Am_0003.pdf
PDF 55 KB Posted
- Attached to
- West Bank and Vicinity, Segnette Pumping Station Federal contract opportunity
- Solicitation number
- W912P8-09-R-0105
About this file
Amendment 0003 for W912P8-09-R-0105
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q A.pdf | ||
| 09-R-0105-Amend0005.pdf | ||
| Am_0004.pdf | ||
| Am_0002.pdf | ||
| Amendment 001 WBV-16b.pdf | ||
| W912P809R01052.pdf | ||
| W912P809R0105SPECS.pdf | ||
| W912P809R0105.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
WBV-16b, West Bank and Vicinity, Louisiana, Segnette Pumping Station Fronting Protection and Modifications is amended as follow s:����� Proposal Due Date The Proposal due date of 13 October 2009 at 2pm local time remains unchanged.
SECTION 31 23 16.16 12
Delete this section in its entirety and replace w ith the attached revised section therefore.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Oct-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P8-09-R-0105
X 9B. DATED (SEE ITEM 11)
11-Sep-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Oct-2009
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION 31 23 16.16 12
STRUCTURAL EXCAVATION AND BACKFILL
01/06
PART 1 GENERAL
1.1 SCOPE
The work covered by this section consists of furnishing all plant, labor, materials, equipment, and performing all operations necessary for stockpiling materials, excavating for structures, and for all incidental work specified herein or as shown on the drawings. Backfill shall be embankment, compacted fill, as specified in Section 31 24 00.00 12
EMBANKMENT.
1.2 MEASUREMENT AND PAYMENT
1.2.1 Structural Excavation and Backfill
No separate measurement will be made for structural excavation. Payment for structural excavation will be made at the applicable lump sum price for "Structural Excavation", unless otherwise specified to be included in the contract prices for items of work to which the work is incidental thereto.
Price and payment shall constitute full compensation for furnishing all plant, labor, materials, and equipment to complete the work as specified herein and as shown on the drawings. Backfill will be measured and payment will be made as specified in Section 31 24 00.00 12 EMBANKMENT.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D 422 (1963; R 2007) Particle-Size Analysis of Soils
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2008) Safety -- Safety and Health Requirements
1.4 QUALITY CONTROL
The Contractor shall establish and maintain quality control for excavation operations to assure compliance with contract requirements and maintain records of his quality control for all construction operations including but not limited to the following:
(1) Equipment. Type, size, and suitability for construction of the prescribed work.
(2) Structural Excavation. Check grade, slopes, and dimensions for compliance with design sections.
(3) Grade Tolerances. Check fills to determine if placement conforms to prescribed grade and design section.
(4) Construction. Layout, maintaining existing drainage, moisture control, thickness of layers, spreading and compacting.
(5) Classification of soils, placing and compacting of structural fill, and density tests.
(6) Control Testing. The Contractor shall perform all control testing such as particle size analysis. No separate measurement and payment will be made for control testing required in this paragraph. The Contractor shall include any and all costs for control testing in the contract prices for items of work to which the work is incidental thereto.
1.4.1 Reporting
The original and two copies of these records of inspections and tests, as well as the records of corrective action taken, shall be furnished to the Government daily. Format of the report shall be as prescribed in Section
01 45 04.00 12 CONTRACTOR QUALITY CONTROL.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.2 Suitable From Excavation
Material meeting the specifications of Section 31 24 00.00 12 EMBANKMENT and not classified as unsuitable, as described in paragraph UNSUITABLE MATERIALS, may be used for backfill operations.
2.2 EQUIPMENT
Equipment for compaction shall conform to the requirements herein and the applicable requirements of Section 31 24 00.00 12 EMBANKMENT.
2.2.1 Hand Tampers
Hand tamping shall be used in the compaction of structural fill within three feet of any floodwall or structure and near floodwalls and structures where vehicular equipment cannot be used. These hand tampers should be power driven, hand operated type.
2.2.2 Alternative Compaction Equipment
The Contractor may propose for use alternative types of compaction equipment not included in these specifications. The suitability of the alternative equipment must be demonstrated to the Contracting Officer's Field Representative by a field test conducted by and at the expense of the Contractor. The alternative compaction equipment must be capable of properly compacting the soil so that no planes of weakness or laminations are formed in the fill. Additionally, the alternative compaction equipment must not detrimentally affect any adjacent structure. The field test shall consist of compacting a minimum of three layers of an area of embankment with the alternative type equipment.
2.2.3 Miscellaneous Equipment
Scarifiers, disks, spring-tooth or spike-tooth harrows, spreaders, power tampers and other equipment shall be of types suitable for the required construction. Sprinkling equipment shall be designed to apply water uniformly and in controlled quantities to variable widths of surface.
PART 3 EXECUTION
3.1 STRUCTURAL EXCAVATION AND BACKFILL
3.1.1 General
The Contractor shall make all excavations required for the construction of the floodwall monoliths. Suitable material from required structural excavation shall be used in the structural backfill. Materials determined to be unsuitable by the Contracting Officer's Field Representative shall be ordered wasted.
3.1.2 Backfill
Backfill is defined as any soil material, which is placed within the limits of the structural excavation and the final grade as indicated on the drawings, and as herein specified. The Contractor shall fill all excavations to grades shown on the drawings. Backfill shall not be placed against concrete structures for a minimum of 14 days after the concrete is placed. The Contractor may at his expense place fill sooner if he furnishes and tests cylinders to demonstrate that the concrete has achieved 75 percent of its design capacity.
3.1.4.1 Compacted Backfill
Compacted backfill shall be compacted in accordance with Section
31 24 00.00 12 EMBANKMENT.
3.2 UNSUITABLE MATERIALS
Materials, which are classified as unsuitable structural backfill, are defined as material containing organic matter, sticks, branches, roots, brick, concrete, rock, and other debris.
3.3 FROZEN MATERIALS
Under no circumstances shall frozen earth, snow or ice be placed in the fill. The Contracting Officer may require the wasting of frozen material.
3.4 DRESSING
The fill shall be brought to not less than the prescribed design cross section at all points. Unreasonable roughness of surface shall be dressed out to permit fertilizing and seeding operations.
3.5 SHORING
The Contractor shall provide all necessary shoring, bracing, sheeting, underpinning, and/or supports as may be required for the construction of structures. A design and the method of installing the proposed shoring shall be submitted to the Contracting Officer for approval at least 30 days prior to its actual intended use. Upon completion of the structure, the Contractor shall remove the shoring at the direction of the Contracting Officer or his representative. The void created by the shoring removal shall be backfilled and the surface area shall be treated to match the existing surface prior to the installation of the shoring. Excavations more than 5 feet deep shall be shored unless shown otherwise on the drawings. Additional requirements for shoring shall be in accordance with Section 25 "Excavations" of EM 385-1-1.
-- End of Section --