Bid_Abstract_28_Oct_10.pdf
PDF 297 KB Posted
- Solicitation number
- W912P8-10-B-0079
About this file
Bid Abstract under W912P8-10-B-0079
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NO. 2. DATE ISSUED 3. DATE OPENED
10/27/2010
4. ISSUING OFFICE I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
DISTRICT ENGINEER
USACE, HURRICANE PROTECTION OFFICE SIGNATURE
7400 LEAKE AVE.
NEW ORLEANS, LA 70118 Jason Meyers, BID OPENING OFFICER
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE
(CHECK A, B, OR C AND COMPLETE
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
Quality Trust Inc., Healtheon, INC. Benetech David Boland, Inc K & K Industries, Inc.
A. HIRED LABOR 133 East Home Street 201 St Charles Ave Suite 4310 915 S. White Street P.O. Box 1870 4996 State Highway M-117
Junction City, KS 66441 New Orleans, LA 70170 New Orleans, LA 70125 Titusville, FL 32781-1870 Newberry, MI 49868
B. REASONABLE CONTRACT B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY
(WITHOUT PROFIT) Yes Yes Yes Yes
C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED
(INCLUDING PROFIT) Yes Yes Yes Yes Yes
6. NUMBER OF ADDENDA ISSUED LB LB LB LB LB
7A. ITEM NO. 7B. DESCRIPTION OF OFFERED ITEM 7C. EST QTY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT
0100 Mobilization and Demobilization 1 LS 129,355.00$ 129,355.00$ 125,000.00$ 185,000.00$ 119,254.00$ 119,254.00$ 255,750.15$ 255,750.15$ 2,000.00$ 2,000.00$ 901,365.00$ 901,365.00$
0101 Selective Demolition 1 LS 125,598.00$ 125,598.00$ 180,000.00$ 208,000.00$ 266,436.00$ 266,436.00$ 39,133.43$ 39,133.43$ 180,000.00$ 180,000.00$ 264,500.00$ 264,500.00$
0102 Sitework 1 LS 7,125.00$ 7,125.00$ 60,000.00$ 73,000.00$ 34,536.00$ 34,536.00$ 4,569.40$ 4,569.40$ 15,000.00$ 15,000.00$ 50,225.10$ 50,225.10$
0105 Architectural work 1 LS 207,969.00$ 207,969.00$ 45,000.00$ 54,000.00$ 143,184.20$ 143,184.20$ 255,474.49$ 255,474.49$ 250,000.00$ 250,000.00$ 181,782.80$ 181,782.80$
0106 Roof System 1 LS 601,780.00$ 601,780.00$ 275,000.00$ 307,000.00$ 716,077.40$ 716,077.40$ 361,149.05$ 361,149.05$ 491,000.00$ 491,000.00$ 576,480.05$ 576,480.05$
0107 Removable Flood Barriers 1 LS 63,669.00$ 63,669.00$ 22,000.00$ 28,000.00$ 32,250.00$ 32,250.00$ 35,438.45$ 35,438.45$ 60,000.00$ 60,000.00$ 38,646.00$ 38,646.00$
0108 Structural steel 1 LS 121,558.00$ 121,558.00$ 52,000.00$ 79,000.00$ 819,776.00$ 819,776.00$ 332,825.33$ 332,825.33$ 316,000.00$ 316,000.00$ 509,437.90$ 509,437.90$
0109 Steel Decking 1 LS 158,754.00$ 158,754.00$ 158,000.00$ 188,000.00$ 78,137.00$ 78,137.00$ 120,025.98$ 120,025.98$ 148,000.00$ 148,000.00$ 126,611.98$ 126,611.98$
0110 Cast-in-place Concrete 1 LS 2,180.00$ 2,180.00$ 235,000.00$ 279,000.00$ 47,942.00$ 47,942.00$ 12,077.80$ 12,077.80$ 14,000.00$ 14,000.00$ 2,551.54$ 2,551.54$
Reinforcing steel for existing masonry walls (installation) 1 LS 3,981,465.00$ 3,981,465.00$ 4,852,000.00$ 5,000,000.00$ 2,130,568.00$ 2,130,568.00$ 2,576,195.60$ 2,576,195.60$ 2,586,000.00$ 2,586,000.00$ 1,809,700.00$ 1,809,700.00$
0111A
Reinforcing steel for existing masonry walls (material) 31,990 LF 37.00$ 1,183,630.00$ 591,000.00$ 698,000.00$ 87.10$ 2,786,329.00$ 60.53$ 1,936,354.70$ 75.50$ 2,415,245.00$ 70.32$ 2,249,664.76$
Grouting and spiral wall ties for existing masonry walls (installation) 1 LS 708,060.00$ 708,060.00$ 442,000.00$ 492,000.00$ 762,314.00$ 762,314.00$ 700,145.26$ 700,145.26$ 827,000.00$ 827,000.00$ 642,855.87$ 642,855.87$
0112A
Grouting and spiral ties for existing masonry walls (material) 14,462 SF 73.00$ 1,055,726.00$ 246,000.00$ 285,000.00$ 42.88$ 620,130.56$ 38.97$ 563,584.14$ 37.00$ 535,094.00$ 36.16$ 522,945.92$
113 Masonry cleaning 1 LS 98,611.00$ 98,611.00$ 80,000.00$ 92,000.00$ 169,925.00$ 169,925.00$ 31,911.82$ 31,911.82$ 95,000.00$ 95,000.00$ 126,379.20$ 126,379.20$
Masonry restoration (square foot of wall area) 2,980 SF 13.00$ 38,740.00$ 22,000.00$ 29,000.00$ 244.70$ 729,206.00$ 9.70$ 28,906.00$ 27.90$ 83,142.00$ 19.34$ 57,633.20$
115 Plumbing System 1 LS 131,482.00$ 131,482.00$ 155,000.00$ 179,000.00$ 181,344.00$ 181,344.00$ 365,743.63$ 365,743.63$ 308,000.00$ 308,000.00$ 62,737.60$ 62,737.60$
116 Fuel Storage and Piping System 1 LS 79,834.00$ 79,834.00$ 135,000.00$ 167,000.00$ 227,020.00$ 227,020.00$ 83,756.59$ 83,756.59$ 166,000.00$ 166,000.00$ 102,095.50$ 102,095.50$
117 Ventilation System 1 LS 59,446.00$ 59,446.00$ 43,000.00$ 55,000.00$ 152,253.00$ 152,253.00$ 111,977.16$ 111,977.16$ 159,000.00$ 159,000.00$ 52,545.00$ 52,545.00$
118 Power System Analysis 1 LS 14,242.00$ 14,242.00$ 14,000.00$ 19,000.00$ 17,317.00$ 17,317.00$ 3,210.27$ 3,210.27$ 4,000.00$ 4,000.00$ 15,820.00$ 15,820.00$
House Generator and Transfer
Switch 1 LS 118,254.00$ 118,254.00$ 60,000.00$ 71,000.00$ 200,410.00$ 200,410.00$ 56,198.50$ 56,198.50$ 116,000.00$ 116,000.00$ 69,000.00$ 69,000.00$
Grounding and Lightning
Protection Systems 1 LS 22,721.00$ 22,721.00$ 19,000.00$ 25,000.00$ 23,479.00$ 23,479.00$ 8,092.52$ 8,092.52$ 10,000.00$ 10,000.00$ 21,850.00$ 21,850.00$
Electrical Distribution Systems
(Under 600-volts) 1 LS 391,035.00$ 391,035.00$ 302,000.00$ 319,000.00$ 373,180.00$ 373,180.00$ 351,991.81$ 351,991.81$ 469,000.00$ 469,000.00$ 347,300.00$ 347,300.00$
122 Lead paint abatement 1 LS 17,178.00$ 17,178.00$ 25,000.00$ 27,000.00$ 33,985.00$ 33,985.00$ 34,432.70$ 34,432.70$ 76,000.00$ 76,000.00$ 115,000.00$ 115,000.00$
Flood Damaged Raw Water Piping
Replacement DPS 19 1 LS 212,741.00$ 212,741.00$ 24,000.00$ 28,000.00$ 125,065.00$ 125,065.00$ 81,657.07$ 81,657.07$ 50,000.00$ 50,000.00$ 26,220.00$ 26,220.00$
9,531,153.00$ 8,887,000.00$ 10,790,118.16$ 8,350,601.85$ 9,375,481.00$ 8,873,347.42$
(Option) Mobilization and Demobilization 1 LS 163,402.00$ 163,402.00$ 125,000.00$ 148,000.00$ 112,457.00$ 112,457.00$ 77,871.61$ 77,871.61$ 26,000.00$ 26,000.00$ 186,047.00$ 186,047.00$
(Option) Selective Demolition 1 LS 51,477.00$ 51,477.00$ 165,000.00$ 188,000.00$ 96,869.00$ 96,869.00$ 20,391.51$ 20,391.51$ 58,000.00$ 58,000.00$ 146,050.00$ 146,050.00$
(Option) Sitework 1 LS 28,385.00$ 28,385.00$ 55,000.00$ 74,000.00$ 113,452.00$ 113,452.00$ 49,038.18$ 49,038.18$ 117,000.00$ 117,000.00$ 70,601.95$ 70,601.95$
(Option) Steel Pipe Piles 459 LF 75.00$ 34,425.00$ 114,000.00$ 148,000.00$ 108.00$ 49,572.00$ 37.15$ 17,051.85$ 72.00$ 33,048.00$ 137.80$ 63,250.20$
(Option) Rigid Pavement 1 LS 23,576.00$ 23,576.00$ 102,000.00$ 114,000.00$ 16,926.00$ 16,926.00$ 2,529.00$ 2,529.00$ 3,000.00$ 3,000.00$ 23,494.50$ 23,494.50$
(Option) Flexible Pavement 1 LS 15,041.00$ 15,041.00$ 72,000.00$ 87,000.00$ 35,685.00$ 35,685.00$ 11,064.36$ 11,064.36$ 21,000.00$ 21,000.00$ 55,823.30$ 55,823.30$
(Option) Architectural work 1 LS 137,799.00$ 137,799.00$ 25,000.00$ 29,000.00$ 143,024.00$ 143,024.00$ 247,129.29$ 247,129.29$ 104,000.00$ 104,000.00$ 213,644.70$ 213,644.70$
(Option) Roof System 1 LS 284,965.00$ 284,965.00$ 245,000.00$ 291,000.00$ 354,029.00$ 354,029.00$ 169,462.30$ 169,462.30$ 189,000.00$ 189,000.00$ 263,614.50$ 263,614.50$
(Option) Removable Flood Barriers 1 LS 39,472.00$ 39,472.00$ 22,000.00$ 26,000.00$ 30,392.00$ 30,392.00$ 38,740.21$ 38,740.21$ 24,000.00$ 24,000.00$ 24,215.90$ 24,215.90$
(Option) Structural steel 1 LS 103,533.00$ 103,533.00$ 48,000.00$ 59,000.00$ 522,192.00$ 522,192.00$ 217,325.27$ 217,325.27$ 96,000.00$ 96,000.00$ 320,439.75$ 320,439.75$
(Option) Steel Decking 1 LS 75,322.00$ 75,322.00$ 110,000.00$ 131,000.00$ 33,149.00$ 33,149.00$ 52,641.45$ 52,641.45$ 52,000.00$ 52,000.00$ 53,714.55$ 53,714.55$
(Option) Cast-in-place Concrete 1 LS 28,545.00$ 28,545.00$ 205,000.00$ 219,000.00$ 59,508.00$ 59,508.00$ 28,068.87$ 28,068.87$ 51,000.00$ 51,000.00$ 5,602.54$ 5,602.54$
(Option)
Reinforcing steel for existing masonry walls (installation) 1 LS 993,188.00$ 993,188.00$ 3,920,000.00$ 4,100,000.00$ 531,444.00$ 531,444.00$ 513,371.10$ 513,371.10$ 480,000.00$ 480,000.00$ 504,664.78$ 504,664.78$ 0212A
(Option)
Reinforcing steel for existing masonry walls (material) 7,980 LF 37.00$ 295,260.00$ 249,000.00$ 268,000.00$ 88.44$ 705,751.20$ 70.79$ 564,904.20$ 69.00$ 550,620.00$ 72.07$ 575,118.60$
(Option)
Grouting and spiral wall ties for existing masonry walls (installation) 1 LS 320,199.00$ 320,199.00$ 1,735,000.00$ 2,200,000.00$ 550,306.00$ 550,306.00$ 507,119.96$ 507,119.96$ 475,000.00$ 475,000.00$ 471,020.00$ 471,020.00$ 0213A
(Option)
Grouting and spiral ties for existing masonry walls (material) 6,540 SF 73.00$ 477,420.00$ 129,000.00$ 139,000.00$ 44.22$ 289,198.80$ 40.28$ 263,431.20$ 34.50$ 225,630.00$ 35.76$ 233,870.40$
(Option) Masonry cleaning 1 LS 46,327.00$ 46,327.00$ 89,000.00$ 98,000.00$ 74,767.00$ 74,767.00$ 19,451.74$ 19,451.74$ 36,000.00$ 36,000.00$ 61,623.42$ 61,623.42$
(Option)
Masonry restoration (square foot of wall area) 1,400 SF 13.00$ 18,200.00$ 18,000.00$ 27,000.00$ 244.70$ 342,580.00$ 10.04$ 14,056.00$ 32.70$ 45,780.00$ 28.25$ 39,550.00$
(Option) Plumbing System 1 LS 89,580.00$ 89,580.00$ 149,000.00$ 189,000.00$ 101,466.00$ 101,466.00$ 182,889.13$ 182,889.13$ 79,000.00$ 79,000.00$ 50,550.55$ 50,550.55$
ABSTRACT OF OFFERS-CONSTRUCTION
W912P8-10-B-0079
Storm Proofing Drainage Pump Station No. 1,2,4,12,19 & I-
10, Storm Proofing Interior Pump Station OSP-08, Orleans
Parish, LA
Bid Items for DPS #2 Pump Station Site (All work at DPS#2 is an “Option” )
Bid Items for DPS#1 Pump Station Site (All work at DPS#1 plus item 0517 in DPS#19 is base bid)
TOTAL BASE BID ITEMS
4. ISSUING OFFICE I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
DISTRICT ENGINEER
USACE, HURRICANE PROTECTION OFFICE SIGNATURE
7400 LEAKE AVE.
NEW ORLEANS, LA 70118 Jason Meyers, BID OPENING OFFICER
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE
(CHECK A, B, OR C AND COMPLETE
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
Quality Trust Inc., Healtheon, INC. Benetech David Boland, Inc K & K Industries, Inc.
A. HIRED LABOR 133 East Home Street 201 St Charles Ave Suite 4310 915 S. White Street P.O. Box 1870 4996 State Highway M-117
Junction City, KS 66441 New Orleans, LA 70170 New Orleans, LA 70125 Titusville, FL 32781-1870 Newberry, MI 49868
B. REASONABLE CONTRACT B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY
(WITHOUT PROFIT) Yes Yes Yes Yes
C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED
(INCLUDING PROFIT) Yes Yes Yes Yes Yes
6. NUMBER OF ADDENDA ISSUED LB LB LB LB LB
7A. ITEM NO. 7B. DESCRIPTION OF OFFERED ITEM 7C. EST QTY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT
ABSTRACT OF OFFERS-CONSTRUCTION
W912P8-10-B-0079
Storm Proofing Drainage Pump Station No. 1,2,4,12,19 & I-
10, Storm Proofing Interior Pump Station OSP-08, Orleans
Parish, LA
(Option) Ventilation System 1 LS 26,246.00$ 26,246.00$ 50,000.00$ 57,000.00$ 112,831.00$ 112,831.00$ 51,241.47$ 51,241.47$ 93,000.00$ 93,000.00$ 91,982.00$ 91,982.00$
(Option) Power System Analysis 1 LS 8,245.00$ 8,245.00$ 9,000.00$ 11,000.00$ 11,122.00$ 11,122.00$ 3,217.39$ 3,217.39$ 3,000.00$ 3,000.00$ 10,170.00$ 10,170.00$
(Option)
House Generator and Transfer
Switch 1 LS 150,163.00$ 150,163.00$ 80,000.00$ 96,000.00$ 208,423.00$ 208,423.00$ 71,304.70$ 71,304.70$ 62,000.00$ 62,000.00$ 90,400.00$ 90,400.00$
(Option) Grounding Systems 1 LS 2,212.00$ 2,212.00$ 5,000.00$ 9,000.00$ 6,179.00$ 6,179.00$ 8,207.03$ 8,207.03$ 8,000.00$ 8,000.00$ 5,650.00$ 5,650.00$
(Option)
Electrical Distribution Systems
(Under 600-volts) 1 LS 362,157.00$ 362,157.00$ 258,000.00$ 289,000.00$ 318,810.00$ 318,810.00$ 236,303.73$ 236,303.73$ 266,000.00$ 266,000.00$ 291,540.00$ 291,540.00$
(Option) Lead paint abatement 1 LS 27,002.00$ 27,002.00$ 25,000.00$ 34,000.00$ 33,985.00$ 33,985.00$ 21,530.65$ 21,530.65$ 118,000.00$ 118,000.00$ 84,750.00$ 84,750.00$
3,802,141.00$ 9,031,000.00$ 4,854,118.00$ 3,388,342.20$ 3,216,078.00$ 3,937,388.64$
(Option) Mobilization and Demobilization 1 LS 108,262.00$ 108,262.00$ 125,000.00$ 148,000.00$ 111,098.00$ 111,098.00$ 52,278.78$ 52,278.78$ 1,000.00$ 1,000.00$ 148,212.00$ 148,212.00$
301 (Option) Selective Demolition 1 LS 48,781.00$ 48,781.00$ 52,000.00$ 59,000.00$ 57,789.00$ 57,789.00$ 16,744.57$ 16,744.57$ 79,000.00$ 79,000.00$ 50,370.00$ 50,370.00$
302 (Option) Sitework 1 LS 8,539.00$ 8,539.00$ 33,000.00$ 38,000.00$ 81,885.00$ 81,885.00$ 2,977.93$ 2,977.93$ 26,000.00$ 26,000.00$ 81,420.00$ 81,420.00$
305 (Option) Architectural work 1 LS 31,168.00$ 31,168.00$ 15,000.00$ 28,000.00$ 64,871.00$ 64,871.00$ 114,797.30$ 114,797.30$ 96,000.00$ 96,000.00$ 128,166.35$ 128,166.35$
306 (Option) Roof system 1 LS 72,613.00$ 72,613.00$ 125,000.00$ 152,000.00$ 158,686.00$ 158,686.00$ 76,403.24$ 76,403.24$ 76,000.00$ 76,000.00$ 92,189.75$ 92,189.75$
307 (Option) Removable Flood Barriers 1 LS 35,566.00$ 35,566.00$ 7,500.00$ 12,500.00$ 29,924.00$ 29,924.00$ 23,320.26$ 23,320.26$ 25,000.00$ 25,000.00$ 27,572.00$ 27,572.00$
308 (Option) Structural steel 1 LS 48,531.00$ 48,531.00$ 58,000.00$ 75,000.00$ 251,614.00$ 251,614.00$ 151,010.68$ 151,010.68$ 88,000.00$ 88,000.00$ 166,429.79$ 166,429.79$
309 (Option) Steel Decking 1 LS 21,263.00$ 21,263.00$ 78,000.00$ 98,000.00$ 6,305.00$ 6,305.00$ 21,687.85$ 21,687.85$ 16,000.00$ 16,000.00$ 15,332.97$ 15,332.97$
310 (Option) Cast-in-place Concrete 1 LS 37,054.00$ 37,054.00$ 72,000.00$ 86,000.00$ 26,601.00$ 26,601.00$ 26,553.21$ 26,553.21$ 28,000.00$ 28,000.00$ 7,374.38$ 7,374.38$
311 (Option)
Reinforcing steel for existing masonry walls (installation) 1 LS 803,512.00$ 803,512.00$ 295,000.00$ 336,000.00$ 415,394.00$ 415,394.00$ 420,844.15$ 420,844.15$ 390,000.00$ 390,000.00$ 395,500.00$ 395,500.00$ 311A
(Option)
Reinforcing steel for existing masonry walls (material) 3,990 LF 60.00$ 239,400.00$ 88,000.00$ 102,000.00$ 91.12$ 363,568.80$ 75.80$ 302,442.00$ 71.00$ 283,290.00$ 76.84$ 306,591.60$
312 (Option)
Grouting for existing masonry walls
(installation) 1 LS 258,607.00$ 258,607.00$ 72,000.00$ 81,000.00$ 356,247.00$ 356,247.00$ 249,461.25$ 249,461.25$ 323,000.00$ 323,000.00$ 300,421.80$ 300,421.80$ 312A
(Option)
Grouting for existing masonry walls
(material) 5,282 SF 73.00$ 385,586.00$ 92,000.00$ 98,000.00$ 46.90$ 247,725.80$ 104.64$ 552,708.48$ 36.50$ 192,793.00$ 39.55$ 208,903.10$
313 (Option) Plumbing System 1 LS 40,854.00$ 40,854.00$ 147,000.00$ 159,000.00$ 86,186.00$ 86,186.00$ 116,499.59$ 116,499.59$ 76,000.00$ 76,000.00$ 39,346.60$ 39,346.60$
314 (Option) Ventilation System 1 LS 7,127.00$ 7,127.00$ 50,000.00$ 55,000.00$ 62,533.00$ 62,533.00$ 32,884.66$ 32,884.66$ 35,000.00$ 35,000.00$ 17,967.00$ 17,967.00$
315 (Option) Power System Analysis 1 LS 14,242.00$ 14,242.00$ 14,000.00$ 19,000.00$ 17,300.00$ 17,300.00$ 3,445.17$ 3,445.17$ 3,000.00$ 3,000.00$ 15,820.00$ 15,820.00$
316 (Option)
House Generators and Transfer
Switches 1 LS 133,572.00$ 133,572.00$ 70,000.00$ 79,000.00$ 192,572.00$ 192,572.00$ 76,517.50$ 76,517.50$ 57,000.00$ 57,000.00$ 79,100.00$ 79,100.00$
317 (Option) Grounding Systems 1 LS 2,212.00$ 2,212.00$ 5,000.00$ 9,000.00$ 6,179.00$ 6,179.00$ 5,544.16$ 5,544.16$ 5,000.00$ 5,000.00$ 5,650.00$ 5,650.00$
318 (Option)
Electrical Distribution System
(Over 600-volts) 1 LS 80,141.00$ 80,141.00$ 10,000.00$ 12,500.00$ 224,897.00$ 224,897.00$ 48,145.49$ 48,145.49$ 54,000.00$ 54,000.00$ 11,300.00$ 11,300.00$
319 (Option)
Electrical Distribution Systems
(Under 600-volts) 1 LS 268,789.00$ 268,789.00$ 291,000.00$ 321,000.00$ 37,071.00$ 37,071.00$ 55,411.58$ 55,411.58$ 172,000.00$ 172,000.00$ 328,830.00$ 328,830.00$
320 (Option) Lead paint abatement 1 LS 8,710.00$ 8,710.00$ 25,000.00$ 29,000.00$ 33,985.00$ 33,985.00$ 8,233.91$ 8,233.91$ 17,000.00$ 17,000.00$ 90,400.00$ 90,400.00$
2,654,529.00$ 1,997,000.00$ 2,832,431.60$ 2,357,911.76$ 2,043,083.00$ 2,516,897.34$
(Option) Mobilization and Demobilization 1 LS 163,402.00$ 163,402.00$ 12,500.00$ 148,000.00$ 111,098.00$ 111,098.00$ 42,168.67$ 42,168.67$ 28,000.00$ 28,000.00$ 148,212.00$ 148,212.00$
401 (Option) Selective Demolition 1 LS 20,872.00$ 20,872.00$ 162,000.00$ 182,000.00$ 73,670.00$ 73,670.00$ 6,595.44$ 6,595.44$ 46,000.00$ 46,000.00$ 55,384.00$ 55,384.00$
402 (Option) Sitework 1 LS 2,819.00$ 2,819.00$ 60,000.00$ 69,000.00$ 62,769.00$ 62,769.00$ 3,274.66$ 3,274.66$ 25,000.00$ 25,000.00$ 24,489.25$ 24,489.25$
403 (Option) Steel Pipe Piles 558 LF 73.00$ 40,734.00$ 129,000.00$ 148,000.00$ 101.96$ 56,893.68$ 120.29$ 67,121.82$ 68.50$ 38,223.00$ 107.17$ 59,800.86$
404 (Option) Rigid Pavement 1 LS 1,804.00$ 1,804.00$ 85,000.00$ 98,000.00$ 21,210.00$ 21,210.00$ 817.02$ 817.02$ 1,000.00$ 1,000.00$ 3,162.50$ 3,162.50$
405 (Option) Flexible Pavement 1 LS 15,746.00$ 15,746.00$ 72,000.00$ 92,000.00$ 59,474.00$ 59,474.00$ 23,635.21$ 23,635.21$ 36,000.00$ 36,000.00$ 25,041.25$ 25,041.25$
406 (Option) Architectural work 1 LS 38,360.00$ 38,360.00$ 45,000.00$ 49,000.00$ 87,108.00$ 87,108.00$ 110,900.35$ 110,900.35$ 40,000.00$ 40,000.00$ 101,526.60$ 101,526.60$
407 (Option) Roof System 1 LS 69,552.00$ 69,552.00$ 268,000.00$ 297,000.00$ 92,864.00$ 92,864.00$ 51,791.62$ 51,791.62$ 55,000.00$ 55,000.00$ 92,006.90$ 92,006.90$
408 (Option) Removable Flood Barriers 1 LS 91,878.00$ 91,878.00$ 22,000.00$ 27,000.00$ 53,980.00$ 53,980.00$ 65,742.27$ 65,742.27$ 49,000.00$ 49,000.00$ 59,607.50$ 59,607.50$
409 (Option) Structural steel 1 LS 91,053.00$ 91,053.00$ 51,000.00$ 59,000.00$ 192,086.00$ 192,086.00$ 204,333.54$ 204,333.54$ 172,000.00$ 172,000.00$ 177,287.96$ 177,287.96$
410 (Option) Steel Decking 1 LS 19,075.00$ 19,075.00$ 110,000.00$ 120,000.00$ 30,289.00$ 30,289.00$ 22,690.70$ 22,690.70$ 18,000.00$ 18,000.00$ 12,397.23$ 12,397.23$
411 (Option) Cast-in-place Concrete 1 LS 14,713.00$ 14,713.00$ 205,000.00$ 221,000.00$ 70,450.00$ 70,450.00$ 99,138.53$ 99,138.53$ 38,000.00$ 38,000.00$ 3,286.04$ 3,286.04$
412 (Option)
Reinforcing steel for existing masonry walls (installation) 1 LS 398,271.00$ 398,271.00$ 2,840,000.00$ 3,229,000.00$ 361,795.00$ 361,795.00$ 369,502.93$ 369,502.93$ 341,000.00$ 341,000.00$ 339,000.00$ 339,000.00$ 412A
(Option)
Reinforcing steel for existing masonry walls (material) 3,200 LF 37.00$ 118,400.00$ 556,000.00$ 778,000.00$ 91.12$ 291,584.00$ 77.68$ 248,576.00$ 71.00$ 227,200.00$ 76.84$ 245,888.00$
413 (Option)
Grouting for existing masonry walls
(installation) 1 LS 230,847.00$ 230,847.00$ 889,000.00$ 999,000.00$ 373,129.00$ 373,129.00$ 377,077.48$ 377,077.48$ 339,000.00$ 339,000.00$ 322,567.54$ 322,567.54$
TOTAL DPS#2 Option
TOTAL Bid Items for DPS #4 Pump Station Site (All work at DPS#4 is an “Option” )
Bid Items for DPS #12 Pump Station Site (All work at DPS#12 is an “Option” )
Bid Items for DPS #4 Pump Station Site (All work at DPS#4 is an “Option” )
4. ISSUING OFFICE I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
DISTRICT ENGINEER
USACE, HURRICANE PROTECTION OFFICE SIGNATURE
7400 LEAKE AVE.
NEW ORLEANS, LA 70118 Jason Meyers, BID OPENING OFFICER
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE
(CHECK A, B, OR C AND COMPLETE
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
Quality Trust Inc., Healtheon, INC. Benetech David Boland, Inc K & K Industries, Inc.
A. HIRED LABOR 133 East Home Street 201 St Charles Ave Suite 4310 915 S. White Street P.O. Box 1870 4996 State Highway M-117
Junction City, KS 66441 New Orleans, LA 70170 New Orleans, LA 70125 Titusville, FL 32781-1870 Newberry, MI 49868
B. REASONABLE CONTRACT B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY
(WITHOUT PROFIT) Yes Yes Yes Yes
C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED
(INCLUDING PROFIT) Yes Yes Yes Yes Yes
6. NUMBER OF ADDENDA ISSUED LB LB LB LB LB
7A. ITEM NO. 7B. DESCRIPTION OF OFFERED ITEM 7C. EST QTY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT
ABSTRACT OF OFFERS-CONSTRUCTION
W912P8-10-B-0079
Storm Proofing Drainage Pump Station No. 1,2,4,12,19 & I-
10, Storm Proofing Interior Pump Station OSP-08, Orleans
Parish, LA
413A
(Option)
Grouting for existing masonry walls
(material) 4,715 SF 73.00$ 344,195.00$ 78,000.00$ 86,000.00$ 46.90$ 221,133.50$ 46.88$ 221,039.20$ 36.00$ 169,740.00$ 39.55$ 186,478.25$
414 (Option) Plumbing System 1 LS 32,984.00$ 32,984.00$ 155,000.00$ 169,000.00$ 65,659.00$ 65,659.00$ 78,979.41$ 78,979.41$ 59,000.00$ 59,000.00$ 41,403.20$ 41,403.20$
415 (Option) Ventilation System 1 LS 17,435.00$ 17,435.00$ 50,000.00$ 55,000.00$ 46,220.00$ 46,220.00$ 12,660.48$ 12,660.48$ 36,000.00$ 36,000.00$ 21,051.90$ 21,051.90$
416 (Option) Power System Analysis 1 LS 8,245.00$ 8,245.00$ 10,000.00$ 12,500.00$ 12,357.00$ 12,357.00$ 3,473.64$ 3,473.64$ 3,000.00$ 3,000.00$ 11,300.00$ 11,300.00$
417 (Option)
House Generators and Transfer
Switches 1 LS 148,650.00$ 148,650.00$ 80,000.00$ 88,000.00$ 208,423.00$ 208,423.00$ 76,486.05$ 76,486.05$ 59,000.00$ 59,000.00$ 90,400.00$ 90,400.00$
418 (Option)
Grounding and Lightning
Protection Systems 1 LS 11,056.00$ 11,056.00$ 13,000.00$ 19,000.00$ 16,065.00$ 16,065.00$ 5,174.89$ 5,174.89$ 5,000.00$ 5,000.00$ 14,690.00$ 14,690.00$
419 (Option)
Electrical Distribution Systems
(Under 600-volts) 1 LS 259,682.00$ 259,682.00$ 182,000.00$ 205,000.00$ 224,897.00$ 224,897.00$ 163,519.54$ 163,519.54$ 159,000.00$ 159,000.00$ 205,660.00$ 205,660.00$
420 (Option)
Electrical Distribution System
(Over 600-volts) 1 LS 15,485.00$ 15,485.00$ 30,000.00$ 39,000.00$ 37,071.00$ 37,071.00$ 48,889.30$ 48,889.30$ 47,000.00$ 47,000.00$ 33,900.00$ 33,900.00$
2,155,258.00$ 7,189,500.00$ 2,770,225.18$ 2,303,588.75$ 1,991,163.00$ 2,274,540.98$
(Option) Mobilization and Demobilization 1 LS 255,658.00$ 255,658.00$ 125,000.00$ 138,000.00$ 192,563.00$ 192,563.00$ 62,225.05$ 62,225.05$ 95,000.00$ 95,000.00$ 148,212.00$ 148,212.00$
(Option) Selective Demolition 1 LS 76,230.00$ 76,230.00$ 175,000.00$ 185,000.00$ 193,189.00$ 193,189.00$ 21,542.56$ 21,542.56$ 245,000.00$ 245,000.00$ 179,975.00$ 179,975.00$
(Option) Sitework 1 LS 20,214.00$ 20,214.00$ 73,000.00$ 88,000.00$ 44,214.00$ 44,214.00$ 31,114.45$ 31,114.45$ 114,000.00$ 114,000.00$ 86,802.00$ 86,802.00$
(Option) Rigid Pavement 1 LS 55,410.00$ 55,410.00$ 102,000.00$ 120,000.00$ 148,061.00$ 148,061.00$ 128,084.82$ 128,084.82$ 88,000.00$ 88,000.00$ 66,182.50$ 66,182.50$
(Option) Precast concrete Pile Installation 1,820 LF 45.00$ 81,900.00$ 210,000.00$ 231,000.00$ 90.50$ 164,710.00$ 112.84$ 205,368.80$ 60.10$ 109,382.00$ 77.06$ 140,249.20$
(Option) Architectural work 1 LS 193,762.00$ 193,762.00$ 45,000.00$ 57,000.00$ 150,669.00$ 150,669.00$ 222,996.15$ 222,996.15$ 486,000.00$ 486,000.00$ 399,335.20$ 399,335.20$
(Option) Roof System 1 LS 452,777.00$ 452,777.00$ 269,000.00$ 279,000.00$ 494,706.00$ 494,706.00$ 327,246.29$ 327,246.29$ 285,000.00$ 285,000.00$ 506,228.85$ 506,228.85$
(Option) Structural steel 1 LS 148,728.00$ 148,728.00$ 48,000.00$ 58,000.00$ 606,312.00$ 606,312.00$ 358,354.61$ 358,354.61$ 236,000.00$ 236,000.00$ 672,780.53$ 672,780.53$
(Option) Steel Decking 1 LS 86,787.00$ 86,787.00$ 153,000.00$ 167,000.00$ 150,084.00$ 150,084.00$ 77,906.49$ 77,906.49$ 83,000.00$ 83,000.00$ 85,860.79$ 85,860.79$
(Option) Cast-in-place Concrete 1 LS 161,519.00$ 161,519.00$ 215,000.00$ 230,000.00$ 205,195.00$ 205,195.00$ 139,435.24$ 139,435.24$ 155,000.00$ 155,000.00$ 4,972.00$ 4,972.00$
(Option)
Reinforcing steel for existing masonry walls (installation) 1 LS 343,011.00$ 343,011.00$ 2,998,000.00$ 3,192,000.00$ 573,630.00$ 573,630.00$ 543,048.64$ 543,048.64$ 501,000.00$ 501,000.00$ 528,939.44$ 528,939.44$ 0510A
(Option)
Reinforcing steel for existing masonry walls (material) 2,756 LF 37.00$ 101,972.00$ 525,000.00$ 615,000.00$ 91.42$ 251,953.52$ 72.99$ 201,160.44$ 71.50$ 197,054.00$ 77.09$ 212,460.04$
(Option) Plumbing System 1 LS 99,987.00$ 99,987.00$ 110,000.00$ 145,000.00$ 282,756.00$ 282,756.00$ 124,515.39$ 124,515.39$ 347,000.00$ 347,000.00$ 89,157.00$ 89,157.00$
(Option) Ventilation System 1 LS 99,076.00$ 99,076.00$ 50,000.00$ 55,000.00$ 312,662.00$ 312,662.00$ 166,615.61$ 166,615.61$ 229,000.00$ 229,000.00$ 52,545.00$ 52,545.00$
(Option) Power System Analysis 1 LS 14,242.00$ 14,242.00$ 15,000.00$ 21,000.00$ 18,536.00$ 18,536.00$ 3,288.57$ 3,288.57$ 3,000.00$ 3,000.00$ 16,950.00$ 16,950.00$
(Option)
House Generators and Transfer
Switches 1 LS 219,713.00$ 219,713.00$ 110,000.00$ 120,000.00$ 318,008.00$ 318,008.00$ 103,914.72$ 103,914.72$ 96,000.00$ 96,000.00$ 124,300.00$ 124,300.00$
(Option)
Grounding and Lightning
Protection Systems 1 LS 23,839.00$ 23,839.00$ 18,000.00$ 23,000.00$ 22,243.00$ 22,243.00$ 7,787.28$ 7,787.28$ 7,000.00$ 7,000.00$ 20,340.00$ 20,340.00$
(Option)
Electrical Distribution Systems
(Under 600-volts) 1 LS 394,543.00$ 394,543.00$ 356,000.00$ 389,000.00$ 439,908.00$ 439,908.00$ 285,813.89$ 285,813.89$ 277,000.00$ 277,000.00$ 402,280.00$ 402,280.00$ 0517A
(Option) Barge Fuel Fill Connection 1 LS 200,859.00$ 200,859.00$ 39,000.00$ 47,500.00$ 14,954.00$ 14,954.00$ 79,760.18$ 79,760.18$ 50,000.00$ 50,000.00$ 31,640.00$ 31,640.00$
3,030,227.00$ 6,160,500.00$ 4,584,353.52$ 3,090,179.18$ 3,603,436.00$ 3,769,209.55$
(Option) Mobilization and Demobilization 1 LS 108,262.00$ 108,262.00$ 125,000.00$ 135,000.00$ 111,098.00$ 111,098.00$ 48,390.27$ 48,390.27$ 1,000.00$ 1,000.00$ 186,047.00$ 186,047.00$
(Option) Selective Demolition 1 LS 46,653.00$ 46,653.00$ 110,000.00$ 120,000.00$ 83,831.00$ 83,831.00$ 15,117.23$ 15,117.23$ 92,000.00$ 92,000.00$ 83,490.00$ 83,490.00$
(Option) Sitework 1 LS 20,408.00$ 20,408.00$ 59,000.00$ 67,000.00$ 116,127.00$ 116,127.00$ 1,323.17$ 1,323.17$ 81,000.00$ 81,000.00$ 49,691.50$ 49,691.50$
(Option) Rigid Pavement 1 LS 25,772.00$ 25,772.00$ 85,000.00$ 92,000.00$ 59,726.00$ 59,726.00$ 1,984.76$ 1,984.76$ 49,000.00$ 49,000.00$ 22,568.75$ 22,568.75$
(Option) Architectural work 1 LS 199,284.00$ 199,284.00$ 38,000.00$ 45,000.00$ 102,726.00$ 102,726.00$ 28,508.52$ 28,508.52$ 133,000.00$ 133,000.00$ 29,325.00$ 29,325.00$
(Option) Roof System 1 LS 125,545.00$ 125,545.00$ 239,000.00$ 251,000.00$ 228,876.00$ 228,876.00$ 216,148.76$ 216,148.76$ 186,000.00$ 186,000.00$ 242,483.25$ 242,483.25$
(Option) Structural steel 1 LS 8,979.00$ 8,979.00$ 95,000.00$ 115,000.00$ 67,162.00$ 67,162.00$ 38,754.56$ 38,754.56$ 29,000.00$ 29,000.00$ 196,735.26$ 196,735.26$
(Option) Steel Decking 1 LS 51,213.00$ 51,213.00$ 198,000.00$ 222,000.00$ 71,364.00$ 71,364.00$ 36,267.00$ 36,267.00$ 30,000.00$ 30,000.00$ 30,584.58$ 30,584.58$
(Option) Cast-in-place Concrete 1 LS 23,663.00$ 23,663.00$ 105,000.00$ 138,000.00$ 4,527.00$ 4,527.00$ 2,507.41$ 2,507.41$ 3,000.00$ 3,000.00$ 3,116.54$ 3,116.54$
(Option) Plumbing System 1 LS 71,160.00$ 71,160.00$ 94,000.00$ 154,000.00$ 52,745.00$ 52,745.00$ 95,855.90$ 95,855.90$ 69,000.00$ 69,000.00$ 30,171.00$ 30,171.00$
(Option) Ventilation System 1 LS 102,670.00$ 102,670.00$ 50,000.00$ 55,000.00$ 94,343.00$ 94,343.00$ 220,852.45$ 220,852.45$ 43,000.00$ 43,000.00$ 60,794.00$ 60,794.00$
(Option) Power System Analysis 1 LS 8,245.00$ 8,245.00$ 10,000.00$ 12,500.00$ 12,357.00$ 12,357.00$ 3,986.15$ 3,986.15$ 4,000.00$ 4,000.00$ 11,300.00$ 11,300.00$
(Option)
House Generators and Transfer
Switches 1 LS 116,769.00$ 116,769.00$ 50,000.00$ 57,000.00$ 157,529.00$ 157,529.00$ 79,080.29$ 79,080.29$ 75,000.00$ 75,000.00$ 56,500.00$ 56,500.00$
(Option)
Grounding and Lightning
Protection Systems 1 LS 18,331.00$ 18,331.00$ 16,000.00$ 21,000.00$ 19,772.00$ 19,772.00$ 10,299.57$ 10,299.57$ 10,000.00$ 10,000.00$ 18,080.00$ 18,080.00$
(Option)
Electrical Distribution Systems
(Under 600-volts) 1 LS 228,435.00$ 228,435.00$ 269,000.00$ 298,000.00$ 332,402.00$ 332,402.00$ 183,890.59$ 183,890.59$ 171,000.00$ 171,000.00$ 303,970.00$ 303,970.00$
TOTAL Bid Items for DPS #12 Pump Station Site (All work at DPS#12 is an “Option” )
TOTAL Bid Items for DPS #19 Pump Station Site (All work at DPS#16 is an “Option” )
Bid Items for DPS #19 Pump Station Site (All work at DPS#16 is an “Option” )
Bid Items for DPS #I-10 Pump Station Site (All work at DPS#I-10 is an “Option” )
4. ISSUING OFFICE I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
DISTRICT ENGINEER
USACE, HURRICANE PROTECTION OFFICE SIGNATURE
7400 LEAKE AVE.
NEW ORLEANS, LA 70118 Jason Meyers, BID OPENING OFFICER
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE
(CHECK A, B, OR C AND COMPLETE
D, E, AND F.) A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
Quality Trust Inc., Healtheon, INC. Benetech David Boland, Inc K & K Industries, Inc.
A. HIRED LABOR 133 East Home Street 201 St Charles Ave Suite 4310 915 S. White Street P.O. Box 1870 4996 State Highway M-117
Junction City, KS 66441 New Orleans, LA 70170 New Orleans, LA 70125 Titusville, FL 32781-1870 Newberry, MI 49868
B. REASONABLE CONTRACT B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY
(WITHOUT PROFIT) Yes Yes Yes Yes
C. REASONABLE CONTRACT C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED C. ADDENDA ACKNOWLEDGED
(INCLUDING PROFIT) Yes Yes Yes Yes Yes
6. NUMBER OF ADDENDA ISSUED LB LB LB LB LB
7A. ITEM NO. 7B. DESCRIPTION OF OFFERED ITEM 7C. EST QTY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE F. ESTIMATED AMOUNT
ABSTRACT OF OFFERS-CONSTRUCTION
W912P8-10-B-0079
Storm Proofing Drainage Pump Station No. 1,2,4,12,19 & I-
10, Storm Proofing Interior Pump Station OSP-08, Orleans
Parish, LA
1,155,389.00$ 1,782,500.00$ 1,514,585.00$ 982,966.63$ 976,000.00$ 1,324,856.88$
(Option)
Water well, including Platform, to depth to 500 ft DPS 1 1 LS 439,134.00$ 439,134.00$ 144,000.00$ 174,000.00$ 512,623.00$ 512,623.00$ 415,765.81$ 415,765.81$ 405,000.00$ 405,000.00$ 315,954.45$ 315,954.45$
(Option) Additional water well depth DPS1 250 LF 353.00$ 88,250.00$ 159,000.00$ 189,000.00$ 154.60$ 38,650.00$ 120.68$ 30,170.00$ 272.60$ 68,150.00$ 273.70$ 68,425.00$
(Option)
Water well, including Platform, to depth to 500 ft DPS 2 1 LS 495,418.00$ 495,418.00$ 144,000.00$ 174,000.00$ 506,189.00$ 506,189.00$ 439,317.77$ 439,317.77$ 393,000.00$ 393,000.00$ 313,998.30$ 313,998.30$
(Option) Additional water well depth DPS2 250 LF 353.00$ 88,250.00$ 159,000.00$ 189,000.00$ 154.60$ 38,650.00$ 120.68$ 30,170.00$ 272.60$ 68,150.00$ 273.70$ 68,425.00$
(Option)
Water well, including Platform, to depth to 500 ft DPS 4 1 LS 439,249.00$ 439,249.00$ 144,000.00$ 174,000.00$ 507,821.00$ 507,821.00$ 502,127.18$ 502,127.18$ 393,000.00$ 393,000.00$ 321,576.80$ 321,576.80$
(Option) Additional water well depth DPS4 250 LF 353.00$ 88,250.00$ 159,000.00$ 189,000.00$ 154.60$ 38,650.00$ 120.68$ 30,170.00$ 272.60$ 68,150.00$ 273.70$ 68,425.00$
(Option)
Water well, including Platform, to depth to 500 ft DPS 12 1 LS 449,356.00$ 449,356.00$ 144,000.00$ 174,000.00$ 507,559.00$ 507,559.00$ 425,532.05$ 425,532.05$ 397,000.00$ 397,000.00$ 314,139.75$ 314,139.75$
(Option) Additional water well depth DPS12 250 LF 353.00$ 88,250.00$ 159,000.00$ 189,000.00$ 154.60$ 38,650.00$ 120.68$ 30,170.00$ 272.60$ 68,150.00$ 273.70$ 68,425.00$
(Option)
Water well, including Platform, to depth to 500 ft DPS I-10 1 LS 442,979.00$ 442,979.00$ 389,000.00$ 410,000.00$ 510,560.00$ 510,560.00$ 489,501.82$ 489,501.82$ 393,000.00$ 393,000.00$ 315,649.70$ 315,649.70$
(Option)
Additional water well depth DPSI-
10 250 LF 353.00$ 88,250.00$ 159,000.00$ 169,000.00$ 154.60$ 38,650.00$ 120.68$ 30,170.00$ 272.60$ 68,150.00$ 273.70$ 68,425.00$
2,707,386.00$ 2,031,000.00$ 2,738,002.00$ 2,423,094.63$ 2,321,750.00$ 1,923,444.00$
9,531,153.00$ 8,887,000.00$ 10,790,118.16$ 8,350,601.85$ 9,375,481.00$ 8,873,347.42$
3,802,141.00$ 41,000.00$ 4,854,118.00$ 3,388,342.20$ 3,216,078.00$ 3,937,388.64$
2,654,529.00$ 1,997,000.00$ 2,832,431.60$ 2,357,911.76$ 2,043,083.00$ 2,516,897.34$
2,155,258.00$ 7,189,500.00$ 2,770,225.18$ 2,303,588.75$ 1,991,163.00$ 2,274,540.98$
3,030,227.00$ 6,160,500.00$ 4,584,353.52$ 3,090,179.18$ 3,603,436.00$ 3,769,209.55$
1,155,389.00$ 1,782,500.00$ 1,514,585.00$ 982,966.63$ 976,000.00$ 1,324,856.88$
2,707,386.00$ 2,031,000.00$ 2,738,002.00$ 2,423,094.63$ 2,321,750.00$ 1,923,444.00$
15,504,930.00$ 28,132,500.00$ 19,293,715.30$ 14,546,083.15$ 14,151,510.00$ 15,746,337.39$
25,036,083.00$ 37,019,500.00$ 30,083,833.46$ 22,896,685.00$ 23,526,991.00$ 24,619,684.81$
Bid Items for Water Wells at all Pump Station Sites
TOTAL Bid Items for DPS #I-10 Pump Station Site (All work at DPS#I-10 is an “Option” )
OPTION ITEM DPS I-10
OPTION ITEM WATER WELLS
TOTAL BASE AND OPTION ITEMS
BASE DPS 1 & ITEM 517
OPTION ITEM DPS 2
OPTION ITEM DPS 4
OPTION ITEM DPS 12
OPTION ITEM DPS 19
TOTAL OPTION ITEMS
TOTAL Bid Items for DPS #I-10 Pump Station Site (All work at DPS#I-
10 is an “Option” )
File details come from the government source that posted it. Updated .