing specific gravity and water absorption test results proving the aggregates are similar.

Page C1-14, Paragraph 8.12.1 Concrete Mixers Q: Will a uniformity test be required and at what cost does the government propose for that test?

Yes, tests are required if the Contractor proposes to reduce the mixing time. The Government will not compensate the Contractor for any expense associated with assisting the Government personnel in conducting the uniformity tests for either manpower, equipment or materials.

When the contractor proposes to reduce the mixing time, uniformity tests at the reduced mixing time will be made by the Government at Contractor’s expense to determine whether the reduced mixing time meets the requirements of the specifications. The Government will not compensate the Contractor for any expenses, such as manpower, equipment or materials associated with assisting Government personnel in conducting the uniformity tests.

Page C1-16, Paragraph 9.1.2 Articulated Concrete Mattress Q: If the contractor is required to utilize a government supplied mix design how are we (the contractor) going to be held accountable if the concrete does not meet 3,000 psi threshold at 90 days? What consequence will the contractor bare if the concrete does not meet the 3,000 psi requirement? As you are aware the 30,000 mats to be poured this contract will be completed well before the 90 day breaks.

Under Paragraph 1(f), Page E-2, the Government will require correction of nonconforming supplies.

Page C1-17, Paragraph 9.1.3.6 Slump Q: Will there be any latitude for individual batches to get the slump in the specified range? With concrete it is difficult to forecast the slump on the first few batches of the casting day.

The maximum allowable variation in the slump is stated on Page C1-14, Paragraph 8.12.1

Page C2-4, Paragraph 3.1.2 Drainage Ditch Maintenance Q: Are the slopes going to be stabilized before the condition is transferred to the contractor?

By 5 May 2016, ditches will be pumped dry and grass will be planted on the slopes.